MS For Excavation & Backfilling Works
MS For Excavation & Backfilling Works
Compaction
1- Purpose
2- Scope
3- Legislation & Code of Practice
4- References
5- Definitions
6- Resources
6.1 Material Approvals
6.2 Subcontractor Approval
6.3 Shop Drawings Approvals
6.4 Equipment’s
6.5 Human Resources
7- Safety Precautions/Risk Assessment
8- Work Procedures/Sequence
9- Appendices
Appendix A Risk Assessment
2- Scope
4- References
5- Definitions
Abbreviation For
PM Project Manager
CM Construction Manager
MS Method Statement
LG Lifting Gear
LM Lifting Machine
6- Resources
Only approved material will be used including separation layer, drainage course
warning tiles and warning tapes etc.
6.2 Sub-Contractor Approval
Most of major excavation will be done by main contractor M/s Emirates Link Maltauro.
6.3 Drawings
ELM will follow the excavation limits & levels as mentioned in the shop drawing prior
to start excavation.
6.4 Equipment
6.4.1 JCB/Excavator
6.4.2 Front End / Backhoe Loader
6.5.5 Foreman
Site Foreman is responsible for following
Proper distribution of work force as per requirement of work.
Continuous coordination and follow up of site engineer’s instruction to meet requirements of
outlined in method statement during excavation, construction and finishing activities.
Coordination with site safety officer to maintain safe work place.
To ensure that all the workers have required information and knowledge of their duties.
Ensure when labor wear suitable eye protection and mask where necessary.
Ensure materials are being properly stored.
HSE engineer will make sure the following precautions were taken prior start activity
on daily basis
Maintain a safe route for pedestrians/other labor involve in project to bypass by the works.
Where required lights to be attached to signing and guarding.
Plant vehicle and tool to be kept inside the work area.
Plant/Machine operators to be trained and competent in the use of the plant/machine they are
using.
Keep plant & vehicles away from the edge of the excavation.
Ensure the correct PPE is used for the type of equipment.
Mechanical excavation equipment shall not be used in the vicinity of other utility services.
Ensure the adequate oxygen level in area of deep foundation.
Ensure the following is worn at all times during the works
Hard Hat
Safety boots or wellingtons
High visibility jacket or jerkin
Coveralls
Ensure the following is worn as required during the works
Dust masks – grinding, sawing, cutting or conducting activities that involve airborne dust.
Gloves – when using power equipment or manual handling.
Waterproofs – in wet weather.
8- Work Procedure/Sequence
General Requirements
All the work activity will be performed as per approved baseline program starting from each
packages.
Do not interrupt any existing services (if found during excavation) and must seek engineer
advice for further action.
Site team will make sure all the required NOC & permit are obtained prior start excavation
from concerned authority.
Existing services shall be located, diverted if necessary and protected at all the times.
Drain, manholes and gullies that are to remain shall be protected and kept clear at all the
times.
Excavation Procedure
After excavation is completed ELM shall notify the engineer for approval of depth of
excavation prior to further structural work.
a) All the excavated material shall be stored at designated stockpile area approved by
engineer Excavated material from site will be tested by approved lab and reports will
be submitted for engineer approval prior backfilling the same. only approved
material will be used for backfilling.
b) Engineer will be notified through writing to start backfilling work around building
and other concrete structure.
c) Do not proceed for filling until the location of utility marked and approved by
engineer.
d) Any form work, trash, debris, any temporary shoring, or any other foreign material
will be removed prior start back fill.
e) Underground utilities (existing or new) shall be inspected & protected during
backfilling.
f) Backfilling material will be placed in loose layers by mean of suitable equipment as
per site condition and level prior compaction.
g) The backfill material shall be watered and mixed as necessary to achieve the required
degree of compaction.
h) Each layer will be compacted 95% of its maximum dry density with help of suitable
roller and plate compactor.
i) Manual compaction will be done in confined spaces or where machine can’t access.
j) One field density test will be carried out per 500m2 of filling and compaction and
reports will be submitted for engineer review and approval.
k) All the backfill will be placed to the original ground level or as indicated on
drawings.
l) If final finish layer is part of permanent work such as interlock, concrete or asphalt
last 20-40 cm will be finished as per approved drawings provided with sub-grade and
drainage course as shown on drawings.