You are on page 1of 3

Important Points to Remember for Quantity Estimation.

Civil Works:
To carefully note the various levels while calculating excavation &
backfilling.
To make note of the various levels of the structure & compare the
measured heights/length of various items with the levels.
To check all the sections & elevations carefully prior to any estimation.
To look into the NOTES given at the right side of the drawing in the
info column.
To look out for trenches, drops, slab elevations, projections & many
others.
To check for different slab depths over the plan.
To carefully look into the openings, their types & numbers.
To measure the height of the pedestal & columns up to the top level of
above Ground (plinth) & Roof beams respectively.
To measure the length of the beam from column face to face.
To carefully note the various given dimensions of the different
structures.
To carefully carry out the estimation of staircase, trenches etc.
separately.
To carefully note the beam positions & their depths while calculating
Block/Brickwork.
To consider the height of the wall for internal plastering works up to
the slab bottom & thereby considering deductions for openings.
To carefully note the beams bottom surface (where there is no block
work) for roof bottom plastering.
Steel Reinforcement:
To carefully name & number every individual rods before any
calculations & workout the no. of rods, length & span accordingly &
individually.
To learn the extra length formulae for the 45 & 30 deg cranks.
To learn the calculations of the length & no. of rods for the top
reinforcement in slab.
To carefully note the data while calculating the length of rods, their
numbers, their span of distribution etc.
To carefully keep note of the covers for various items of the structure.

To carefully note the bends, elevations, cranks, while calculating length


of rods.
To carefully calculate the stirrups, their shapes, bends & the no. of
stirrups for columns & beams Please learn about no. of branches of
stirrups.
To learn the measurement of lengths of 45, 90 deg bends, small cranks,
hooks etc.
Unit Weight of steel (Kg/m)

Unit Weight of steel (Kg/m)


(Kg/m3)

Area (mm2) X Density

(Pi * d2) / 4

7850.

3.141*d2 / 4

7850.

Since d is in mm, convert it into meters by diving it by (1000)

cum
sqm
m
feet
inch

3.141*d2*7850/ (4*(1000)2)

(3.141*7850*d2) / (4000000)

0.00616 * (d2)

d2 / 162.

1
1
1
1
1

=
=
=

1 cum of cement
1 bag of cement (50kg)
1 sqm of block work =

1 cum of brick work =


1 sqm of brick work =

30.31 cft.
10.76 sft.
3.28 ft.
=
0.305 m.
=
25.4 mm.
=
1440 kgs.
=
0.034 cum.
13 blocks (for 6 & 8),
15 blocks (for 4 block)
473 bricks
44 bricks

M5
M7.5
M10
M15
M20
M25

=
=
=
=
=
=

1:5:4
1:4:8
1:3:6
1:2:4
1:1.5:3
1:1:2

Steps in Quantity Estimation


1.
2.
3.
4.
5.
6.
7.

Excavation - Individual footings / Entire Area with extra working space.


Backfilling - By Parts / Total excavation minus concrete qty below GL.
Column Necks/Pedestals - up to Grade Beam top level.
Plinth/Grade Beam - PCC & Concrete (Column face to face).
Columns - Grade Beam top to Roof Beam bottom.
Grade Slab - PCC, moisture insulation polyethylene & concrete.
Water Insulation/Bitumen for the substructure
Footing bottom, side & top
Column neck sides
Concrete Walls
Grade beams below GL
Grade Slab Bottom
8. Roof Beam concrete
9. Roof Slab Concrete
10.
Parappet Wall - RCC / Block work
11.
Lintel Concrete
12.
Block work
13.
Plastering - Ceiling, Wall - ext & int, jambs.
14.
Painting
15.
Flooring - cement, tiles, marble etc.
16.
Schedule of openings
17.
Floor Finishes
Roof Concrete slopes
Heat insulation layers
Screed concrete
Mortar floor

You might also like