[Weekly TANK7]

Photo-1:Tank Area Whole View (Tank area from R38 side)

Photo-2:Tank Area Whole View (Tank area from Laydown side)

2014/08/03

[Weekly TANK7]

Photo-3:Backfilling Area Whole View

Photo-4: The Situation of Excavation

2014/08/03

[Weekly TANK7]

Photo-5: The Situation of Access Road 2

Photo-6: The Situation of Bench Drain Excavation

2014/08/03

[Weekly TANK7]

2014/08/03

Photo-7: The Situation of Worker Shelter Construction


Remarks:
This Week Main Activity
1.Tank Area Excavation/Soil Disposal/Slope Trimming/Interceptor & Bench Drain Excavation
/ Access Road 2 Excavation
2.Laydown Area Worker Shelter Construction
3.Backfilling Area Soil Filling
Next Week Main Activity
1.Tank Area Excavation/Soil Disposal/Slope Trimming
/Interceptor & Bench Drain Excavation & Casting/ Access Road 2 Excavation
2.Laydown Area Worker Shelter Construction/Water Pipe Line installation
3.Backfilling Area Soil Filling/RCP Calvert Installation
Site Work Progress
1.Tank Area Excavation Volume 97,300m3
2.Complete of Road Widening Work for R38
Site Close
28-29/July due to Hari Raya
Staff
9/Aug -18/Aug :Mr. Hayashi will go back to Japan