Table 1 : Job process for Mixing Pond 2 and Tanks operation.

7. Go down from Biogas Tanks.


6. Open the gas outlet valve/close vent-off
valve of Biogas Tanks.
5. Monitor the Tanks pressure.
4. Go up to the Biogas Tanks .
3. Monitor Influent flowmeter.
2.Turn On the Feed Pumps System at Mixing
Pond 2 and Feed Tank.
1. Go Into The Biogas Digester Tanks Area.
Table 2 : Job process for Biogas Pre-Treatment operation.





7. Topup scrubber chemical when necessary
6. Monitor gas level (H2S/CH4/pressure)
and scrubber quality
6.Start the Gas Blower
5. Start the chiller system
4. Start the Scrubber System
3. Go down from Biogas Tank.
2.Open the gas outlet valve.
1. Go up to the Gas Buffer Tank.
Table 3 : Job process for Biogas Engine operation.

11. Stop gas engine after cooling
10. Monitor Gas engine Operation
9. Close Gas outlet after Gas Moisture
Separator
8. Switch Off Starter
7. Switch On Starter/Start Pre-Oil/Start the
Engine
6. Manual Pump Engine Oil
5. Open Gas outlet after Gas Moisture
Separator
4. Check gas pressure
3. Switch On the Biogas Engine Control
Panel
2. Connect the starter battery.
1. Go into the Biogas Engine room