Professional Documents
Culture Documents
Method Statement For Antifugal Paint
Method Statement For Antifugal Paint
M-DT-MS-099123-AR-014-A
AD21094-0201S-FM-18 REV 00
Employer PMC Engineer Contractor
Revision History
02
03
Checked By:
Reviewed By:
Approved By:
2. REFERENCES ................................................................................................................ 4
4. RESOURCES ................................................................................................................. 4
2. REFERENCES
Abbreviation For
PM Project Manager
CM Construction Manager
MS Method Statement
4. RESOURCES
4.4 Equipment
Wire brush, abrasive paper, carborundum stone etc.
Roller, brush, scraper/spatula/putty knife, spray equipment, paint tray, extension rod,
compressor etc.
General Foreman
General Foreman is responsible for following.
• Proper distribution of work force as per requirement of work.
• Continuous coordination and follow up of site engineer’s instruction to meet requirements outlined
in method statement during excavation, construction and finishing activities.
• Coordination with site safety officer to maintain safe workplace.
• To ensure that all the workers have the required information and knowledge of their duties.
• Ensure when labor wear suitable eye protection and mask where necessary.
• Ensure materials are being stored.
Site Surveyor
The site surveyor is responsible for the following.
• Check layout and level for form work as per drawings.
• Report to CM/PM if any discrepancy found in site condition & drawings and take advice for further
action prior proceeding with next activity.
• Making sure all the equipment used in survey must be calibrated as per planned interval.
5. HSE REQUIREMENTS
01 POLICE 999
02 AMBULANCE 998
1. Surface preparation: Proper surface preparation is essential for the successful application of
antifungal paint. Ensure that the surfaces to be painted are clean, dry, and free of any loose
or flaking material. Remove any fungal growth, dirt, or other contaminants from the surface
by using appropriate cleaning methods.
2. Material: Check the manufacturer's recommendations for the surface preparation,
application, and drying times.
3. Weather conditions: Antifungal paint application should be done under favorable weather
conditions. The temperature and humidity should be within the manufacturer's
recommended range. Avoid applying antifungal paint during rainy or extremely humid
weather conditions.
4. Equipment and tools: Ensure that all equipment and tools required for antifungal paint
application, such as brushes, rollers, and sprayers, are in good condition and clean. Use
appropriate protective equipment such as gloves, masks, and eye protection.
5. Safety measures: Ensure that all necessary safety measures are in place, such as the
availability of fire extinguishers, first aid kits, and eye wash stations. Ensure that the work area
is cordoned off and properly marked to avoid any accidents or hazards.
Surface Preparation
Apply the one coat of Fenomastic Projects Matt in the desired colour, using a medium nap cotton
roller, at a spreading rate between 6 sq.m/L to 9.4 sq.m/L and allow to dry for a period between 2
hours (40°C) and 6 hours (23°C). A dilution of around 5 to 10 % with fresh water may be allowed for
ease of application. Ensure that a good and uniform finish is achieved.
Note:
• The spreading rate may vary depending on the substrate, type of roller/brush used and
application practice of the painter.
• Care should be taken to remove masking tape immediately after each coat, without allowing
the paint to dry.
• Before applying each coat, ensure that all the dust on the previous coat is removed.
• The technical data sheet should be referred to for information like spreading rate, recoating
interval etc., which should be adhered to strictly.
7. Construction Program
All the work activity will be performed as per an approved baseline program.
AD21094-0201S-FM-18 REV 00
Contractor PMC Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00
Contractor PMC Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00
Contractor PMC Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00