11th of Moon shutdown Jo

Job Area
MVR VFD Panel
Distribution Panel Evap
Io`s Panel 1601CC01,1601CC02
1637 PU01,1638 PU01, 1639PU01( Past Pump)
Cooling Tower Fans
Air intake fan motor
Fire Water Pump
Dryer & Evap Motors
AHU Panels

11th of Moon shutdown Jobs - April 2015


Job Description
Inspection , cleaning
Inspection & Cleaning & Add New Breaker For Aux Supply
Inspection & Cleaning
Inspection & Cleaning
Inspection & Cleaning
Inspection & Cleaning
Inspection & Cleaning
Inspection & Cleaning
Inspection & Cleaning

- April 2015
Duration reqd (hrs)

Utilities shutdown reqd

2(hrs)

EVAP Shutdown

2 (hrs)

EVAP Shutdown/ Aux Power

2(hrs)

EVAP Shutdown

2 (hrs)

EVAP Shutdown

2(hrs)

EVAP Shutdown

2(Hrs)

Dryer Shutdown

2(hrs)

Dryer Shutdown

5 ( Hrs)

Dryer Shutdown

2 (hrs)

Dryer / Evap Shutdown