SUBSEA LOADING LINE INSPECTION

PT. PERTAMINA EP ASSET 5 TARAKAN FIELD


ID

Task Name

Duration

Start

Finish

Site Activity

37 days? Mon 02/06/14

Predecessors

Tue 08/07/14

Permit clearance

1 day?

Mon 02/06/14

Mon 02/06/14

Site Survey & Visual inspection

3 days

Tue 03/06/14

Thu 05/06/14 2

NDT (onshore)

3 days

Fri 06/06/14

Sun 08/06/14 3

Equipment and diver mobilization

3 days

Mon 09/06/14 Wed 11/06/14

Offshore inspection (Visual + NDT)

6 days

Thu 12/06/14

Tue 17/06/14 5

Additional site inspection (if required)

7 days Wed 18/06/14

Tue 24/06/14 6

Site visit with migas personnel

2 days

Tue 08/07/14 11

Migas Administration

37 days? Mon 02/06/14

10

Migas Appointment Letter

11
12
13

Mon 07/07/14

Tue 08/07/14

21 days

Mon 02/06/14

Sun 22/06/14

Invitation Letter for Migas visit

1 day?

Mon 30/06/14

Mon 30/06/14 10

Migas visit

2 days

Mon 07/07/14

Tue 08/07/14 11

Reporting

14

Re-engineering/Assessment report

15

Certification Report

16

Issuing SKPP (include Migas Review)

Project: Schedule SUbsea Inspection


Date: Sun 01/06/14

02 Jun '14
09 Jun '14
16 Jun '14
23 Jun '14
30 Jun '14
07 Jul '14
14 Jul '14
21 Jul '14
28 Jul '14
04 Aug '14
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

51 days Wed 18/06/14

Thu 07/08/14

30 days Wed 18/06/14

Thu 17/07/14 6

7 days

Fri 18/07/14

Thu 24/07/14 14

14 days

Fri 25/07/14

Thu 07/08/14 15

Task

Progress

Summary

External Tasks

Split

Milestone

Project Summary

External Milestone
Page 1

Deadline