Professional Documents
Culture Documents
NIAGARA TUNNEL
PROJECT
TECHNICAL
FACTS
Last updated on November 21, 2012
1/ 37
12/ 10/ 12
STRABAG INC.
ONTARIO POWER GENERATION
THE ROBBINS COMPANY
BERMINGHAM FOUNDATION SOLUTIONS
2/ 37
12/ 10/ 12
10.4 km (6.5 miles) long, 140 m (459 feet) beneath the City of
Niagara Falls from the Sir Adam Beck Generating Complex to a
water intake complex above Niagara Falls.
The new tunnel will increase the power supply for owner Ontario
Power Generation (OPG) by 150 MW or 1.6 billion kilowatt hours
per year, enough electricity for a city twice the size of Niagara
Falls, Ontario, and its population of 80,000. Annually, the 150MW
generated by the new tunnel will be enough to supply a city of
700,000 people.
Unfinished Tunnel Diameter - 14.44-m (47.5-ft) excavated
diameter
Finished Tunnel Diameter - 12.5 m (41.1 ft) concrete-lined tunnel
with a finished diameter
www. niagar af r ont ier . com / t unnelt echnical. ht m l
3/ 37
12/ 10/ 12
Outlet Works
300 meters (984 feet) long by 20-m (67 feet) deep outlet canal
Outlet structure with downstream closure gate and surge shaft
Intake Works
Intake Grout Tunnel constructed underneath existing Gate #1 of
International Water Control Dam within Niagara River
Deep intake channel excavation
Demolition and replacement of upstream ice control wall
Construction of new shore approach wall
Grout Tunnel Planned Total Length - 403 meters (1,322 feet)
Grout Tunnel Actual Total Length - 298.3 meters (978.6 feet) long
Grout Tunnel Height - 7 meters (23 feet)
Grout Tunnel Width - 8 meters (26 feet)
Grout Tunnel Gradient - 7.150%
4/ 37
12/ 10/ 12
The
Intake
Grout
Tunnel
is
the
entrance
portal
for
water
flowing
into
the
new
Niagara
Tunnel
after
its
completion.
As
the
Tunnel
Boring
Machine
(TBM)
concludes
boring
the
tunnel
it
will
ascend
to
www. niagar af r ont ier . com / t unnelt echnical. ht m l
5/ 37
12/ 10/ 12
the
surface
along
the
Grout
Tunnel.
In
a
simple
sense,
the
Grout
Tunnel
acts
as
the
glide
path
for
the
emerging
Tunnel
Boring
Machine
(TBM).
The
diagram
on
the
left
gives
the
realistic
perspective
of
the
size
of
www. niagar af r ont ier . com / t unnelt echnical. ht m l
6/ 37
12/ 10/ 12
the
Grout
Tunnel
in
comparison
to
the
TBM.
The
most
important
aspect
of
the
Grout
Tunnel
was
to
allow
a
360
high
pressure
grout
injection
into
all
the
rock
cracks
and
crevices
to
form
a
26
meter
diameter
www. niagar af r ont ier . com / t unnelt echnical. ht m l
7/ 37
12/ 10/ 12
waterproof
curtain
to
protect
the
tunnel
from
flooding
from
the
river
above
as
the
TBM
surfaces.
The
Grout
Tunnel
was
built
using
the
drill
and
blast
method.
Four
www. niagar af r ont ier . com / t unnelt echnical. ht m l
8/ 37
12/ 10/ 12
large
3
meter
deep
expansion
holes
were
drilled
near
the
lower
middle
of
the
rock
face.
The
remainder
of
the
rock
face
had
3
meter
deep
blast
holes
drilled
approximately
every
80
centimeters
apart.
The
holes
with
the
www. niagar af r ont ier . com / t unnelt echnical. ht m l
9/ 37
12/ 10/ 12
exception
of
the
expansion
holes
were
packed
with
explosives
and
detonated
in
a
diamond
pattern
so
that
the
blast
would
expand
toward
the
expansion
holes
resulting
in
a
controlled
explosion.
Every
blast
would
expand
the
tunnel
another
3
meters.
www. niagar af r ont ier . com / t unnelt echnical. ht m l
10/ 37
12/ 10/ 12
The
blasting
was
restricted
to
day
time
hours
only
as
not
to
disturb
nearby
neighbourhoods.
Contract
Hatch Energy in association with Hatch Mott MacDonald, is
providing Owners Representative services to Ontario Power
Generation for the construction of the $640M Niagara Tunnel
facility project. This includes preparation of design/build contract
documents, design review, construction monitoring and contract
administration. The design/build project is for a 10.4-km, 14.44-m
diameter water diversion tunnel and associated intake and outlet
works.
The project is a design/build project with a partnering approach. A
negotiated Geotechnical Baseline Report (GBR) was used to
equitably share underground risks on the project.
PROJECT COST: C$985 million
After evaluation and negotiations, the contract was signed in midAugust 2005, with the start of construction in September of that
year. Actual tunneling commenced a year later after procurement,
www. niagar af r ont ier . com / t unnelt echnical. ht m l
11/ 37
12/ 10/ 12
Tunnel Design
The tunnel is being constructed in two passes with rock dowels,
steel ribs, mesh and shotcrete, followed by a polyolefin
membrane and unreinforced 600-mm thick cast-in-place concrete
lining. The lining will be prestressed to resist internal water
pressure using a high-pressure 'interface' grout applied between
the shotcrete and the final lining. The combination of the
membrane and prestressed lining system will prevent water from
entering the rock and resultant swelling. Two layers of membrane
are being applied to the shotcreted rock enabling the space
between the membranes to be vacuum tested after installation in
order to ensure membrane integrity. The membrane will also
protect the concrete lining from the aggressive groundwater
conditions found in the Queenston Formation.
12/ 37
12/ 10/ 12
Cutter-Face
Cutters Face Series (size) - 508 mm (20 in.)
Center Series (size) - 431.8 mm (17 in.)
Number of disc cutters - 85
Nominal recommended individual cutter load 35 t /cutter
Cutter-Head
Cutter-head drive Electric motors/safe sets, gear reducers
Cutter-head power - 6330 HP (15 422 HP) Expandable to 16
422 HP
Cutter-head speed 05.0 rpm
Approximate torque (low speed) 02.4 rpm - 18,800 kNm
Approximate torque (high speed) 5 rpm - 9,025 kNm
Thrust cylinder boring stroke - 1,729 mm (68 in.)
Hydraulic system - 300 HP (225 kW)
System operating pressure at maximum - 275.7 bar (4,000 psi) recommended cutter-head thrust
Maximum system pressure - 310 bar (4,500 psi)
13/ 37
12/ 10/ 12
Electrical System
Motor circuit 690 VAC 3-phase, 60 Hz
Lighting system/control system 120V/24 VDC
Transformer size 4 1,700 kVA + 1 1,000 kVA
Primary voltage 13,800 V 60 Hz
Machine conveyor
Width 1,370 mm (54 in.)
14/ 37
12/ 10/ 12
15/ 37
12/ 10/ 12
16/ 37
12/ 10/ 12
TBM Assembly
To comply with the aggressive construction program outlined by
OPG/Strabag, the supplied TBM system had to be designed,
manufactured, assembled and made ready to bore within 12
months after contract award. The project team achieved this by
the preassembly of the major critical components in a workshop
and final assembly and commissioning of the complete machine
at the project site. By doing this, the workshop assembly was
done at the jobsite using the operating personnel. Robbins
supplied experienced supervision and specialty labor, while
Strabag supplied the local labor. This practice of jobsite assembly
achieved a 12-month, ready-to-bore schedule, which saved
approximately four to five months on the TBM delivery schedule.
In addition, there were project cost savings associated with labor
and freight, as these operations only needed to be done once and
not multiple times as with a workshop.
www. niagar af r ont ier . com / t unnelt echnical. ht m l
17/ 37
12/ 10/ 12
Ground support
The design concept of handling the ground support is to bring the
primary support into the tunnel and handling of the support on top
of the TBM. This allows the invert to be clear, which allows free
access of equipment for cleanup of the invert area. Contract
requirements necessitated several different support systems
based on the type of ground encountered. TBM and backup
assembly in launch pit.
The rock so far encountered, up to 180 MPa UCS, has been
largely competent with some minor broken ground. A specially
designed foam system has also helped increase the TBM
performance in sticky ground. The water spray normally applied to
the cutter-head has been temporarily replaced with the foam
system to assist in the flow of the material through the cutter-head.
Five openings in the cutter-head allow the foam to be plumbed in,
where it mixes with water and air.
18/ 37
12/ 10/ 12
Rock Drills
Two Atlas Copcp 6.4-m- (21-ft-) long BMH 6000 series hydraulic
drills with powerful COP 1532 hydraulic hammers were installed.
The drills are installed on a rotary position locator, which allows
independent operation of each drill. The position locator allows
the various drill positions to be achieved to install the 6-m- (20-ft-)
long rock bolts as per project requirements. Design of the system
allows the bolts to be installed during the boring operation.
Work Platforms
To assist the tunnel operating personnel in the installation of the
rock support, there are various stationary and mobile work
platforms located in the L-1 area. These platforms allow rock
scaling, wire mesh and other ground support functions to be
performed.
19/ 37
12/ 10/ 12
Shotcrete Robot
Should shotcrete be needed in the L-1 area, a shotcrete robot has
been installed and integrated into the work platforms. The robot
has been supplied by Rowa (Wangen, Switzerland)/Meyco-BASF
(Switzerland, TX). It includes a boom to allow shotcrete coverage
over a 180 section of the tunnel crown and at a rate of 15 m3 /h
(530 cu ft/hour).
Shotcrete is being used throughout the drive as the primary
means of tunnel support. Rubber-tired tractors transport shotcrete
from the onsite batching plant to two shotcrete robots located on
the back-up system. Each robot has 360-degree coverage and
can travel up to 8m in the longitudinal direction to spray shotcrete
at the rate of 20m per hour. Additional types of rock support
include ring beams, wire mesh, and rock bolts.
Modifications
Other major changes to the TBM L1 area became necessary to
reach the caved areas, including the addition of two hydraulic man
baskets and special drill rigs, mesh and anchors. These changes
were made incrementally as TBM progress allowed it. With the
new method, the over-break could be limited to 0.5m - 1 m (1.6 3 ft), though the excavation process slowed to a maximum 5 m/d
(16 ft/day).
20/ 37
12/ 10/ 12
Shotcrete Robots
Two remote controlled shotcrete robots were installed in the L-2
area. The units consist of a Meco-BASF spray head attachment,
which allows 360 coverage. Each unit is independently controlled
and has the ability to travel 6 m (20 ft) in the longitudal direction.
The robots are charged by two Meco-BASF shotcrete pumps that
deliver the shotcrete at a rate of 15 m3/hour (530 cu ft/hour) per
pump.
Muck Haulage
Muck haulage is achieved by the use of a continuous conveyor
system. As the backup is advanced, sections of conveyor are
installed to allow continuous operation of the system. Muck is
transported to the portal on the continuous conveyor where it is
then discharged to an overland conveyor and to the storage area
located adjacent to the jobsite.
includes a 105 m (345 ft) long back-up system, which will
transport 1.7 million m3 (2.2 million cubic yards) of rock debris via
conveyor belt.
Air Compressors
two CompAir L160 compressors
The boring machine rides on the front of a sledge, which tunnels
through the rock at a speed of up to 15 metres per day, creating a
14.4 metre diameter hole that must be lined and reinforced
rapidly to prevent the tunnel collapsing behind it. A critical safety
component The compressors are a critical component in this
operation, as they provide a totally dependable source of
compressed air, 24 hours a day, which is used to propel the
injection concrete to form the inner wall of the tunnel. For Strabag
therefore, choosing the right compressor supplier was vital to both
the projects on-time completion and the safety of the contractors
working in the tunnel. CompAir technical representative, Bob
Paton explains. Strabag was very keen to use our compressors
www. niagar af r ont ier . com / t unnelt echnical. ht m l
21/ 37
12/ 10/ 12
from the outset. Its own engineers and the manufacturers of the
drilling machine had worked successfully with CompAir on other
projects, including the renowned English Channel Tunnel and a
number of other drilling applications across the world, where the
compressors had proved their reliability in a harsh environment.
Various quotes were received from all the major compressor
manufacturers, but it was our excellent track record in an identical
application, coupled with our local service capability that won the
day.
In order for the project to be completed on time and on budget,
drilling must continue 24 hours a day, seven days a week,
meaning that the L160 compressors have to perform
continuously. CompAir Canada was also the only compressor
manufacturer that could offer its own, local service organization,
helping Strabag to ensure that the compressors remain fully
operational at all times. With its head office only 45 minutes from
the site, CompAir provides a dedicated engineer, who has
undergone special health and safety training to allow him to work
underground, backed by a team of technical support staff.
CompAir Canada also supplied an L37 rotary screw compressor
complete with dryer, filters and additional ancillary equipment for
Strabags maintenance cabin above ground.
22/ 37
12/ 10/ 12
Invert Structure
As part of the logistics process, Strabag will pour the final invert
section underneath a bridge system designed and supplied by
BMTI (Austria), a sister company owned by Strabag. Once the
TBM has advanced approximately 2.5 km (1.6 miles), the balance
of the final concrete section will be installed on a secondary
working bridge, also supplied by BMTI. This system allows the
final lining to be installed independent of the TBM boring
operation.
Time will be saved on the overall project schedule in other ways
as well. The 12.5m finished diameter tunnel will require 50cm
thick concrete lining with a waterproof membrane to prevent water
from leaking out of the tunnel. As the TBM bores, the tunnel will be
concurrently lined with in-situ concrete and PVC waterproofing
membrane.
The invert structure will be cast and set approximately 500m
behind the TBM boring operations, while the arch structure will be
separately cast approximately 1500m behind the machine. An
87m long bridge will allow rubber-tired supply vehicles to travel
over the invert concrete installation area. While the arch is cast,
www. niagar af r ont ier . com / t unnelt echnical. ht m l
23/ 37
12/ 10/ 12
24/ 37
12/ 10/ 12
Arch Forms
THE ARCH FORMS
A double layer of polyolefin (3 millimeters thick) waterproof membrane is
being applied to the tunnel wall in advance of the final concrete pouring.
The membrane is attached to the Shotcrete coated wall by use of Velcro.
The first arch form is always 2 bay lengths (one already poured and one
ready for pouring) ahead of the second arch form. The front arch form
pours every other bay, the rear arch form fills the gaps.
The Arch Forms are pouring the finish concrete to upper 248 of the
tunnel lining. At the current time one shift is operating daily pouring
concrete into a 12.5 meter long bay. The concrete is poured continuously
until the bay is filled. The concrete is poured on both sides of the form on
an equal basis to ensure the form remains centered. During the pour,
selected sections of the arch form vibrates by use of pneumatics. This
vibration helps the concrete to settle and compress properly. Moisture is
drawn to the form and aids in forming a smooth surface skin. Access
portals on the arch form allow workers to aid the distribution and settling
of the concrete using handheld vibration tools. Typically it takes about 7
hours to pour one 12.5 meter long bay of the arch form utilizing
approximately 240 m3 of concrete. Concrete is pumped through concrete
ports built into the arch form. After the concrete is poured the forms of the
arch remain in place for 10 hours to allow the concrete to dry. Twenty-two
men are employed on the arch form. Currently, concrete is supplied to the
forms from the surface via pipeline. This will continue for the initial 500
meters. A support bridge is being prepared to attach to the arch form that
will allow concrete to be delivered by vehicles as it progresses further into
www. niagar af r ont ier . com / t unnelt echnical. ht m l
25/ 37
12/ 10/ 12
the tunnel.
There are two Arch Forms in the tunnel. In the near future, both forms will
be utilized at the same time resulting in the pouring of a daily maximum
limit of 25 meters. The two forms work in tandem following behind a
membrane liner. The Arch Form train is 368 meters in length.
The arch forms will pour 3-4 bays per week.
Grouting
GROUTING
There will be two different types of grouting:
1. the contact grouting to make sure that the inner lining concrete is
properly bedded, and
2. the pre-stress grouting to compensate for shrinkage and creeping of
the inner lining concrete. Basically this is an substitute for reinforcement.
Restoration
The Restoration is taking place at two locations within the tunnel at the
"Fall of Ground" and "St. David's Cathedral". It is a two stage restoration
process to re-shape the tunnel. The first stage are abutments consisting
of rockbolts, steel channels and reinforced shotcrete. The second stage
consists of steel panels that are suspended from the arch and are acting
as a lost formwork for the shotcrete/concrete infill.
26/ 37
12/ 10/ 12
27/ 37
12/ 10/ 12
28/ 37
12/ 10/ 12
29/ 37
12/ 10/ 12
30/ 37
12/ 10/ 12
31/ 37
12/ 10/ 12
worlds largest diameter tunnel carry water from the river to the Sir
Adam Beck Power Station to generate hydroelectricity.
Stop-Log Gates
The intake gate is comprised of 10 steel stop logs. Each is 13.5
meters wide for a total height of 14.8 meters. The combined
weight of all 10 sections are approximately 215 tonnes (enough
steel to make 260 average cars) . The lowest gate holds back a
water depth of 38.6 meters, which results in a water pressure of
almost 4 Bar (60 psi).
Geology
The geology is varied, consisting of limestone, dolostone,
sandstone, shale and mudstone. The rock strength ranges from
15 to 180 MPa (2,100 to 26,000 psi), with most of the rock in the
40 to 100 MPa (5,800 to 15,000 psi) range. With the exception of
sandstone, the geology is basically nonabrasive. Most of the
debris (approximately 30 percent) removed from the tunnel will
consist of Queenston shale.
During the first 200 m (656 ft), problems were encountered
including higher than expected water inflows and handling of the
water due to the 7.82-percent decline. The water removal system
has been modified and the progress has increased to the
expected advance rates. After 850 m (2,780 ft) of excavation, the
TBM entered the Queenston shale formations. Horizontal banked
www. niagar af r ont ier . com / t unnelt echnical. ht m l
32/ 37
12/ 10/ 12
layers, which were not able to arch until rock support was placed,
led to huge over-break and caving up to 3 m (10 ft) above the roof
shield in the L1 area. Strabag designed a special ground support
method with grouted umbrella spiles to mine through this geology.
As part of the logistics process, Strabag will pour the final invert
section underneath a bridge system designed and supplied by
BMTI (Austria), a sister company owned by Strabag. Once the
TBM has advanced approximately 2.5 km (1.6 miles), the balance
of the final concrete section will be installed on a secondary
working bridge, also supplied by BMTI. This system allows the
final lining to be installed independent of the TBM boring
operation.
The tunnel is located predominantly in Queenston shale with
some limestone, dolostone, sandstone and mudstone up to 200
MPa (29 ksi) UCS.
The rock along the tunnel bore path is known to have high in-situ
stress and there is potential for squeezing ground. An initial rock
support lining of wire mesh, steel ribs, rock bolts, and shotcrete
will be installed as the TBM advances.
After tunnel excavation is completed, an in-situ placed concrete
lining will be installed, and the final lining will include a
waterproofing membrane system to ensure that water does not
seep from the tunnel into the rock and cause swelling.
Rock swelling in the Queenston Formation is caused by a
combination of reduced in-situ stresses in the rock surrounding
the tunnel and availability of a source of fresh water from within the
tunnel. The pore-water of the Queenston Formation is highly
saline and, through a process of pore-water dilution and ion
diffusion, the clay minerals in the rock expand and absorb water
resulting in swelling of the rock. This process would impart large
pressures on the tunnel linings if these conditions are allowed to
occur.
Extensive modeling of the swelling process and its effects on the
load build-up on tunnel linings were studied throughout the 1990s.
Modeling included development of a 'swelling law' to characterize
www. niagar af r ont ier . com / t unnelt echnical. ht m l
33/ 37
12/ 10/ 12
34/ 37
12/ 10/ 12
Tunnel Crews
The tunneling crew operates the TBM and equipment 24 hours a
day, seven days a week. About 30 crew members are onsite in a
given shift, with one maintenance shift each morning in order to
monitor and test the equipment. The crew has endured winter
conditions reaching below -20C at the jobsite, which caused the
conveyor systems to freeze over with ice. Antifreeze was sprayed
on the affected conveyors and the ice was chipped off in order to
keep them running. Big Becky is now operating on a 24-hour-aday, seven-day-a week basis. The typical day is divided into two
production shifts and a maintenance shift. About 30 people are
needed to crew Big Becky during each shift.
An onsite geologist monitors progress, watching for any danger
signs.
As the machine moves forward workers erect steel ribs in a full
circle around the tunnel every few feet to reinforce the rock. The
rock surfaces are then covered with a heavy wire mesh and a
layer of concrete is blown on top to form a temporary shell.
Eventually, the entire tunnel will be lined with concrete slabs about
two-feet thick and a waterproof liner will be installed. The design
will give the tunnel a minimum 90-year life span.
An overhead conveyor belt is used to transport the chewed up
rock from the cutting head to the surface. Dump trucks haul the
material, which will later be used to make bricks, to a nearby
location that was cleared as a temporary storage site.
The underground operations are supported by staff working on
the surface. To supply concrete to the tunnel, a concrete plant
was built on the surface just above the tunnels entrance. Theres
also a small water treatment plant thats used to clean water
pumped out of the tunnel before its dumped into the nearby
hydroelectric canal.
Inside the tunnel away from the tunnel entrance, the air
www. niagar af r ont ier . com / t unnelt echnical. ht m l
35/ 37
12/ 10/ 12
HISTORICAL ARCHIVE
History Index
SITE MAP
36/ 37
12/ 10/ 12
NIAGARA TUNNEL
PROJECT
TECHNICAL FACTS
PAGE
RETURN TO THUNDER
ALLEY
37/ 37