You are on page 1of 30

APPENDICES

Malaysian Sewerage Industry Guidelines Volume II

219

220

Sewerage Works Procedures (This page is intended to be blank)

Appendices

Appendices

Appendix A

Guide For An EIA Reports

Appendix B

Report Format and HAZOP Study and Checklists

Appendix B1

HAZOP Checklist for Sewage Treatment Plant

Appendix B2

HAZOP Checklist for Pump Station

Appendix C

Basic Guide of Sewerage Layout Plan Submission in Digital Format

Appendix D

Content for Operation and Maintenance Manuals

Appendix E

Tabular Amounts of Performance Bond

Appendix F

Standard Format for Performance Bond

Appendix G

Bank Guarantee for Upgrading of Existing Public Sewerage System

Appendix H

Letter of Indemnity for Upgrading Works

Appendix I

Typical Project Signboard for Upgrading Works

Malaysian Sewerage Industry Guidelines Volume II

221

Appendix A

Guide for an EIA Report


WATER SERVICES INDUSTRY ACT 2006

GUIDE FOR DETERMINING THE NEED FOR AN EIA


Developments of certain criteria will require an EIA study that covers its sewerage works
proposals. The EIA must be submitted and approved by the Department of Environment
(DOE) prior to detail sewerage works planning approval. However, regardless of the type and
size of a development, all sewerage works will need to submit a complete Environmental
Criteria Evaluation form.
Development EIA
As per the Environmental Quality Order (Prescribed Activities) (Environmental Impact Assessment),
1988, Schedule 7, for a development that covers an area of 50 hectares or greater, the developer must
obtain an EIA approval for the entire project. A section of the assessment must cover the sewerage
aspects of the development, which includes the network system, sewage treatment plants, and/or
sludge treatment facilities. The EIA must address land area requirements for the STP and ensure
sufficient buffer to minimize impact onto its surrounding developments. Buffer requirements as
stipulated in this guideline must be addressed.

Preliminary EIA
All STPs constructed by government or its appointed agents, and STPs constructed by developers
which are given permanent status and to be handed over as regional public STPs would require a
separate preliminary EIA approval from DOE.

Environmental Criteria Evaluation


The purpose of this criteria checklist is to ensure that the environmental impacts associated with the
plant are minimized when the plant becomes operational. The evaluation includes issues on siting the
plant, water quality and design with environmental considerations.

Procedure for EIA Approval for Development


EIAs shall be prepared according to the DOEs guidelines and requirements covering all aspects of
sewerage works which includes network, sewage treatment plant and/or sludge treatment facilities,
where applicable.
The Commission shall be informed of any submissions to the DOE and a copy must be attached with
other application documents. The same shall be done once the EIA approval is received from the
DOE, highlighting the approval conditions. This is necessary, as EIA approval is part of the
Commission sewerage works approval procedure.
Note: All developments which do not fit the above development criteria are exempted from EIA
requirements.

222

Sewerage Works Procedures

Appendices

Appendix B Report Format for HAZOP Study and Checklist


GUIDE TO CARRY OUT HAZOP STUDY AND FORMAT FOR HAZOP REPORT 20,000 PE.

The methods presented here are not intended to be prescriptive and a certain amount of flexibility will
be required to apply these techniques to different types of projects with different contract strategies.

1.0

HAZOP Study

HAZOP study is a procedural tools designed to identify the safety and operability deficiencies in the
design of a treatment facility.
Once a potential cause has been identified in the HAZOP study, the HAZOP study team will identify
the potential consequences. If the cause is feasible, and the consequences severe enough, a member
of the study team may have to investigate the potential means of eliminating or reducing the problem.
Fact finding actions may also be raised if sufficient information is not available at the meeting to
discuss causes and consequences.

2.0

HAZOP Study Team Members

HAZOP Study ideally should have team members of multi-disciplines involved in the design and
operation of the plants. Team members must have a detailed knowledge of the design intentions
and/or intended operation of the plant. The team must contain people with sufficient knowledge and
experience to identify and understand the consequences and importance of deviation or deficiencies
pertaining to design of the plants.

3.0

Format of HAZOP Report

Upon ultimate completion of a HAZOP, i.e. once all actions have been satisfactorily resolved, a
HAZOP report will be produced and the report should consist but not limited to the followings:

1. Executive Summary
2. HAZOP Signoff Sheet
3. Introduction and Objective
4. HAZOP Methodology and Techniques
5. HAZOP Team, Attendance and Meeting Agenda
6. The minutes of the HAZOP Study conducted comprising issues raised and action or
safeguard taken to resolve the issues, significance of issues raised, amended detailed
drawings to suit the HAZOP requirements and signing off of actions by the
responsible party

7. Summary of findings and outcome of the Study


8. Conclusion

Malaysian Sewerage Industry Guidelines Volume II

223

Appendix B1

HAZOP Checklist for Sewage Treatment Plant


CHECKLIST

ITEMS TO BE IDENTIFIED IN THE DRAWINGS

1.0 Overall Layout of Treatment Plant


1.1 General Layout

Property are fenced and gated and the fence height.

State where these problems/impacts occur and give


a description of the method employed in
controlling these impacts.
a.
Odour Control
b.
Noise Level
c.
Visual (Landscape)

Are all tanks and chambers above the safe flood


level and the highest flood level of the nearby
rivers/drain and design to what flood return period.

Are there any buried pipelines or cables under


buildings within the treatment facility and is it
clearly indicated on the layout drawings.

The layout of temporary diversion and location of


temporary treatment facilities.

Where is the location of the screening bins and


what is the basis of sizing the bins area.

Are lifting devices provided and state what type


and their location and capacity.

1.2 Access Road

Is the facility located near to a public road to allow


immediate access to the plant/facility? If not, state
where is its access route.

Are the ingress and egress routes to and from the


plant suitable for desludging tankers?

Are the entrance and exit gate nearby the public


road

Road access should be provided adjacent to the


equipment or crane extended to the nearest road.

If fixed crane beam extends over the road,the


minimum vertical clearance shall be 5.5m.

Adequate signage provided

Head clearance for tanker trucks entering the gate


provided and what is the clearance height.\

224

Sewerage Works Procedures

YES

NO

COMMENTS

Appendices

CHECKLIST
ITEMS TO BE IDENTIFIED IN THE DRAWINGS

Sufficient turning radius on the roads to enable


access and maneuverability for tankers and heavy
vehicles.

Location of sludge desludging area is suitable for


tankers to access and empty the sludge into the
chamber.

YES

NO

COMMENTS

1.3 Handrails/Guardrails and Access Ladders

Have safety handrails or grating been installed at


walkways and around open holes at the plant?

Toe plates and kick plates shall be fitted along the


outer edges of all walkways or ladders and shall
be part of the structure and not the floor panels.
Toe plates shall extends 100mm above the top
level of the floor panels. Floor panels shall be
sized so that each panel does not weight more
than 50 kg.

Handrailing provided at all places where there is


potential of falling around al tanks and other
places where falling height is greater than 1.5m.

Is staircases provided where height is greater than


300 mm. Fixed ladder to access working areas for
purposes of servicing, maintenance or normal
operation works.

1.4 Precaution Against Damp

All wall mounted equipment is fitted with spacers


to provide minimum gap of 5 mm.

All holes in equipment is sealed against the


ingress of water

Any items exposed to weather or water shall be


free of water traps and drain holes shall be
provided where necessary.

Electrical equipment which is not sealed against


free movement of air shall be protected from
condensation with anti-condensation heaters and
thermostatically controlled.

1.5 Substation / Electricity Meter/ Lamp Post

Location of electricity meter or the substation

Is adequate street lighting provided around the


plant and what is the number of lamp post
provided

Malaysian Sewerage Industry Guidelines Volume II

225

CHECKLIST
ITEMS TO BE IDENTIFIED IN THE DRAWINGS

Are all buildings and major process units at the


treatment facility lighted adequately

1.6 Buffer Zone

The following buffer zone requirements satisfied?

30 m minimum from fence to nearest


habitable building property line within
residential and commercial development
20 m minimum from the fence of treatment
plant to the nearest property line within
industrial development
10 m minimum from the fence of the
treatment plant to the nearest habitable
building property line if the proposed
treatment plant is fully enclosed.
1.7 Effluent Discharge Point

Where is the location of effluent discharge point


for the facility and is it clearly indicated on the
layout drawings with relation to existing receiving
water bodies.

1.8 Water Supply

If tankers and desludging activities take place, is


there provision for stand pipes for cleaning
purposes.

Where is the location of the stand pipe and


location for toilets for operators to change and
clean themselves after work.

2.0 Screen Chamber (Fine And Coarse Screens)


2.1 Bar Screens

Dewatering or perforated plate or trough,


provided for ease of maintenance of the screens

2.2 Mechanically Raked Screens

Automatic conveyor to transfer screenings to


skips.

Screen motor located above the high water level


and access provided for maintenance.

Provision of explosion proof floodlights.

Provision of emergency stop button at a


convenient and visible location

226

Sewerage Works Procedures

YES

NO

COMMENTS

Appendices

CHECKLIST
ITEMS TO BE IDENTIFIED IN THE DRAWINGS

A working platform for ease of operations and


maintenance.

Provision of hand rail or guard (Refer to item 1.3)

Location of screening bins must be near the


screen area.

Bins provided should have adequate capacity and


must be equipped with leachate collection tray
and covers to prevent odour release. Bins should
be provided with rollers.

YES

NO

COMMENTS

2.3 General

Provision of staircase access with sufficient width


(Refer to item 1.3)

All screen chamber sumps to be fully open at the


top for good ventilation

Inlet penstock provided to isolate the inlet works


for maintenance purposes.

All drive units shall be weatherproof

3.0 Pump Sump

Emergency overflow pipe to by-pass the influent


sewage during power failure (away from
residents) and location of overflow pipe
discharge.

Provision of crane for maintenance purposes

Sufficient access to the pump station either from


the top surface or via entry from the screen
chamber

Is dry well provided with force ventilation and air


outlet shall be located adjacent to pump motors to
assist cooling

Lighting systems shall be interconnected with


ventilation

Provision of handrails and MS grating (Refer to


item 1.3)

If the valve chamber is located in the sump, the


opening of the valve chamber shall be enclosed
with MS grating

Provision of working space or platform for ease


of operation in both wet well and valve chamber

Malaysian Sewerage Industry Guidelines Volume II

227

CHECKLIST
ITEMS TO BE IDENTIFIED IN THE DRAWINGS

Dry well adequately lit and it should be weather


proof, vapour proof and explosion proof.

Miscellaneous Issue

4.0 Grit Chamber

Provision of working platform along the grit


channel.

Provision of handrails or guardrail at exposed


sumps or elevated working areas (Refer to item
1.3).

Provision of grit storage bin or skip with rollers,


perforated tray and covers

Easy access to the grit removal facility by dump


trucks and sufficient maneuver space (Refer item
1.2).

To provide a chute to remove the grit into the


skips.

To provide sufficiently big grit chamber for ease


of maintenance.

To provide a drain pipe to drain water into the


pump sump to avoid ponding.

Provide steps into the chamber (pump).

Misc Issues

5.0 Grease Chamber

Provision of working platform along the grease


chamber

Provision of hopper to collect scum and grease

Provision of handrails or guardrail at exposed


sumps or elevated working areas. (Refer to item
1.3)

Provision of grease storage tank with rollers and


with drain pipes and valves at the bottom of the
tank for removal of settled solids

Easy access to the grease removal facility by


dump trucks and sufficient maneuver space.
(Refer to item 1.2)

Staircases must not be beneath the walkway


(staircase need to be away from walkway)

Miscellaneous Issue

228

Sewerage Works Procedures

YES

NO

COMMENTS

Appendices

CHECKLIST
ITEMS TO BE IDENTIFIED IN THE DRAWINGS

YES

NO

COMMENTS

6.0 Blower Room/Control Panel Or Room

Provision of acoustic enclosures for blowers


including acoustic door

Provision of exhaust fan with silencer to circulate


air around the blower room.

Toilet facilities to be isolated from the blower


room due to heat and noise hazards.

Provision of lifting davit for maintenance of the


blowers.

Provision of rotating strobe light at the control


room to indicate malfunction of blower or other
equipment.

Provision of adequate space for blower removal


or installation during maintenance.

Water storage tank to be located in such a way


that water will not splash on the control panels.

Control panels in the Blower/Control Panel room


is to be isolated from the blower room

Allow at least 900 mm access space even when


cabinet doors and the like are open.

Miscellaneous Issue

7.0 Balancing Tanks

Sufficient walking or working space along the


tanks

Provision of handrails or guards if the tanks are


elevated. (Refer to item 1.1 on handrail and guard
rail)

Miscellaneous Issue

8.0 Primary / Secondary Clarifier


9.0 Biological Treatment System

Malaysian Sewerage Industry Guidelines Volume II

229

CHECKLIST
ITEMS TO BE IDENTIFIED IN THE DRAWINGS

10.0 Sludge Thickener

Provision of adequate walking or working space

Provision of potable/clean water for regular


cleaning of the overflow weir

Provision of force main type of pipe from the


thickener to the sludge holding tank

Desludging pipe provided to be situated above


ground

All sludge holding tanks to be on sloped flooring

11.0 Sludge Holding Tank

Adequate access for desludging tanker. (Refer to


item 1.2 on access road)

Provision of desludging pipe (if the sludge


holding tank is elevated) appropriately positioned.

Sufficient walking or working space along the


sludge holding tank. (Refer to item 1.3).

Provision of handrails or guards if the sludge


holding tank is elevated. (Refer to item 1.1 on
handrail and guard rail)

Provision of desludging pipe either by force main


or gravity flow

All sludge holding tanks to have isolating


facilities.

Each sludge holding tank to have separate feeding


pipes with individual isolating valves.

The top level of holding tanks to be


approximately 6 inches above ground should the
tank be below ground level.

Overflow pipe from sludge holding tank to the


aeration tank to be of sufficient diameter to
prevent possibility of the pipe choking.

Miscellaneous Issues

230

Sewerage Works Procedures

YES

NO

COMMENTS

Appendices

Appendix B2

HAZOP Checklist for Pump Station


WATER SERVICES INDUSTRY ACT 2006
HAZOP CHECKLIST FOR PUMP STATION
Checklist

Items to be identified in the drawings

1.
2.

3.
4.

5.

6.
7.

8.
9.
10.

Yes

No

Comments

Has safe and suitable access to the wells


been provided?
Has a penstock been installed upstream of
the wet well to isolate the pump station
should there be a flood in relation to the
bypass and emergency overflow?
Has a double penstock system been
provided for safety reasons?
Has ventilation for all hazardous zones of
the pump stations been provided? If not
state how this area will be ventilated?
Is a separate ventilation system provided
for the wet wells and dry wells? If not state
how both wells have been ventilated.
Are the wet wells and dry wells adequately
lighted?
Are guard rails and safety chains around
all pits, wells, and floor openings provided
for safety reasons? State safety provisions
in this area.
Are all electrical installations in the pump
stations vapour proof and explosion proof.
Are there adequate level controls for startstop level of pumps in the pump station?
Have corrosion resistant materials been
used for the guardrails, lifting devices and
other well fittings?

Malaysian Sewerage Industry Guidelines Volume II

231

Appendix C Basic Guide of Sewerage Layout Plan Submission in Digital Format


1. INTRODUCTION

Basic guidelines on preparing developments layout plans in digital format using AutoCAD
software or others compatible CAD software where can converted to DXF format.

2. OBJECTIVE

The objective is to establish feature codes on digital layout plan with proper format in
layering name, element, color and object type by using CAD software. This digital layout
plan will then be use for the Catchment Planning Strategies and Geographical Information
System (GIS) and day to day Operation & Maintenance and billing purposes etc.

3. BASIC REQUIREMENT OF SOFTWARE OR FILES


3.1 Software to prepare digital layout plan.

AutoCAD (Release 14 or latest version or others CAD software with DXF format
facility)

3.1 Backup or storage media to deliver)

Diskette 1.44 MB (size 3.5") or Iomega Zip disk 100 MB or Compact Disk (CD)

3.3 Scale unit for layout plan Metric


4. DETAILS OF DIGITAL LAYOUT PLAN

232

Lots boundary for layout plans shall be based on Certified Plan (CP) and also shall be comply
to the survey ordinance (can be obtained from Survey Department).

Benchmark shall be accordance with the Cadastral Map sheet in Cassini coordinate system (in
metre).

Boundary measurement shall be in metre (Refer Drawing).

Sewerage Works Procedures

Appendices

Technical requirements of layout plan depend on the type on development (Application


for one proposed element).

5.1

NO

LAYERS NAME

ELEMENT

COLORS

TYPE OF OBJECT

Base map

Boundary lines

Black

Polyline

Benchmark

Boundary lines

Red

Polyline

Layout

Proposed lot lines

Black

Polyline

Road

Road reserve

Yellow

Polyline

Water

River/water course

Blue

Polyline

Text

Text

Flexible

Text

Frame

Directional

Black

Text and others

Building line

Building line

Flexible

Polyline

10

Sewer line

Sewer line

Blue

Polyline

11

Manhole

Manhole

Black

Circle

Malaysian Sewerage Industry Guidelines Volume II

233

(Application for more than one proposed element.)

5.2

NO

LAYERS NAME

ELEMENT

COLORS

TYPE OF OBJECT

Base map

Boundary lines

Black

Polyline

Boundary

Boundary lines

Rred

Polyline

Layout

Proposed lot lines

Flexible

Polyline

Residential
Commercial
Industrial
Institutional
Open space
Agricultural
Forest
Topography
Reserve area

234

Road

Road reserve

Yellow

Polyline

Water course

River/stream/pond

Blue

Polyline

Text

Any text use

Flexible

Text

Forest

Directional (inclusive of
lines and text)

Black

Text

Sewer line

Sewer line

Blue

Polyline

10

Manhole

Manhole

Black

Circle

Sewerage Works Procedures

Appendices

6.1

SUBMISSION

Two (2) copies in Diskette or Zip disk or CD shall be forwarded during the submission of
design approval stage or after completion of the development(as-built drawing).

Drawing
North (y)

West,Nort
(-ve, +ve)

East,
(+ve, +ve)

West (-x)

East (x)
West, South
(-ve, -ve)

East,
(+ve, -ve)

South (-y)

68 o 33" 00"
11
0

5
30

75
.6
8
m

40.38m

247 o 04" 00"

70 o 25" 00"
90.70m

15
70
25

00

61
.3
0
m

2470 04 00
87.50m

45.94
m
Bench mark

S = 24268.0
E = 58508.7

Boundary line

East and South Coordinate system converted to x,


y
(Unit are in meter)

x= 58508.7
y = 24268.0

Malaysian Sewerage Industry Guidelines Volume II

235

Appendix D Content for Operation and Maintenance Manuals


Table of content for Operations & Manuals
Process, Operation, Maintenance, Installation and Trouble-Shooting
This sample outline is intended as a guide to be used when developing an O&M manual. Use of this
sample outline will facilitate the development, review and approval of the O&M manual. However,
all aspects of the sample outline may not be relevant for all facilities.

Volume I : Operation
Item
1
1.1
1.2
1.2
1.3
1.4
2
2.1
2.2

Description
Introduction
Description and Type of Development
Description and Status of Existing Treatment Facilities (Upgraded Plants)
Selection of Site
Choice of Treatment System
Effluent Quality

2.2.1
2.2.2
2.2.3

Process Description
General Process Flow
System Description
Physical Treatment Process
Chemical Treatment Process
Biological Treatment Process

3
3.1
3.2

Design Calculation
Basis of Design Information
Details of Design Calculations

4
4.1
4.2
4.3
4.4

Treatment Plant Operation


Initial Start-up Procedure
Testing & Commissioning
Procedure for Operating Plant Constructed in Stages or Phases
Plant Shut-down Procedure

5
5.1
5.2

Schedule of Equipment
Main Mechanical & Electrical Equipment
Pipes, Valves & Fittings, Instrumentation

6
6.1
6.2
6.3
6.4

6.8.1
6.8.2
6.8.3

Unit Process Trouble-shooting & Investigation


Anticipated Problems & Investigation Works
Causes of Process Disruption & Non-Compliance of Effluent Quality
Recommended Corrective Actions
Description of the appropriate response or adjustment to minimize impact of emergency situations with the potential to affect
the discharge or compliance with the permit
Periodic Maintenance Procedures for each unit process
Details on how inspections will be conducted and a schedule for the inspection of collection systems and pump stations, where
applicable
Inspection checklist
Record Keeping:
Date of entry, inspection observations, maintenance performed
Process efficiency monitoring results
Operating cost records and recommendations

7
7.1
7.2
7.3

Monitoring Process Efficiency


Monitoring programme
Sample equipment used to perform tests, sample locations, collection and handling
Effluent sampling-lab protocol for in-house testing or reference to off-site laboratory. Sampling and analysis manual

8
8.1
8.2
8.3

Safety & Health


Security Measures
Noise Control
Odour Control

6.5
6.6
6.7
6.8

236

Sewerage Works Procedures

Appendices

Volume I I: Maintenance
Item

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
23
25
26
27
28
29
30
31

Description
Catalogues, Technical specification, Performance data, Equipment installation, Equipment trouble-shooting, Periodic
maintenance procedures, Start-up/shutdown for mechanical & electrical equipment, Spare parts inventory, Certificates of
warranty, JPP equipment approval letter, etc.
Pump
Motor
Gearbox
Penstock
Static Screen
Mechanical Screen
Screw Conveyor/Compactor
Screenings Bin
Grit Removal System
Grease Removal System
Scraper Mechanism Primary Sedimentation
Aerators
Diffusers
Mixers
Blowers
Main Control Panel
Scraper Mechanism Secondary Clarifier
Thickeners
Dewatering Equipment
Disinfection Equipment/Apparatus
Measuring Instruments/Devices/Sensors
Pipes/Valves/Fittings
Lifting Devices
Electrical Equipment
Diesel Generator
Fire-Fighting Equipment
Sound-Proof Installations
Dryer
Odour Control Equipment
Progamme Logic Controller
Manhole Cover/Grating

Volume III : As-Built Drawings


Item
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26

Description
Process, Hydraulic, PID, Layout, Structure, Mechanical, Electrical, Architecture, Schedule, Standard Drawings, etc.
Hydraulic profile & Schematic Flow Diagram
Schematic Flow Diagram
Process & Instrument Diagram (PID)
Site Layout
Plant Layout
Inlet Works (Primary Screen, Wet Well & Dry Well)
Secondary Screen & Grit/Grease Chamber
Equalisation Tank & Distribution Chamber
Aeration Tank
Blower House & Control Room
Secondary Clarifier
Sludge Holding Tank
Sludge Digester
Sludge Thickener
Sludge Dewatering
Sludge Drying Bed & Cake Storage Shed
Chlorination Plant & Disinfection Tank
Effluent Discharge Chamber
Perimeter Fencing & Lighting
Schematic Line Diagram for Power Supply
Instrument Layout of Control Panel
Electrical Line Diagram of all Equipment
Schedule of Pumps
Schedule of Other Mechanical Equipment
Schedule of Pipes, Valves & Fittings
Architectural Drawing of Buildings

Malaysian Sewerage Industry Guidelines Volume II

237

Item
27
28
29
30

Notes
i.
ii.

238

Description
Ladder Diagram for Programmable Logic Controller (PLC)
Architectural Drawings
Locations of Fire-Fighting Equipment
Mass Balance Diagram

A draft to be submitted for approval 60 days before date of operation of the facility and if manuals found to be inadequate, the
owner is required to make appropriate modifications.
A review of the approved manuals one year after initiation of plant operation and subsequent to the review, the manuals shall be
revised to reflect actual treatment plant experience.

Sewerage Works Procedures

Appendices

Appendix E: Tabular Amounts of Performance Bonds


Population
Equivalent
PE
150
200
250
300
350
400
450
500
550
600
650
700
750
800
850
900
950
1,000
1,100
1,200
1,300
1,400
1,500
1,600
1,700
1,800
1,900
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
10,000
11,000
12,000

Sewer Reticulation
RM

Treatment Plant
RM

Pumping Station
RM

6,200
7,600
9,100
10,600
12,000
13,500
15,000
16,400
17,900
19,400
19,700
21,100
22,500
22,600
23,900
25,200
25,400
25,600
25,700
26,800
27,900
29,100
30,200
31,400
32,600
33,700
34,900
36,000
37,200
38,300
44,900
55,400
58,900
64,400
70,200
72,000
73,900
75,700
77,500
86,200
90,500
94,900
97,000
101,600
108,800
113,600

15,000
16,200
17,400
18,600
19,800
21,000
22,200
23,700
25,200
26,700
28,200
29,700
31,400
33,100
34,900
36,700
38,600
40,500
42,500
44,500
46,800
49,100
51,600
54,100
56,900
59,700
62,700
65,700
70,700
75,700
80,700
85,700
90,700
96,700
102,700
108,700
114,700
120,700
126,700
132,700
138,700
144,700
150,700
156,700
164,700
172,700

7,200
7,300
7,500
7,700
7,900
8,100
8,400
8,700
9,000
9,300
9,600
10,000
10,400
10,800
11,200
11,600
12,100
12,600
13,100
13,600
14,100
14,700
15,300
15,900
16,500
17,100
17,700
18,300
19,100
20,300
21,500
22,700
24,200
25,700
27,200
28,700
30,200
32,000
33,800
35,600
37,400
39,200
41,000
42,800
45,000
47,200

Malaysian Sewerage Industry Guidelines Volume II

239

Notes:

240

Population
Equivalent
PE

Sewer Reticulation
RM

Treatment Plant
RM

Pumping Station
RM

13,000
14,000
15,000
16,000
17,000
18,000
19,000
20,000
21,000
22,000
23,000
24,000
25,000
26,000
27,000
28,000
29,000
30,000
31,000
32,000
33,000
34,000
35,000
36,000
37,000
38,000
39,000
40,000
41,000
42,000
43,000
44,000
45,000
46,000
47,000
48,000
49,000
50,000
>50,000

118,600
126,300
131,500
136,800
139,400
144,900
150,400
159,100
161,900
164,700
167,500
170,200
173,000
175,800
178,600
181,400
184,200
186,900
189,700
192,500
195,300
198,100
200,900
203,600
206,400
213,100
216,000
222,900
229,900
237,000
244,200
247,200
250,200
257,700
260,800
268,300
271,500
297,500
6/PE

180,700
188,700
196,700
205,700
214,700
223,700
232,700
241,700
251,700
261,700
271,700
281,700
291,700
302,700
313,700
324,700
335,700
346,700
358,700
370,700
382,700
394,700
406,700
419,700
432,700
445,700
458,700
471,700
486,700
501,700
516,700
531,700
546,700
561,700
576,700
591,700
606,700
621,700
12/PE

49,400
51,600
53,800
56,300
58,800
61,300
63,800
66,300
68,600
70,900
73,200
75,500
77,800
79,800
81,800
83,800
85,800
87,800
89,000
90,200
91,400
92,200
93,000
93,800
94,400
95,000
95,600
96,200
96,800
97,400
98,000
98,600
99,200
99,800
100,300
100,800
101,300
101,800
2/PE

1. For development below 150 PE, a minimum Bond value as per 150 PE or as fixed by the
Commission shall be imposed for the duration of the Defect Liability Period.
2. Actual PE shall be rounded up to next higher PE as shown in table.
3. For works involving > 50,000 PE, the following values are to be adopted:
sewer reticulation - RM 6/PE, treatment plant - RM12/PE and pumping station - RM2/PE.

Sewerage Works Procedures

Appendices

Appendix F Standard Format for Performance Bond


THIS AGREEMENT is made on the ______ day of _________________ BETWEEN
________________________________ (hereinafter called the Guarantor) of the one Part and Indah
Water Konsortium Sdn. Bhd. (hereinafter called the Indah Water) of the other Part.

WHEREAS
A.

Indah Water is authorised pursuant to the Water Services Industry Act 2006 to operate and
maintain public sewerage systems and sewer networks.

B.

__________________________(the Developer) has constructed a sewerage plant, associated


sewerage works and sewer network (altogether known as sewerage system) at
___________________________________ (full details of address preferred). Pursuant to the
Water Services Industry Act 2006, the Developer must hand over the sewerage system to Indah
Water to operate and maintain the same whereupon Indah Water shall only accept the sewerage
system or part of the systems, after Indah Water is satisfied that the sewerage system or part of
the systems, as the case may be, meets the requirements set out in the approved plans,
specifications and standards.

C.

Subject to para B above and rights of the parties pursuant to Water Services Industry Act 2006,
in consideration of Indah Water maintaining and operating the sewerage system, the Developer
agrees to guarantee the due performance of the sewerage system for a period of twelve (12)
months.

D.

At the request of the Developer, The Guarantor agrees to irrevocably and unconditionally
guarantee the due performance of the sewerage system in the manner herein after appearing.

NOW THE GUARANTOR HEREBY AGREES WITH INDAH WATER AS FOLLOWS:


1.

Upon the Indah Waters written demand, the Guarantor shall forthwith pay to the Indah Water
up to and not exceeding the sum of Ringgit Malaysia:______________________ (hereinafter
referred to as the said Sum) or such part thereof as specified in such demand notwithstanding
any contestation or protest by the Developer or Guarantor or by any other third party and
without proof or condition. The total amount recoverable against the Guarantor under this
Agreement shall not exceed the said Sum. Such payment or payments shall be made by the
Guarantor within five (5) working days of the issuance of the Indah Waters written demand.

2.

Indah Water reserves the right to make any partial demands if it shall so desire and the total of
all such partial demands so made shall not exceed the said Sum and the liability of the
Guarantor to pay Indah Water the aforesaid shall correspondingly be reduced proportionate to
any payment of partial demands having been made by the Guarantor.

3.

The Guarantor shall not be discharged or released from this Guarantee by any arrangement with
the Developer or any arrangement made between the Developer and Indah Water and/or any
third party in whatever manner with or without the consent of the Guarantor or by any
forbearance whether as to payment, time, performance or otherwise.

4.

Whenever Indah Water makes a demand on the Guarantor, the Guarantor shall (subject to the
proviso in paragraph 1) forthwith make to Indah Water such payment of the amount so
demanded and any dispute between Indah Water, and the Developer and/or any third party as to

Malaysian Sewerage Industry Guidelines Volume II

241

the right of Indah Water to make such a demand shall not in any way relieve the Guarantor from
the obligation to pay upon such demand by Indah Water.

5.

This Guarantee given by the Guarantor is a continuing guarantee and shall be irrevocable and
shall remain in force and effect from ____________ to ____________for a period of thirteen
(13) months (hereinafter referred to as the said Period).

6.

The liability of the Guarantor to make any payment hereunder shall arise upon receipt of a
demand from Indah Water to make such payment. Any demand from Indah Water shall be
submitted in writing not later than ninety (90) days after the Expiry of the said Period.

7.

This Guarantee shall not be assigned without the Bank/Guarantors prior written consent.

8.

Any failure by Indah Water to demand for payment under this Guarantee (in accordance with
the terms herein) within the period as specified in Clause 6 above shall discharge the Guarantor
of all obligations and liabilities under this Guarantee without the need for any notice by the
Guarantor to Indah Water.

9.

This Guarantee shall be construed in accordance with the laws of Malaysia, and the Malaysian
Courts shall have jurisdiction to try any matter relating to this Guarantee.

IN WITNESS WHEREOF the parties hereto have hereunto set their hands the day and year first
above written.

Signed for and on behalf of the said


Guarantor in the presence of

)
)
)
)

(Witness)

Name: ...

Name: ..

Designation: .

Designation:

Bankers Stamp:

242

Sewerage Works Procedures

Appendices

Appendix G

Bank Guarantee for Upgrading of Existing Public Sewerage System

THIS AGREEMENT is made on the ______ day of _________________ BETWEEN


_________________________ (hereinafter referred to as the Guarantor) of the one Part AND Indah
Water Konsortium Sdn.Bhd. (hereinafter referred to as the Indah Water ) of the other part.
Whereas
A

_________________________ (hereinafter referred to as the Developer/Contractor) to


carry out upgrading and refurbishment works (Works) at the existing sewage treatment
plant located at _________________________________ (the STP).

B.

In consideration of the aforementioned and at the request of the Contractor, the Guarantor has
agreed to guarantee the due performance of the said Works to its full completion by the
Developer in the manner hereinafter appearing.

NOW THE GUARANTOR HEREBY AGREES WITH THE INDAH WATER AS FOLLOWS:
1.

Upon the Indah Waters written demand, the Guarantor shall forthwith pay to the Indah Water
up to and not exceeding the sum of Ringgit Malaysia:______________________ (hereinafter
referred to as the said Sum) or such part thereof as specified in such demand
notwithstanding any contestation or protest by the Developer or Guarantor or by any other
third party and without proof or condition. The total amount recoverable against the
Guarantor under this Agreement shall not exceed the said Sum. Such payment or payments
shall be made by the Guarantor within five (5) working days of the issuance of the Indah
Waters written demand.

2.

The Indah Water reserves the right to make any partial demands if it so desires and the total
of all such partial demands so made shall not exceed the said Sum and the obligation of the
Guarantor to pay the Indah Water shall correspondingly be reduced with each payment of the
partial demands.

3.

The Guarantor shall not be discharged or released from this Guarantee by any arrangement
with the Developer or between the Developer and the Commission or any third party in
whatever manner with or without the consent of the Guarantor or by any alteration in the
obligations undertaken by the Developer or by any forbearance whether as to payment, time,
performance or otherwise.

4.

The right of the Commission to make demands on the Guarantor under this Agreement shall
be an independent right and shall be without prejudice to any other rights of the Commission
against the Developer under the law.

5.

This Guarantee given by the Guarantor is a continuing guarantee and shall be irrevocable and
remain in force and effect from ____________ to ____________for the entire period of
upgrading works (hereinafter known as the Validity Period). Immediately upon the expiry of
the Validity Period, this Guarantee shall, subject to clause 6, cease to be of any force and/or
effect and the obligations or liabilities of the Guarantor hereunder terminated or if the
Contract is deemed abandoned or terminated after the said abandonment or termination of the
said Contract (hereinafter referred to as the Validity Period), irrespective of whether the

Malaysian Sewerage Industry Guidelines Volume II

243

original of this Guarantee is returned to the Guarantor for cancellation. The Guarantor shall
extend the Validity Period for not more than One (1) year from the Validity Period
(hereinafter referred to as Extended Validity Period) upon the request of the Commission
and the Bank Guarantee shall be deemed extended.
6.

On completion of the upgrading works, the Contractor shall request for Final Inspection
before the upgraded plant can officially be handed over to the Commission. Any demand
from the Commission hereunder shall be submitted in writing to the Guarantor before the
handing over date.

7.

This Guarantee shall be governed by and construed in accordance with the laws of Malaysia
and the Guarantor hereby agrees to submit to the exclusive jurisdiction of the Courts of
Malaysia over any claim arising out of this Guarantee.

IN WITNESS WHEREOF the parties hereto have hereunto set their hands the day and year first
above written.

Signed for and on behalf of the said


Guarantor in the presence of

)
)
)
)

(Witness)

Name: ...

Name: ..

Designation: .

Designation:

Bankers Stamp:

244

Sewerage Works Procedures

Appendices

Appendix H Letter of Indemnity for Upgrading Works


(To be submitted together with WSIA/PDC/6)
Date: __________________

TO

: _______________________________________________ (Commission)

PROJECT TITLE

: _______________________________________________ (Project)
_______________________________________________

DEVELOPER

: _______________________________________________ (Developer)

CONSULTANT

: _______________________________________________ (Consultant)

PERMIT HOLDER:

_______________________________________________ (Contractor)

The Developer has applied to National Water Services Commission (herewith referred to as
Commission) to carry out upgrading and refurbishment works (Works) at the existing sewage
treatment plant located at _________________________________( the STP) which is being
operated and maintained by Service Licensee upon the direction of the Commission. The Developer
has appointed the Contractor to carry out the Works at the STP.
In consideration of the Commission approving the Developers application for the Works and Service
Licensee handing over the possession of the STP to the Developer to enable the Works to be carried
out, the following terms shall apply;
1)

The Developer hereby IRREVOCABLY AND UNCONDITIONALLY UNDERTAKES that


the Developer shall at all times from the date hereof fully indemnify and hold the
Commission and/or Service Licensee, harmless to the extent and in respect of all actions,
suits, proceedings, demands, claims, liabilities, damages, losses, judgments and all costs
arising out of or resulting from the Works including legal costs on a solicitors and client basis
which may be suffered by, accrued against, be charged to or recoverable from the
Commission and/or Service Licensee, arising out of the Works.

2)

The Developer shall accept full responsibility for any breaches by the Developer, its
employees, agents, Contractors, Sub-Contractor, Consultants, and any other persons in the
upkeep, security, safety and health, operation and maintenance of the STP in all its entirety
and associated appurtenances, for the purpose of such Works until specifically released by the
Commission and/or Service Licensee in writing.

3)

Upon a written demand from the Commission and/or Services Licensee, the Developer shall
pay the Commission and/or Service Licensee the amount specified in the said demand
notwithstanding any objections or protest by the Developer or any certificate of completion of
Works. Such payment shall be made by the Developer within seven (7) working days of the
issuance of the said written demand and paid in the manner stipulated by the Commission
and/or Service Licensee.

4)

The Developer shall comply with the provisions of any laws, regulations, by laws in force and
further any conditions and directions imposed from time to time by the Commission in
relation to the execution of the Works.

Malaysian Sewerage Industry Guidelines Volume II

245

5)

This Indemnity shall be governed by and construed in accordance with the laws of Malaysia
and the Developer hereby agrees to submit to the exclusive jurisdiction of the Courts of
Malaysia over any claim arising out of this Indemnity.

6)

This Indemnity shall continue to be valid and binding on Developer the notwithstanding any
change whether by way of amalgamation, reconstruction or otherwise in the constitution of
the Developer and all successors entitled and assigned thereto.

The Developer understands and is aware of the full import of taking up such indemnities and
is prepared to face and discharge its duties and responsibilities accordingly.

__________________________
(Signature & Stamp)

__________________________
(Signature & Stamp)

Developer:
Name:
I/C No. :
Developer License No. :

Licensed Contractor:
Name:
I/C No.:
Commission License No.:

___________________________________________________________________________
For Official Use
Date received:
Reference No.:
c.c.

Certifying Agency, Indah Water Konsortium


Operations & Maintenance Department, Indah Water Konsortium

246

Sewerage Works Procedures

Appendices

Appendix I

Typical Project Signboard for Upgrading Works

Malaysian Sewerage Industry Guidelines Volume II

247

248

Sewerage Works Procedures

You might also like