PROCESS
SIMPLIFICATION
Preliminary
Hazards
Review
FEL- A: Design
Management Plan
25-30% of Engineering
Lessons
Learned
PDRI
FEL-L Information
Management Plan
Constructability
FEL 2
PFD's
Team
Integration
PLOT
PLAN
EQUIPMENT
LIST
Team
Integration
FEL- B: Materials
Management Plan
FEL- F: Cost
Management Plan
P&ID'S
ISSUED
FOR
COMMENT
DEFINE:
AREAS/CBS/WBS
FEL-C Construction
Management Plan
Matrix
INITIATE FORMAL
MANAGEMENT OF
CHANGE PROCESS
FEL- I: QA/QC
Management Plan
VALUE
ENGINEERI NG
PDRI
15%
P&ID's
ISSUE
FOR
APPROV AL
CONDUCT
HAZ ARDS
REVIEW
FEL-E Specialist
Participation Plan
Responsibility
Tie-In
List
Management Plan
Session 2
Session 1
PDRI
FEL- G: Schedule
FEL 3
CLASS III
ESTIMATE Decision DEVELOP
P&ID'S
-25%, +30 %
Contract &
Procurement Strategy
SP List
Check List
Formal Review
Risk Analysis
Contingency
Setting
Line List
P&ID's
ISSUE
FOR
DESIGN
Risk Analysis
Contingency
Setting
CLASS III
ESTIMATE
-10% , +10%
FEL- M: Change
Management Plan
FEL-H
Commissioning
& Startup Plan
FEL- J: Safety
Management Plan
EQUIPMENT
Responsibility
Matrix
LOCATION
DRAWINGS
SCHEDULE LEVEL:
III Engineering
II Construction
DEVELOP MATERIALS MANAGEMENT PLANNING FOR ENGINEERED EQUIP , FABRICATED PIPE/STEEL, THEN BULKS
ENGINEERED EQUIPMENT - DEVELOP EQUIPMENT DATA SHEETS
DESIGN FOR SAFETY & CONSTRUCTABILITY: Establish Philosophy and then conduct Ongoing Constructability/Safety Reviews