Tie in Planning
Tie in Planning
- Unit Number
- Issue Date
- Issue Description
- Prepared By (name)
- Checked By (name)
- Approved By (Name)
A Tie-In List Data area should (or may) have the following:
For the new line: [indicates responsibility]
- Tie-In No. [piping]
- P&ID No. [piping]
- Piping Plan No. (new) [piping]
- Tie-In Iso. No. (if different than Line Number)[piping]
- Line No. [piping]
- Conn. Type [piping]
- Commodity [piping or process]
- Oper. Press. (this should be the same as the existing line so you do not need it twice)[piping or
process]
- Oper. Temp. (this should be the same as the existing line so you do not need it twice) [piping or
process]
- Test Media [piping]
- Test Press. [piping]
- NDE Req'd. [piping]
For existing line being tied into:
- Exist. Piping Plan [piping]
- Exist. Line No. [piping]
- Exist P&ID [piping]
- North Coord. [piping]
- East (or West) Coord. [piping]
- Center line Elev. [piping]
Construction:
- Pre-weld Inspection [welding engineer]
- Welding Comp/tested [construction]
Schedule Data:
- Req'd Complete Date [Client]
- Schedule Shut-down [Client]
- Completion Client Sign-Off [Client]
Other:
-