Professional Documents
Culture Documents
Ted E. Robbins
Technical Services Administrator
Martin County Utilities and Solid Waste Dept.
Stuart, Florida
SPECIFICATIONS
3.1
Composition of
Specications
3. A division called general conditions. This division describes procedures generally required to
be followed during construction of all projects,
including procedures to be followed by all
parties; that is, the owner, engineer or architect,
and contractor. A well crafted general conditions is likely to be reused many years for
similar projects.
4. A division called supplemental conditions,
which modies the general conditions to the
specic or special requirements of the project.
Using this method to modify the general conditions ensures the integrity of the general
conditions and encourages familiarity with the
general conditions. Contractors can focus their
attention on the supplemental conditions with
condence when they are fully aware of the
standard general conditions that were used to
administer their past projects.
5. A division called technical specications. This
division is organized into logically arranged
sections that describe comprehensively the material, equipment, or performance of items that
must be incorporated into the completed work.
This combination of requirements, together
with the contract drawings and bidding documents, comprises the contract documents. When
faced with the task of preparing specications for
an engineered project, the engineer must consider
many factors, among which the most important
are:
3.1
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
SPECIFICATIONS
3.2
SPECIFICATIONS
Specications n 3.3
actually inserted or not. All the documents constitute one legal instrument.
3.2.1
Adoption of Standards by
Reference
3.2.2
Noncollusion Afdavits
3.2.3
Contract Revisions
3.3
Types of Contracts
3.3.1
Unit-Price Contract
SPECIFICATIONS
3.3.2
Lump-Sum Contract
3.3.3
3.3.4
Negotiated Contract
SPECIFICATIONS
Specications n 3.5
in construction cost. This creates a situation where
there would be no incentive for the contractor to
effect any economies during construction.
A construction-management agreement requires the contractor to divide the work into
segments, usually by trade. The contractor takes
bids for the work from a group of subcontractors
and awards the work to them. The prime contractor
usually performs a certain prescribed segment of
the work and coordinates the work of others. The
owner reimburses the prime contractor for all the
subcontractors work and for the contractors work
plus a small prot and pays a negotiated fee for
management of the subcontracts.
In some states, public-agency projects of larger
size are required to be bid by separate trades, such
as general civil; mechanical; heating, ventilating,
and air conditioning (HVAC); and electrical. To
accommodate this and to ensure proper contract
management, some specications have been written to require the general civil contractor to include
an item for construction contract administration of
the other trades. Bids for all major trades are taken
by the owner with direct assignment of the mechanical, HVAC, and electrical subcontractors to
the general civil contractor. In effect, the general
civil contractor signs a construction management
agreement along with an agreement for completion
of the general civil work. The specications require
the bid of the civil contractor to include costs to
account for coordination and control of the
subcontractors to the same degree as if the civil
contractor had taken direct bids and signed
agreements with the various trade subcontractors.
Incentive-type contracts vary. The basic premise is that the owner will pay bonuses for economic construction and earlier completion and that
the contractor may have to suffer for inefciency
and late completion.
3.3.5
Specialty Contracts
generally recognized as specialists in the manufacture and installation of such facilities. When
competition is possible, it is so arranged. The
contract documents prepared by the owners
engineer in such instances are as described in Art.
3.2, with certain exceptions. Since advertisement is
not used, this and related items of the documents
are not included, but the contracting procedure is
substantially that followed for contracts publicly
bid. Public agencies can use a modied procedure
that involves preparation of and public bid on a
prequalication bid package, prepared by their
engineers.
See also Art. 3.8.
3.4
Standard Specications
3.5
Master Specications
SPECIFICATIONS
3.6
General Provisions of
Specications
SPECIFICATIONS
Specications n 3.7
and control of the work; materials inspection,
sampling, and testing; handling of unauthorized or
defective work; contractors claims for additional
compensation or extension of time; delivery of
spare parts, record documents; acceptance of work
upon completion of project; and warranty
maintenance.
Legal and Public Relations n This section
of the general provisions deals with legal aspects
that determine the relations between the contractor and the owner agency and between the
contractor and the general public. It sets up the
requirements to be observed and protective
measures to be taken by the contractor so that
the liabilities for actions arising out of the
prosecution of the work are properly oriented and
provided for. Topics included are the disclaimer of
any personal liability upon the contracting ofcer
or the agency, the engineer, and their respective
authorized representatives in carrying out the
provisions of the contract or in exercising any
power or authority granted them by virtue of their
position; in such matters, they act as agents and
representatives of the owner agency, such as
federal government, state department, municipality, or authority.
Other features of legal and public relations that
control contractors procedures are damage claims;
laws, ordinances, and regulations; responsibility
for work; explosives; sanitary provisions; public
safety and convenience; accident prevention;
property damage; public utilities.
Damage Claims. Indemnication and saveharmless provisions are invoked to protect
owners and their agents. The protection extends
to suits and costs of every kind and description and
all damages to which they may be subjected by
reason of injury to person or property of others
resulting from the performance of the contract
work or through negligence of the contractor, use of
improper or defective machinery, implements, or
appliances, or any act or omission on the part of the
contractor or contractors agents or employees.
These provisions are made to apply to subcontractors, material suppliers, and laborers performing
work on the project.
These requirements are often implemented by
requiring the contractor to provide insurance of
specied character and in specied amounts as will
provide adequate protection for the contractor, the
SPECIFICATIONS
SPECIFICATIONS
Specications n 3.9
Prosecution and Progress n This section
of the general provisions deals with such pertinent
considerations as commencement and prosecution
of the work, time of completion of the contract,
suspension of the work, unavoidable delays,
annulment and default of contract, liquidated
damages, and extension of time.
Commencement and Prosecution of the Work.
This article establishes the date on which work is to
start and from which contract time is to run. It
requires that construction proceed in a manner
and sequence ensuring completion established by
the contractors progress schedule previously reviewed and accepted by the engineer. It describes
whatever limitations of operations there may be at
the site of work, including trafc, work by others,
and schedule of stage completion. It also requires
that the ability, adequacy, and character of workers,
construction methods, and equipment be suitable
for full prosecution of the work to completion in
the time and manner specied.
Time of Completion. It is advantageous to specify
time of completion in calendar days from date of
commencement of work rather than working days
because the actual determination of a working day
is often a cause of contention. Herein may be
specied stage completion when it is to the owners
advantage to have occupancy of a part of the work
prior to completion of the entire contract or where a
priority of construction of a particular feature of the
work is essential to subsequent procedures.
Suspension of Work. This article covers the usual
conditions under which the owner may suspend
work, in whole or in part, for such period of time
as may be deemed necessary, without breach of
contract, and the period of time that suspension
may be effected without allowance of compensation. These conditions may include weather,
owners or adjacent owners operations, or other
conditions unfavorable for prosecution of the work
and the contractors failure to perform in
accordance with provisions of the contract or to
correct conditions unsafe for workers or the general
public.
Unavoidable Delays. For delays for any reason
beyond the contractors control, other than those
caused by suspension of the work, the contractor
may be granted an extension of the contract time.
This citation, however, gives the contractor no right
or claim to additional compensation unless the
SPECIFICATIONS
3.7
Technical Specications
SPECIFICATIONS
Specications n 3.11
Materials and Workmanship Specications n This type of specication is almost
universally used on construction contracts. It is
comprehensive in its coverage of the principal
factors entering into the prosecution and completion of the work covered by the contract. These
factors include the general and special conditions
affecting the performance of the work, material
requirements, construction details, measurement
of quantities under the scheduled items of work,
and basis of payment for these items.
Material Procurement Specications n
These specications are used on projects of
considerable magnitude requiring many separate
general construction contracts, usually in simultaneous operation and under which the types of
construction are similar. For example, material
procurement specications may be desirable for a
considerably long highway involving the construction of grade-crossing structures of structural steel
or precast and prestressed concrete items. In such
cases, it has often been found advantageous to
separate contracts for the structural steel or prestressed concrete from the general contracts for the
overall project. This procedure ensures uniformity
and availability of the materials. It facilitates
construction by scheduling deliveries to coincide
with the general contractors needs for these items
at any particular location throughout the entire
project. A similar procedure may also be used for
the procurement of other construction materials in
quantity.
The specications for contracts of this nature
contain, besides fabrication processes, all the
elements of materials and workmanship specications, except for the eld construction details. If
erection of the items is to be included in the
procurement specications, the procedure is the
same as for materials and workmanship specications.
Performance Specications n These specications are used to a great extent in procurement
contracts for machinery and plant operating
equipment, as distinct from material procurement
contracts. Contracts for machinery and equipment
may be let separately by the owner prior to a
construction contract under which installation will
be made, to ensure delivery to the job in time for
installation within the scheduled construction
sequence. Advance letting of procurement contracts is usually necessary because of the great
amount of time consumed in the manufacture of
such items. In general, performance specications,
in addition to dening the materials entering into
the manufacture of equipment, with all the
pertinent physical and chemical properties, prescribe those characteristics that evidence equipment capability under actual operating conditions.
Thus, the specications must completely dene
quality, function, and other requirements that must
be met. Since a performance specication requires
samples, tests, afdavits, and other supporting
evidence of compliance, it tends to increase
contractors costs for furnishing the items and
engineers costs for checking submitted data. It
also adds to the designers responsibility for an
unsatisfactory or inadequate product.
Requirements for tests and certication of
the results are set up in the specications in
accordance with test procedures established by the
appropriate industry associations.
When not critical from the standpoint of
manufacture and delivery schedules, machinery
and equipment may be covered by the construction
specications. For a typical technical specication,
see Art. 3.12.
3.7.1
Materials Specications
SPECIFICATIONS
3.7.2
Reference Standards
3.7.3
SPECIFICATIONS
Specications n 3.13
11700Pumping Equipment; Section 11800Sampler Equipment; Section 11810Rotary Fine
Screens; Section 11820Sludge Degritting Equipment; Section 11830Gravity Sludge Thickeners;
Section 11831Odor Control Systems; Section
11950Fiberglass Weirs and Troughs
Division 12 Furnishings: Section 12100Interior
Furnishings
Division 13 Special Construction: Not used.
Division 14 Conveying Systems: Section 14300
Hoists and Cranes; Section 14500Belt Conveyors;
Section 14600Screw Conveyors
Division 15 Mechanical: Section 15100General
Mechanical Requirements; Section 15200Piping;
Section 15210Valves; Section 15250Sluice and
Slide Gates; Section 15400Plumbing; Section
15600Heating, Ventilating and Air Conditioning
(HVAC); Section 15700Fuel System
Division 16 Electrical, Instrumentation and Controls:
Section 16000Electrical; Section 16500Instrumentation and Controls; Section 16600Supervisory Data and Control Acquisition (SCADA)
System; Section 16720Fire Detection System
As indicated above, each division is composed
of sections. The detailed specications for each
section (for example, Section 04200, Masonry,
under Division 4) are generally arranged under the
following headings:
1. Description
2. Materials
3. Construction Requirements
4. Method of Measurement
5. Basis of Payment
Items 4 and 5 may be combined under a single
heading, Measurement and Payment.
Description n Under this heading, a concise
statement is made of the nature and extent of the
work included in the section and its pertinent
features, including the general requirement that
work conform to the plans and specications.
Materials n This article presents the requirements for the various materials involved in the
performance of the work of the section. If a separate
division on materials has been included as a part of
SPECIFICATIONS
SPECIFICATIONS
Specications n 3.15
lump-sum bids, the contractor should be required
to submit a breakdown for the components of
the work. This breakdown is referred to as the
schedule of values. The breakdown should include
quantities for the different types of work or trades
involved and unit prices applicable to each. When
extended and summarized, the prices should equal
the lump-sum bid for the completed item or
contract. The specications should require submittal of the schedule of values prior to the
preconstruction conference. The schedule must be
approved by the engineer before it becomes
effective.
See also Art. 3.11 & 3.12.
3.8
3.8.1
SPECIFICATIONS
3.8.3
Following the opening of bids, a public announcement is made of the prices bid for the various items
listed in the proposal. These data then are tabulated, the totals for each item veried, and their
summation, establishing the total amounts of bids,
is checked for each bid submitted. Comparison of
the total amounts of the bids establishes the lowest
bid and those that follow in the order of increasing
amounts.
3.8.4
3.9
Specications Writing:
Style and Form
SPECIFICATIONS
Specications n 3.17
projects. A descriptive denition of these two types
of specications follows. Design specications are
those that tightly circumscribe the contractors
latitude in choosing products that achieve the
specied standard of performance. Whereas performance specications prescribe an objective or
standard to be achieved and leave it to the ingenuity of the contractor to select the methods and
materials to achieve the specied results.
One example of a design specication is to
specify a brand name product without allowance
for possible substitution. Conversely, courts have
ruled that specifying a brand-name product with
an or equal clause allowing substitution is an
example of a technical specication. A contract
due date has been determined to be a performance
specication. Courts have decided that a due date
is a warranty by the bidding contractor that it can
do the work in the specied time and thus is a
performance specication.
Design specication should be used when the
project owner has strong preferences such as using
one brand and type of motor actuated valve for all
valves serving a specic duty. This allows owners
to minimize the need for warehouse space and the
use of maintenance staff. However, there is more
risk on the part of the writer when design specications are used. Performance specications
should be used when the owner is unfamiliar with
a process of mechanism and it wishes to employ
the knowledge and expertise of the contractor to
accomplish the end goal.
3.9.1
Specications Format
3.9.2
Precedence of Contract
Documents
3.9.3
References to Standard
Specications
SPECIFICATIONS
3.9.4
SPECIFICATIONS
Specications n 3.19
Refer to these specications rather than this
specication; use the plural.
Workmanship should be in accordance with,
and materials should conform to, a reference
specication.
Use the phrase at no additional cost to the
owner only when there is a denite possibility of
the contractors not understanding that he or she is
to bear a certain expense. Liberal use of the phrase
might imply that other work specied is not at the
contractors expense.
Use the word shall for requirements placed on
the contractor and the word will for expressions
of intent on the part of the owner.
Do not confuse the meaning of words; proper
word usage is of utmost importance.
Do not use indenite words when more exact
words may be substituted.
Avoid repeated use of stock phrases and
stereotyped expressions. Specications should not
be encumbered with legal phrases that obscure
their meaning or subordinate their function to that
of a legal document.
Streamlined Specications n An alternative to the traditional style of specications is a
streamlined form. This is accomplished by shortening sentence structure wherever practicable.
Properly employed, streamlining may be a major
improvement. In general, streamlining omits from
the specications, without a change in meaning,
those words having no legal signicance. Only
necessary provisions are retained. A good longform specication can be streamlined without the
slightest adulteration and yet reduce its bulk by
one-third or more.
The technique of streamlining specications may
be adopted as a simplication of style, productive
of a distinctive form of writing specications,
whereas the general format remains the same.
However, note that this style is more readily adaptable to building construction contracts, wherein
each section of the technical specications relates
directly to a particular construction trade.
Some aspects and considerations in streamlining specications advocated by Ben John Small
(The Case for Streamlined Specications, The
Construction Specier, July 1949) are:
The term streamlining should not be interpreted
to mean that it refers to a specication lacking
thoroughness or that streamlining is synonymous
SPECIFICATIONS
3.10
Word Processing of
Specications
3.11
Example of a Standard
Specication in CSI
Format
Description:
SPECIFICATIONS
Specications n 3.21
utility service facilities; guardrail and posts,
highway and street signs and fences; and
other miscellaneous structures which interfere with construction, as indicated on the
Contract Drawings or as required by the
Engineer.
3.03
3.04
3.05
Removal:
Salvage:
4.01
Measurement:
Description:
SPECIFICATIONS
Part 3: Execution
Measurement:
A. Removal of concrete driveways and alleyways will be paid for as Removal of Sidewalk.
B. All work not otherwise paid for will be
included for payment in the Contract lump
sum price for Site Preparation.
3.12
3.01
Removal:
Salvage:
Example of a Technical
Specication Not in CSI
Format
SPECIFICATIONS
Specications n 3.23
welded splices. Mill certicates for chemical
composition and two certied copies of the
records of the physical tests performed on
the newly manufactured pipe in accordance
with the above ASTM requirements shall be
furnished before any driving is started.
b.
c.
d.
e.
f.
Welding Electrodes shall conform to the requirements of the American Welding Society
Specications for Mild-Steel Covered-Arc
Welding Electrodes.
g.
3. Construction Details.
a.
Protective Coatings. Zinc-rich paint and coaltar epoxy shall be applied to exterior surfaces
of pipe piles, including splice areas, within
the respective limits shown on the plans. The
Contractor shall apply the protective coatings to a sufcient length of pile sections to
insure that the pile when driven to its required resistance, will be protected within
the required limits.
Prior to the application of the zinc-rich
paint and coal-tar epoxy, bare surfaces shall
be blast cleaned to white metal in accordance
with the Steel Structures Painting Council
Specication No. SP-5.
The zinc-rich paint shall be applied in the
shop to a dry-lm thickness of 2 mils. The
coal-tar epoxy may be applied in the shop or
in the eld and shall have a total dry lm
thickness of 16 mils. Coated pile sections
shall not be stored in direct sunlight longer
than one month without a tarpaulin
covering.
Care shall be taken while handling coated
pile sections during loading, transporting,
unloading and placing, so that the protective
coating is not penetrated or removed. Coated
pile sections shall be inspected before placing in the leads and any damaged surfaces
shall be repaired and recoated to the satisfaction of the Engineer.
The Contractors attention is directed to
the Hazardous Warning Label on the
coal-tar epoxy products and the manufacturers literature regarding the use of
protective clothing, gloves, creams and
goggles during mixing, application and
cleanup.
The cured coal-tar epoxy coating will be
tested by the Engineer to determine resistance to lm removal by a mechanical
force, as follows:
(1) Lay a sharp wood chisel almost at on
the coating surface in line with the pipe
length.
(2) Drive the chisel using a hammer, through
the coating and along the substrate.
(3) If the coating lm is acceptably bonded
to the surface, considerable force will be
required to lift a layer of the lm.
SPECIFICATIONS
c.
d.
e.
f.
SPECIFICATIONS
Specications n 3.25
g.
h.
i.
l.
m.
n.
o.
Pile Load Tests: Load tests shall be performed in accordance with the requirements of ASTM Designation D1143, LoadSettlement Relationship for Individual
Vertical Piles Under Static Axial Load as
modied herein:
j.
Inspection. The Contractor shall have available at all times a suitable drop-light for the
inspection of each pile throughout its entire
length.
k.
SPECIFICATIONS
b.
5. Basis of Payment.
a.
b.
3.13
Qualications for
Specications Engineers