Doc. Name: METHOD STATEMENT For BLINDING/LEAN CONCRETE Rev. No.

: 00
Doc. No.: STC CPBP-SITE-MS-0002 Date Issued: 20 MARCH, 2019

`
                 
   
   
   
   
   
   
   
  STC CAR PARK BUILDING PROJECT  
   
 
Riyadh, K.S.A.  
   
   
   
   
 
 
METHOD STATEMENT FOR  
 
 
 
LEAN/BLINDING CONCRETE  
 
   
   
   
   
   
   
   
                 

00 06 MARCH 2019

01 METHOD
STATEMENT
02 FOR
  LEAN/BLINDING
CONCRETE
03
       

04

REV. DATE DESCRIPTION PREPARED BY CHECKED BY APPROVED BY


QA/QC ENGINEER PROJECT MANAGER PROJECT
Page | 1
Doc. Name: METHOD STATEMENT For BLINDING/LEAN CONCRETE Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0002 Date Issued: 20 MARCH, 2019

MANAGER RZM
20 MARCH, LEAN/BLINDING TAYYAB ABDUL SYED ATHER ULLAH
00 2019 CONCRETE GHAFOOR HUSSAINI KHALID MKHTALI

Table of Content

Section No. Title Page

1.0 Table of Content 2

2.0 Purpose & Scope 3

3.0 References 3

4.0 Materials 3

5.0 Resources 3

6.0 Manpower 4

7.0 Work Procedure 4

8.0 Electricity 6

9.0 Health Safety 6

Page | 2
Doc. Name: METHOD STATEMENT For BLINDING/LEAN CONCRETE Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0002 Date Issued: 20 MARCH, 2019

2. Purpose & Scope


2.1 The purpose of this is to describe the measures and ways of doing blinding
works in our project site. Works shall be carried outin compliance with the
drawing and project specification.

3. References
3.1 Specification Section
3.2 Approved Drawings for Construction
3.3 Contract Documents and Specifications
3.4 Project Specification
3.5 APPLICABLE ACI, ASTM and SA STANDARD
3.6 Concrete Works, Drawings

4. Materials
20 Mpa Blinding Concrete (C20/20 Grade)

5. Resources

5.1 Construction Tools & Equipment


5.1.1 Mixer truck
5.1.2 Vibrator
5.1.3 Auto Level
5.1.4 Total Station
5.1.5 Metal Tape
5.1.6 Wheel barrow
5.1.7 Water Tanker
5.1.8 Generator 30 KVA
5.1.9 Generator 70 KVA
5.1.10 Shovel
5.1.11 Trowel
5.1.12 Bucket

6. Manpower

Page | 3
Doc. Name: METHOD STATEMENT For BLINDING/LEAN CONCRETE Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0002 Date Issued: 20 MARCH, 2019

S/N DESCRIPTION REQUIRED REMARKS


1 QC Inspector 1 no.  
2 Site Engineer 1 no.
3 Safety Officer 1 no.  
4 supervisor 1 no.  
5 Surveyor 1 no.
6 Foreman 1 no.  
7 Elastration 1 no.
7 workers 12 no.  

7.0 Work Procedure

 Setting out
 Surveyor would conduct site survey to stake-out the lines and
levels of the areas of the blinding to be cast. The mark shall
be as per the approved drawing.

- Application

 After getting compaction test results which shall be equal or


above the 95% of the Maximum Dry Density.
 The shuttering form on the blinding must be fixed, aligned
and leveled properly before start pouring concrete.

 The Engineer must check the setting out, dimensions,


alignment, thicken and the level for the shutter of the blinding
through inspection request from the contractor.

 Approved ready-mix concrete will transported from batching


plant to the site by mixer truck.

 The contractor must prepare a sketch showing the casting


areas, pump and trucks access, pump location, concrete trucks
checkpoints and submit to the Engineer.

Page | 4
Doc. Name: METHOD STATEMENT For BLINDING/LEAN CONCRETE Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0002 Date Issued: 20 MARCH, 2019

 Concrete after pouring to position shall compacted by


immersion vibrator.

 Skilled labourers provided with all safety requirements such s


safety helmet, overalls, safety shoes, goggles. Gloves, vest
etc.

 Safety precautions shall be taken into considerations starting


from the site entrance gate including the pump and trucks
access till the surrounding of the casting area.

 Proper light must be available for when of concrete pouring at


night.

 The concrete trucks must unload the concrete within One-and-


a-half hours or 300 revolutions from the batch loading time.

 The blinding thickness shall be achieved as per drawing or


specification.

 The cast blinding shall be cured properly with covering wet


hessian clothe.

 Concrete must be cured from two to three times daily for a


period of 7 days.

 The blinding shall then be protected with safety warning


device to prevent the cast blinding from damages may cause
by the working machineries.

 The surface of blinding shall be made smooth, repair of


thermal cracks and make true leveling to receive
waterproofing bitumen.

Page | 5
Doc. Name: METHOD STATEMENT For BLINDING/LEAN CONCRETE Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0002 Date Issued: 20 MARCH, 2019

8. Electricity

 Electricity will be supplied by stand by generator on site.

9.0 Health Safety, Environment & Security

9.1 Health & Safety


 All works shall comply with the safety procedure or
instruction as set out in project safety plan and municipality
rules and regulations.

 Basic PPE shall be worn by all staff or labourers all the times.

 Trained operator or banksman would be engaged to control or


operate heavy equipment machine.

 Banksman present during excavation and concrete pouring


works.

 No un-authorized persons allowed on site during concrete


pours.

 Warning signs

 Rubber Safety shoes, Goggles, and gloves MUST be worn


during concreting operations.

 Risk Assessments for Excavations and for concrete work to be


carried out prior to the works commencing.