Professional Documents
Culture Documents
Project Engineering in Oil & Gas Industry Shared
Project Engineering in Oil & Gas Industry Shared
Content
Engineering Management :
Reasons to be an Engineer in Oil & Gas Industry
Q&A
NEW EXPL
. INITIATIVE
DISCOVERY
WELL
PRODUCTION
START-UP
DEVELOPMENT
PRODUCTION
Evaluation
Gt1
Concept
Selection
Gt2
Concept
5
Definition
Gt3
Execution
Value Realization
Activities
Selection of the
Preferred Option
(s) of the
Development
Basic Design,
Tender, FEED
EPCI
Well Operation
Pre-Commissioning
Generate concept
alternatives, select
and optimise the
preferred concept
based on
technical,
economics and
risks evaluation
Refine selected
concept, complete
tendering and
produce a Project
Execution Plan
which allows
project sanction
Execute the
project to achieve
a fully operating
system meeting
cost, time and
quality targets
Is the
selected
concept the optimal
development
alternative?
Can the
planned project
be successfully
executed and
create value?
Main Question
Discovery
Evaluation
Screening
Objective
Value Identification
Does the
opportunity
support an
economic
development?
Commissioni
ng, Start-Up
and
Perf. Test
Hand
over
Is the asset
ready for
production
?
Commissioning
Production Start-Up
Project Evaluation
Close Out
.
Start up, operate
and evaluate the
asset to maintain
performance &
maximum return
to shareholders.
Evaluation
Gt1
Concept
Selection
Gt2
Concept
Definition
Gt3
Execution
Hand
over
Commissioni
ng, Start-Up
and
Perf. Test
Study Preparation
Basic Design
FEED
Detail Engineering
Construction,
Installation & PreComm
Commissioning &
Production Startup
Study Preparation
Objective
To define preliminary facilities layout and treatment plant options on the basis of the
existing production parameters evaluation, drilling development options and other
constraints
To estimate expenditure with the degree of uncertainty expected in the different
exploration and development project phases
To estimate the technical and economical feasibility of the different facilities concept
alternatives.
Deliverables
Pre-feasibility study
(evaluation phase)
oBlock diagrams
oProcess schemes
oGeneral layout
oConstruction and installation
Feasibility study
(concept selection phase)
oBlock diagrams
oFacilities schemes
oGeneral layout
oMain equipment general arrangement
oSite technical requirements
oConstruction and installation criteria
o Cost/Schedules estimates
Basic Design
Objective
To specify the content of the work carried out during the Detail Engineering phase and
point out critical design aspects.
To define the project specifications and tender documents for the Detail Engineering and
Construction phase and for the acquisition of critical items.
To define and identify the project elements to a level of technical completeness sufficient to
evaluate their initial and operating costs with a target accuracy of 20% for plants and
equipment and of 10 % for structural items.
Deliverables
Basic Design Book.
First version of Project Development Plan (PDP).
oFacilities Technical documents
oProject Scope for Joint Ventures and
(schemes, layout etc.)
Authority approval
oTechnical Specifications for long
oDescription of selected concept
lead items
oCreation/alignment with Business Plan
oEquipment lists
oDevelopment Schedule
Decommissioning Study
Cost Estimates.
Risk Management Plan (Update)
Information Communication Technology
Maintainability / Operability Philosophy.
Strategy and
Constructability and installability analysis. implementation plan.
Logistics Plan
FEED
Objective
To update and complete the Basic Design results.
To define the project specifications and tender documents for the Detail Engineering and
Construction phase and for the procurement of critical and Long Lead Items.
To define and identify the project elements to a level of technical completeness sufficient to
evaluate their initial and operating costs with a target accuracy of +/-15% based on
documented cost definition of main and secondary items and systems from Vendors and
market analysis.
To prepare more accurate time schedule .
Deliverables
FEED Design book.
oFacilities Technical documents (schemes,
layout etc.)
oTechnical Specifications for long lead ad main
items
oUpdated Equipment lists
oDevelopment Schedule
Decommissioning Study
Logistics study and functional
specifications
Constructability and installability analysis.
Revised documented Cost Estimates.
Objective
Design all plant systems, structures, items and bulk materials with the detailed
information needed for their procurement, construction, transportation and installation.
Prepare the necessary documentation Approved for Construction, including specifications
for materials to be acquired and adequate procedures to support the planned operations.
Support the engineering activities related to material procurement, construction,
transportation, installation and pre-commissioning.
Manage the activities deriving from changes and integrations arisen during all the above
said activities up to the Handover.
Deliverables
Detail Engineering book including:
o Final Technical Specifications
o As built General plant layout and
arrangement drawings
o As built PFD and P&ID
o Final Equipment and Instrument Data
sheets
o Final as built drawings
Deliverables
Final ESD study
Final Hazard reports
Environmental compliance reports
Waste management report
SCADA reports
Final project IT Plan
Final document list
Transportation Plan
Test run specifications
Reference Cost database
Engineering CAPEX
Engineered Equipment CAPEX
Bulk material CAPEX
Construction CAPEX
Objective
Organize construction, installation, hook-up activities and pre-commissioning at site according
to the following:
Onshore/Offshore Constructions at Contractors/Vendors sites; i.e.
construction and pre-fabrication of equipment, tubing and components for treatment
facilities, off-shore structures, etc. This may be carried out at a Contractor/Vendor workshop
or at a work area situated (on the coast) close to the plant site.
Onshore Construction on Company sites; i.e.
construction of treatment plants, pipelines and components. When large spaces are
available close to the construction site most of the plant may be built there. Such spaces may
also be used for locating Contractors/ Vendors stores and warehouses.
Offshore Constructions in Company Areas; i.e.
installation of jackets, decks and flowlines and corresponding hook-up. This activity usually
requires large cranes barges for pre-fabricated jackets, decks and skids installation and for
following hook-up activities
Deliverables
Fabrication, Construction, Installation & Hook-up
Material Manufacturing
Data book
o Technical Specification
o Data sheets
o As-built drawings
o As-built 3D model
Installation, operation and maintenance
manual
o Test run specifications
o Operating plan and procedures
o Spare parts list
Pre-Commissioning
Test run specifications, including:
o Disposal of hazardous hydrocarbons during testing
o Commissioning procedures for introducing hydrocarbons
Mechanical Completion Certificates, including:
Testing Certificates
Operation permit
As-builtdrawings and documents
Objective
Commissioning: The main objective of this activity is to verify the proper running of all
components of asset and to test the overall process, output, quality and performance
against design specifications.
Start Up: Once the Commissioning has ended with positive results the Start Up can begin,
aimed at reaching the plant nominal operating conditions
Performance Test: This activity, also named Test Run, is the final test operated in the plant
in order to verify that the global throughput of the plant, and its related subsystems,
corresponds to the contractual requirements and that it can be satisfactorily operated in
any operating condition.
Deliverables
Performance Test certificate
Risk Assessment Report
Operations Organisation Plan
Start Up certificate
.As-built. Documentations and
Drawings
Facilities acceptance report
Engineering Organization
Ocean/Offshore/Naval
Engineering
Offshore
Structure
Subsea Pipeline
Marine/Naval
Mechanical
Engineering
Piping
Pipeline
Mechanical
Chemical Engineering
Process
Process Safety
Flow Assurance
Material/Metalurgy
Engineering
Material
Welding
Coating/
Corrosion
Physic
Engineering
Instrument
Subsea Control
Civil
Engineering
Civil
Structure
Electrical
Engineering
Electrical
Engineering Schedule
Oil Company
Project Team
Operator
EPCI
Companies
Vendors &
Manufacturers
Life of Field
7 Essentials of
Successful Engineering
Recruitment Process/Step
Process
Fresh Graduate
Experience
Administration Screening
Psikotest
Technical Test
Interview Psikologi
Group Discussion
Interview [User]
Interview [Manager/BoD]
Salary offering
Medical Test
PASS or FAIL
Engineering Resume
8 Killer Questions
Engineering Resume
Eight (8) Killer Questions
Questions ?