You are on page 1of 5

Revision No : 3

Projek :- PMU TUNJANG


Building :-
No Drawing :-
Element :-
EXCAVATION, CONCRETE, FORMWORK, FILLING & LEAN CONCRETE
Loc/Area typ nos High grd High length Width Exc (m3) LeanConc (m2) Conc (m3) Fwk (m2) Filling (m3)
Excavation 59.880
Lean Concrete 31.880
concrete 19.591
FORMWORK 84.750
Total : - 31.880 19.591 84.750 -
Prepared & Verified by: Checked by: Verified by:
Contractor Consultant's C.O.W/ Representative TNB Project Engineer
Signature: .. Signature: Signature:
Name: Name: .. Name: ..
Staff No.: . Staff No.: ..
Date: .. Date: Date:
Revision No : 3
Projek :- PMU TUNJANG
Building :-
No Drawing :- 0
Element :- SUMMARY
Loc/Area typ Exc (m3) LeanConc (m2) Conc (m3) Fwk (m2) Filling (m3) Plaster (m2) Paint (m2)
Painting Plinth (7-16) 130.200
Total - - - - - - -
Prepared & Verified by: Checked by: Verified by:
Contractor Consultant's C.O.W/ Representative TNB Project Engineer
Signature: .. Signature: Signature:
Name: Name: .. Name: ..
Staff No.: ..
Date: .. Date: Date:
SCHEDULE/TAKING-OFF SHEET OF MILD/HIGH TENSILE STEEL BAR REINFORCEMENT
JOB NO. : PMU TUNJANG HEADING : SHEET NO. :
ELEMENT NO. : CABLE TRENCH DESCRIPTION : DRAWING NO. : Revision No : 3
a b c d e f Total 8mm 10mm 12mm 16mm 20mm 25mm 32mm
CABLE TRENCH
Sloping landing slab - - - - - - - -
(A) Y12-200c/c (t/b) 12 1 2 12 0.500 2.600 1.200 0.100 105.600 - - 105.60 - - - -
(B) Y12-200 c/c horizontal (t/b) 12 1 2 14 2.160 60.480 - - 60.48 - - - -
section 5-5 (as EI08) - - - - - - - -
horizontal - - - - - - - -
( C ) Y12- 200c/c (t/b wall) 12 2 2 10 0.100 2.500 0.100 108.000 - - 108.00 - - - -
( D ) ditto side wall 12 2 2 4 0.100 2.500 0.100 43.200 - - 43.20 - - - -
( E ) Y12- 200c/c (t/b slab & coverl) 12 2 2 14 2.160 120.960 - - 120.96 - - - -
( F ) ditto side wall (both side) 12 2 1 14 0.633 1.150 0.633 67.667 - - 67.67 - - - -
( F ) ditto side wall (int - both side) 12 2 1 14 0.433 1.000 0.433 52.267 - - 52.27 - - - -
Trench under road - - - - - - - -
Based slab - - - - - - - -
( G ) t/b T12-150 c/c 12 2 1 99 0.188 2.100 0.188 490.050 - - 490.05 - - - -
( H ) t/b T12-150 c/c 12 2 1 16 8.400 268.800 - - 268.80 - - - -
( J ) 4T16 16 2 1 4 8.400 67.200 - - - 67.20 - - -
side wall - - - - - - - -
( K ) T16-150 c/c 16 2 1 99 0.15 1.625 0.633 476.850 - - - 476.85 - - -
( L ) T16-150 c/c 16 2 1 99 0.15 1.575 0.200 381.150 - - - 381.15 - - -
( M ) T12-200 c/c 12 2 2 6 8.400 201.600 - - 201.60 - - - -
- - 1,518.62 925.20 - - -
0.395 0.616 0.888 1.579 2.466 3.854 6.313
- - 1,348.54 1,460.89 - - -
2,809.43
Prepared & Verified by: Checked by: Verified by:
Contractor Consultant's C.O.W/ Representative TNB Project Engineer
Signature: .. Signature: Signature:
Name: Name: .. Name: ..
Staff No.: ..
Date: .. Date: Date:
TOTAL LENGTH FOR DIAMETER
Total Length:
Kg/m:
Total/Kg:
LOCATION SHAPE DIA. REPEAT
BAR NO. TOTAL
BARS
LENGTH OF BAR
SCHEDULE/TAKING-OFF SHEET OF MILD/HIGH TENSILE STEEL BAR REINFORCEMENT
JOB NO. : PMU TUNJANG HEADING : SHEET NO. :
ELEMENT NO. : CABLE TRENCH DESCRIPTION : DRAWING NO. : Revision No : 3
a b c d e f Total 8mm 10mm 12mm 16mm 20mm 25mm 32mm
CABLE TRENCH cont'd
Cover - - - - - - - -
( N ) t/b T10-230 c/c 10 2 1 9 7.560 136.080 - 136.08 - - - - -
( P ) T16-100 c/c 16 1 1 77 0.150 1.800 0.150 161.700 - - - 161.70 - - -
( Q ) T12-150 c/c 12 1 1 77 0.950 1.800 0.950 284.900 - - 284.90 - - - -
( R ) T12-200 c/c 12 1 1 77 0.450 0.550 0.900 0.550 0.450 223.300 - - 223.30 - - - -
section 2-2 opening for MH cover
(EI05)
- - - - - - - -
( S ) 4T20 - ring beam 20 1 1 4 0.200 0.810 0.200 4.840 - - - - 4.84 - -
( T ) T10-200 c/c link 10 1 1 21 0.230 0.250 0.230 0.250 20.160 - 20.16 - - - - -
( U ) T16-100 c/c 16 1 1 9 0.200 0.800 0.200 10.800 - - - 10.80 - - -
( V ) t/b T10-230 c/c 10 2 1 4 0.840 6.720 - 6.72 - - - - -
( W ) T12-150 c/c 12 1 1 7 0.950 0.875 0.125 13.650 - - 13.65 - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- - - - - - - -
- 162.96 521.85 172.50 4.84 - -
0.395 0.616 0.888 1.579 2.466 3.854 6.313
- 100.38 463.40 272.38 11.94 - -
848.10
Prepared & Verified by: Checked by: Verified by:
Contractor Consultant's C.O.W/ Representative TNB Project Engineer
Signature: .. Signature: Signature:
Name: Name: .. Name: ..
Staff No.: ..
Date: .. Date: Date:
Total/Kg:
LOCATION SHAPE DIA. REPEAT
BAR NO. TOTAL
BARS
LENGTH OF BAR TOTAL LENGTH FOR DIAMETER
Total Length:
Kg/m:
SCHEDULE/TAKING-OFF SHEET OF MILD/HIGH TENSILE STEEL BAR REINFORCEMENT
JOB NO. : PMU TUNJANG HEADING : SHEET NO. :
ELEMENT NO. : CABLE TRENCH DESCRIPTION : DRAWING NO. : Revision No : 3
COLLECTION PAGE
8mm 10mm 12mm 16mm 20mm 25mm 32mm
- - 1,348.54 1,460.89 - - -
- 100.38 463.40 272.38 11.94 - -
-
-
- 100.38 1,811.94 1,733.27 11.94 - -
3,657.53
Prepared & Verified by: Checked by: Verified by:
Contractor Consultant's C.O.W/ Representative TNB Project Engineer
Signature: .. Signature: Signature:
Name: Name: .. Name: ..
Staff No.: ..
Date: .. Date: Date:
PAGE 1