Professional Documents
Culture Documents
(Closed Book)
1.
2.
Non-essential variables
Essential variables
Ranges of 1 & 2 above
All of the above
4.
welder is qualified
base metals are strong enough
weldment has the desired properties
skill of the welder
3.
The
The
The
The
essential variables
qualification test & examination results
supplementary essential variables (when notch toughness is
required)
1958
1992
1987
1962
5.
6.
A.
B.
C.
D.
7.
8.
Flat only
Flat and horizontal
Flat and vertical
None of the above
11.
Vertical
Flat & horizontal
Flat & overhead
Horizontal
10.
Manufacturer
Welder
Authorised Inspector
Foreman
9.
Stud welds
Overhand welds
C.
D.
12.
13.
True
False
15.
Tensile strength
Ductility
Notch toughness
All of above
14.
Fillet welds
All of the above
3.5%
0.5%
5%
All of the above
1/16
3/32
1/8
None of the above
ASME Section V
ASME Section IX
ASME Section VII
The referencing code
qualify
welder,
the
acceptance
A.
B.
C.
D.
18.
19.
Essential variables
Nonessential variables
Supplementary essential variable when required for notch
toughness
All of the above
Nonessential variables
Essential variables
Results of Welder Qualification tests
Project description & NDE methods
Inspector
Manufacturer or contractor
Welder
All of the above
22.
Groove design
Post Weld Heat Treatment
Root spacing
Method of cleaning
23.
24.
If a welder qualified with the SMAW process on Jan. 1,1994 and last
welded with SMAW on March 15, 1994, would he still be qualified
on October 7, 1994?
A.
B.
25.
Yes
No.
26.
PQR
WQR
WPS
WPQ
Without backing
With all base metals
With backing only
With P1 backing only
8
Max to be welded
1
D.
29.
30.
32.
Electrodes
Flux
Base metals
Joints
31.
AWS class
ASME specification
SFA
F number
P number
Welder I.D.
A number
Page number
33.For
welder
qualifications
with
the
SMAW
______________________ is an essential variable.
A.
B.
C.
D.
34.
P number
Unique identifier
process
C.
D.
35.
36.
B.
C.
D.
Yes
No
Not enough information provided
Yes, provided a backing strip is provided in the 2 weld.
39.
A welder has been tested in the 6-G position, using as E-7018 F-4
electrode, on 6 Sch 160 (0.718 nom) SA 106B pipe. Is this welder
qualified to weld a 2 300# ANSI schedule 80 bore flange to a 2
Schedule 80 SA 106 B nozzle neck?
A.
B.
C.
D.
38.
Yes
No
Not enough information provided
Yes, provided pipe is carbon steel, P#1
37.
Yes
No
Not enough information provided
Yes, because backing is not an essential variable for a welder
C.
D.
40.
41.
The
The
The
The
Inspector
A.I.
Shop Foreman
Manufacturer of Contractor
44.
45.
Or
2
4
6
3
What positions are necessary to qualify a welder for all position pipe
welding?
A.
3G and 4G
B.
C.
D.
2G and 5G
3G and 1G
4G and 5G
electrode
storage
IX
VIII
B31.1
II Part C
Yes
No
Not enough information given
Yes, if properly heat treated
Yes
No
Not enough information given
Yes, provided bend tests are done
50.
welding
49.
has
48.
ASME
ASME
ASME
ASME
Section
A.
B.
C.
D.
51.
52.
Yes
No, must be re-qualified
Is only applicable for 1965 pressure vessels
Cannot be used for new construction repairs only
What are the various positions in which a welder may qualify for
plate groove welds?
A.
B.
C.
D.
53.
Yes
No
Not enough information provided
None of the above
1G
3G
4G
All of the above
You are reviewing a WPQ (QW-484) for a welder testing in the 6G position, on SA-53 grade B pipe (TS-60,000 psi). The test results
indicate the following:
No.1
No.2
No.1
No.2
Yes
No
Not enough information given
Tension test is acceptable but No.1 is unacceptable
55.
56.
57.
The WPS
The PQR
The WPQ
All of the above
59.
E6010
E7018
E9028
All of the above
58.
F,H,OH
F,V,OH
V,OH,SP
H,V,OH
5G and 6G
2G and 4F
4G and 5G
None of the above
Porosity, underfill
Lack of penetration/fusion
Slag, overlap
Any of the above
A.
B.
C.
D.
Essential variable
Non-essential variable
Supplementary essential variable
All of the above
63. A change in a supplementary essential variable requires requalification, when notch-toughness is a consideration.
True
64.
False
(circle one)
When using Macro-examination of fillet weld tests, the weld and the
HAZ must not reveal cracks when magnified at:
A.
B.
C.
D.
65.
or
5X
2X
10X
No magnification is required visual examination is required,
only
Or
and,
if
applicable,
C.
D.
68.
69.
Or
Or
73.
Pass
Fail
72.
71.
or
70.
The AI approves
The test data on a PQR is a record of what occurred and
should never be changed. Only editorial information can be
changed on a PQR.
The API 510 inspector approves
The date of the WPS is changed
Or
True
Or
SMAW
76.
procedure
qualification
is
an
Essential
Non-Essential
Supplemental essential
None of the above
Or
Essential
Non-essential
Supplemental essential
None of the above
Or
80.
SAW
79.
78.
is
77.
qualification
Essential
Non-essential
Supplemental essential
None of the above
procedure
Or
True
81.
85.
Or
1G
2G
5G
6G
All of the above
The maximum preheat temperature decrease allowed without requalification of a GMAW groove weld procedure is:
A.
500F
B.
1000F
C.
1250F
D.
1500F
E.
None of the above
A welder is qualified to weld all thick nesses of material when:
A.
B.
C.
D.
86.
84.
Or
83.
82.
Or
A.
B.
C.
D.
E.
87.
88.
90.
3 months
6 months
9 months
12 months
As stated by the AI
89.
inch
1/8 inch
1/16 inch
3/16 inch
No defects are allowed
E7015
E6011
E6010
E7024
All of the above
91.
Designer or architect
Designer or installer
Architect or installer
Installer or assembler
Assembler or designer
92.For
P-11
materials,
weld
grooves
for
thick
nesses
________________ shall be prepared by thermal processes, when
such processes are to be employed during fabrication.
A.
B.
C.
D.
E.
93.
94.
Or
96.
95.
2 inches
21/2 inches
3 inches
31/2 inches
4 inches
A.
B.
C.
D.
E.
97.
98.
Two plate tensile test specimens have been tested and found to be
acceptable. The characteristics of each specimen are as follows:
Specimen 1: Width of 0.752; thickness of 0.875; ultimate tensile
value of 78.524 psi
Specimen 2: Width of 0.702; thickness of 0.852; ultimate tensile
value of 77,654 psi
What is the ultimate load for each specimen that was reported on
the laboratory report?
A.
B.
C.
D.
GMAW
SAW
PAW
All of the above
ANSWER KEY
1. C
2. D
3. D
4. D
5. B
6. B
7. C
8. C
9. D
10.
11.
B
C
52. C
53. D
54. A
55.
56.
57.
58.
59.
60.
61. A
62. B
C
B
D
D
A
B
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
C
A
C
C
B
D
B
B
B
A
B
D
B
C
A
C
C
C
C
D
C
C
B
B
A
B
B
A
D
C
B
B
A
B
D
B
B
C
A
A
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
True
D
C
False
B
False
Pass
True
False
False
False
B
A
True
A
True
False
True
False
True
C
B
C
B
B
E
E
D
D
A
D
False
C
D
A
A
D