ID Task Name Duration 08 Sep '08 15 Sep '08 22 Sep '08 29

W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 Analysis 15.25 days
2 Initial meeting with client 2 hrs
3 Project Proposal 1 day
4 Functional specification 1 day
5 Project proposal, scope and initi 2 hrs
6 Project Propoal Meeting 2 hrs
7 Initial Design 8 days
8 Initial Design 4 days
9 Updated Designs 4 days
10 Prototyping and formative testing 72 days
11 Introduction 2 days
12 Formative Testing 1 day
13 Main Menu 2 days
14 Main menu Buttons 1 day
15 Formative Testing 1 day
16 Brief Overview of the H10 Hotels 3 days
17 Text Scroll Box 1 day
18 Formative Testing 1 day
19 Location Of H10 Palmasol 3 days
20 Text Scroll Box 1 day
21 Formative Testing 1 day
22 Gallery 5 days
23 Scroll Over Picture Viewer 1 day
24 Formative Testing 1 day
25 H10 Palmasol Hotel 3 days
26 Links 1 day
27 Formative Testing 1 day
28 Contingency- illness 4 days
29 Hotel Features 3 days
30 Links 1 day

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 1
ID Task Name Duration 08 Sep '08 15 Sep '08 22 Sep '08 29
W T F S S M T W T F S S M T W T F S S M T W T F S S M
31 Formative testing 1 day
32 Hotel Services 3 days
33 Text Boxes 1 day
34 Formative Testing 1 day
35 Cost Of Rooms and Boards 3 days
36 Table & text boxes 1 day
37 Formative Testing 1 day
38 Review Of the Hotel 3 days
39 Text Box 1 day
40 Formative Testing 1 day
41 Video 3 days
42 Inserting and editing video 3 days
43 Formative Testing 1 day
44 Inserting sound 4 days
45 Formative Testing 1 day
46 Contingency- Computer Breakdo 7 days
47 Summative Testing 10 days
48 Test Plan 4 days
49 Feedback 2 days
50 Contingency- Illness 4 days
51 Documentation 9 days
52 Getting started with instructions 4 days
53 User Guide 2 days
54 Auto Run CD 3 days
55 Hand Over 1.25 days
56 Hand Over to client 1 day
57 End of project review meeting 2 hrs

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 2
ep '08 06 Oct '08 13 Oct '08 20 Oct '08 27 Oct '08 03 Nov '08
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 3
ep '08 06 Oct '08 13 Oct '08 20 Oct '08 27 Oct '08 03 Nov '08
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 4
10 Nov '08 17 Nov '08 24 Nov '08 01 Dec '08 08 Dec '08 15 Dec '08
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 5
10 Nov '08 17 Nov '08 24 Nov '08 01 Dec '08 08 Dec '08 15 Dec '08
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 6
22 Dec '08 29 Dec '08 05 Jan '09 12 Jan '09 19 Jan '09 26 Jan '09
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 7
22 Dec '08 29 Dec '08 05 Jan '09 12 Jan '09 19 Jan '09 26 Jan '09
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Milestone External Tasks


Project: Initial Project Plan1
Split Summary External Milestone
Date: Tue 03/03/09
Progress Project Summary Deadline

Page 8

You might also like