M-DT-MS-099123-AR-015-A
AD21094-0201S-FM-18 REV 00
Employer PMC Engineer Contractor
Revision History
02
03
Checked By:
Reviewed By:
Approved By:
2. REFERENCES ................................................................................................................ 4
4. RESOURCES ................................................................................................................. 5
2. REFERENCES
Abbreviation For
PM Project Manager
CM Construction Manager
MS Method Statement
4. RESOURCES
4.4 Equipment
Wheelbarrows As per requirements
Spirit Levels As per requirements
Measuring Tapes As per requirements
Steel/Plastic Trowels As per requirements
Electric Power Mixer As per requirements
Angle Rule As per requirements
Aluminum Rule As per requirements
5. HSE REQUIREMENTS
01 POLICE 999
02 AMBULANCE 998
07 Contractor CM 0555458894
08 Contractor HSE 0562526739
Surface Preparation:
Hardware materials which are already fixed and not to be painted shall be removed. Removal
if not possible, it shall be covered/protected appropriately before surface preparation and
painting will commence. Clean and prepare concrete or cement plaster surfaces to be
painted. Efflorescence, chalk, dust, dirt, grease and oils shall be removed. The surface of the
area to be painted would be prepared by removing loose particles, blemishes, and
deleterious materials by way of sanding.
All surfaces must be thoroughly brushed with stiff fiber bristles to remove loose particles.
Remove all loose or defective paint back to a firm edge. Use soft wire brush to remove dirt,
powder, laitance, loose particles and other contaminants. Smooth surfaces must be sanded
thoroughly to allow proper penetration and adhesion. Oil and grease contamination should
be removed using alkaline cleaner.
Note: For working at height, fixed and movable scaffolding would be erected as per area
requirements. Scaffolding when erected shall be inspected with Safety officer prior to usage.
Operatives will be inductive before working at site. Pre-start meeting would be conducted
before the start of painting activities and toolbox meeting would be regularly conducted by
safety officer for all concern operatives.
7. Construction Program
All the work activity will be performed as per an approved baseline program.
AD21094-0201S-FM-18 REV 00
Contractor PMC Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00
Contractor PMC Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00
Contractor PMC Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00