01 - Superconducting Fault Current Limiters - Latest Developments at Nexans SuperConductors (Noe For Bock)
01 - Superconducting Fault Current Limiters - Latest Developments at Nexans SuperConductors (Noe For Bock)
Mathias Noe
Karlsruher Institut fr Technologie
&
Joachim Bock, Achim Hobl, Judith Schramm
Nexans SuperConductors GmbH
EPRI 2011
Nexans SuperConductors
Outline
Introduction
SFCL systems
Function
Operation behaviour
Commercial Projects
ASL I 12-100
ASL II 12-400
Vattenfall 12-800
Development Projects
ENSYSTROB
ECCOFLOW
Conclusions
EPRI 2011
Nexans SuperConductors
Chemiepark Knapsack
in Hrth
Chemiepark Knapsack
10 km South-west of Kln
EPRI 2011
Nexans SuperConductors
Nexans SuperConductors
in new premises 2010
Office building and
assembly hall
bldg. 2728
Assembly of Fault Current Limiter systems
Building height allowing crane hook of 7 m
Optimisation of the production
EPRI 2011
Nexans SuperConductors
YBa2Cu3O7-x
buffer
buffer
2
1
substrate
Y-123 cc-tape
2nd generation
Systems
realized
Y-123 bulk
Bi-2212 bulk
EPRI 2011
Nexans SuperConductors
Production of HTS-bulk
BSCCO-2212
Melt Cast Processing
Highly efficient and
very flexible process
Melting
Metal oxides
Mixing
Casting
EPRI 2011
Annealing
Nexans SuperConductors
Operating behaviour
of the FCL
normal operation
short-circuit
recovery
w/o FCL
ultrafast
reacts in 1-2 milliseconds
current
automatic
max
wear-free
td
ta
tr
time
EPRI 2011
Nexans SuperConductors
FCL systems
Commercial Projects
12-100 (ASL 1)
first commercial system
Field tested for ~8 months
12-800 (Vattenfall)
first system in a power station
Field tested Nov. 2009- Dec. 2010
XX-YYY
XX: Voltage [kV]
YYY: Current [A]
12-400 (ASL 2)
second system for UK (bifilar)
Presently under installation
EPRI 2011
Nexans SuperConductors
ASL I 12-100
Realisation
EPRI 2011
Nexans SuperConductors
ASL I 12-100
Field test
ASL, Newcastle
ENW, Bamber Bridge
Live on grid
10-2009 to 06-2010
EPRI 2011
Nexans SuperConductors
ASL II 12-400
Testing
EPRI 2011
Nexans SuperConductors
ASL II 12-400
Installation site
Ainsworth Lane
(Scottish Power)
Nexans SuperConductors
Vattenfall 12-800
Brown Coal Power Plant
Block Q in Boxberg
EPRI 2011
Nexans SuperConductors
EPRI 2011
Nexans SuperConductors
EPRI 2011
Nexans SuperConductors
Auxiliary Power
EPRI 2011
Nexans SuperConductors
Auxiliary Power
Investment
Current [A]
63.000
800
rating
fault
Nexans SuperConductors
Location
in Boxberg power plant
EPRI 2011
Nexans SuperConductors
Nexans SuperConductors
BSCCO-2212
tubes
BiSrCaCuO
powder
EPRI 2011
Nexans SuperConductors
Basic design
of the FCL
Connection for adaptation
Current in parallel
Voltage in series
component
module
set-up
of a phase
accomodation
in a cryostat
Nexans SuperConductors
Realisation
of the FCL
Nexans is mastering
the full chain.
EPRI 2011
Nexans SuperConductors
Testing scheme
75 kV lighting impulse
28 kV withstand voltage (1 min)
Testing scheme
63 kA (peak) maximum
3-phase full loads (4 shots)
EPRI 2011
Nexans SuperConductors
New developments:
FCL systems based on cc-tape
12-600 (ENSYSTROB)
first MV system with cc-tape
This project has received funding
from German government under grant 03KP102A
EPRI 2011
Nexans SuperConductors
New developments:
ENSYSTROB
Specification
ENSYSTROB
voltage
12 kV
normal operating current 800 Arms
inrush current (50 ms)
4100 Ap
High current
inrush(15
currents
inrush
s)
1800 Arms
Small window
current
prospective
currentfor limited
60 kA
first peak limitation
< 30 kAp
limitation time
120 ms
limitation after 100ms
6.6 - 7 kA
EPRI 2011
Nexans SuperConductors
New developments:
ENSYSTROB - component
U = 433 Vrms
I = 850 Arms
P = 360 kW
I
2 twins in, 2 twins out
sc-length: 8 x 4.30
Central contact
EPRI 2011
Nexans SuperConductors
New developments:
ENSYSTROB characterisation (1)
inrush currents
1367 Ap / 50 ms
600 Arms / 15 s
EPRI 2011
Nexans SuperConductors
New developments:
ENSYSTROB characterisation (2)
short circuits
partial load
I prosp = 2 kAp
Erms = 0.05 V/ m
full load
I prosp = 32 kAp
Erms = 50 V/ m
EPRI 2011
Nexans SuperConductors
New developments:
ENSYSTROB system integration
3 x 32 =96
components
EPRI 2011
Nexans SuperConductors
New developments:
ENSYSTROB Testing at IPH Berlin
Nexans SuperConductors
New developments:
ENSYSTROB Next steps
EPRI 2011
Nexans SuperConductors
EU-project: ECCOFLOW
cc-tape based FCL 24-1000
15 partners involved
5 utilities
coordinated by
Stockholm
Siegen
Kosice
Barcelona
Mailand
EPRI 2011
New developments:
ECCOFLOW
ECCOFLOW is:
A project to prepare
commercialisation of SFCL
The 3-phase resistive limiter with
the highest voltage today
Including 15 project partners
5 of which are utilities
The first SFCL foreseen for two
different applications
EPRI 2011
Nexans SuperConductors
New developments:
Project 24-1000 ECCOFLOW
Palma de Mallorca
transformer
feeder
FCL
High voltage
Medium
voltage
FCL
busbar coupler
EPRI 2011
New developments:
Project 24-1000 ECCOFLOW
2nd site for installation
Koice (VSE)
High voltage
transformer
feeder
FCL
VSE grid
Koice, Slovakia
Medium
voltage
FCL
busbar coupler
EPRI 2011
Nexans SuperConductors
New developments:
Project 24-1000 ECCOFLOW
Endesa
VSE
Eccoflow
Nominal voltage
16.5 kV
24 kV
24 kV
Nominal current
1000 A
1005 A
1005 A
AC withstand voltage
50 kV
50 kV
50 kV
Lightning impulse
125 kV
125 kV
125 kV
22 kA
26 kA
26 kA
10.8 kA
17 kA
10.8 kA
Fault duration
1s
120 ms
1s
80 ms
80 ms
80 ms
Recovery time
< 30 s
< 30 s
< 30 s
EPRI 2011
Nexans SuperConductors
New developments:
Project 24-1000 ECCOFLOW
limitation
time > 120 ms
Air Core
System
Reactor
Module of
FCL
FCL inside
components
cryostat
with
parallel impedance
FCLbreaker
and circuit
Circuit
Breaker
Black Box
inrush currents
> 1.2 kA
EPRI 2011
Nexans SuperConductors
New developments:
Project 24-1000 ECCOFLOW
Component Design
3 x 2 x 2 conductors, about 8 m each
1 kArms / 800 Vrms
no parallel connection of components
needed
excellent use of volume
low voltage for the single component
small AC losses due to multifilar
geometry
short single pieces of superconducting
tape with mutual protection.
EPRI 2011
Nexans SuperConductors
New developments:
Project 24-1000 ECCOFLOW
Module Design
Stack of 12 components in
series
Liquid / gaseous nitrogen
insulating against cryostat
wall
EPRI 2011
Nexans SuperConductors
New developments:
Project 24-1000 ECCOFLOW
Cryostat Design
3 nitrogen vessels
One common
vacuum vessel
Boiling nitrogen at
77 K
About 100 W
thermal losses
G-M cryocooler
Compact design
Design close to
series production
EPRI 2011
Nexans SuperConductors
New developments:
Project 24-1000 ECCOFLOW
Cryostat Design
3 nitrogen vessels
One common vacuum vessel
Loss contribution
Loss at 0.1 Ic
Loss at 0.5 Ic
Loss at 1 Ic
<1W
~ 10 W
150 W
180 W
~ 220 W
270 W
Cryostat loss
120 W
120 W
120 W
1W
15 W
60 W
~ 300 W
~ 365 W
600 W
~ 6990 W
8504 W
13980 W
EPRI 2011
Nexans SuperConductors
Latest Project
AmpaCity
110-kV-substation
110-kV-substation
(suburban area)
(suburban area)
40 MVA
Conventional
110-kV-Cable
10-kV-HTS cable
40 MVA
10-kV-substation
10-kV-substation
(city center)
(city center)
Nexans SuperConductors
AmpaCity
Feasibility Study
Nexans SuperConductors
AmpaCity
in the City of Essen
Herkules
Dellbrgge
position of joints
EPRI 2011
Nexans SuperConductors
AmpaCity
HTS cable with stand alone FCL
EPRI 2011
Nexans SuperConductors
Conclusions
Full chain mastered from production of HTS material to
final FCL system (for bulk)
Nexans SuperConductors
Thank you
for listening!
EPRI 2011