Professional Documents
Culture Documents
• A panacea for all ills – it cannot turn a fundamentally bad design into a
good one (although it can reveal how bad it is!).
Even if every aspect could be modelled, the desirability of accepting and certifying an
electrification system without one or more practical demonstrations is open to
debate.
Approximately 175 single track kilometres of lines were wired from Britomart
station to Swanson, Papakura, Manukau and Onehunga.
A simple 25kV electrification system with rail return and aerial earth wire / return
conductor is being used. No booster transformers are provided.
6kA maximum fault level.
25kV Switchgear is Siemens GIS Vacuum (35 panels), housed in prefabricated steel
buildings.
Protection and control functions integrated into Intelligent Electronic Devices (IEDs)
directly interfacing with the SCADA system.
OLE is a licensed version of the Balfour Beatty Mk3 design (used extensively in the
UK, Australia and Asia). Major steelwork and fittings manufactured locally.
Early liaison with industry regulators (such as Radio Spectrum Management and NZ
Electricity Regulator) to identify necessary standards, specifications and test
protocols.
AEP identified need for a dedicated, experienced resource to perform the role of
“Commissioning Manager” at least 1 year before first commissioning activity to
develop and manage testing activities.
As testing would involve high risk activities (short circuit testing) it was decided to
seek out personnel that had recent experience of this type of test. The last AC short
circuit tests in NZ took place in 1983.
How:
• Basic electrical integrity tests,
• Cable insulation resistance,
• Sheath integrity,
• OLE construction earths removed?
• Current return paths healthy,
• Loop impedance values OK.
• Majority of short circuit tests performed from the trailer mounted on the hi-rail
flatbed.
• A number of locations utilised the trailer in “road” mode.
• Typically takes 60 to 90 minutes to set up circuit breaker and measurement
equipment
• Incoming current.
• Track feeder currents.
• Return current via rails and their red
bond connections to the return
current busbar.
• Return current via the feeder station
earth system.
• Total return current.
• Busbar voltage.
Incoming feeder
CB
This short circuit is closest to the This short circuit is closest to the
feeder station, but most distant TSC, but most distant from the
from the TSC feeder station
This circuit breaker trips All current now flows along long path with
first, having detected higher impedance, the total current falls
fault in Zone 1
WSF13 track feeder current 1 hour r.m.s. (A) 186A 81.2 -56%
WSF18 track feeder current 1 hour r.m.s. (A) 17A 13.9A -18%
WSF12 track feeder current 1 hour r.m.s. (A) 94A 69.0A -26%
WSF13 track feeder current 1 second peak. (A) 664A 379A -54.0%
WSF18 track feeder current 1 second peak. (A) 189A 156A -17%
WSF12 track feeder current 1 second peak. (A) 363A 277.9A -23%