S.

No SCOPE
1 4 NOS OF PSD FIXING AND COMMISSIONING IS BALANCE FOR BREAKERS. SIEMENS
2 LEAKAGE IN NEUTRAL BUSHING OF SHUNT REACTOR -2 NEED TO BE REPLACED.
SIEMENS
3 LEAKAGE FROM BELLOW IN TOP OIL HEADER NEED TO REPLACE IN SHUNT REACTOR-2. SIEMENS
4 ACDB CONTROL CKT IS NOT IN SERVICE. SIEMENS
5 SWITCHYARD TRANSFORMER -2 IS NOT COMMISSIONED AND CHARGED. SIEMENS
6 EMERGENCY DISTRIBUTION BOARD PANEL IS NOT COMMISSIONED AND CHARGED. SIEMENS
7 LEAKAGE IN AC KIOSK -1 NEED TO RECTIFY WATER ENTERS DURING THE RAIN. SIEMENS
8 FIRE DETECTION SYSTEM OF AC KIOSK IS NOT COMMISSIONED. SIEMENS
9 FIRE FIGHTING SYSTEM OF SWITCHYARD AND CONTROL ROOM IS NOT COMMISSIONED .
NEWFIRE
10
VENTILATION FANS OF SWITCHYARD CONTROL ROOM IS NOT COMMISSIONED(CABLING AND
TERRMINATION BALANCE).
STERLING
WILLISON
11
SWITCHYARD AREA DRAINAGE SYSTEM NEED TO BE THROUGH, HEAVY WATER LOGGING IS
OBSERVED IN CABLE TRAYS SIEMENS
12 4CP3 & 4CP4 PANEL CIRCUIT CHECKING FOR UNIT #2 ARE PENDING SIEMENS
13 UPS-1 IS ALARMING AT EACH 10 SECONDS NEED TO RECTIFY THE FAULT
SIEMENS
14
PERMANENT DATA COMMUNICATION SYSTEM BY COMMTEL COMMISSIONED BUT REPEATION
OF ANALOG IN PATICULARLY IN ANALOG SET AND ANALOG IS NOT CHANGING EVERY 10
SECOND SIEMENS
15 SCADA SERVER NOT COMMISSIONED PROPERLY AS PER MOM, IT HANGS FREQUENTLY SIEMENS
16 AC OF KIOSK 3 NOT WORKING SIEMENS
17 DIA 3 BAY 404-52 SF6 LOCKOUT AND LOSS OF SF6 INDICATION SIEMENS
18 DIA 3 BAY 405 BAY NOT IN SERVICE SIEMENS
19 SIEMENS HAS TO TAKE THE DAMAGED CVT BACK AND SUPPLY 2NO OF CVT (4400pF ,8800pF)
SIEMENS
20 OWS 2 IS NOT OPERATING AND UNIT2 SCADA NOT COMISSIONED SIEMENS
21 DCDB CONTROL CIRCUIT (220V & 48VOLT ) NOT COMISSIONED SIEMENS
22 AMMETER & VOLTMETER OF 220VOLT BATTERY CHARGER ARE FAULTY SIEMENS