Professional Documents
Culture Documents
The Role of The Consulting Engineer in Design-Build
The Role of The Consulting Engineer in Design-Build
The Design Build process involves a number of distinct phases which include:
- Planning, investigation, and conceptual design
- Procurement (negotiation)
- Implementation
- Operation
To obtain the highest Basis of Value and proper selection of the Design Build team, selection
criteria should include:
- Full compliance with the procurement specification or tender.
- Quality and track record of the total design-build team, including the design professionals.
- Quality of planning and design - how well the project will work.
- Quality and durability of materials offered.
- Life-cycle costing.
- Constructability.
It is further recommended that Owners use a prequalification process to limit the proposers
to no more that 3 to 5 teams (ideally no more than 3).
Contracting opportunities for the consulting engineer
Whenever there is horizontal or vertical infrastructure to be constructed or renovated in a
design-build delivery system, an opportunity generally exists for a Consulting Engineer
(CE). The CE can perform in one of at least three roles: 1) the designer employed by a
construction contractor, 2) the holder of the prime contract with the Owner and secure
construction services from a third party (either a corporate partner or independent
constructor), and 3) be the trusted advisor to the Owner by assisting with the planning,
investigation, and conceptual design leading to the procurement of the DESIGN BUILD team
and as so, act as the Owners representative during the initial planning, design, construction,
and commissioning phases.
The opportunities are numerous for the CE in this system; however, the CE should
understand the risks involved with each potential role. The Design Build process is a team
effort; therefore, the CE should be selective as to his associates. The CE should exercise care
in the contractual (risk, delivery, and payment conditions, etc.) relationships.
Guiding principles
The CE functioning in any of the three roles previously mentioned continues to be bound by
the requirement of ethical practice. Health, safety, and public welfare are not to be
compromised. However, in each case all parties must be aware of their contractual
responsibilities; but in no case are ethical standards to be compromised.
Selection of the consulting engineer
Whether the CE is hired by the Owner to serve as their representative (trusted advisor) or
by the constructor to act as the project designer, the method of procurement should follow
Quality Based Selection (QBS) principles.
The contractor as prime
This approach is the most common throughout the world. When this model is used the CE
must understand the issues and exercise sound business judgment. Some of the issues
relative to this arrangement include: 1) the contractor expecting the CE to produce tender
designs for no compensation, 2) fee negotiations after selection, and 3) the expectation of
tender designs to be accurate in all respects (i.e. perfect), and 4) pressure to sacrifice quality
for the profitability of the project.
In order to protect himself the CE should:
1. Scope of tender design
Make sure the scope of the tender design includes:
A review of available site data, and advice on what additional data is required;
A concept design (or review and extension of owner's concept design);
Preliminary designs and drawings, sufficient to indicate sizes, arrangements, capacities, etc.
for tender pricing (refer to FIDIC scope definitions, in preparation [2]);
Specification references;
No, or limited, responsibility for design accomplished during the proposal stage (limited
information, but contractor uses this design to bid);
Limited Bill of Quantities (BOQ), with some items indicated by rates or units (e.g.
reinforcement);
Procedures to address quantity adjustments;
Input to contract terms and conditions, design coordination, value engineering, construction
engineering, client liaison, etc.
The owner needs to have enough preliminary design to level the playing field. As a guide,
the extent of design input necessary to provide a reasonable order of tender accuracy, may
be in the range of 15% to 30% of a full design.
2. Agreement
The CE should contract with the contractor on a standard form of agreement. This will
include terms of payment and an accepted order of accuracy of design information provided
by the CE. The level of Professional Liability coverage should not be excessive. It is
important that the Contractor understands and accepts the preliminary nature of the tender
design and includes due contingencies in his tender. It is important that the agreement for
tender design recognizes that the CE will continue to produce the final design should the bid
be successful.
3. Fees
The CE must be paid for the tender design services. FIDIC has issued a Practice Note on the
subject of the Consultant in Design-build Contract. It is indicated in this note that the
Consultant should never work without compensation. While many fee structures exist,
FIDIC recommends the following options. Payment should be in full for the time inputs, or
the CE may share in the contractors bidding risks through acceptance of a cost recovery
basis which translates as 60% to 70% of the full fee for time inputs. (The fees may be
converted to lump sum.)
In cases where a cost recovery basis is agreed and the contractors bid is successful, the CE
is subsequently paid the balance of the tender design fee, plus a bonus of equal amount. For
example, if the agreed fee is 70% of full rates for tender preparation, then where the bid is
successful, the CE is due the balance of 30% plus a further 30% as a bonus, and thus is paid
130% in total.
In the case of the successful bid, the CE is subsequently engaged to complete the design and
construction phase services under a separate fee arrangement, at a fee agreed prior to
bidding and allowed in the bid. This fee for final design will reflect the payment already
received for the input to tender.
The consulting engineer as prime contractor
In this model the CE holds the direct contract with the Owner and must have financial,
managerial, and technical skills as well as equipment and manpower resources whether inhouse or through subcontractor arrangements to properly execute the entire project. As the
prime contractor, his obligations as engineer are not to be compromised. The Prime should
use the same good business practices in this model that a constructor would use in the
earlier described model.
The consulting engineer as the agent of the owner
This model is the most traditional role for the CE and services are contracted under a
Professional Services Agreement. As stated earlier, in order for a successful DESIGN BUILD
process to be realized there must be a clear definition of the work including a preliminary
design in the range of 10% to 30% depending upon the project type. In this approach the CE
would develop sufficient detail for the Owners documents such that the prospective
DESIGN BUILD constructors proposals would be consistent to the point of making a rational
selection. However, if the work cannot be quantified for pricing or the Owner cannot live
with a substitute, then the work must be fully designed or specified and FIDIC recommends
that the conventional Design-Bid-Build method would be more appropriate. The Owners CE
may also function as a technical advisor throughout the project by providing such services
as:
- Procurement
- Design review
- Quality control during construction
- Payment verification
- Dispute resolution
- Assistance during commissioning.
In this model the CE may augment an in-house engineering staff, or perform all the
necessary engineering functions which the Owner may require.
- See more at: http://fidic.org/node/747#sthash.2LrqUPwm.dpuf