PROJECT IMPLEMENTATION PLAN - 2015 - WIRE DRAWING 240

BUDGETED FOR 2015 - SAR 3,000,000 - 9X1200 WIRE DRAWING MACHINE

30

1-Mar-15

30-Mar-15

Civil Work

62

1-Apr-15

1-Jun-15

154

1-Mar-15

1-Aug-15

30

1-Sep-15

30-Sep-15

30-Sep-15

30-Sep-15

Excavation, Back Filling Compaction etc.


Machine Foundations and Trenches
Electrical & Mechanical M/C Connection
3

Plant Machineries

Technical Evaluation, Finalizing and Contract Signing


Booking of the Order
Scope of Supply
a.1

Coil Pay-of

a.2

Drawing Machine - 9 Blocks

a.3

Spooler

a.4

Pneumatic / Hydraulic Connections

a.5

Electronic Components Connections

a.6

Operator Control Stations Console Connections

a.7

Electrical Cabinet Connections

Infrastructure Connections

Installation & Commisioning

Testing and Acceptance

December

Design-Basis Verification of Infrastructure Connections,


Detailed Design & Engineering

November

October

September

August

June

Finish

May

Start

April

Duration

March

Details

February

No

July

Y 2015

IN ORDER TO MAINTAINED GOOD INPUT MATERIAL BUFFER FOR STRANDING GALVANIZING


ALSO FOR PRODUCTION OF BIG SIZE OF SPRING WIRE
January

AIM :-

PROJECT IMPLEMENTATION PLAN - 2015 - WIRE DRAWING 240


BUDGETED FOR 2015 - SAR 3,000,000 - 9X1200 WIRE DRAWING MACHINE

Line Production

1-Oct-15

December

November

October

September

August

July

June

Finish

May

Start

April

Duration

March

Details

February

No
6

Y 2015

IN ORDER TO MAINTAINED GOOD INPUT MATERIAL BUFFER FOR STRANDING GALVANIZING


ALSO FOR PRODUCTION OF BIG SIZE OF SPRING WIRE
January

AIM :-