Technical Readiness Review
Aaron Kreutzjans
CP4
11/10/14
ME 597-Intro to Systems Engineering
1
Agenda
Verification Testing
Testing Hazard
Verification Event: Power distribution pass/fail test
Hazard: Power disconnection device fails to break circuit during
power shortage logic test
Causal Factors
1) Overheating
2) Supplier failure to verify test equipment
3) FOD
Mitigation Plan
Effects
Test Resources
Set-Up
1. Assemble integrated truss structure
2. Mount system into test stand
Facilities
3. 600ft x 600ft floor space
4. Mount
5. UV simulation bulbs
6. Control Room
6
Test Resources
Data Collection
1.Digital oscilloscopes
Verification Status
Risks
Cost Risk:
Contingency Plan