A1

7 min

A2

13 min

A3

12 min

A4

30 min

A5

5 min

There are three servers


S1, S2, S3
S1= A1 and A2
S2= A3

7+13=20 min

12 min

S3= A4 and A5

30+5=35 min

IU1: Bottleneck = S3 = 1/35= .029


IU2: Utilization depend upon bottleneck that is .029
Question no 2
A)
Beds = 120
Stays= 10 days
I=R*T
1200= R*10
R=120
B)
First day spending=50*120=6000
Additional day spending=30*1080=32400
Total revenue= 38400
Stay days changes from 10 to 5 day
So,

Flow rate will be 240


First day spending=50*240=12000
Additional day spending=30*960=28800
Total revenue= 40800
Change in revenue = 40800-38400=2400 per day

Question 4
DMV1:
400*1%, fail 4, 396*15%, fail 59.4, 366.6*30%, fail 100.98, pass 235.62
Pass 235.62 per day
DMV2:
Activity

Capacity per hour Demand per hour

Implied utilization

A.I

4/5*60=48

400/8=50

50/48=1.04

W.E

2/3*60=40

396/8=49.5

49.5/40=1.24

R.E

15/20*60=45

336.6/8=42.075

W.E is bottleneck as implied utilization is 1.24

DMV3:
Answer 190

42.075/45=.935