Grand total (JOD)

Earth Works #VALUE!

Prefab Option 1 #VALUE!

Prefab Option 2 #REF!

Latrine Units #VALUE!

Fences and Gates #VALUE!

Steel Shaded Area #VALUE!

Access Pathways #VALUE!

Total #VALUE!
UNICEF JORDAN - RFP

Required Materials Unit Price Amount


No. Item Description
Unit QTY JOD JOD
-        The Contractor shall remove all organic materials, obstacles or irregularities from the project site, it is the contractor responsibility to remove
all existing site obstruction prior commencing earth works.
-        The Contractor shall level the site to one project level as instructed by UNICEF Engineer using all types of required machinery at no extra
charge.
-        The Contractor shall be responsible to cut and fill the soil up to one (1) meter above and/or below the agreed project level at no extra charge.
1 Ground Levelling m2 800
Whenever the cut and fill works exceed one (1) meter, the Contractor should promptly notify UNICEF before executing the works. UNICEF will not
be liable for any costs or additional charges that are not previously agreed with the Contractor in writing.
-        Extra material and or gravel embankment should be removed from the site and dumped properly as per the national regulations. In case of
need for additional material the contractor shall take the proper procedure to supply to the site the needed quantity of approved quality materials
subjects the level difference does not exceed the limits explained above.

The land lot should be gravelled with grade A-1-a as per the AASHTO Code base course with maximum aggregate size of 19mm to a
2 Supply and Lay Base total thickness of 150mm and compacted with proper roller then topped with a spray of sealing coat 80/100, finally, the surface m2 635
Coarse Aggregate Layer should be sprayed with a layer of basalt key aggregate made of single size 5mm then compacted with the proper roller.
and Seal Coat Layer

TOTAL 0
UNICEF JORDAN - RFP

Required Materials Unit Price Amount


No. Item Description
Unit QTY JOD JOD
Supply and Install Prefabricated Structure with the dimensions 9mx10m made of sandwich panel ribbed section of 40mm thickness for walls using
0.35mm galvanized painted steel sheets, and corrugated sandwich panels for roof, with cold formed C-sections for skeleton members utilizing
No. 1
trusses if needed and smooth surface troweled concrete flooring, toped with non slip layer of ceramic tiles. referecen to be made to sections 2.1 ,
2.1.1 and 2.2 for the technical details and requirements
1 Prefab units option 1
Supply and Install Prefabricated Structure with the dimensions 9mx10m made of sandwich panel ribbed section of 40mm thickness for walls using
0.35mm galvanized painted steel sheets, and corrugated sandwich panels for roof, with cold formed C-sections for skeleton members utilizing
No. 1
trusses if needed and smooth surface troweled concrete flooring, toped with epoxy coating layer . referecen to be made to sections 2.1, 2.1.1 and
2.2 for the technical details and requirements

TOTAL 0
UNICEF JORDAN - RFP

Required Materials Unit Price Amount


No. Item Description
Unit QTY JOD JOD
Supply and Install Prefabricated Structure to be used as Latrine Unit with the dimensions 4x4m made of sandwich panel ribbed section of 40mm
thickness for walls using 0.35mm galvanized painted steel sheets, and corrugated sandwich panels for roof, with cold formed C-sections for skeleton
members and
One layer of 18 mm thick cement boards finished with non-slip ceramic tiles.
The latrine units’ internal partitions should be made from 15 mm thick melamine boards with all the requires accessories to install the dividers. The
latrine units’ doors shall will be a single leaf door made insulated sandwich panel with extruded aluminum frames. the external door sizes will be
1 Latrines No. 2
90x210 cm for the non-disabled entrance and 110x210 for the disabled wash unit the inner ones should be 75x210 cm, work should cover all doors
accessories and ironmongery.
Each unit should comprise of 2 No, of toilet seat and one toilet seat for disabled, the No of wash basin should be 2 for non-disabled and one for the
disabled units, work should cover water sprinklers and accessories. Work should also cover all the required electrical connections for lighting units,
switches and plugs considering circuit breakers and main input, the works include leveling, testing and calibration on site and all accessories to
make it safe and operational.

Each Latrine unit will be equipped with steel Stair Steps and Ramps should be made of pre-painted 1.5mm steel chequered plate with tread
2 Steel Ramps and steps dimension of 25 cm and riser dimension of 16cm with strengthening 8mm thickness flat bar of 25mm width at the interior of the nosing welded to No. 2
the flights. All structures designated to be used by disabled personnel should be equipped with Entrance Ramp of 10% slope made of pre-painted
1.5mm steel chequered plate and reinforced at 25cm intervals with 8mm thickness flat bars of 25mm width welded to the adjacent flights
2m3 capacity PVC water tank installed on it steel tower, steel stand made from painted steel angle size 50*50*5mm with H: 2.00m from the floor
3 PVC tanks with stands finish. No. 2

TOTAL 0
UNICEF JORDAN - RFP

Required Materials Unit Price Amount


No. Item Description
Unit QTY JOD JOD

Work to cover the supply and Installation of new steel fence of IPE 100x5 section: 3m high with additional 75cm installation below ground level
distributed at 3m spacing. Price includes 21MPa concrete foundation for the poles and IPE 100x5x 50 cm (45 degree angle) top extensions, with 3
Steel Fences supporting steel wires 4mm. With Galvanized 6cm x 6cm x 4mm wire mesh up to 2m height, strongly tied to 4mm passing wires between sections L.M 114
at every meter height, wire mesh should be casted to the ground with 20cm x 20cm ground beam of 21MPa concrete. All steel elements should be
1 painted with one layer of primer paint and two layers of mutt river blue RAL5012 enamel paint. As per technical drawing.
Sliding gates, 3 meter wide made of 8cm x 4cm x 2mm steel tube frame and middle vertical and horizontal beams, interior 4cm x 4cm x 2mm steel
tubes should be used at 10cm clear spacing, with (2cm x 2cm) x 30cm handles and steel angle track and all required pulleys and Three guarding
Steel Gate/Vehicle No. 1
fixed columns with proper rollers and pad lock plates. All elements should be painted with one layer of primer paint and two layers of mutt river
blue RAL 5012 enamel paint.
1m clear width and 2m , made of 8cm x 4cm x 2mm steel tube frame and middle horizontal beam, interior 4cm x 4cm x 2mm steel tubes should be
Steel Gate/Pedestrian used at 10cm clear spacing, with (2cm x 2cm) x 30cm handles and three heavy duty 10cm steel hinges and 15mm diameter sliding bolt with pad No. 2
lock plates. All elements should be painted with one layer of primer paint and two layers of mutt river blue RAL 5012 enamel paint.
TOTAL 0
UNICEF JORDAN - RFP

Required Materials Unit Price Amount


No. Item Description
Unit QTY JOD JOD
The scope of work should cover providing and installing a steel shade heavy duty cover not less .5 mm thickness on truss height 80 cm price
includes installation and all civil work composed of steel vertical 10*10 cm thickness 3mm the vertical tube fixed at the bottom with depth not less
than 75 cm and dimension 50*50 cm casting reinforcement concrete with 25Mpa compressive strength. The horizontal truss composed of steel m2 140
1 Steel Shaded Area
tube 8*4 cm thickness 2 mm and the height 3 m from the natural ground. All steel sections supporting the steel shaded should be painted with one
layer of primer paint and two layers of mutt river blue RAL 5012 enamel paint.

TOTAL 0
UNICEF JORDAN - RFP

Required Materials Unit Price Amount


No. Item Description
Unit QTY JOD JOD
Intelocking Tiles m2 165
1
Kerbstone L.M 140

TOTAL 0
Required Materials Unit Price Amount
No. Item Description
Unit QTY JOD JOD
The prefab units’ internal partitions should be made using low-ribbed sandwich panel boards with total thickness of 50mm and formed of
galvanized steel sheets of 0.35mm thickness pre-painted to RAL9002 white and stuffed with polyurethane foam of 38 kg/m3 density with
1 Internal Partitions U value of less than 0.46 W/m20c. The panels should be placed using tongue and groove joining system and bolted at all edges to the main m2 100
skeleton with cold formed galvanized steel U-section of minimum thickness 1.2mm, the bolts should be spaced at 40cm distance.
Referecen to be made to sections 2.1 and 2.1.1 for the technical details and requirements.
The prefab units’ internal doors shall will be a single leaf door made insulated sandwich panel with extruded aluminum frames. the door
sizes will be 110x210 cm, work should cover all doors accessories and ironmongery. Referecen to be made to sections 2.1 and 2.1.1 for the
2 Internal Doors No. 4
technical details and requirements