Professional Documents
Culture Documents
Production Activity Control Cap 11 Fall 2007
Production Activity Control Cap 11 Fall 2007
PAC
Planning has already been done and the
actual order to produce a product has
been executed.
PAC inputs:
Newly released orders (MRP)
Existing order status
Routing information steps, sequence
needed to complete the job
Lead time information
Status of resources (quantity available,
maintenance schedules, machine
problems, etc.)
Prioritizing work
Practice exercise data
Suppose the
following jobs
have arrived
at a WC in the
order listed:
JOB
Due in
Hrs. work
remaining
3 hrs.
9 hrs.
4 hrs.
15 hrs.
11 hrs.
3.5
19 hrs.
Due date
job
Due in
Work
remaining
Start time
Completion
time
Late?
3 hrs.
4 hrs.
Yes
4 hrs.
1 hr.
Yes
9 hrs.
2 hrs.
No
10.5
No
15 hrs.
5 hrs.
10.5
15.5
Yes
19 hrs.
4 hrs.
15.5
19.5
Yes
Due in
Work
remaining
Start time
Completion
time
Late?
4 hrs.
1 hr.
No
9 hrs
2 hrs.
No
6.5
No
3 hrs.
4 hrs.*
6.5
10.5
Yes
19 hrs. 4 hrs.*
10.5
14.5
No
15 hrs.
14.5
19.5
yes
5 hrs.
3. Total slack:
Total time until the job is due
-Total processing time____
Total slack
Slack = buffer time, time that can pass
without danger of the job being late.
Work first the jobs with the least total slack
(greatest danger of being late)
Total slack
Job
Due in
Work
remaining
Slack
Start time
Completion
time
3 hrs.
4 hrs.
-1 hr.
4 hrs.
1 hr.
3 hrs.
11 hrs.
3.5 hrs.
6.5 hrs.
8.5
9 hrs.
2 hrs.
7 hrs.
8.5
10.5
15 hrs.
5 hrs.
10 hrs.
10.5
15.5
19 hrs.
4 hrs.
15 hrs.
15.5
19.5
Job Due in
Work
remaining
3 hrs.
-1
-.33
4 hrs.
9 hrs.
.77
2 hrs.
4 hrs.
.75
1 hrs.
15 hrs.
10
15
.66
5 hrs.
11 hrs.
6.5
11
.59
3.5 hrs.
19 hrs.
15
19
.79
4 hrs.
Job
Due in
Slack per
operation
Work
remaining
Start
Completion Late?
3 hrs.
-.33
4 hrs.
11 hrs.
.59
3.5 hrs.
7.5
15 hrs.
.66
5 hrs.
7.5
12.5
4 hrs.
.75
1 hrs.
12.5
13.5
9 hrs.
.77
2 hrs.
13.5
15.5
19 hrs.
.79
4 hrs.
15.5
19.5
6. Critical ratio:
Time remaining until due / work remaining
Work remaining = total processing time
If critical ratio is greater than 1 : there is slack
If critical ratio = 1 : there is no slack
If critical ratio is less than 1 : past due, late
Critical ratio
Job
Due in
Work
remaining
Ratio
Late?
3 hrs.
4 hrs.
.75
Yes
15 hrs.
5 hrs.
No
11 hrs.
3.5 hrs.
3.14
12.5
Yes
4 hrs.
1 hr.
12.5
13.5
Yes
9 hrs.
2 hrs.
4.5
13.5
15.5
Yes
19 hrs.
4 hrs.
4.75
15.5
19.5
Yes
Two approaches:
1. backward scheduling : start with the due
date (promised date) and use lead time
to estimate when job will reach each
center. (MRP)
2. Forward scheduling: start when the job
will be released into the production
process. Estimate final completion date
and this becomes the promise date.
Example data
It is now the start of day 214, and there is
one shift in the operation with 7 productive
hours. The job calls for a quantity of 100
to be built:
21 Hours
14 hours
35 hours
7 hours
10.5 hours
3.5 hours
Forward scheduling
Operation Lead time Completed
hours
A
21
End of day 216 (3 shifts:
214,215,216)
B
14
End of day 218
C
35
10.5
3.5
Backward scheduling
Suppose the
salesperson
has promised
the job for
delivery on day
240 using a
standard quoted
lead time.
Job must be
finished on
day 239.
Operation; Must be
Lead time completed
by:
Must start
by:
F; 3.5 hrs.
End of 239
Mid-day 239
E; 10.5 hrs.
Mid-day 239
Start of 238
D; 7 hrs.
End of 237
Start of 237
C; 35 hrs.
End of 236
Start of 232
B; 14 hrs.
End of 231
Start of 230
A; 21 hrs.
End of 229
Start of 227
Loading
Work center load: total time estimate to complete
all the jobs at a given work center. Measured in
time units (hours). Two approaches:
1. Infinite loading: jobs are loaded according to
when the customer needs them, regardless of
capacity.
Assume the work center has infinite capacity.
Need for capacity expanding alternatives
(overtime, temporary workers).
Loading
2. Finite loading: known measurable finite capacity
for the work center.
Work is moved to the next time period if there is no
more capacity in the given period.
Advantages:
Smoothing the load
Save on extra expenses
Stability of the work center
Disadvantages:
Customer service
Loading example:
Job
(arrival
order)
130
136
10
1.5
100
137
30
1.8
50
137
10
0.6
200
138
25
0.8
120
138
15
1.1
100
138
20
1.3
Setup time
Total time
A; 130
130x1.5=195 min.
10 min.
205 min.
B; 100
100X1.8=180 min.
30 min.
210 min.
50X0.6=30 min.
10 min.
40 min.
D; 200
200X.08=160 min.
25 min.
185 min.
E; 120
120X1.1=132 min.
15 min.
147 min.
F; 100
100X1.3=130 min.
20 min.
150 min.
C; 50
Infinite loading
Load the work center according to due
date. Jobs A, B, and C would be loaded
into day 137.
Jobs D, E, and F would be loaded into day
138.
It will require 455 minutes in day 137 and
482 minutes in day 138.
Minutes available =420
Need for overtime