CQAM/ Site Design Environm No COP/DCO nt nt t Responsibilities DCQA Inspect Manag ent TOCOR . P Engine Controll Contr M or er Officer er er ol (A Interpretation of Plans and Specifications: ) Provide clarification of Task Order 1. I A R I C C documents and related codes. Process and maintain a log of all 2. I A C R requests for information (RFI) Process material submittals for 3. I A C R review. Maintain a submittal log. (B) Construction Schedule: Monitor and review the Contractor’s work schedules, verify 1. I A R C C I and take actions to pursue timely project completion Notify the Contractor to update his 2. I A R C C I construction schedules as required. Monitor and coordinate construction scheduling for 3. I A R C C I continuity and logical placing of the various work components (C) Construction Operations: Confirm that the Contractor installs temporary facilities as required and 1. removes them when no longer I C A R I needed and restores the area to its original condition. Monitor other work within the project limits, which could 2. I C A R I impact/affect construction operations. (D Safety: ) 1. Monitor the Contractor at all I C A R I construction worksites, and immediately notify the Contractor’s R = Responsible A = Accountable C = Consulted I = Informed RESPONISBILITY ASSIGNMENT (RACI) MATRIX
management staff of any unsafe
conditions or unsafe acts observed. A written notice must succeed any verbal notice. Monitor construction activities and procedures to ensure that minimal 2. damage is done to the environment I C C R A I including introduction of pollutants and control of erosion. Reside Docume Projec CQAM/ Site Design Environm No COP/DCO nt nt t Responsibilities DCQA Inspect Manag ent TOCOR . P Engine Controll Contr M or er Officer er er ol (E Quality Assurance: ) Observe the work, materials, and witness tests so that all are following the Task Order 1. I C A R I documents and all applicable codes and that the work conforms to good construction practices Notify and verify whether the Contractor corrects/remedies any 2. I C A R I work in non- compliance of Task Order documents. Confirm and review the Contractor’s quality control programs. Monitor compliance of 3. the Contractor of their quality I A R C I control programs and take necessary corrective actions when appropriate. Secure certified copies of all test results from the Contractor. Review 4. I C A R all test results for compliance with the Task Order. 5. Witnessing testing conducted by I C A R I the Contractor, random checking
R = Responsible A = Accountable C = Consulted I = Informed
RESPONISBILITY ASSIGNMENT (RACI) MATRIX
and sampling of construction
materials to ensure compliance with agreed upon quality. (F Materials Receiving: ) 1. Review Contractor’s reports. I C A R I Verify materials for conformance 2. I C A R I with the Task Order documents Verify quantities of the materials 3. I C A R I stored on site (G Construction Changes and ) Claims: Maintain accurate records of facts regarding materials, labor and 1. I C A R C I equipment associated with any potential claim or dispute. Review and submit recommendations to the TOCO regarding the validity of all 2. A R C C C C Contractor changes or claims related to costs, price, time, or design.
R = Responsible A = Accountable C = Consulted I = Informed
RESPONISBILITY ASSIGNMENT (RACI) MATRIX
Reside Docume Projec
CQAM/ Site Design Environm Social No COP/DCO nt nt t Responsibilities DCQA Inspect Manag ent Mobiliz TOCOR . P Engine Controll Contr M or er Officer er er er ol Prepare for issuance by the TOCO supporting documents for all change orders, change order 3. sketches or drawings or any other I C A R C I material modification or adjustment relating to proposed construction changes. (H Record of Task Order Drawings ) Maintain a record of Task Order 1. I A C R drawings (I) Progress Payments: Review the Contractor’s monthly 1. progress estimates for progress I A R C I payments (J) Records: Obtain, account for, and maintain: meeting minutes, correspondence, 1. test records and reports, shop I A C R drawings, submittal logs, RFI logs, submittal samples etc. (K Inspection Services: ) Conduct pre-final and final inspections with the Contractor, 1. C A R I and other agencies required to participate Prepare a punch list of deficient 2. items and substandard work for I A R C I review by the TOCOR Continue inspection services until 3. the Contractor completes all punch I C A R I list items (L) Post-construction Services: R = Responsible A = Accountable C = Consulted I = Informed RESPONISBILITY ASSIGNMENT (RACI) MATRIX
Confirm submission of field posted
As-built Drawings to the TOCOR 1. I A R C I within 60 days from Final Acceptance of the project. File project records in accordance 2. I C A C R I with TOCOR Turn over guarantee and warranty 3. I A R C I data to the TOCOR
R = Responsible A = Accountable C = Consulted I = Informed
RESPONISBILITY ASSIGNMENT (RACI) MATRIX
Reside Docume Projec
CQAM/ Site Design Environm Social No COP/DCO nt nt t Responsibilities DCQA Inspect Manag ent Mobiliz TOCOR . P Engine Controll Contr M or er Officer er er er ol Turn over construction contract maintenance monitoring 4. responsibilities to the TOCOR after I A R C I the completion of all punch list items or plant establishment period Verify and take actions within the Contractor’s authority to ensure 5. the I C A R I Contractor corrects all deficient items in a timely manner Confirm submission of 3 hard copies of Project Operations and 6. I A R C I Maintenance (O & M) manual and an electronic copy.
R = Responsible A = Accountable C = Consulted I = Informed