Team #1:
Main Concerns
Timing/Scheduling
Predecessors
Start/End Dates
Budget
Absolutely cant miss date of opening
night January 13th, 1994
Students and building not always
available
Critical Path #1
Recommendations
Hire Master Builder
Shortens set build time by a week
Adds $80/day in cost
Was in last years budget
Conclusions
Recommended changes are
necessary, or else show will not be
ready for opening night
No further changes will make new
critical path any shorter
Questions?