Doc. No.: STC CPBP-SITE-MS-0007 Date Issued: 20 MARCH, 2019
`
STC CAR PARK BUILDING PROJECT
Riyadh, K.S.A.
METHOD STATEMENT FOR
LIQUID APPLIED BITUMINOUS
WATERPROOFING
20 MARCH,
00 2019
01 METHOD
STATEMENT
02 FOR LIQUID
APPLIED
03 BITUMINOUS
WATERPROOF
ING
04
Table of Content
This method statement shows how is the proper way of application of liquid
applied bituminous waterproofing to blinding or PCC as specified in the
specification and approved drawing.
5. Work Procedure
Make sure that material is sealed with labels indicating the manufacturer name,
trade mark, date of manufacture and expiry.
Material shall be stored in a safe material storage with shade and or at the area
out of direct sunlight.
2. Surface Preparation
Preparation and cleaning shall be made on the area by removing loose material
and using soft broom stick or the like.
Oil, grease and paints shall be removed by using rug cloth and paint scraper
respectively.
Page | 3
Doc. Name: METHOD STATEMENT FOR LIQUID APPLIED BITUMINOUS WATERPROOFING Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0007 Date Issued: 20 MARCH, 2019
3. Application
Application of liquid applied bituminous waterproofing shall be carried out by
approved subcontractor or main contractor.
The substrate shall be free from cracks, if any repair of crack shall then be made.
Firstly, earth pits and pipes shall be completed before application of bituminous
waterproofing.
Liquid applied bituminous waterproofing shall be laid with roller but extra care
would be taken to avoid splash and wastage of material.
Page | 4
Doc. Name: METHOD STATEMENT FOR LIQUID APPLIED BITUMINOUS WATERPROOFING Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0007 Date Issued: 20 MARCH, 2019
Page | 5