Water Quality and Planning Table April 2006

Listed below are those 37 Hotspot locations and the current proposed completion
dates for WWTW improvements at each of those locations as detailed in the Water
Service Capital Works Programme (CWP) dated November 2005.
Updated list of 37 Hotspot locations
(Based on Water Service CWP November 2005)
Location

Impact

CWP completion dates

ANNALONG

Low

Sep-07

ANTRIM

Medium

Jun-08

#ARMAGH

High

Oct-08

BALLYCASTLE

Low

BALLYGOWAN

Medium

Dec-09
Interim solution complete, complete by
Dec-06

BALLYHALBERT

Low

BALLYMONEY
GLENSTALL

Low

BALLYSTRUDDER

Medium

Aug-06

BALLYWALTER

Medium

Mar-08

#BANGOR /
GROOMSPORT

Medium

CARRICKFERGUS

Medium

Jun-06

CASTLEROCK

Medium

Jul-07

CASTLEWELLAN

High

Dec-06

CLOUGHY

Low

Mar-09

COLERAINE

Low

Jul-07

*COOKSTOWN

High

Sep-06

*CULMORE

High

Dec-05

#DONAGHADEE

Medium

Dec-07

IRVINESTOWN

High

LISBARNET

High

LOUGHRIES

High

Dec-06

#MILLISLE

Low

Dec-07

*NEWRY

Medium

Complete

NEWTOWNABBEY

Medium

Jun-06

#NEWTOWNARDS /
COMBER

Low

*OMAGH

High

Mar-09

Dec-09

Dec-07

Dec-06
Interim solution complete, complete by
Dec 06

Oct-08
Complete

Water Quality and Planning Table April 2006 (Continued)


Updated list of 37 Hotspot locations
(Based on Water Service CWP November 2005)
Location

Impact

CWP completion dates

PORTAFERRY

Medium

Jan-08

PORTAVOGIE

Low

Mar-09

PORTRUSH

Medium

Jul-07

PORTSTEWART

High

Jul-07

RAHOLP

Medium

Feb-07

RAVARNET

Low

Jul-07

#SEAGOE

Medium

Oct-08

STEWARTSTOWN

Medium

Dec-07

STRANGFORD

Low

Apr-07

TANDRAGEE

High

Apr-07

WHITEHEAD /
ISLANDMAGEE

Low

May-07

# - denotes new WWTW to be constructed and operated as a Public


Private Partnership (PPP) Scheme
* - new WWTW has been constructed at these locations. However, their original inclusion on
the hotspots list is also related to problems with the sewerage system, which have not yet
been resolved.