IR VISION SDN BHD Doc. Ref.

: IRV/JMS/WP
Rev. No. : 0
METHOD OF STATEMENTS Issue Date : 1/4/2022
Page : 1 OF 6
INSTALLATION OF WATERPROOFING

1.0 OBJECTIVE

To specify the requirements installation work of waterproofing membrane type to describe the
measures and ways of the proper application of waterproofing membrane.

2.0 SCOPE

This method statement applies for work installation of waterproofing membrane type by
replaced existing waterproofing at roof of building.

3.0 REFERENCE

3.1 Standard Specification


3.2 Approved Construction Drawings
3.3 Contract Document & Bill of Quantities

4.0 RESPONSIBILITY

NO. POSITIONS ROLES AND RESPONSIBILITIES

Responsibilities for overall commercial,


5.1 Project Manager/Assistant Project contractual and technical performances.

Manager Associated with specific projects.


Responsible to the Project Director.
Planning, coordinating and supervise
5.2 Site Engineer/ Site Supervisor
Site activities.

Safety Officer/Site Safety Supervisor / To control and ensure the safety, health
5.3
Environmental Officer and environmental is adhere at site.

5.4 Checking quality of material


QAQC

5.5 General workers Working as manpower and workforce base on


site requirement

1
IR VISION SDN BHD Doc. Ref. : IRV/JMS/WP
Rev. No. : 0
METHOD OF STATEMENTS Issue Date : 1/4/2022
Page : 2 OF 6
INSTALLATION OF WATERPROOFING
5.0 MATERIALS

Approval shall be obtained for all the materials with reference to client’s preferred
vendor list, prior to commencement of activities. Material approval request will be
submitted to client upon material arrival to site. All materials must be stored properly as
per the manufacturer’s recommendations. The material shelf life will be monitored as
per Manufacturer’s data sheets.

6.0 HANDLING AND STORAGE OF MATERIALS

Handling :Shovels, Vibrators, Dewatering Pump, Angle Grinders, Cutters, Drilling


Machines, Wheel Barrows, Bagger Mixer and Manpower

Storage :Store at designated areas on the site.

7.0 PLANT, MACHINERY, EQUIPMENT & TOOLS

NO EQUIPMENT/PLANT/TOOLS DESCRIPTION
1 Wheelbarrow To deliver small quantity of material
2 Shovels To shove soil / material
3 Self-Loaders To load/unload
4 Rollers/compactors To compact soil / surface
5 Transit Mixers To transit concrete
6 Vibrators For removing air in concrete
7 Dewatering Pump For dewatering water
8 Angle Grinders For grinding work
9 Cutters For cutting work
10 Drilling Machines To drill hole

2
IR VISION SDN BHD Doc. Ref. : IRV/JMS/WP
Rev. No. : 0
METHOD OF STATEMENTS Issue Date : 1/4/2022
Page : 3 OF 6
INSTALLATION OF WATERPROOFING

8.0 WORK METHODOLOGY

8.1 General

8.1.1 Before installation work, contractor need to prepare request for inspection (RFI) for
Client will inspect and check whether the situation at site in good order before starting
work such as the condition of the machine, the environment of site, and other related
issues.

8.1.2 All of the installation work activities must be supervised by site engineer and assist by
site supervisor to make sure all activities working according to the specification and
standard.

8.1.3 Site Engineer/Site Supervisor needs to identify all of the utilities before start work and
make sure installation work activities not disturb the utilities and be careful with the
utilities during works.

8.2 Initial Survey & Site Checking

Upon received of job instruction / drawing from Client, as initial site visit to be made along with
the Client representative to confirm the site and demarcations.

8.3. Setting Out

The existing waterproofing shall be set out and elevations marked by the specialist. In case of
any obstruction or existing services, it shall be intimated to the client and necessary modifications
shall be carried out after getting approval from client.

3
IR VISION SDN BHD Doc. Ref. : IRV/JMS/WP
Rev. No. : 0
METHOD OF STATEMENTS Issue Date : 1/4/2022
Page : 4 OF 6
INSTALLATION OF WATERPROOFING

8.4. Waterproofing

Ensure that all preceding activities or activities completed which cannot be accessed after
waterproofing works are inspected, released and approved.

i. Site Clearance
Existing waterproofing at work surface shall be removed and scrapped all existing waterproofing
residue material to achieve clean surface area. Prepare and level the concrete surfaces for
waterproofing either by chipping, hacking or scraping the surface. Repair the excessive
pinholes, and similar imperfections (if any) to eliminate uneven surface. The surface will be
smooth cement render and level up to elevation approved by Client.

ii. Surface Preparation


The floor screed shall be done at slope ranging 1% to 5% between 25mm to 50mm thickness to
achieve gradient and crossfalls. The surface area shall be clean, dry, smooth and treated with a
coat of Bostik Bituminiuos Primer to provide good bonding between the membrane and the
substrate. Barricade the working area as to be a non-trafficking passage. Raise an inspection
request for surface preparation prior to the waterproofing work commences.

iii. Application of Membrane Waterproofing

a. Priming
Before installation, prime substrate with Bostik Bitumen Primer at the rate of 5 m 2 per liter
depends on substrate condition

b. Placing
Starting from the lowest point where the drainage outlet is positioned unrolled the
Boscoseal Torch On membrane from its original packaging and placed on the correct
position where it will be torched later. The membrane is then re-rolled without changing its
original alignment. Slowly unrolled again and whilst unrolling, heat up the burn-off film on
the undersideof the membrane by a propane gas torch at controlled temperature causing
surface changes and subsequent adhesion to the substrate. All overlaps, edges end and
seams must be overlap by at least 75 to 100mm and shall be formed to shed water. The
bitumen compound coming out from the lightly pressed heated overlap of the membrane
should be carefully leveled by spreading it on the lap with a heated round trowel to form a
sealing bead.

4
IR VISION SDN BHD Doc. Ref. : IRV/JMS/WP
Rev. No. : 0
METHOD OF STATEMENTS Issue Date : 1/4/2022
Page : 5 OF 6
INSTALLATION OF WATERPROOFING

iv. Protection
Ensure all other trades in the said location are put on hold during the waterproof application so
to protect and avoid any damage to the waterproofing layers. Ensure all surfaces to receive
waterproof fluid application firmly to achieve good adhesion and to be in one continuous
operation.

9.0 SAFETY AND HEALTH

9.1 Hazard Identification, Risk Assessment and Determining Control

Hazard identification, risk assessment and determining control shall be carried out for the
drainage work. Prior to any works commencement, cautions and awareness signs shall be
established at location of work. The hazards in a particular activity and the control measures
implemented shall be brief to the workers during ESH induction and tool box talk.

9.2 Information to Personnel

9.2.1 All workers employed in the project site compulsory have CIDB green card.

9.2.2 All new workers and staff to attend the ESH training / induction before commencing work
site and attendance shall be recorded in an induction list.

9.2.3 All site personnel shall wear proper personnel protective equipment (PPE). Workers who
fail to comply with this requirement will be removed from site.

9.2.4 All workers to attend the weekly toolbox meetings conducted by SSS/ SHO held at site
and attendance shall be recorded.

9.2.5 In summation, in order to achieve safe, free risk and healthy working environment,
including loss prevention, every practicable step must be taken by each and every one
engaged in this project site.

9.3 Permit Requirement

The permit required for this activity will be acquired when necessary.

5
IR VISION SDN BHD DOC. REF. : IRV/JMS/
REV. NO. : 0
METHOD OF STATEMENTS ISSUE DATE : 1/3/2021
CONSTRUCTION OF CIVIL WORKS PAGE : 6 OF 14

10.0 ENVIRONMENTAL ISSUES

- Environment implementation and control at site shall be complied with Environmental


Management Plan (EMP), Erosion and Sedimentation Control Plan (ESCP), and Noise
and Vibration Compliance Management Plan.

10.1 Housekeeping
- Housekeeping is an essential part of safety for the daily routine. Housekeeping would
include the following items:

11.2.1 Maintain the access/egress to all working area

11.2.2 Store and stack all construction materials in safe and orderly manner

11.2.3 No littering around the site and provide sufficient waste bin.