Cameron cleans sealing area on well head.

Wrap control line around tubing


hanger neck, make terminations at Exit Block. Pressure tests same to 9000psi for
10 minutes, bleed off pressure to 0 psi.

Remove Xmas tree from transport rack. Nipple down wing valves off Cameron X
Mas tree. Position X mass tree for installing onto well head with assistants for rig
crane and rig floor tuggers .

Cameron clean sealing on well head and X mas tree. Orientated and as per
Cameron instruction, Land off and nipple up X Mas Tree.1

Pressure test cavity with hydraulic oil to 6500psi hold for 10 minutes.1

.Unable to nipple up due to restricted access of platform wind wall. Removed


wind wall and continued nipple up of X Mas tree wing valves.1.5

(OFF- LINE) Pressure Test Expro Well test equipment and surface lines with
Halliburton cement unit.1

Held PJSM with drill crew and Halliburton coil Tubing personal for rigging up BOP
and BX-115 10k riser section.

Halliburton coil Tubing removed Xmas Tree Cap adapter and install BX-115 10k
adapter flange onto Xmas Tree. (OFF LINE) Halliburton coil Tubing install Coil
tubing injector head onto stripper Assembly on deck.

PJSM with Halliburton. Install Halliburton BOP on well head as per Halliburton
instruction

PJSM. P/U, M/U, and RIH with Halliburton coil tubing riser and connect to
Halliburton BOP as per Halliburton instruction.

PJSM with Expro for rigging up slickline and pressure testing equipment. Prepare
rig floor for rig up of slick line.
Rig up Expro riser adaptor, pump in T, BOP, and slickline lubricator as per Expro
instruction.