Professional Documents
Culture Documents
Heat Treatment Manual Nov 2010
Heat Treatment Manual Nov 2010
INDEX
Sl.No.
01
02
03
04
05
06
07
08
Description
Cover Sheet
Index
Preface
Foreword
Approval Sheet
Important Note
Status of Amendments
Table of Contents
Page No.
01
02
03
04
05
06
07
08
IMPORTANT
THIS HEAT TREATMENT MANUAL PROVIDES BROAD BASED GUIDELINES FOR
HEAT TREATMENT WORK AT SITES. HOWEVER, SITES MUST ENSURE
ADHERENCE TO THE PRIMARY DOCUMENTS LIKE CONTRACT DRAWINGS,
ERECTION
WELDING
SCHEDULE,
PLANT
CORPORATE
STANDARDS,
CONTRACTUAL
OBLIGATIONS,
IF
ANY
AND
SPECIAL
STATUS OF AMENDMENTS
Sl.No.
Description
Remarks
TABLE OF CONTENTS
Chapter
Description
Page No.
8 - 23
24 - 25
General
26
1.
27
2.
Pre heat & PWHT of Critical Piping with Turbine & Auxiliaries
28 - 29
30
CHAPTER-1
HEAT TREATMENT PROCEDURE - BOILER AND AUXILIARIES
1.0
PURPOSE:
1.1
This procedure provides information, method and control for Pre-Heat, Post Heat and
Post Weld Heat Treatment (PWHT) of welds at sites.
2.0
DOCUMENT:
2.1
2.1.1
ASME Sec.I
2.1.2
ASME B31.1
2.1.3
2.1.4
AWS D1.1
2.1.5
Welding Manual
2.2
Contract drawings
Erection Welding Schedule or equivalent
2.2.1
Where parameter for Pre-Heat ,Post Heat and PWHT are not available in the primary
documents, reference may be made to this procedure.
2.2.2
Where such parameters are not contained either in the primary documents or in this
procedure, reference may be made to Manufacturing Units.
3.0
PROCEDURE:
3.1
Pre Heating :
3.1.1
When parts of two different thicknesses are welded together, the preheating requirements
of the thicker shall rule
10
3.1.2 When parts of two different P numbers are joined together, the material requiring higher
preheat shall govern (please refer Welding Manual for P numbers).
3.1.3
3.1.4
In case of any power interruption during welding, the joint shall be wrapped with dry
thermal insulating blankets to ensure slow and uniform cooling. Requirement of
uninterrupted power supply shall be ensured for materials like P-91, T-91 &
BS EN 10025
3.1.5
3.1.5.1 Preheating & Post Heating shall be applied by any of the methods given below:
a.
b.
Induction heating
c.
3.2
3.2.1
The method shall be by locally heating a circumferential band including the entire weld
and adjacent area of base metal, by induction or electrical resistance heating.
3.2.2
When heat treating welded joints in components in the boiler proper, width of the
heated circumferential band (W) on either side of the weld, W = 3 times the width
of the widest part of the weld groove but in no case less than twice the width of
weld at reinforcement.
b.
When used in post weld heat treatment in sections - W = 3 times the plate
thickness.
c.
For nozzle and other welded attachments - W must be wider than the nozzle or
attachment or 3 times the wall thickness.
11
3.3.1
The weldment shall be free of grease, oil etc. prior to Pre-Heat / PWHT.
3.4
3.4.1
Post weld heat treatment temperature cycle shall be measured and monitored by use
of thermocouples with calibrated recorders.
3.4.2
3.4.3
Where the soaking temperature is found to be lesser than specified, the PWHT cycle
shall be repeated.
3.4.4
In case of interruption during PWHT, the following actions are to be taken, depending
on the stage during which interruption occurred.
a.Interruption during heating cycle:
-
The joint can be treated subsequently for the balance left over soaking
period.
3.5.1
Thermocouples shall be used for recording Post Weld Heat Treatment temperatures.
12
3.5.2
3.5.3
b.
For other type of t/c: Insert the elements in a SS tube of internal diameter
approximately 6 mm. Apply force on tube and crimp it. Place this t/c and weld the
crimped button to the pipe in area of interest. Do not weld the elements.
c.
Insulate the t/c leads suitably and protect t/c ends from direct radiation from
heating elements.
3.5.3.1 Where a bunch of closely placed tube welds (e.g. Super Heater / Reheater Coils)
require to be Post Weld Heat Treated, the same shall be grouped together as if they
form a single component.
3.5.3.2 In such cases attachment of a minimum of three thermocouples, two at the end tubes
and one at the middle is recommended.
3.6
Soaking Time:
3.6.1
Wherever not specified the soaking time shall be as per Tables I, II and III.
3.6.2
The following guidelines shall be used to determine the thickness and subsequent
selection of the soaking time of PWHT:
a.
For butt welds, the thickness shall be the thickness of the material at the weld.
For bar stock, the thickness shall be the diameter.
b.
c.
For partial penetration branch welds, the thickness shall be the depth of the
groove prior to welding.
d.
For repairs, the thickness shall be the depth of the groove as prepared for repair
welding.
e.
3.6.3
Soaking time is to be reckoned from the time temperature of the joint crosses the
recommended lower temperature of the cycle, to the time it comes down below the
same recommended lower temperature of the cycle.
3.7
3.7.1
Wherever not specified, the heating rate above 300C and cooling rate after soaking
upto 300C shall be as follows: This is applicable for all materials.
13
Thickness of Material
Maximum Cooling
Rate Upto 300C
25 mm
220C/hour
220C/hour
> 25 50 mm
110C/hour
110C/hour
> 50 75 mm
75C/hour
75C/hour
> 75mm
55C/hour
55C/hour *
Temperature Records:
3.8.1
All the heat treatment cycles may be controlled within 10C around the
midpoint of the recommended range of temperature for the material.
4.0
4.1
Prior to start of PWHT operations, a job card may be prepared including details of
weld reference, soaking time, soaking temperature, maximum rates of heating and
cooling, temperature recorder details, date of PWHT as per sample format.
4.2
On completion of PWHT the actual parameters shall be recorded on the job card.
4.3
5.0
5.1
Please refer Welding Manual vide document No. PSQ-WDM-COM for heat treatment of
welds in P-91 materials.
5.2
5.3 Please refer Welding Manual vide document No. PSQ-WDM-COM for heat treatment of
welds in T-91 materials
14
5.4
6.0
LIST OF TABLES:
Table-I Weld preheat and PWHT for tubes and pipes outside diameter 102 mm.
Table-II Weld preheat and PWHT for Boiler Header welds.
Table-III Weld preheat and PWHT for pipes outside diameter > 102 mm.
Table-IV P Number and Group Number for Base Materials.
Table-V Pre-heat and PWHT for Non-Pressure Parts including Structural.
Table-VI Preheat for Flame Cutting.
7.0
RECORDS :
7.1
15
Date : ________________________
Package : _____________________
Description : ___________________
1. Make : _____________________
2. Type : _____________________
3. Sl.No.: _____________________
Thermocouple Locations :
Minimum 2
d = 1.5 x t from weld centre
Heating Band = 6 x t
Insulation Band = 12 x t
Date of PWHT _________________
Start Time : ___________________
Required
Actual
Contractor
BHEL
16
Thickness
(mm)
Preheat C
PWHT C
P1 Gr 1& SA 106
Gr C (Note 1)
19
Nil
Nil
Nil
Nil
>9
Nil
620 - 650
13
Nil
Nil
> 13
80 (Note 2)
620 - 650
13
150
Nil (Note 3)
> 13
150
640 - 670
150
Nil (Note 3)
>8
150
680 -710
P15 E Gr 1
(Note 4)
All
220
750 770
P8
All
Nil
Nil
12 x 1M
All
220
730 - 760
P1 Gr 2
P3 Gr 1
P4 Gr 1
P5 A Gr 1
17
Thickness
(mm)
Preheat
C
Post Heating
C
PWHT
C
t 19
Nil
Nil
Nil
19 < t 5
Nil
Nil
595 - 625
25 < t 75
100
Nil
595 - 625
t > 75
150
Nil
595 - 625
t 9
Nil
Nil
620 650
19 < t 5
Nil
150
for 2 hours
620 - 650
25 < t 75
100
150
for 2 hours
620 - 650
t > 75
150
P4 Gr 1
All
P5 A (Note 1)
12 x 1M
P1Gr 1
P1Gr 2
150
150
for 2 hours
Nil
640 - 670
All
150
680 - 710
All
220
Nil
710-740
620 - 650
Note :
1.
All P5A headers shall be inter stage heat treated at 700 - 750C for 30 minutes
soaking prior to any cold straightening operation. In lieu of this, the straightening
can be done after final PWHT. Any P5A Header with weld thickness above
50mm requires inter stage H.T. at 700-750C for 30 minutes soaking minimum
(max. shall be limited to 2.5 minutes/mm of thickness).
2.
Soaking for PWHT shall be at the rate of 1 hour per 25 mm of thickest weld (but
not less than 30 minutes for carbon steel and 1 hour for alloy steel). Soaking
time for 12 x 1 M header material shall be 4 minutes per mm of the applicable
thickness with a minimum of 180 minutes.
3.
Seal welding of Hand Hole Plates, Radiographic plugs and Screws can be
carried out after final PWHT, provided the preheat is carried out as per the
table.
For P number and Group number refer Table - IV.
4.
18
P No. of
Material
P1 Gr 1
& SA106 Gr C
P1 Gr 2
& SA 106 Gr C
P4 Gr 1
TABLE - III
WELD PREHEAT AND PWHT FOR PIPES
OUTSIDE DIAMETER >102 mm
Stub and Attachment welds
BUTT WELDS
Note 1 & 2
Thickness
Throat 19 mm
Throat > 19 mm
Preheat
PWHT
(mm)
C
C
Preheat
PWHT
Preheat
PWHT
C
C
595 625
(Note
3)
19
Nil
Nil
Nil
Nil
Nil
>1925
Nil
595 625
Nil
Nil
Nil
595 625
Nil
>2575
150
595 625
150
Nil
150
595 625
Nil
>75
150
595 625
150
595625
150
595 625
Nil
Nil
Nil
Nil
Nil
Nil
620 650
Nil
>919
Nil
620 650
Nil
620650
Nil
620 650
Nil
>19
150
620650
150
620650
150
620 650
150
for 2
hrs
All
150
640670
150
640670
150
640670
Nil
150
680 710
150
680710
150
680710
250
for 2
hrs
All
220
750770
220
750770
220
750770
280
for 2
hrs
All
220
730760
220
730760
220
730760
280
for 2
hrs
Pipes
P5 A
Post
heat
C
Castings &
Nil
Forgings
P15 E Gr1
P15 E Gr1
+
P5 A
Note :
1.
Irrespective of the stub or attachment materials, the PWHT cycle shall be governed by the pipe
material.
2.
Throat shall be specified in the drawing. Wherever flanges are welded to pipes combined throat
shall be taken into consideration.
3.
19
4.
For butt welds of different P group combinations, PWHT temp. may be as follows:
P1 + P3
620 to 650C
P1 + P4
640 to 670C
P4 + P5A
680 to 710C
a.
For P1 & P3 materials soaking time shall be 1 hour per 25mm up to 50mm
thickness and 2 hours + 15 minutes for each 25mm thickness over 50mm.
b. For P4 & P5 materials, soaking time shall be 1 hour per 25mm up to 125mm
thickness and 5 hours + 15 minutes for each 25mm thickness over 125mm.
20
TABLE - IV
P NUMBER AND GROUP NUMBER FOR BASE MATERIALS
P.No
Grou
Common Name
p No.
Tubes
SA192
Carbon
Steels
P1
Pipes
SA106GRB
SA210GRA1
Plates
SA36
Forgings
Castings
SA266CL
SA216WC SA234
SA515GR55 1
A
SA352LC
SA515GR60
A
SA352LC
SA515GR65
Fittings
WPB
SA516GR55
SA516GR60
SA516GR65
SA210GRC
P1
P3
P3
P4
P5A
P15
1
2
SA106GRC
Carbon Steels
Carbon-Moly
Steels
CrMo Steels
SA209T1
SA515GR70 SA266CL
SA216WC SA105
SA516GR70 2
B
SA234
SA216WC
SA299
C
SA352LC
C
SA217WC
SA335P1
1
SA213T2
1CrMo/
SA213T12/
1CrMo Steels
SA213T11
2Cr1Mo Steels
SA213T22
9Cr1MoV Steels
SA213T91
SA335P2
SA387GR2
SA335P12
SA387GR12 SA182F1
SA217WC SA234
SA335P11
2
SA387GR11 SA182F1
SA335P22
1
SA387GR22 SA182F2
WP11
SA217WC SA234
SA335P91
2
9
SA387GR91 SA182F91
P8
P8
18Cr-8Ni Steels
WP12
SA234
WP22
SA234
WP91
E
Gr 1
WPC
SA213TP304
SA376TP304
SA240TP304 SA182F3
SA351CF
SA213TP304
SA376TP304H SA240TP321 04
SA182F3
3
SA351CF
H
SA213TP347
SA376TP321
SA240TP347 21
SA182F3
8
SA351CF
SA213TP347
SA376TP347
47
SA336F3
3M
SA351CF
H
SA213TP321
SA376TP347H
04
SA336F3
8M
SA351CF
21
SA336F3
10
SA351CF
25Cr-20Ni Steel
(Type 310)
SA240TP310 47
SA182F310 10M
SA351CK
20
Note : IS1239 & API 5L GR B Pipes, IS2062 Plates may be treated as P No.1 Gr No.1 material.
21
SA403
TABLE - V
PREHEAT AND PWHT FOR NON PRESSURE PARTS INCLUDING STRUCTURALS
P.No. of
Material /
Material
Specification
Gas Cutting
Welding
Thickness
(mm)
Preheat
C
Thickness
(mm)
Preheat
C
25
Nil
38
Nil
> 38 63
100
> 63
150
150
P1 / IS 2062
> 25
IS 8500
Fe 540
( Ceiling
Girder )
BS EN
10025 Gr
420 N
( Ceiling
Girder )
100
220
PWHT
C
595-625
a)All butt welds > 50
mm thick
b)Any welds to a
tension member
620- 650 ( Soaking
time 2.5 Mts. Per mm.
Minimum 120 Mins)
P4 Gr 1
All
150
All
150
P5 A
All
150
All
(Note 3)
150
680-710
All welds
(Note 4)
NOTE :
1.
All gas cut edges may be chipped off, ground or machined to remove the HAZ with
3mm minimum removal.
2.
Clip angles above 10mm, used for beam connections, which are sheared to length,
shall require heat treatment.
3.
All fabricated structural components of P-4 material, with any member above
16mm thickness, the entire assembly shall be post weld heat treated.
4.
All welds of P5 A material shall be post heated at 250C for 2 hours immediately
following welding.
5.
TABLE - VI
PREHEAT FOR FLAME CUTTING
P.No. of Material
Thickness (mm)
Preheat C
P1 Gr 1
< 25
Nil
(Note 1)
25
100
All
150
All
150
All
150
All
150
P1 Gr 2
(Note 1)
P3
(Note 1)
P4
(Note 1)
P5 A
(Note 2)
NOTE :
1. For P1, P3 and P4 materials, when the flame cut edge will be machined
after cutting and when no forming operation is required after cutting, no
preheat is required for flame cutting.
2. P5 A materials, except when the part is scheduled for hot forming, shall
be inter stage heat treated at 680-710C for 30 minutes minimum after
flame cutting and prior to any welding. Subsequent to this heat
treatment, a minimum 3 mm of the gas cut edge shall be removed by
machining / grinding.
23
CHAPTER -2
HEAT TREATMENT PROCEDURE STEAM TURBINE, TURBO-GENERATOR AND AUXILIARIES
24
HEEP,
25
CHAPTER - 3
GENERAL
26
SCOPE :
1.1
This procedure details the method of batch testing of Temperature indicating Crayons
(Thermal chalks).
2.0
PROCEDURE :
2.1
Setup:
2.1.1
Rig a test heating arrangement including a test pipe/plate heating arrangements with
controls and a calibrated temperature recorder/thermometer.
2.2
Heat the test pipe / plate (specimen) to a temperature 10 lower than the rated
temperature of the thermal chalk in study, monitoring the temperature through
thermometer/recorder.
2.3
Stroke the thermal chalk as close to the sensing point on the specimen.
2.4
Raise the temperature of the specimen gradually up to 10% higher than the rated
temperature of the thermal chalk in study, stroking the thermal chalk on the specimen
during this period.
2.4.1
When the thermal chalk changes to the specified colour or melts (depending on the
type), within 5 of the rated temperature, the thermal chalk is acceptable.
2.5
Consistent results for 2% of any brand and temperature will qualify the brand for the
rated temperature.
2.6
Where thermal chalks are accepted brand wise, they shall undergo this test at least
once a year.
3.0
RETESTS :
3.1
Any failure in the 2% sample chosen, will call for additional 4% for qualification of the
brand for the rated temperature.
3.2
Where retest results in further non-acceptance, the brand shall stand rejected for the
particular temperature.
4.0
RECORDS :
4.1
27
SCOPE :
1.1
This
procedure
provides
for
checking
the
compatibility
and
accuracy
of
HT TEST SYSTEM :
2.1
2.2
2.0
PROCEDURE :
3.1
3.2
Raise the temperature of the test specimen to around 200 C and maintain the same.
3.3
Place the sensor of the direct reading thermometer as close to the thermocouple
junction as possible.
3.4
3.5
3.6
Repeat steps 3.2 to 3.5 for test specimen temperatures of 400 C and 600 C
3.7
3.7.1
Where the results are not within the tolerance specified above, further tests are to be
repeated to identify the fault either in thermocouple or compensating cable or both.
3.8
3.9
This compatibility is recommended for each of the thermocouple available for use; this
procedure validates the thermocouple also.
4.0
RECORDS :
4.1
28
Report No.
Date :
Details
Temperature Recorder
Thermometer
Make:
Model:
Sl. No.:
Range:
Test Results
Temperature Reading C
Sl. No. t/c No. C/C. No.
Recorder Thermometer
Difference C Results*
Witnessed by
29
Pre heat & PWHT of Critical Piping with Turbine & Auxiliaries
Sl
no
Material
Spec 1
Material
Spec 2
OD
GS 17
CrMoV 511
G17 CrMo 9
10
21 Cr Mo Ni
V47
SA335
P91
SA335
P22
SA335
P22
110
>30
110
>30
110
>30
2
3
Notes :-
PWHT
Temp.
Deg. C
200 TO 690+10
300
(Notes)
200 TO 690+10
300
(Notes)
200 TO 690+10
300
(Notes)
***********
BHEL - POWER SECTOR
30
Holding
time
minimum
(minutes)
240
240
240