1. Write the name of phase of project cycle. 2. Write the nine components of project management. 3. Draw a skeleton of a Problem tree. 4. Draw a skeleton of an Objectives tree. 5. Draw a skeleton of logical frame analysis. 6. Three Activity time Estimate of a project are following: Task Immediate Predecessors Optimistic Most likely Pessimistic A None 3 6 15 B None 2 4 6 C A 6 12 24 D A 2 5 8 E C 5 11 17 F D 3 6 15 G B 3 9 21 H E,F 1 4 7 I G,H 4 13 22 a. Draw the activity network diagram of the project. b. Draw a CPM network and show the critical path. c. What is Project duration? d. What is the probability of finishing this project within 52 weeks? e. What is the probability that the project duration exceeding 52 weeks? 7. You have a project to be completed in 12 months and the total cost of the project is BDT.100,000 . Six months have passed and the schedule says that 50% of the work should be completed. What is the Planned Value (PV)? 8. You have a project to be completed in 12 months and the total cost of the project is BDT.100,000 . Six months have passed and BDT. 60,000 has been spent, but on closer review you find that only 40% of the work is completed so far. What is the Earned Value (EV)? 9. You have a project to be completed in 12 months and the total cost of the project is BDT. 100,000 . Six months have passed and BDT. 60,000 has been spent, but on closer review you find that only 40% of the work is completed so far. What is the Actual Cost (AC)? 10. Determine the Schedule variance, Cost variance and Schedule Performance Index and Cost Performance index to follow the problems Nos.7-9. 11. X Group of companies has 4 investment proposals in hand. The cash flows before tax & depreciation is given below. The initial investment and the project life is same in all the 4 projects. Tax rate is 40% discounting rate- 12%. Cash Flows in Taka Project life in Project-A Project-B Project-C Project-D years 0 (60,000) (60,000) (60,000) (60,000) 1 8,000 10,000 15,000 10,000 2 12,000 15,000 25,00 10,000 3 25,000 20,000 30,000 15,000 4 20,000 25,000 10,000 15,000 5 25,000 30,000 5,000 20,000 6 22,000 28,000 5,000 30,000 (Salvage 6,000 3,000 6,000 12,000 value) Calculate IRR and NPV.