Bill of Quantities for Construction of House Type 250m2

1. All the works should be done according to Iraqi General Technical Specification (I.G.S.T) that
complies
with SORB Applied according to the instructions of the supervisor engineer.
2. All materials must be NEW of best types. Approved by supervisor Engineer.
3. All construction materials should be tested according to Construction Works Specification by
NCCL (National Center for Construction Laboratories 1981 edition), and (ASTM) American
Society for Testing and Materials specifications.
4. The contractor shall provide samples for all materials to be used in the project prior to using
them in order to get approval from supervisor Engineer.
5. It is the duty of the contractor to check the designs for accuracy and adequacy, otherwise the
Employer takes no risk of the contractor's failure to accomplish the work.
6. The contractor shall provide all required manpower, transportation, equipment, tools,
machinery ... etc unless otherwise stated below.
7. In case of any difference between BoQ, designs and/or drawings; the instructions of supervisor
Engineer will govern.
8. After all works are finished, the site must be cleaned from all debris, and neglected materials
must be removed to a location defined by municipality.
9. The contractor shall provide all safety equipment and requirements in the site (warning tape,
cap, vest, etc,,,).
N.B
10. The contractor shall supply and prepare site engineer office with furniture, survey
instruments, and stationary, computer with printer as well as suitable kitchen and W.C.
11. The contractor shall employ permanent site engineer who has min. 3 years of experience,
12. The final Design and BoQ might be changed according to the site topography, requirements
and conditions.
13. For the excavation activities, the contractor shall erect safe crossing bridges with protecting
hand rails in numbers and locations based on the site engineer instructions.
14. In case of crossing water alignment with public streets and roads, the contractor shall
construct on his own expenses alternative temporary roads with good maintenance till the
finishing date of the work and he shall repair all the streets to match the original case.
15. The contractor shall erect 3 signboards for the project in dimensions (2*1.5m) to be fixed till
the finishing date.
16. The contractor shall fix warning signals across the trench according to the instructions of
supervisor engineer.
17. The contractor shall restrict the locations of the manholes as indicated by supervisor
engineer.
18. For the excavation works, the contractor shall excavate the needed span for both sides of the
trench edges to have the adequate space for the work activities.
19. The contractor shall use only best quality/brands of paints.

Page 1 of 4
Unit
Total Amount
No. Items and Description Unit Qty. price
IQD
IQD
1st Construction Works:

1 Site Preparation & Earth Works.


Insect control : Supplying and using chloride or
Durspan (according to the instructions of the
producing company) by spraying it under the
1.1 L.S. 1
foundations, floors, under the walkways, as well as the
sides of the foundations, according to the directions of
the supervising engineer.
2 Concrete Works :
Concrete Works: All works will be carried out accoring to section 600 of I.G.T.S
details in the attached drawings and instrutions of supervising engineer, the price
includes supply of materials (cement,steel bar, aggregate, water, etc)
Reinforced Concrete Foundation: Supply
materials,with thick nylon laying and casting
reinforced concrete for foundation with strength not
less than 26 Mpa, using salt-resistant cement with a
water content of not more than 45% of the weight of
2.1 m3 67
the cement,the price includes using vibrators ,curing
and form works for columns foundation should be
using a new playwood as long as it has a clean surface,
according to the drawings and instructions of site
engineer.
Reinforced concrete(Columns of ground floor ) :Supply
materials, equipment ,forms and all requirements for
casting concrete 1:1.5:3 with compressive strength 35
Mpa for columns of ground floor (height 3.2m) and
with water content of not more than 45% of the weight
2.2 m3 10
of the cement,,the price includes using vibrators
,curing and form works for columns should be using
new playwood as long as it has a clean surface,
according to the specifications, details, drawings and
instructions of site engineer.

Page 2 of 4
Reinforced concrete (Columns of first floor ): Supply
materials, equipment ,forms and all requirements for
casting concrete 1:1.5:3 with compressive strength 35
Mpa for columns of first floor (height 3.2m) with water
content of not more than 45% of the weight of the
2.3 m3 8
cement,the price includes using vibrators ,curing and
form works for columns should be using new
playwood as long as it has a clean surface, according to
the specifications, details, drawings and instructions of
site engineer.
Reinforced concrete (slabs,beams,tie beams, stairs,
lintels for ground floors) :Supply materials, equipment
,forms and all requirements for acting slabs, beams, tie
beams, stairs, lintels using concrete with a mixing
ratio of (1:1:5:3) and with a compressive strength of
2.4 m3 45
not less than 35 MPa, with a water percentage of not
more than 45% of the weight of the cement,according
to the specifications, details, drawings and instruction
of site engineer,the price includes using vibrators
,curing and form works.
Reinforced concrete(slabs,beams,tie beams, stairs,
lintels for first floors ) :Supply materials, equipments
,forms and all requirements for acting slabs,beams,tie
beams, stairs,lintels using concrete with a mixing
ratio of (1:1:5:3) and with a compressive strength of
2.5 not less than 35 MPa, with a water percentage of not m3 35
more than 45% of the weight of the cement should be
using new playwood as long as it has a clean surface,
according to the specifications, details, drawings and
instructions of site engineer, the price includes using
vibrators ,curing and form works.
Supply and istallation Lintel precast (10x10) for doors
2.6 M.L 26
according to to the dimensions
Supply and istallation Lintel precast (10x20) for
2.7 M.L 30
windows according to to the dimensions
3 Masonry Works :

MANSORY WORKS: All works will be carried out accoring to section 500 of
I.G.T.S details in the attached drawings and instrutions of supervising engineer,
the price includes materials creation pointing, with all other necessery works.

Page 3 of 4
Building Walls : Supply materials and construct wall
by red bricks (just labor without buying) with
dimensions 20 * 20 * 40 cm manufactured cement
3.1 mortar with a mixing ratio of (1:3) and according to m3 85
the dimensions and levels shown in the drawings and
according to the directions of the supervising engineer.
(A Machine saw should be used for cutting bricks )
Hollow concrete block Wall : Supply materials and
construct walls for fence by hollow concrete block (just
labor without buying) 20x20x40cm with cement
3.2 m3 25
mortar (1: 3). All the works should be done according
to specifications, details and instructions of site
engineer.
Hollow concrete block Wall : Supply materials and
construct walls for parapets by hollow concrete block
(just labor without buying) 15x20x40cm with cement
3.3 m3 15
mortar (1: 3). All the works should be done according
to specifications, details and instructions of site
engineer.
4 Sanitary Works :
Supply and fıxıng water pıpe (4'' )110MM SN4,PN6
U.PVC- for heavy water, (Egyptian made) the prıce
4.1 m.l 95
ıncludes all fıttıngs wıth all necessary works accordıng
to detaıls and instructions of supervising engineer.
Supply and fıxıng water pıpe (2.5'' )63MM SN4,PN6
U.PVC- for heavy water, (Egyptian made) the prıce
4.2 m.l 10
ıncludes all fıttıngs wıth all necessary works accordıng
to detaıls and instruction of supervising engineer.
Supply excactor to drilling Cesspool for
W.C depth is 10m and diameter is 0.8 cm
4.3 with installation of concrete pipes and caps with all m.l 10
necessary works accordıng to detaıls and
instructions of supervising engineer.
supply and intallation plastic manholes
0.3x0.3x0.3 with all necessary works
4.4 NO 10
accordıng to detaıls and instructions of
supervising engineer.

Total