5.1 During operation and maintenance of Sub Transmission and Distribution
Project following activities are involved :
Continuity of Service
Operation and Maintenance
Training and retaining of Operational Staff
Renewal of Maintenance Contract
Upkeep of spare parts Inventory
Record Keeping of Faults in the network/Equipment Problems,solutions,modifications and enhancements
Close monitoring of budgeted expenditure
Preparation ,Continuous updation and proper maintenance of operational and network data
Record of protective & isolating devices installed and their relay settings
Record of schedule of maintenance and preventive and routine maintenance of network elements
Development/indegenisation of spare parts
Development of maintenance practices ,tools & procedures for trouble free operation
Record of transformer/switchgear oil testing and its parameters
5.2 Operation and Maintenance is an essential part of the project after its completion. Failure to accomplish the same deprive the user of its benefit and lead to chaotic conditions. The manuals for O&M are pre-requisite for efficient and trouble free operation of the system/equipment. Manuals for Operation and Maintenance should contain the following :
Factory and Site test certificates for each item of the system with reference to relevant design calculation and quality assurance standards.
Maintenance instructions for all plants and cover preventive and corrective maintenance procedures.
Maintenance and inspection schedules for all items/equipment giving type of works required on a weekly ,monthly, annual basis
Proforma of the required maintenance record sheets for all the component/equipment.
5.3 The guidelines given here are the broad guidelines just to give the feel of the type of O&M required to be carried on each and every sub-station equipment. Individual equipment standards such as relevant ISS/BIS/IEC and manufacturer recommendations must not be ignored in any case. 5.4 During plant shut-downs for overall maintenance and before re- energisation , the sub-transmission and distribution plants will be subjected to certain inspection and testing procedures. This also applies to cable route, that has been de-energised for a long period of time. Planned maintenance schedules should be carefully drawn up by electricity supply utility before the installation contractor has completed his work. 5.5 On line inspection and testing is normally limited to visual, external, physical examination in order to ensure that plant is in a safe condition. Infra red detector must be used periodically for inspection of overhead lines and open terminal, sub-station bus bars for hot spots caused by faulty terminals. 5.6 In addition live line washing techniques are also available for cleaning overhead lines or open terminal sub-station insulators. Purified water with a high resistance value is used in a fine spray fitted from well-earthed nozzle. Functional testing and trip schemes require special switching arrangements initially to reconfigure the power system network. Such planned shut down of the plant to be tested and network reconfiguration ensure continuity of supply to consumers while the testing takes place. The electricity supply utility must formulate such planned outage schemes at different time of the year (depending upon the load demands) for different maintenance period in such a fashion that consumer supply is least affected. 5.7 Switchgear site tests during operational maintenance stage which may depend upon utility to utility depending upon the quality of upkeep of the equipment and environmental conditions of the site. These generally include the following : General checks : These tests include Tightness of terminal connection piping junctions and bolted joints. Painting and corrosion protection Cleanliness Cracking and chipping of bushings. Checking of foundation bolts Inspection of contacts lubrication of moving parts of mechanism of circuit breakers Electrical Circuit Checks : Insulation check Die-electric strength of the insulating oil. Level of the oil. Quality of SF6 gas/ insulating medium such as humidity content, filling pressure or density except for sealed apparatus Leakage of oil etc. Mechanical tests: Operating circuits(hydraulic, pneumatic, spring charged) consumption during operation. Verification of correct rated operating sequence(recharging etc)
Time quantities: Checking and adjustment of the track alignment and interlocking mechanism. Closing and opening times. Operation and control of auxiliary circuits. Recharging time of operating mechanism after specified sequence. Checks on specific operations.
Electric tests: Dielectric tests Resistance of main circuit.
5.8 If the sub-station is constantly attended, the rounds of switchgear are usually planned for each shift so that all the equipment will be looked at least once a day . Equipment should also be inspected immediately after a trip out. 5.9 Sub-stations switchgear requires regular cleaning in accordance with its design, type of insulation, the degree of pollution of the atmosphere or ambient air etc. The frequency of cleaning depends upon the type of layout of the apparatus and insulators. However, cleaning must be done during each preventive maintenance. 5.10 Even though the vacuum switchgear do not require elaborate maintenance like that of oil insulated, it is still necessary to make periodic routine inspection. 5.11 There are two aspects of problem of maintenance. Firstly, the parts which wear during the normal operation must from time to time, be replaced and secondly there is preventive maintenance for detecting deterioration and mal-operation of mechanism. The absence of ionized gas and carbon during interruption removes the major source of insulation contamination. 5.12 In the daily operation of the sub-station it is the duty of the attendant to inspect the equipment externally and remedy any abnormality that does not require disconnection of the apparatus. During this inspection, a watch is required to be kept for deposits of dust and dirt on the insulators heating of a contact, joint or some part, low oil level and oil leakage etc. 5.13 A check should also be made that the locks and doors of the switch house are in good condition, no leaks have developed in the roof, the ventilating and heating systems are operating normally, the prescribed safety aids are in place and in good order, the earthing connection remain unbroken, the packing of the cables entering or leaving a cable trench or tunnel within the premises are intact, the ventilating louvers are not damaged , the access roads leading to the oil filled apparatus are unobstructed and will allow the approach of the fire engines in the event of an oil fire during an emergency. 5.14 Guidelines for O & M of Vacuum type Circuit Breaker 1. Vacuum circuit breakers require little maintenance. Only the parts subject to normal wear and tear need to be serviced to ensure fully reliable operation.The interval at which the maintenance depends are ,number of operations on faults, switching frequency and actual service time. 2. Maintenance and inspection should be performed in accordance with the maintenance schedule given by the manufacturer and should be adjusted to suit particular operating condition. Visual inspection should be made once a year and if necessary the older insulating parts wiped with a clean rag. Under normal conditions vacuum interrupters need not be serviced. The maximum permissible contact wear is 3 mm. 3. Before starting any maintenance work breakers should be isolated short circuited earthed auxiliary supply disconnected springs through normal operation be discharged safety regulations be followed visually inspected for any loose or damaged parts slow closing operation after ensuring the breaker truck is in withdrawal position be performed contact erosion on the interrupter be checked vacuum of the interrupter be checked mechanism be lubricated electrical operation of the breaker be performed after putting the truck in test position 4. The operating mechanism should be oiled and lubricated every 10 years or after 10,000, make break operations.
5. Breaker should be overhauled after 30,000 operations. 6. The interrupter must be replaced after 30,000 mechanical operation or when the contacts have eroded by the maximum amount as recommended by the supplier. Generally it is 3 mm. 7. The vacuum circuit breakers with very high switching frequency and exposed to dust laden atmosphere shall be serviced at 6 months interval.
5.15 Because of relatively low energy arc , the contact erosion is negligible in most applications and contact adjustments may not be necessary throughout the life of the vacuum interrupter.
5.16 The periodicity of Maintenance is given below :
Sl No Item of Maintenance Periodicity Remarks
1 Measuring I.R Values of the poles with Breaker open(ie across contacts)and Breaker closed(pole to earth) Monthly Compare with recommended Values/Earlier Values 2 Measuring Insulation Resistance of control Circuit winding Yearly Minimum 2 Mega Ohms with a 500 Volt Megger 3 Anti Condensation Heaters Daily Ensure that heater is on and is working
5.17 Guidelines for O&M of SF6 Circuit Breakers SF6 switchgear require virtually no maintenance .Complete protection against ambient conditions prevents deterioration of insulating strength .There is no need to clean the insulators with conventional equipment. Moisture content remains roughly constant at the value set at commissioning.
The maintenance mainly involves following jobs : Sl No Item of Maintenance
Periodicity Remarks
1 SF6 density Monitoring Daily in each shift If Change Carry Leakage Test 2 Humidity Measurement Yearly Use Dew Meter.if Change,Evacuation,Re- Cycling and Refilling required 3 Acid concentration Measureme Yearly -do- 4 Air Content Measurement Yearly 5 Gas Leakage Test Yearly Consult Manufacturer if any Leakage
6 Control Circuit Insulation Checking Yearly Min 2 Mega Ohm with 500 V Megger 7 Measurement of Contacts Insulation Yearly To be done by 2.5 kV megger or above
8 Evacuation,Recycling and refilling 5 yearly or To be done if humidity is in excess or permissible value 9 Checking the Br level with sprit level Yearly
2. Following precaution is required to be taken in case unit is suspected of leakage of SF6 gas : All personnel should be evacuated from the area Good Ventilation should be provided in that area Contaminated SF6 gas should be removed through pipes vented to outside atmosphere The gas should be removed by pumping through absorbents and stored in cylinders 5.18 O & M of Air Blast Circuit Breakers : Following Maintenance Schedule is recommended for Air Blast Circuit Breakers : Sl No Item of Maintenance Periodicity Remark 1 Checking of Pressure Daily in Each shift Carry Leakage Test if appreciable Change 2 Draining out Condensed water From HP Cylinders Twice Daily Increase Frequency of Draining during Rainy Season 3 Draining out condensed water from CB tanks Monthly -do- 4 Visual checking of oil level in the dash pot,checking of manometer reading Monthly 5 Capacitance ,Measurement Yearly For Grading capacitors 6 Insulation Resistance Measurement for control circuit Yearly Minimum 2 Mega Ohms with a 500 V Megger 7 Measurement of IR Values across Contacts(CB off ) Yearly Minimum 2.5 kV Megger to be used 8 Checking the Br level with Sprit Level Yearly
5.19 O & M of Minimum Oil Circuit Breakers For 6.6 kv/11 kV service the circuit breaker bushing have a hollow porcelain shell which houses the current carrying rods but contains no filling, while for 33 kV service the current carrying rod or tube is covered with insulation and hollow space within the porcelain shell is filled with bitumen filling compound. Bushing inspection includes a check of the cemented joints. It should not show the sign of cracking and grumbling or any sign of filling compound leakage at the cemented joint if disintegration of the cement extends deeply into the joints, the bushing must be replaced otherwise surface can be patched with cement of same composition and then, after it dries coated with oil paint. The porcelain shells be cleaned with dry clothes or cloth wetted in transformer oil. Insulation of the internal moving parts of a circuit breaker, the arc control devices the inter-phase barriers the light rods and guide bars and the tank insulators be checked. The maintenance schedule for oil circuit breakers are given below : Sl No Item of Maintenance Periodicity Remarks 1. Checking of oil leakage from guage glass, drain valve and other joints Daily 2. Testing of oil sample for dielectric strength Quarterly If the value is low oil should be replaced with fresh tested oil. Oil shall also be replaced after 12 trippings on fault or as per recommendations of manufacturer. Oil filling instructions given by the manufacturer shall be followed. 3. Measuring IR values across contract with breaker off and pole to earth with breaker on Quarterly Note:Before closing MOCB on a fault, the operator should ensure that adequate oil level is available in the breaker by observing the gauge glass and if adequate oil is not available, the breaker should not be test charged. 4. Checking the Br. Level with spirit level Yearly
5.20 O & M of Distribution Transformers Following maintenance schedule is recommended for distribution transformers.
Sl No Item of Maintenance Periodicity 1. Cleaning of bushing and external surface of tank cooling pipes Monthly 2. Checking of oil levels in the conservator and gauge glass Monthly 3. Checking of the breather and replacement if necessary Monthly 4. Checking of oil level in the oil seal of breather and top up if necessary Monthly 5. Checking of HG fuse & L.T fuse and renew if necessary(correct gauge shall be maintained) Checking breaker operation in case of CSP transformer. Monthly 6. Checking of vent pipe diaphragm Monthly 7. Checking of terminal loose connections if any and tightening the same Monthly 8. Checking for any oil leaks & rectification (including replacement of oil seals if required) Monthly 9. Taking long tester reading during peak load hours and remedial action whenever load exceeds 80% rated capacity Quarterly 10. Noting down neutral currents and load balancing in the three phase Quarterly 11. Measurement of IR values Half yearly 12. Testing of oil for BDV, acidity,water content Half yearly 13. Checking of lightening arrestors and replacement if required (preferably once before monsoon) Half yearly 14. Measurement of earth resistance checking of earth in system and rectification if required Half yearly 15. Tap Changer equipment During Transformer Maintenance 16. Overhaul of transformer One in 5 years
1.21 Guidelines for O & M of Control Circuits and Power Sources 1. In sub-stations lead acid storage batteries are normally used to supply D.C. power required for control and other auxiliary purposes. The following are the activities to be performed during O&M of auxiliary equipment. Cleaning of battery room Checking of proper functioning of exhaust system. Exhaust system should be in operation while charging of battery is in progress. Prohibit smoking, striking of match boxes or use of blow lamps or welding torches and display in this regard is intact in the battery room Avoid flange joints in the heating system in these rooms, 5% soda solution as spare be kept so as to neutralize splash of acid on the skin or clothing Use of canvas work gloves and apron is must. Use of small glass plates of slightly smaller size than inside dimension to cover open jars Glazing of windows with frosted glass to protect batteries from direct action of sunrays. Use acid paint to paint walls, ceilings and metal parts and accessories. Check specific gravity of the electrolyte at the bottom and top of the battery cells once every quarter. Boost charging of the battery once in three months/as per manufacturer recommendation. Monitor the voltage conditions and specific gravity (once a month). Regular inspection of the battery room/battery daily/weekly for
Visual checking of battery room, ventilation and lighting(daily) Checking of electrical connections for tightness (weekly) Application of petroleum jelly to joints and cell connections (weekly) Complete intactness of the jars (daily) Level of electrolyte and topping of jars with DM water (weekly) Correct position of the plates (daily) No leaks (daily) Clean the jars, stands, walls and floors (daily) Specific gravity measurement of pilot cell (daily) Voltage reading of pilot cell (daily) Indentification of lagging cells(low specific gravity cells) (daily) Look for white spots (sulphation) buckling or short circuiting of plates (daily) Traces of corrosion (daily) Mud in the bottom of the jars (daily) Checking electrolyte temperature(random cells) (daily) Checking operation of rectifier (daily)
1.22 Time interval for preventive maintenance of sub-station equipment. 1. Preventive maintenance tests are to be carried out on the sub-station in accordance with the rules and standards covering each kind of equipment. The intervals at which they should be carried out depend on number of factors such as, number of trippings , quality of earlier maintenance of equipment, severity of faults occurred etc .However the following interval is generally recommended Circuit breakers, insulators, earthing , no load disconnectors and their operating mechanism as a rule are tested following each general overhaul (but intervals no longer than 3 years)
Dry type reactors, carrier frequency coupling capacitors,power factor correction capacitors and oil immersed instrument transformer must be tested at least once every three years. Busbars etc. must be tested/maintained once a year. Transformer inspection must be carried out disconnecting the units from the line and are timed for the following frequency: (a) In permanently attended sub-stations the maintenance and service transformer must be inspected once every day, all the other transformer once every five days. (b) In unattended sub-station all the units must be inspected once a month (c) In small transformer sub-station and kiosks all the units are inspected at intervals not longer than 6 months.
2. During the above inspection, check must be made for oil leaks at the joints, oil cocks and radiator etc. for bad or defective joints in the bushing and for signs of chipping cracks or flashover on the bushings porcelain. Other abnormality that can be detected by external inspection are : loud and irregular noise crackling sounds from within the transformer Oil discharge through the diaphragm of the relief vent High and rising oil at normal load
5.23 O & M of Relays It is essential to test protection equipment on site in order to ensure the following : That the relays are correctly installed. That the relay equipment has not been damaged during transit and that any packaging restraint has been correctly removed. That the relay equipment is correctly connected and wired up in accordance with the approved drawing. That the relays and associated trip coils operate within the required margins and are set to required settings.
5.23.1 The following checks are required to be made on relays & associated circuitry: Physical check on all wiring and connections Check on all fuses, MCBs, links, test switches and earthing terminals etc. Proper earthing of relay cases Polarity of DC supply Cleaning of relay cases or racks for dirt etc. Insulation resistance measurement on all DC and AC circuits Secondary current and voltage injection tests Checks for correct setting of relays Directional tests in case of directional relay Any other tests based on manufacturer recommendation for various types of relays 5.23.2 Periodicity of tests may be decided based on manufacturers recommendation, site conditions, number of operations, trouble in operation etc. However, these tests should be carried out at least once in six months.
5.24 Typical transformer, on load tap changer and sub-station maintenance inspection report are given in Annexure-PEVOM1 to Annexure-PEVOM4. These appendix are general guidelines.However it is recommended that manufacturer recommendation and relevant ISS/BS/IEC must also be referred to. 5.25 Premonsoon inspection This is done before the onset of monsoon which is the severest operating season for the overhead lines. Inspection must be done by climbing each support after making the lines dead and effectively earthing them. Defects are rectified preferably then and there to ensure a satisfactory performance during monsoon. All the points enumerated under ground patrolling are to be effectively tested, the check being visual at close quarters as well as by handling of the equipment. Items involving special methods of inspection are enumerated below. Insulators, conductors and fittings : i) Check insulators for cracks by ringing methods (with a wooden hammer), use meggar methods wherever possible. A check for defects concealed by the binding. Check condition of stiffner and armour tape covering in the case of Aluminium conductor pin bindings. ii) Check condition of the conductor within the suspension clamps by removing the conductor from the clamp by means of a chain or rope blocks in case of heavy conductors and any broken strands in the outer layer resulting from vibration will then be apparent. Check the condition of inner layers of conductors at the suspension clamp for break in strands due to conductor vibrations. To do this the conductor is gripped by the suspension clamps at a point 8 or 9 inches from normal position and a twist is applied by means of a special wooden level fixed to the conductor at the corresponding position on the opposite side of the normal position of the clamp. Two or three fractured Aluminium strands in the case of heavy conductors after a number of years of service would not call for immediate action, although the fact must be carefully recorded to ensure that a further check is made at the next inspection. In the case of small size conductors it is desirable to replace that section of the conductor and a new length inserted with a joint on each side of the clamp. When fractured strands are found a special examination of the vibration dampers is made on the tower affected and on those immediately adjacent, and if all are found in good order, it may be assumed that the vibration in those spans is such that additional dampers are necessary. Inspect parallel groove clamps for signs of bad contact. Slight burning can be dealt with by wire brushing the conductors and the grooves of the clamps, the whole being reassembled after applying grease having a high melting point to the conductors and the clamps, new clamps must be fitted and, if the jumpers are long enough, the conductors may be shortened by cutting off the burned ends. Where this is not possible owing to clearances being too far reduced, one of the spares must be lowered and a new piece of conductor joined to provide a new jumper of sufficient length. If this is not possible in the time available, a short length of conductor may, as a temporary expedient, be inserted in the number itself by using two parallel groove clamps, but the work necessary to eliminate the second clamps should be undertaken. Check condition of eye botls, hooks, shackles, pins, links, etc., of the insulator and conductor fittings as a result of conductor swing especially on lines in exposed location running at right angles to the direction of prevailing winds, and for rust and corrosion. Vibration dampers, Replace dampers if sagging of weights is noticed in the case of stock bridge type dampers and looseness of weights at the stacks in the case of other type of dampers. Tighten loose clamping bolts. Conduct/Examine conductor in mid-spans for broken stands. Temporary repair can be carried out by binding with copper wind in case of copper conductor or aluminium tapes in case of ACSR conductor.When a large number of strands are broken ,or when the steel core, in case of ACSR conductor , is damaged, a new length must be inserted. Check ACSR conductor for corrosion which has spread to inner strands in the case of coastal areas due to salt spray penetrating the aluminium strands and setting up an electrolytic action between the steel core and the aluminum in contract with it. The conductor should be replaced as early as possible in this case. When corrosion is limited to outer strands only, as is usual in industrial areas, it is rarely so serious as to warrant the replacement of the conductors before the years of anticipated life have lapsed.. II. Pole mounted; secondary Distribution sub-station : The annual maintenance of the sub-stations may be carried out during the pre-monsoon inspection as per the approved schedule of maintenance.
5.26 Maintenance of lines Pre-monsoon inspection of all 33 kV lines have to be completed between January and March every year under the supervision of the S.D.O /Deputy Manager duly obtaining approval for pre-arranged shut downs for the entire programme. The staff carrying out the pre-monsoon inspection should carry all the T&P like, ropes, Petroleum Jelly, cotton waste and sufficient O&M materials like insulator, discs, nuts for the pins, binding wire etc. The tree clearance shall be done, and all the minor defects like (1)damaged insulators(2) improper pin binding (3) Loose jumpering (4) loose stays shall be rectified during the inspection itself. All the insulators shall be cleaned with the dungry cloth. All the A.B switches shall be lubricated and defective blades replaced. The defects which may take considerable time for rectification shall be noted down(Such as insertion of poles, replacement of damaged conductor, replacement of damaged supports etc) and attended within the next one week, properly programming. Periodical patrolling of 33 kV lines are to be done monthly by the area L.I The patrolling shall also be done and suspected defects rectified by the area L.I, whenever the line trips on fault. The 33 kV break downs are to be attended under the personal supervision of the S.D.O/deputy Manager. 1. The pre-monsoon inspection of 11 kV lines are to be carried out under the personal supervision of the Section Officer. 2. All the steps mentioned in that of 33 kV lines are to be taken while carrying out the inspection. 3. The periodical patrolling every month and the patrolling whenever trips on fault, shall be carried out by the area maintenance staff under the supervision of the L.I. 4. The 11kV breakdowns are to be attended under the personal supervision of the Section Officer. L.T. Lines. 1. The pre-monsoon inspection of the L.T lines are to be carried out by the area lineman, duly monitored by the L.I. 2. All the steps mentioned in that of 33 kV lines are to be taken during the inspection. 3. The L.T lines are to be patrolled and defects rectified by the area LM/ALM/JLM, whenever the section fuse/HG fuses blow off frequently. 4. The area LM/ALM/JLM is responsible for providing spacers, wherever, loose spans are observed. 5. The rectification of loose stays, insertion of poles in the lengthy spans etc. have to be programmed by the L.I/Section Officer and completed in a limited frame of time. 5.27 Procedure for Permit to Work(Line Clear) A Line Clear is a permit to work on any electrical equipment or line. It will be issued by an authorised person to another authorised person. If there are more than one gang working under the same supervisor, each gang should take sub-line clears from the supervisor who has taken the line clear.In case, if the line clear has to be issued for himself, he shall take self line clear. In this case also, all the precautions that are to be followed in issue and return of line clear shall be followed. Line clear books are very important records. Pages in these books should be serially numbered, no paper from this book should be used for any other purpose. If any, page is to be destroyed, the custodian should specifically mention the reasons for doing so. It should be attested by his dated signature. The line clear books shall be reviewed periodically by the Asstt. Divisional Engineer. Line clear can be issued/received over telephone. It is desirable that the issuer/receiver recognises each others voice. The requisition for line clear and the line clear issue messages shall be repeated by both the parties to ensure that line clears are issued/received on the equipment on which it is intended. A secret code number shall be followed in such cases. Procedure before issue of Line Clear i) Approval of the competent authority for shut-down of line/equipment should be verified. ii) Line/equipment shall be switched off. iii) No back feed certificates, wherever necessary shall be obtained. iv) The issuer should personally see and ensure that all the blades of the AB Switch are physically in open condition and locked. v) The line/equipment shall be earthed by discharge rods. vi) A Danger Do not operate Board shall be exhibited on the Concerned control panel a Men on line board shall be exhibited on the outdoor AB/Switch/equipment. vii) All operations for issue of line clear shall be done personally by the issuer or it shall be done under his personal supervision. viii) After following all the precautions the Line clear book shall be filled up carefully without leaving any column left unfilled. It shall be signed with date and time by the issuer and issued to the receiver. Signature with date and time of the receiver shall be obtained on the duplicate, and this shall be kept in safe custody Responsibilities of the receiver: i) The receiver should very clearly indicate the specific equipment/line which he wants to work when requisitioning for L.C. ii) If the receiver is at the same place as that of the issuer he shall follow all the operations being conducted so as to ensure that line clears are being issued on the correct line/equipment. iii) At the work spot, after receiving line clear, he shall earth the line/equipment on either side of the workspot. iv) In case if any other power lines are crossing near to work spot of the line on which LC is received he shall also obtain LCs on all such lines to avoid induction. v) He shall write down on the duplicate form the number of persons engaged on the work. Rules to be followed when returning of LC: i) The persons who has received the LC only should return it. ii) He shall personally ensure that there are no men, material or earth on the line. iii) He shall inform all the workmen that it is no longer safer to work on the line as the line clear is being returned. iv) The Line/equipment shall not be charged until the LC is cancelled. Before cancellation of LC the following precautions shall be taken: a) The returned LC shall be carefully examined.It shall be ensured that all the certificates required are furnished. b) Men on Line Danger do not operate boards shall be removed. c) It shall be ensured that no other LC is pending. All men material removed; Earthing is removed. d) All no back fed certificates shall be returned. e) After charging the line/equipment check should be made for unusual sound/noise. f) All the workmen/supervisor shall be permitted to leave the work spot only after the normalcy is restored.
5.28 Line Maintenance Through Hotline Techniques. 1. Hot lines maintenance of lines mainly deals with the maintenance of energised line without any interruption to the power from Low Voltage line to Ultra High Voltage line. Equipment or machinery suffers from minor ailments, which leads to major breakdowns.These breakdowns can be attended by adopting Hot Line Maintenance Techniques without taking the shut down. 2. Maintenance Methods Following are the methods adopted by some of the Electrical Utilities for maintenance in Transmission and Distribution System. i) Pre-arranged shutdown methods after identifying the faults ii) Sudden faults developed as breakdowns and rectification is a breakdown maintenance. iii) Preventive Hotline maintenance.
3. Broadly there are two types of techniques at present in use. i) Hot Stick Technique ii) Bare Hand Technique.
Hot Stick Technique : Hot Stick Technique can be used from 11 kV to 220 kV lines where as bare Hand Methods is a must for Ultra High Tension lines i.e. from 400 kV and above. APTRANSCO of Andhra Pradesh is using Bare Hand Techniques for the preventive maintenance of 132 kV and 220 kV EHT Lines and Sub-stations .BBMB is using Hot Line Technique for 220 kV and below. Epoxy Glass made stick of high Mechanical and Dielectric strength, wrapped inside a foam material is used for tying or untying the insulator bindings. Wire Tong holds the conductor or jumper and move them for a safe clearance of the maintenance crew. Flexible wrench-By fixing the suitable sockets of the required size, the bolt and nuts, of pad clamps, T clamps etc. can be tightened or loosened. For these Hot Sticks different suitable metal heads are fitted for carrying out number of operations like changing of broken insulators, flashed over insulators and all the connected parts of tension and suspension points of the live lines without interruption to the power or without availing any shutdown. And also tightening or loosening of cut point jumper bolt and nuts, replacing vibration dampers, replacing suspension shoe clamps etc., of the EHT Lines and Lifting up of the conductors, changing of cross arms up to 11 kV and 33 kV can be carried out by this Hot Stick Method. Bare Hand Technique : Bare Hand Technique means to charge a person to the required voltage level on an insulated platform either by traversing the person by insulated ladder or by raising through an insulated boom, and carrying out the work on charged line with Hands. The chargeable person will wear a conductive suit comprising of cotton, asbestos and stainless steel threads, along with conductive shoes of copper threaded carbon sole with conductive socks and conductive hand gloves. Total continuity will be maintained from Head of Toe covering the head with hood except the face. The Bare Hand Technique is not a single man operation, it requires both Hot Stick Method as explained previously and a bare hand person. By this Bare Hand Technique damaged Bus jumpers, T Clamps, isolator pad clamps, female contacts are being replaced without the interruption to the bus bars, and conductor damages also being attended when sufficient clearances are there for operation. By adopting this Bare Hand Technique lot of problems like taking Bus shut downs, line clear etc. can be avoided and there by saving lot of time and revenue as also interruptions. While making the project proposals these maintenance tools are required to be procured. 5.29 Guidelines for operation of Capacitors. 1. The status of the capacitor would be determined by the voltage at the highest voltage bus available at the substation subject to the maximum permissible voltage at the bus on which the capacitor bank is connected and the loading factor i.e. ratio of the total MVA load on the bus at which the capacitor is installed to the MVAR rating of the capacitor. 2. Accordingly, the switching on/off of the capacitor bank would be done as per the following table: Voltage of highest level at the substation(kV). Above Between Below 230 230-220 220-215 215-205 205(For 220 kV level) 140 140-132 132-128 128-122 122(For 132 kV level) 70 70-68 68-65 65-60 60(For 66 kV level) 30 35-34 34-32 32-30 30(For 33 kV level) Loading factor
Loading factor Above 2 Off Status-Quo On On On 1 to 2 Off Off Status-Quo On On Below 1 Off Off Off status-quo On
LV bus voltage should be controlled by changing transformer taps.
3. Notwithstanding the above, if the voltage at the bus on which capacitor is connected is 1.1 per unit or higher, the capacitor will be switched off. 5.30 A routine check of the capacitor performance is to be made by measuring current with the help of Ammeter /Tong tester once in two months and maintain the record. If any reduction in current /failure of capacitor is noticed, supplier/manufacturers must be contacted immediately and replacement of capacitor be initiated.