4 x 210 MW : CSTPS : CHANDRAPUR

EVENT

ANALYSIS

1. Event No. 3

REPORT

Time 11:23 hrs.

UNIT NO. 1
Date 24.03.08

2. Operating conditions at the time of Event :


Load

Coal Cycles in service

Oil Support

164 MW

A, B, C, E, F

Nil

3. Nature of Event : Unit withdrawn to attend Water Wall tube leakage near soot Blower IR

26.
4. Observations :

At 10:00 hrs feed water flow increased by 50 tones .also furnace found pressurised, tube
leakage voice
noticed at RHS water wall.
5. Analysis

Water wall tube near IR-26 found opened.


Leakage due to steam errosion.

6. Works carried out by maintenance section

Primary failure Tube no.T-2(LHS)


Preventive measure Tube T-1, T-2, T-3 cut & 2200 mm length new tubes welded.
Total no. of joints-6

7. Works carried out for the restoration by operation :


Boiler lighted up

Time - 19:00 hrs.

Date 25.03.2008

T-A Set Synchronised

Time - 03:00 hrs.

Date 26.03.2008

8. Recommendations to avoid reoccurrence :


a) Short term Nil
b) Long term tube thickness survey near wall soot blowers will be carried out in coming
O/H and eroded tubes will be replaced in O/H.

9.

Remarks Nil

General
Manager-I