Insulation works

Cost of labour
Total area to be insulated 0.00 m2
Production per day 55 m2
Total crew = 1fab+1 fitt+2 helpers 4 nos Hours per day
Number of days required 0.0 Rate per hour
Total manhours required 0.00 hours
Cost of labour 0.00 AED
Cost of materials M2 Wastage Rate per m2 Wastage
Area of 75mm thick insulation 0.00 2% 0.00 AED 102%
Area of 40 mm thick insulation 0.00 10% 0.00 AED 0%
Area of 25mm thick insulation 0.00 10% 0.00 AED 0%
Total cost of materials
Rate of accessories 5.00 AED/m2
Total cost of accessories 0.00 AED
Total material dry cost 0.00
Overhead 10% 125%
Cladding works
Total area to be cladded 15000.00 m2
Production per day 75 m2
Total crew = (1fab+2 fitt+2 helpers)*3 10 nos Hours per day
Number of days required 200.0 Rate per hour
Total manhours required 18000.00 hours
Cost of labour 378000.00 AED
Cost of materials
Total area including 0.00 m2
Cost of sheet per m2 0.00 AED/m2
Cost of sheets 0.00 AED
Cost of accessories 0.00 AED
Total cost of materials 0.00 AED
Costing sheet
Installation cost 378000.00 AED (20% OH included)
Cost of mobilisation 15000.00 AED Including transportation
Omanisation 3600.00 AED
Contingency 11340.00 AED
Engineering cost + accessories 11340.00 AED
Food and accm backcharge 120000.00 AED
Tranportation 70000.00 AED
Total cost of project 609280.00
Overheads 121856.00 AED
Net total 731136.00 AED
Final rate 5.099 OMR/m2
76478.66
12600
3000
92078.66
8 hrs
19 AED
Total 0
0.00 0
0.00 0
0.00 0
0.00 AED
Insulation works
Labour #DIV/0! AED/m2
Material #DIV/0! AED/m2
9 hrs
21 AED
Cladding works
Labour 25.20 AED/m2
Material 0.00 AED/m2
tr 10000
Area Rate Amount
Ductlines 15000 5.200 78000
Pipelines 3000 4.300 12900
Valve boxes 300 10.000 3000
total 93900