The weekly report documents 7 photos from August 3rd, 2014 showing the progress of excavation work for a tank area, including soil disposal, slope trimming, and interceptor and bench drain excavation. Access road 2 and worker shelter construction are also in progress. Next week's planned activities include continuing excavation and drainage work, access road excavation, shelter construction, and water pipe installation. As of the report date, 97,300 cubic meters of soil have been excavated from the tank area and road widening of R38 is complete. The construction site was closed on July 28-29 for Hari Raya.
The weekly report documents 7 photos from August 3rd, 2014 showing the progress of excavation work for a tank area, including soil disposal, slope trimming, and interceptor and bench drain excavation. Access road 2 and worker shelter construction are also in progress. Next week's planned activities include continuing excavation and drainage work, access road excavation, shelter construction, and water pipe installation. As of the report date, 97,300 cubic meters of soil have been excavated from the tank area and road widening of R38 is complete. The construction site was closed on July 28-29 for Hari Raya.
The weekly report documents 7 photos from August 3rd, 2014 showing the progress of excavation work for a tank area, including soil disposal, slope trimming, and interceptor and bench drain excavation. Access road 2 and worker shelter construction are also in progress. Next week's planned activities include continuing excavation and drainage work, access road excavation, shelter construction, and water pipe installation. As of the report date, 97,300 cubic meters of soil have been excavated from the tank area and road widening of R38 is complete. The construction site was closed on July 28-29 for Hari Raya.
Photo-1:Tank Area Whole View (Tank area from R38 side)
Photo-2:Tank Area Whole View (Tank area from Laydown side)
2014/08/03
[Weekly TANK7]
Photo-3:Backfilling Area Whole View
Photo-4: The Situation of Excavation
2014/08/03
[Weekly TANK7]
Photo-5: The Situation of Access Road 2
Photo-6: The Situation of Bench Drain Excavation
2014/08/03
[Weekly TANK7]
2014/08/03
Photo-7: The Situation of Worker Shelter Construction
Remarks: This Week Main Activity 1.Tank Area Excavation/Soil Disposal/Slope Trimming/Interceptor & Bench Drain Excavation / Access Road 2 Excavation 2.Laydown Area Worker Shelter Construction 3.Backfilling Area Soil Filling Next Week Main Activity 1.Tank Area Excavation/Soil Disposal/Slope Trimming /Interceptor & Bench Drain Excavation & Casting/ Access Road 2 Excavation 2.Laydown Area Worker Shelter Construction/Water Pipe Line installation 3.Backfilling Area Soil Filling/RCP Calvert Installation Site Work Progress 1.Tank Area Excavation Volume 97,300m3 2.Complete of Road Widening Work for R38 Site Close 28-29/July due to Hari Raya Staff 9/Aug -18/Aug :Mr. Hayashi will go back to Japan
CH-CP-In-Extension of Existing Breakwater, Construction of Beach Protection Bund and Groyne Using Geotextile Tubes, Petronet, Kochi Rev 01 July 2015.compressed