Professional Documents
Culture Documents
Application can be made by filling in Form SAJH501 for permanent or temporary water supply.
Applicant is required to appoint a registered plumber who shall fill in form SAJH501 with the
consumer information (section 1), plumber information (section 2), layout plan and piping
system (section 3) and SAJH approval for tapping point (section 4).
Completed application form shall be submitted together with copies of the following
documents:
i) Identification Card (IC) for individual application or Form 9/13, 44 and 49 for company
application; and
ii) Certificate of Fitness & Occupation (CFO) or Certificate of Completion & Compliance (CCC);
and
iii) Land Title or Letter of Consent from the land owner; and
iv) Water bill for adjacent premises.
Upon approval of submission, the plumber may proceed with the necessary installation. The
plumber is required to inform SAJH when all installation is completed for inspection.
If the installation is in order, SAJH will issue the invoices for the followings:-
i) Deposit
ii) Connection fee
iii) Contribution fee (if applicable)
The above payments shall be made at SAJH payment counter only. The proof of payment is
required before the water meter can be installed.
Water will be supplied after the water meter is installed.