Professional Documents
Culture Documents
Rate Analysis For Site Concept, All Item
Rate Analysis For Site Concept, All Item
Site:
0
Computer Code No. :
Location : Pune
W1
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing box type waterproofing treatment to RCC raft, wall, footings, columns, beams in basement by
fixing rough shahabad stone slabs of about 25 mm thickness in C:M. 1:3 with waterproofing layer in
between shahabad stone and slab bottom/ wall surfaces well pointed with cement plaster mixed with
waterproofing compound carefully well pressed and cured. The said treatment shall be carried out at
the hands of approved waterproofing agency.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Shahabad stone with 5% wastage
d) Waterproofing compound
2
Labours :
Masons for laying tiles & finishing
Unskilled labour
Others
Quantity
Unit
Rate per
Amount
1.28
0.04
1.05
0.60
Bags
Cum
Sqm.
Kg.
245.00
1060.00
82.50
40.00
313.60
42.40
86.63
24.00
0.15
0.30
No.
No.
150.00
80.00
22.50
24.00
0.00
0.00
0.00
TOTAL (A)
5
6
7
2.00%
0.50%
0.00%
15.00%
513.13
on total (A)
on total (A)
on total (A)
TOTAL (B)
10.26
2.57
0.00
525.95
on total (B)
78.89
TOTAL
Say Rs.
604.85
605 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
Default Date :
W2
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Cum
Providing & laying brick bat coba of required thickness in C:M. 1:4 over the specified area including
rubbing and cleaning the base formwork if necessary giving proper slope compacting and curing etc.
complete, (in sunk portion of toilets) including providing and fixing 1" dia GI water escape pipe etc.
complete.
Sr.No.
1
4
5
6
Particulars
Assuming the thickness of 200mm
Materials :
a) Cement
b) Sand
c) Brickbats
d) Waterproofing compound
e) 1" dia. GI pipe
Quantity
Unit
Rate per
Amount
0.63
0.07
0.16
0.63
0.30
Bags
Cum
Cum
Kg.
Rmt.
245.00
1060.00
250.00
40.00
89.00
154.35
74.20
40.00
25.20
26.70
Labours :
Laying of brickbats & finishing
Mason
Helper
0.50
0.50
No.
No.
200.00
80.00
100.00
40.00
Others
Lift
1.00
Cum
17.75
17.75
TOTAL (A)
478.20
9.56
2.39
0.00
TOTAL (B)
490.16
73.52
TOTAL
563.68
2.00%
0.50%
0.00%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
2,818 /- Per
per Cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and laying cement bonded waterproofing treatment using brick bats fixed in concrete 1:2:4
in required slope and finishing top with neat cement punning, marking lines at 300 mm c/c including
providing and mixing waterproofing compound ( work to be carried out at the hands of approved
nominated sub contractors) including curing, testing against watertightness
Sr.No.
Particulars
Quantity
Assuming 1 sqm. Of area with 115 thk. Coba
Unit
Rate per
Amount
a) Cement
b) Sand
c) Metal
d) Brickbats
e) Waterproofing compound
0.40
0.03
0.03
0.08
0.43
Bags
Cum
Cum
Cum
Kg.
245.00
1060.00
340.00
250.00
40.00
98.74
31.80
10.20
20.00
17.20
Labours :
Laying of brickbats & finishing
Mason
Helper
0.40
0.40
No.
No.
200.00
80.00
80.00
32.00
Others
Lift
0.12
Cum
17.75
2.04
TOTAL (A)
291.98
5.84
1.46
0.00
TOTAL (B)
299.28
44.89
TOTAL
344.17
4
5
6
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
344 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : 35
Description :
Location : Pune
W4
Default Date :
Revision on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Labours :
Others
5
6
7
Quantity
1.00
2.00%
0.50%
1.00%
15.00%
Unit
Sqm
Rate per
Amount
275.00
275.00
TOTAL (A)
275.00
5.50
1.38
2.75
TOTAL (B)
284.63
42.69
TOTAL
327.32
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
327 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
White wash
Providing and applying white wash to walls and ceilings , to concrete / brick /block/ stone surfaces
including preparing the surface by cleaning, including scaffolding of required type, all labour and
material complete.
Sr.No.
1
Particulars
Assuming 10sqm of area
Materials :
a) Slaked Lime
b) Ultramarine blue
c) Glue
d) Sodium chloride
Quantity
2.80
7.00
8.00
365.00
Unit
Kg.
Gram
Gram
Gram
Rate per
Amount
1.50
0.11
0.05
0.01
4.20
0.80
0.39
3.65
100.00
80.00
22.50
8.40
TOTAL (A)
39.95
0.80
0.20
0.00
TOTAL (B)
40.94
6.14
TOTAL
47.09
Labours :
For 10 sqm. Area , labour required
= (0.085+0.035) for first coat &
(0.07+.035)*2 for two coat
Lime washer
Helper
4
5
6
0.23
0.11
No.
No.
Others
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
5 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Dry distemper
Providing and applying dry distemper of approved make, colour and shade to walls and ceilings , to
concrete / brick /block/ stone surfaces including preparing the surface by cleaning, including scaffolding
of required type, all labour and material complete.
Sr.No.
1
Particulars
Assuming 10sqm of area
Materials :
a) Dry distemper
b) Glue
d) Putty
Quantity
Unit
Rate per
Amount
1.35
80.00
0.20
Kg.
Gram
Kg.
67.00
0.05
40.95
90.45
3.91
8.19
0.37
0.09
No.
No.
150.00
80.00
54.75
7.20
TOTAL (A)
164.50
3.29
0.82
0.00
TOTAL (B)
168.61
25.29
Labours :
For 10 sqm. Area , labour required
= (0.22+0.05) for first coat &
(0.145+.04) for second coat
Painter
Helper
4
5
6
Others
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
19 /- Per
193.90
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and applying oil bound distemper of approved make,colour and shade to walls and ceilings ,
to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks,
putty filling, rubbing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1
Particulars
Assuming 10sqm of area
Materials :
a) OBD
b) Primer
c) Glue
d) Whitning
e) Putty
Quantity
Unit
Rate per
Amount
1.50
0.85
80.00
1.00
0.20
Kg.
lts.
Gram
Kg.
Kg.
90.00
60.90
0.05
20.00
40.95
135.00
51.77
3.91
20.00
8.19
0.50
0.11
No.
No.
150.00
80.00
74.25
8.80
TOTAL (A)
301.91
6.04
1.51
0.00
TOTAL (B)
309.46
46.42
Labours :
For 10 sqm. Area , labour required
= (0.275+0.06) for first coat &
(0.22+.05) for second coat
Painter
Helper
4
5
6
Others
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
36 /- Per
355.88
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and applying synthetic enamel paint of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material
complete.
Sr.No.
1
Particulars
Assuming 10sqm of area
Materials :
a) Synthetic enamel
b) Primer
c) Glue
d) Whitning
e) Putty
Quantity
Unit
Rate per
Amount
1.50
0.85
80.00
1.00
0.20
Kg.
lts.
Gram
Kg.
Kg.
141.75
60.90
0.05
20.00
40.95
212.63
51.77
3.91
20.00
8.19
0.56
0.15
No.
No.
150.00
80.00
84.00
12.00
TOTAL (A)
392.49
7.85
1.96
0.00
TOTAL (B)
402.30
Labours :
For 10 sqm. Area , labour required
= (0.295+0.09) for first coat &
(0.265+.06) for second coat
Painter
Helper
4
5
6
Others
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
60.34
TOTAL
Say Rs.
46 /- Per
462.64
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Lustre paint
Providing and applying lustre paint of approved make,colour and shade to walls and ceilings , to
concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks,
putty filling, rubbing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1
Particulars
Assuming 10sqm of area
Materials :
a) Luster paint
b) Primer
c) Glue
d) Whitning
e) Putty
Quantity
Unit
Rate per
Amount
1.50
0.85
80.00
1.00
0.30
Ltr.
lts.
Gram
Kg.
Kg.
218.75
60.90
0.05
20.00
40.95
328.13
51.77
3.91
20.00
12.29
0.85
0.30
No.
No.
150.00
80.00
127.88
23.76
TOTAL (A)
567.72
11.35
2.84
0.00
Labours :
For 10 sqm. Area , labour required
= (0.4+0.15) for first coat &
(0.375+.12) for second coat
Painter
Helper
4
5
6
Others
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
581.91
87.29
TOTAL
669.20
on total (B)
Say Rs.
67 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Cement paint
Providing and applying cement paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and
material complete.
Sr.No.
1
Particulars
Assuming 10sqm of area
Materials :
a) Cement paint
b) Putty
Labours :
For 10 sqm. Area , labour required
= (0.25+0.15) for first coat &
(0.2+.1) for second coat
Painter
Helper
Unskilled
Others
4
5
6
Quantity
Unit
Rate per
Amount
4.00
0.15
Kg.
Kg.
49.35
40.95
197.40
6.14
0.45
0.25
0.20
No.
No.
No.
150.00
80.00
80.00
67.50
20.00
16.00
TOTAL (A)
307.04
6.14
1.54
0.00
TOTAL (B)
314.72
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
47.21
TOTAL
Say Rs.
36 /- Per
361.93
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Sandtex paint
Providing and applying sandtex paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and
material complete.
Sr.No.
1
4
5
6
Particulars
Assuming 10sqm of area
Materials :
a) Sandtex paint
b) Cement paint
c) Putty
Labours :
For 10 sqm. Area , labour required
= (0.3+0.1) for first coat & (0.25+.1)
for second coat
Painter
Helper
Unskilled
Quantity
Unit
Rate per
Amount
4.50
1.50
0.20
Kg.
Kg.
Kg.
86.36
49.35
40.95
388.63
74.03
8.19
0.65
0.20
0.20
No.
No.
No.
150.00
80.00
80.00
97.50
16.00
16.00
TOTAL (A)
600.35
12.01
3.00
0.00
TOTAL (B)
615.35
92.30
Others
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
71 /- Per
707.66
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Antifungal paint
Providing and applying anti fungal paint of approved make,colour and shade to walls to concrete /
brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling,
rubbing , curing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1
4
5
6
Particulars
Assuming 10sqm of area
Materials :
a) Antifungal paint
b) Cement paint
c) Putty
Labours :
For 10 sqm. Area , labour required
= (0.3+0.1) for first coat & (0.25+.1)
for second coat
Painter
Helper
Unskilled
Quantity
Unit
Rate per
Amount
4.50
1.50
0.20
Kg.
Kg.
Kg.
123.38
49.35
40.95
555.19
74.03
8.19
0.65
0.30
0.20
No.
No.
No.
150.00
80.00
80.00
97.50
24.00
16.00
TOTAL (A)
774.90
15.50
3.87
0.00
TOTAL (B)
794.28
Others
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
119.14
TOTAL
Say Rs.
91 /- Per
913.42
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
W3
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and applying plastic emulsion paint of approved make,colour and shade to walls and ceilings
, to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks,
putty filling, rubbing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1
Particulars
Assuming 10sqm of area
Materials :
a) Plastic emulsion paint
b) Primer
c) Glue
d) Whitning
e) Putty
Quantity
Unit
Rate per
Amount
1.75
0.85
80.00
1.25
0.40
Kg.
lts.
Gram
Kg.
Kg.
205.15
60.90
0.05
20.00
40.95
359.01
51.77
3.91
25.00
16.38
0.80
0.40
No.
No.
150.00
80.00
120.00
32.00
TOTAL (A)
608.06
12.16
3.04
0.00
TOTAL (B)
623.27
Labours :
For 10 sqm. Area , labour required
= (0.425+0.25) for first coat &
(0.375+.15) for second coat
Painter
Helper
4
5
6
Others
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
Say Rs.
TOTAL (B)
623.27
93.49
TOTAL
716.75
on total (B)
72 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
0.38
0.0152
1.2768
17.7
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) AC trafford sheets
72.77
(adding 100mm for side laps &
200mm for end lap & 5% for
wastage)
Amount
149.10
10849.26
0.30
64.00
0.30
Kg.
Nos.
Kg.
32.00
6.30
47.25
9.60
403.20
14.18
Labours :
For fixing the sheets
60.00
Sqm.
35.00
2100.00
0.00
0.00
TOTAL (A)
13376.24
267.52
0.00
66.88
TOTAL (B)
13710.64
2056.60
TOTAL
15767.24
Others
Nil
4
5
6
Rate per
Sqm.
Unit
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
263 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Ac 6mm thk.ridges
Providing and fixing in positional AC ridges as required including all fixing accessories complete
Sr.No.
Particulars
1 Materials :
a) AC ridges
(adding 5% for wastage)
Rate per
Amount
Rmt.
94.50
99.23
0.02
2.00
0.02
Kg.
Nos.
Kg.
32.00
6.30
47.25
0.64
12.60
0.95
Labours :
For fixing the sheets
1.00
Rmt
25.00
25.00
0.00
0.00
TOTAL (A)
138.41
2.77
0.00
0.69
TOTAL (B)
141.87
21.28
TOTAL
163.15
Others
Nil
4
5
6
Unit
1.05
Quantity
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
163 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
Cladding, flashing etc.
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) AC trafford sheets
69.30
(adding 100mm for side laps &
5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.
Labours :
For fixing the sheets
Rate per
Amount
Sqm.
149.10
10332.63
0.30
48.00
0.30
Kg.
Nos.
Kg.
32.00
6.30
47.25
9.60
302.40
14.18
1.00
Sqm.
42.00
42.00
0.00
0.00
TOTAL (A)
10700.81
214.02
0.00
53.50
TOTAL (B)
10968.33
1645.25
Others
Nil
4
5
6
Unit
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
210 /- Per
12613.57
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Ac gutter
Providing and fixing in required slope AC gutter including fixing with MS flat brackets at 600 mm c/c of
required size, filling the joints with polysulphide sealants etc with all labour and material and testing
against watertightness. (MS bracket to be measured & paid separately)
Sr.No.
Particulars
1 Materials :
a) AC Gutter
(adding 5% for wastage)
Rate per
Amount
Rmt.
105.00
110.25
0.02
2.00
0.02
Kg.
Nos.
Kg.
32.00
6.30
47.25
0.64
12.60
0.95
Labours :
For fixing the sheets
1.00
Rmt
25.00
25.00
0.00
0.00
TOTAL (A)
149.44
2.99
0.00
0.75
Others
Nil
4
5
6
Unit
1.05
Quantity
0.00
2.00%
0.00%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
153.17
22.98
TOTAL
176.15
on total (B)
Say Rs.
176 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
MS precoated sheets
Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc
complete with all labour and material.
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :
a) MS precoated sheets
0.55mm
97.74
(adding 70mm for side laps &
200mm for end lap & 5% for
wastage)
Rate per
Amount
Sqm.
319.00
31180.50
0.38
80.00
0.38
Kg.
Nos.
Kg.
32.00
6.30
47.25
12.00
504.00
17.72
Labours :
For fixing the sheets
84.00
Sqm.
72.80
6115.20
0.00
0.00
Unit
Others
Nil
0.00
4
5
6
2.00%
0.00%
0.50%
15.00%
TOTAL (A)
37829.41
756.59
0.00
189.15
TOTAL (B)
38775.15
5816.27
TOTAL
44591.42
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
531 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
MS precoated ridges
Providing and fixing in position MS precoated ridges as required including all fixing accessories
complete
Sr.No.
Particulars
1 Materials :
a) MS precoated ridges
(adding 5% for wastage)
Unit
Rate per
Amount
1.05
Rmt.
181.50
190.58
0.02
2.00
0.02
Kg.
Nos.
Kg.
32.00
6.30
47.25
0.64
12.60
0.95
Labours :
For fixing the sheets
1.00
Rmt
55.00
55.00
Quantity
Others
Nil
4
5
6
0.00
2.00%
0.00%
0.50%
15.00%
0.00
0.00
TOTAL (A)
259.76
5.20
0.00
1.30
TOTAL (B)
266.25
39.94
TOTAL
306.19
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
306 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc
complete with all labour and material. For Cladding
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 2 = 30 sqm.
Materials :
a) MS precoated sheets
0.55mm
33.71
(adding 70mm for side laps &
5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.
0.23
48.00
0.23
Unit
Rate per
Amount
Sqm.
319.00
10751.90
Kg.
Nos.
Kg.
32.00
6.30
47.25
7.20
302.40
10.63
Labours :
For fixing the sheets
Sqm.
90.00
2880.00
0.00
0.00
TOTAL (A)
13952.13
279.04
0.00
69.76
TOTAL (B)
14300.93
2145.14
TOTAL
16446.07
Others
Nil
4
5
6
32.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
514 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
MS precoated gutter
Providing and fixing in required slope precoated sheet gutter including fixing with MS flat brackets at
600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and
material and testing against watertightness. (MS bracket to be measured & paid separately)
Sr.No.
Particulars
1 Materials :
a) MS precoated Gutter
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.
Quantity
Unit
Rate per
Amount
1.05
Rmt.
216.15
226.96
0.02
2.00
0.02
Kg.
Nos.
Kg.
32.00
6.30
47.25
0.64
12.60
0.95
Labours :
For fixing the sheets
Rmt
90.00
90.00
0.00
0.00
TOTAL (A)
331.14
6.62
0.00
1.66
TOTAL (B)
339.42
50.91
TOTAL
390.33
Others
Nil
4
5
6
1.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
390 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Alluminium sheets
Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :
Unit
Rate per
Amount
a) MS precoated sheets
0.55mm
97.74
Sqm.
415.80
40642.16
0.38
80.00
0.38
Kg.
Nos.
Kg.
32.00
6.30
47.25
12.00
504.00
17.72
Labours :
For fixing the sheets
84.00
Sqm.
72.80
6115.20
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
47291.08
945.82
0.00
236.46
TOTAL (B)
48473.36
7271.00
TOTAL
55744.36
Others
Nil
5
6
7
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
664 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Alluminium ridges
Providing and fixing in position aluminium ridges as required including all fixing accessories
complete
Sr.No.
Particulars
1 Materials :
a) MS precoated ridges
(adding 5% for wastage)
Rate per
Amount
Rmt.
236.50
248.33
0.02
2.00
0.02
Kg.
Nos.
Kg.
32.00
6.30
47.25
0.64
12.60
0.95
Labours :
For fixing the sheets
1.00
Rmt
55.00
55.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
317.51
6.35
Others
Nil
Unit
1.05
Quantity
0.00
0.00
0.00
2.00%
on total (A)
6
7
Water charges
Electricity Charges
0.00%
0.50%
15.00%
on total (A)
on total (A)
0.00
1.59
TOTAL (B)
325.45
48.82
TOTAL
374.26
on total (B)
Say Rs.
374 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
cladding
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 2 = 30 sqm.
Materials :
a) MS precoated sheets
0.55mm
33.71
(adding 70mm for side laps &
5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.
0.23
48.00
0.23
Unit
Rate per
Amount
Sqm.
415.80
14014.54
Kg.
Nos.
Kg.
32.00
6.30
47.25
7.20
302.40
10.63
Labours :
For fixing the sheets
Others
Nil
5
6
7
32.00
Sqm.
90.00
2880.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
17214.77
344.30
0.00
86.07
TOTAL (B)
17645.14
2646.77
TOTAL
20291.91
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
676 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Alluminium gutter
Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600
mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material
and testing against watertightness. (MS bracket to be measured & paid separately)
Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600
mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material
and testing against watertightness. (MS bracket to be measured & paid separately)
Sr.No.
Particulars
1 Materials :
a) MS precoated Gutter
(adding 5% for wastage)
Amount
302.50
317.63
0.02
2.00
0.02
Kg.
Nos.
Kg.
32.00
6.30
47.25
0.64
12.60
0.95
Labours :
For fixing the sheets
1.00
Rmt
90.00
90.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
421.81
8.44
0.00
2.11
TOTAL (B)
432.36
64.85
TOTAL
497.21
Others
Nil
Rate per
Rmt.
5
6
7
Unit
1.05
Quantity
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
Say Rs.
Prepared by :
on total (A)
on total (A)
on total (A)
on total (B)
497 /- Per
per Rmt.
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
FRP sheets
Providing and fixing in position FRP sheet of 1.5 mm thick of Finoram or any other approved make at
all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and
material.
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :
97.74
a) FRP sheets 1.5mm
(adding 70mm for side laps &
200mm for end lap & 5% for
wastage)
Rate per
Amount
Sqm.
423.50
41394.80
0.38
80.00
0.38
Kg.
Nos.
Kg.
32.00
6.30
47.25
12.00
504.00
17.72
Labours :
For fixing the sheets
84.00
Sqm.
72.80
6115.20
0.00
0.00
Unit
Others
Nil
0.00
0.00
0.00
5
6
7
2.00%
0.00%
0.50%
15.00%
0.00
0.00
0.00
0.00
TOTAL (A)
48043.71
960.87
0.00
240.22
TOTAL (B)
49244.81
7386.72
TOTAL
56631.53
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
674 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
FRP ridges
Providing and fixing in position FRP ridges as required including all fixing accessories complete
Sr.No.
Particulars
1 Materials :
a) MS precoated ridges
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.
Quantity
Unit
Rate per
Amount
1.05
Rmt.
154.00
161.70
0.02
2.00
0.02
Kg.
Nos.
Kg.
32.00
6.30
47.25
0.64
12.60
0.95
Labours :
For fixing the sheets
Others
Nil
5
6
7
1.00
Rmt
48.05
48.05
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
223.93
4.48
0.00
1.12
TOTAL (B)
229.53
34.43
TOTAL
263.96
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
264 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
FRP sheets cladding
Dec 30, 99
14-08-06
per Sqm.
Providing and fixing in position FRP sheet roofing with 1.5 mm thick sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
cladding
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 2 = 30 sqm.
Materials :
a) MS precoated sheets
0.55mm
33.71
(adding 70mm for side laps &
5% for wastage)
14274.07
0.23
48.00
0.23
Kg.
Nos.
Kg.
32.00
6.30
47.25
7.20
302.40
10.63
Labours :
For fixing the sheets
32.00
Sqm.
90.00
2880.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
17474.30
349.49
0.00
87.37
TOTAL (B)
17911.16
2686.67
Others
Nil
Amount
423.50
5
6
7
Rate per
Sqm.
Unit
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
687 /- Per
20597.83
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
FRP gutter
Providing and fixing in required slope FRP gutter including fixing with MS flat brackets at 600 mm c/c
of required size, filling the joints with polysulphide sealants etc with all labour and material and testing
against watertightness. (MS bracket to be measured & paid separately)
Sr.No.
Particulars
1 Materials :
a) MS precoated Gutter
(adding 5% for wastage)
Unit
Rate per
Amount
1.05
Rmt.
209.00
219.45
0.02
2.00
0.02
0.03
Kg.
Nos.
Kg.
Kg.
32.00
6.30
47.25
500.00
0.64
12.60
0.95
12.50
Labours :
For fixing the sheets
1.00
Rmt
105.00
105.00
Quantity
Others
Nil
5
6
7
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
351.14
7.02
0.00
1.76
TOTAL (B)
359.91
53.99
TOTAL
413.90
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
414 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Polycarbonate sheets
Providing and fixing in position polycarbonate sheet roof as per detail design and drawing with
minimum thickness of sheet as 2 mm of Lexan or any other approved make including making the
joints waterproof with all labour and material and accessories to complete the work.
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :
a) Polycabonate sheets 2mm
88.20
Unit
Sqm.
Rate per
1500.00
Amount
132300.00
0.38
80.00
0.38
Kg.
Nos.
Kg.
32.00
6.30
47.25
12.00
504.00
17.72
Labours :
For fixing the sheets
84.00
Sqm.
72.80
6115.20
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
138948.92
2778.98
0.00
694.74
TOTAL (B)
142422.64
21363.40
TOTAL
163786.04
Others
Nil
5
6
7
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,950 /- Per
per Sqm.
16.5
4.2
1.21275
72.765
(sheets in row + 1) x no. of purlins
64 hooks
1100
1100
1014
950
0.9218181818 0.8636364
150.72
4.71
1.536
122.88
7.7
15.4
347908.2
160650
3080
757
73920 97.648613
2587777
2601726.8
538200
6075612
30378.06
15.4
1972.6012987
9863.0064935
Rate analysis
Site:
0
Computer Code No. :
Location :
F1
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 25 cm x 25 cm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2
Quantity
Labours :
a) for fixing & joint grouting
b) for polishing (including 3 coats)
Others
Nil
5
6
7
Unit
Rate per
Amount
0.16
0.03
1.05
0.01
Bags
Cum
Sqm
Bags
245.00
1060.00
150.00
150.00
39.20
31.80
157.50
1.50
1.00
1.00
Sqm
Sqm
32.00
20.00
32.00
20.00
0.00
0.00
TOTAL (A)
282.00
5.64
1.41
1.41
TOTAL (B)
290.46
43.57
TOTAL
334.03
0.00
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
334 /- Per
per sqm
Prepared by :
Name : _________________________________
Rate analysis
Sign: ________________
Site:
0
Computer Code No. :
Location :
F1
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 30 cm x 30cm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2
Quantity
Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)
Others
Nil
5
6
7
Unit
Rate per
Amount
0.16
0.05
1.05
0.01
Bags
Cum
Sqm
Bags
245.00
1060.00
220.00
150.00
39.20
53.00
231.00
1.50
1.00
Sqm
32.00
32.00
1.00
Sqm
20.00
20.00
0.00
0.00
TOTAL (A)
376.70
7.53
1.88
1.88
TOTAL (B)
388.00
58.20
TOTAL
446.20
0.00
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
446 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F1
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & laying mosaic tile flooring of 20 to 25 mm thk. & size 25x25cm of White colour in required
positions & set in a bed of 1:6 cement mortor including neat cement float, filling the joint with
appropriate coloured cement slurry, curing, polishing etc. complete
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2
Quantity
Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)
3
4
5
6
7
Unit
Rate per
Amount
0.16
0.03
1.05
0.55
Bags
Cum
Sqm
Kg
245.00
1060.00
244.00
30.00
39.20
31.80
256.20
16.50
1.00
Sqm
32.00
32.00
1.00
Sqm
20.00
20.00
0.00
0.00
TOTAL (A)
395.70
7.91
1.98
1.98
TOTAL (B)
407.57
61.14
TOTAL
468.71
0.00
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
469 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F1
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing,laying and fixing marble mosaic tiles in white cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 30 cm x 30 cm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2
Quantity
Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)
Others
Nil
5
6
7
Rate per
Amount
0.16
0.05
1.05
0.55
Bags
Cum
Sqm
Kg
245.00
1060.00
350.00
30.00
39.20
53.00
367.50
16.50
1.00
Sqm
32.00
32.00
1.00
Sqm
20.00
20.00
0.00
0.00
TOTAL (A)
528.20
10.56
2.64
2.64
TOTAL (B)
544.05
81.61
TOTAL
625.65
0.00
2.00%
0.50%
0.50%
15.00%
Say Rs.
Prepared by :
Unit
on total (A)
on total (A)
on total (A)
on total (B)
626 /- Per
per sqm
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F2
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing filling the joints with cement slurry, polishing, cleaning complete - gray
mosaic tile skirting 125 mm high
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile skirting(as
approved)
Quantity
Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)
3
4
5
6
7
Unit
0.02
0.01
Bags
Cum.
1.05
Rate per
Amount
245.00
1060.00
4.90
10.60
rmt
23.00
24.15
1.00
rmt
10.00
10.00
1.00
rmt
9.00
9.00
0.00
0.00
TOTAL (A)
58.65
1.17
0.29
0.29
TOTAL (B)
60.41
9.06
TOTAL
69.47
0.00
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
69 /- Per
Say Rs.
per rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F2
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, polishing, cleaning, curing etc complete - gray mosaic tile skirting 150 mm
high
Sr.No.
Particulars
1 Materials :
a) Cement
b) Mosaic tile skirting(as
approved)
c) Mosaic tile skirting(as
approved)
2
Quantity
Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)
Others
Rate per
Amount
0.02
Bags
245.00
4.90
0.01
Cum
1060.00
10.60
1.05
rmt
32.00
33.60
1.00
rmt
10.00
10.00
1.00
rmt
9.00
9.00
0.00
0.00
TOTAL (A)
68.10
1.36
0.34
0.34
TOTAL (B)
70.14
10.52
0.00
Nil
5
6
7
Unit
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
81 /- Per
80.66
per rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F2
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry,polishing, cleaning curing etc complete white mosaic tile skirting 125 mm high
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
b) Mosaic tile skirting(as
approved)
c) White/ coloured cement
2
Quantity
Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)
3
4
5
6
7
Unit
0.02
0.01
Bags
cum.
1.05
0.25
Rate per
Amount
245.00
1060.00
4.90
10.60
rmt
Kg
30.00
30.00
31.50
7.50
1.00
rmt
10.00
10.00
1.00
rmt
9.00
9.00
0.00
0.00
TOTAL (A)
73.50
1.47
0.37
0.37
TOTAL (B)
75.71
11.36
0.00
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
87 /- Per
87.06
per rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F2
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing,filling the joints with cement slurry, cleaning complete - white mosaic tile
skirting 150 mm high
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile skirting(as
approved)
d) White/ coloured cement
2
Quantity
Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)
3
4
5
6
7
Unit
0.02
0.01
Bags
Cum
1.05
0.25
Amount
245.00
1060.00
4.90
10.60
rmt
Kg
45.00
30.00
47.25
7.50
1.00
rmt
10.00
10.00
1.00
rmt
9.00
9.00
0.00
0.00
TOTAL (A)
89.25
1.79
0.45
0.45
TOTAL (B)
91.93
0.00
2.00%
0.50%
0.50%
Rate per
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
13.79
TOTAL
Say Rs.
106 /- Per
105.72
per rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F1
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Provding and laying in position IPS flooring 50mm thick in proportion of 1:2:4 laid in proper line and
level including finishing the top surface with cement punning, curing, cleaning etc complete with all
labour and material.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal 12mm
3
4
5
6
7
Quantity
Labours :
a) for pouring
b) for finishing
c) for shuttering
Centering & Shuttering
Nil
Others
Nil
Unit
Amount
0.22
0.02
0.05
Bags
Cum
Cum
245.00
1060.00
340.00
53.90
23.85
15.30
1.00
1.00
1.00
Sqm
Sqm
Sqm
16.00
23.00
10.56
16.00
23.00
10.56
1.00
Sqm
4.00
4.00
0.00
0.00
TOTAL (A)
146.61
2.93
0.73
0.73
0.00
2.00%
0.50%
0.50%
Rate per
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
151.01
22.65
TOTAL
173.66
on total (B)
Say Rs.
174 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F3
Pune
Default Date :
Revised on Date :
Unit :
Item No. : 29
Description :
Dec 30, 99
14-08-06
per sqm
Providing and laying ceramic tiles of approved quality of approved colour, size & thickness for flooring in
required position laid on a bed 30mm thk.in 1:6 cement mortor including cement float filling joints with
white/colour cement slurry cleaning curing etc. complete as shown in detailed drawing or as directed by
architect incharge.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tile (as approved)
d) white cement
2
Labours :
for flooring including fixing,
cleaning & curing etc. complete
Others
Quantity
Unit
Rate per
Amount
0.16
0.05
1.05
0.55
Bags
Cum
Sqm
Kg
245.00
1060.00
380.00
30.00
39.20
53.00
399.00
16.50
1.00
0.00
Sqm
75.00
0.00
75.00
0.00
0.00
0.00
TOTAL (A)
582.70
0.00
5
6
7
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
11.65
2.91
2.91
TOTAL (B)
600.18
90.03
TOTAL
690.21
on total (B)
690 /- Per
Say Rs.
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Marble Flooring
Providing, laying and fixing in position marble slabs for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
3
4
Unit
Rate per
Amount
0.22
0.04
Bags
Cum
245.00
1060.00
53.90
42.40
d) White cement
1.05
0.22
Sqm
Kg
860.00
30.00
903.00
6.60
Labours :
a) for fixing & joint grouting
b) for polishing
1.00
1.00
Sqm
Sqm
100.00
129.00
100.00
129.00
0.00
0.00
0.00
TOTAL (A)
1234.90
Quantity
5
6
7
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
24.70
6.17
6.17
TOTAL (B)
1271.95
190.79
TOTAL
1462.74
1,463 /- Per
Say Rs.
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Marble Skirting
Providing and fixing in position dado of tiles / stone as per requirement, including fixing with C:M 1:4
backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete -marble stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Marble (including 10%
wastage)
c) White cement
d) Sand
2
3
4
5
6
Quantity
Unit
Rate per
Amount
0.22
Bags
245.00
53.90
1.10
1.00
0.01
Sqm
Kg
Cum
860.00
30.00
1060.00
946.00
30.00
10.60
Labours :
a) for fixing & joint grouting
b) for polishing
1.00
1.00
Sqm
Sqm
110.00
148.35
110.00
148.35
0.00
0.00
0.00
TOTAL (A)
1298.85
25.98
6.49
2.00%
0.50%
on total (A)
on total (A)
Electricity Charges
0.50%
on total (A)
15.00%
6.49
TOTAL (B)
1337.82
200.67
TOTAL
1538.49
on total (B)
Say Rs.
154 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Kota Flooring
Providing, laying and fixing in required position machine cut machine polished Kotah stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Kota (including 5% wastage)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.22
0.04
1.05
0.35
Bags
Cum
Sqm
Kg
245.00
1060.00
290.52
30.00
53.90
42.40
305.05
10.50
Labours :
a) for fixing & polishing
1.00
Sqm
100.00
100.00
0.00
0.00
0.00
TOTAL (A)
511.85
10.24
2.56
2.56
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
527.20
79.08
TOTAL
606.28
on total (B)
Say Rs.
606 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Kota Skirting
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, polishing, cleaning , curing etc complete
- kotah stone 100 mm height
Sr.No.
Particulars
1 Materials :
a) Cement
b) Kota (including 15% wastage)
c) White / coloured cement
d) Sand
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.34
1.15
1.10
0.01
Bags
Sqm
Kg
Cum
245.00
290.52
30.00
1060.00
83.30
334.10
33.00
10.60
Labours :
a) for fixing & polishing
1.00
Sqm
121.00
121.00
0.00
0.00
0.00
TOTAL (A)
582.00
11.64
2.91
2.91
TOTAL (B)
599.46
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
599.46
89.92
TOTAL
689.38
on total (B)
Say Rs.
69 /- Per
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Tandoor Flooring
Providing, laying and fixing in required position machine cut machine polished Tandur stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Tandoor (including 5%
wastage)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.22
0.04
Bags
Cum
245.00
1060.00
53.90
42.40
1.05
0.35
Sqm
Kg
291.00
30.00
305.55
10.50
Labours :
a) for fixing & polishing
1.00
Sqm
86.00
86.00
0.00
0.00
0.00
TOTAL (A)
498.35
9.97
2.49
2.49
TOTAL (B)
513.30
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
77.00
TOTAL
Say Rs.
590 /- Per
590.30
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt
Tandoor Skirting
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning , curing etc complete - tandur
stone 100 mm height
Sr.No.
Particulars
1 Materials :
a) Cement
b) Tandoor (including 15%
wastage)
c) White / coloured cement
d) Sand
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.34
Bags
245.00
83.30
1.15
0.35
0.01
Sqm
Kg
Cum
291.00
30.00
1060.00
334.65
10.50
10.60
Labours :
a) for fixing & polishing
1.00
Sqm
94.60
94.60
0.00
0.00
0.00
TOTAL (A)
533.65
10.67
2.67
2.67
TOTAL (B)
549.66
82.45
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
63 /- Per
632.11
per Rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Granite Flooring
Providing, laying and fixing in position granite stone for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
Quantity
3
4
5
6
7
Rate per
Amount
0.22
0.04
Bags
Cum
245.00
1060.00
53.90
42.40
1.05
0.35
Sqm
Kg
1695.00
30.00
1779.75
10.50
Labours :
a) For fixing
1.00
Sqm
172.00
172.00
0.00
0.00
0.00
TOTAL (A)
2058.55
41.17
10.29
10.29
TOTAL (B)
2120.31
318.05
Unit
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
2,438 /- Per
2438.35
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Granite Skirting
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with white cement, cleaning, curing etc complete - granite
stone / tile 100 mm height
Sr.No.
Particulars
1 Materials :
a) Cement
b) Granite (including 15%
wastage)
c) White cement
d) Sand
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.34
Bags
245.00
83.30
1.15
0.35
0.01
Sqm
Kg
Cum
1695.00
30.00
1060.00
1949.25
10.50
10.60
Labours :
a) for fixing & polishing
1.00
Sqm
215.00
215.00
0.00
0.00
0.00
TOTAL (A)
2268.65
45.37
11.34
11.34
TOTAL (B)
2336.71
350.51
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
269 /- Per
2687.22
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing, laying and fixing in required position machine cut rough shahabad stone flooring of required
size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement
float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Rough shahabad (including 5%
wastage)
d) White / coloured cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.22
0.04
Bags
Cum
245.00
1060.00
53.90
42.40
1.05
0.35
Sqm
Kg
75.00
3.00
78.75
1.05
Labours :
a) For fixing
1.00
Sqm
65.00
65.00
0.00
0.00
0.00
TOTAL (A)
241.10
4.82
1.21
1.21
TOTAL (B)
248.33
37.25
TOTAL
285.58
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
286 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing, laying and fixing in required position machine cut machine polished shahabad stone flooring
of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Polished shahabad (including
5% wastege)
d) White / coloured cement
2
3
4
5
6
7
Quantity
Labours :
a) For fixing
Centering & Shuttering
Nil
Others
Nil
Unit
Rate per
Amount
0.22
0.04
Bags
Cum
245.00
1060.00
53.90
42.40
1.05
0.35
Sqm
Kg
110.00
30.00
115.50
10.50
1.00
Sqm
80.00
80.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
302.30
6.05
1.51
1.51
TOTAL (B)
311.37
46.71
0.00
0.00
0.00
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
358 /- Per
358.07
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position ceramic tile of various sizes such as 200 x 200 mm, 300 x 300 mm, 200
x 300 etc of approved make, color and shade on C:M 1:6 bedding including filling the joints with neat
cement slurry of matching colour, including cutting the tiles to required size, curing, cleaning etc
complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tiles(including 5%
wastage)
d) White / coloured cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.22
0.03
Bags
Cum
245.00
1060.00
53.90
34.45
1.05
0.25
Sqm
Kg
380.00
30.00
399.00
7.50
Labours :
a) For fixing
1.00
Sqm
75.00
75.00
0.00
0.00
0.00
TOTAL (A)
569.85
11.40
2.85
2.85
TOTAL (B)
586.95
88.04
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
675 /- Per
674.99
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete ceramic tiles of approved make and type and given height.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tiles(including 10%
wastage)
d) White / coloured cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.03
Bags
Cum
245.00
1060.00
68.60
26.50
1.10
0.30
Sqm
Kg
380.00
30.00
418.00
9.00
Labours :
a) For fixing
1.00
Sqm
90.00
90.00
0.00
0.00
0.00
TOTAL (A)
612.10
12.24
3.06
3.06
TOTAL (B)
630.46
94.57
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
725 /- Per
725.03
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete ceramic tiles of approved make and type and colour 100 mm height
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tiles(including 10%
wastege)
d) White / coloured cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.02
Bags
Cum
245.00
1060.00
68.60
15.90
1.07
1.00
Sqm
Kg
380.00
30.00
406.60
30.00
Labours :
a) For fixing
1.00
Sqm
80.00
80.00
0.00
0.00
0.00
TOTAL (A)
601.10
12.02
3.01
3.01
TOTAL (B)
619.13
92.87
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
71 /- Per
712.00
per Rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position vitrified tile flooring of approved make,size and shade on bed of cement
mortar 1:6 in required line and level, filling the joints with white cement, cleaning etc complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Vetrified tiles(including 5%
wastage)
d) White / coloured cement
2
Quantity
Labours :
a) For fixing
Others
Rate per
Amount
0.20
0.03
Bags
Cum
245.00
1060.00
49.00
26.50
1.05
0.25
Sqm
Kg
800.00
30.00
840.00
7.50
1.00
Sqm
80.00
80.00
0.00
0.00
TOTAL (A)
1003.00
20.06
5.02
5.02
TOTAL (B)
1033.09
154.96
0.00
Nil
5
6
7
Unit
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
1,188 /- Per
1188.05
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Item No. : 30
Description :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position vitrified tile flooring of approved make,size and shade in required line
and level, filling the joints with white cement, cleaning etc complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Vetrified tiles(including 10%
wastage)
d) White / coloured cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.02
Bags
Cum
245.00
1060.00
68.60
21.20
1.10
0.30
Sqm
Kg
800.00
0.00
880.00
0.00
Labours :
a) For fixing
1.00
Sqm
96.00
96.00
0.00
0.00
0.00
TOTAL (A)
1065.80
21.32
5.33
5.33
TOTAL (B)
1097.77
164.67
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
1,262 /- Per
1262.44
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Item No. : 30
Description :
Unit :
Dec 30, 99
14-08-06
per Rmt.
Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete
-polished vitrified tile 100 mm height
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Vetrified tiles(including 10%
wastage)
d) White / coloured cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.02
Bags
Cum
245.00
1060.00
68.60
15.90
1.07
0.30
Sqm
Kg
800.00
30.00
856.00
9.00
Labours :
a) For fixing
1.00
Sqm
85.00
85.00
0.00
0.00
0.00
TOTAL (A)
1034.50
20.69
5.17
5.17
TOTAL (B)
1065.54
159.83
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
1,225 /- Per
1225.37
per Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position interlocking type designer tiles of approved make, colour and shade,
over bed of 1:6 mortar in proper line and level including finishing, compaction, filling joints cleaning etc
complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Designer tiles(including 5%
wastage)
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.18
0.04
Bags
Cum
245.00
1060.00
44.10
41.34
1.05
Sqm
430.40
451.92
Labours :
a) For fixing
1.00
Sqm
60.00
60.00
0.00
0.00
0.00
TOTAL (A)
597.36
11.95
2.99
2.99
TOTAL (B)
615.28
92.29
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
708 /- Per
707.57
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on
bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating
etc complete. ( of strength M20 - 65 mm thick)
Sr.No.
Particulars
1 Materials :
Quantity
a) Sand
b) Paver blocks (including 5%
wastege)
2
3
4
5
6
7
Unit
Rate per
Amount
0.05
Cum
1060.00
53.00
1.05
Sqm
242.10
254.21
Labours :
a) For fixing
1.00
Sqm
30.00
30.00
0.00
0.00
0.00
TOTAL (A)
337.21
6.74
1.69
1.69
TOTAL (B)
347.32
52.10
TOTAL
399.42
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
399 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on
bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating
etc complete. ( of strength M40 - 65 mm thick)
Sr.No.
Particulars
1 Materials :
Quantity
a) Sand
b) Paver blocks (including 5%
wastage)
3
4
5
6
7
Unit
Rate per
Amount
0.05
Cum
1060.00
53.00
1.05
Sqm
386.00
405.30
Labours :
a) For fixing
1.00
Sqm
30.00
30.00
0.00
0.00
0.00
TOTAL (A)
488.30
9.77
2.44
2.44
TOTAL (B)
502.95
75.44
TOTAL
578.39
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
578 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and laying chequered tiles in required position in proper line and level, on bed of C:M 1:6
including filling the joints with neat cement slurry, cleaning, curing etc complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Chequered tiles(including 5%
wastage)
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.21
0.04
Bags
Cum
245.00
1060.00
51.45
41.34
1.05
Sqm
102.00
107.10
Labours :
a) For fixing
1.00
Sqm
60.00
60.00
0.00
0.00
0.00
TOTAL (A)
259.89
5.20
1.30
1.30
TOTAL (B)
267.69
40.15
TOTAL
307.84
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
308 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing etc
complete -kotah stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Kota steps (including 5%
wastege)
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.04
Bags
Cum
245.00
620.00
68.60
24.80
1.05
Sqm
250.00
262.50
Labours :
a) for fixing & polishing
1.00
Sqm
400.00
400.00
0.00
0.00
0.00
TOTAL (A)
755.90
15.12
3.78
3.78
TOTAL (B)
778.58
116.79
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
895 /- Per
895.36
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt
Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing etc
complete -marble stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Marble steps (including 5%
wastage)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.04
Bags
Cum
245.00
1060.00
68.60
42.40
1.05
0.35
Sqm
Kg
1032.00
30.00
1083.60
10.50
Labours :
a) for fixing & polishing
1.00
Sqm
167.70
167.70
0.00
0.00
0.00
TOTAL (A)
1372.80
27.46
6.86
6.86
TOTAL (B)
1413.98
212.10
TOTAL
1626.08
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
163 /- Per
per Rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Rmt
Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc
complete -granite stone of approved colour
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Granite steps (including 5%
wastage)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.04
Bags
Cum
245.00
1060.00
68.60
42.40
1.05
1.00
Sqm
Kg
2118.75
30.00
2224.69
30.00
Labours :
a) for fixing & polishing
1.00
Sqm
223.60
223.60
0.00
0.00
0.00
TOTAL (A)
2589.29
51.79
12.95
12.95
TOTAL (B)
2666.97
400.04
TOTAL
3067.01
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
307 /- Per
per Rmt
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing, curing etc
complete -tandur stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Tandoor steps (including 5%
wastage)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.22
0.04
Bags
Cum
245.00
1060.00
53.90
42.40
1.05
0.35
Sqm
Kg
378.30
30.00
397.22
10.50
Labours :
a) for fixing & polishing
1.00
Sqm
111.80
111.80
0.00
0.00
0.00
TOTAL (A)
615.82
12.32
3.08
3.08
TOTAL (B)
634.29
95.14
TOTAL
729.43
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
73 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Description :
Kota for sill & Jams
Providing and fixing in position window sills and jambs of stone as per requirement, including fixing with
C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing
etc complete -kotah stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Kota sill (including 10%
wastege)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.20
0.02
Bags
Cum
245.00
1060.00
49.00
21.20
1.10
1.00
Sqm
Kg
290.52
30.00
319.57
30.00
Labours :
a) for fixing & polishing
1.00
Sqm
132.00
132.00
0.00
0.00
0.00
TOTAL (A)
551.77
11.04
2.76
2.76
TOTAL (B)
568.33
85.25
TOTAL
653.57
2.00%
0.50%
0.50%
15.00%
Say Rs.
Prepared by :
on total (A)
on total (A)
on total (A)
on total (B)
654 /- Per
per sqm
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Description :
Marble for Sills & jams
Providing and fixing in position window sills and jambs of stone as per requirement, including fixing with
C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing
etc complete -marble stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Marble sill (including 10%
wastage)
d) White cement
Quantity
Labours :
a) for fixing & polishing
Others
Amount
0.20
0.02
Bags
Cum
245.00
1060.00
49.00
21.20
1.10
1.00
Sqm
Kg
860.00
30.00
946.00
30.00
1.00
Sqm
132.00
132.00
0.00
0.00
TOTAL (A)
1178.20
23.56
5.89
5.89
TOTAL (B)
1213.55
182.03
TOTAL
1395.58
2.00%
0.50%
0.50%
15.00%
Say Rs.
Prepared by :
Rate per
0.00
Nil
5
6
7
Unit
on total (A)
on total (A)
on total (A)
on total (B)
1,396 /- Per
per sqm
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Description :
Granite for sills & Jams
Providing and fixing in position window sills and jambs stone as per requirement, including fixing with
C:M 1:4bedding, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc
complete -granite stone of approved colour
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Granite sill (including 10%
wastage)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.28
0.04
Bags
Cum
245.00
1060.00
68.60
42.40
1.10
1.00
Sqm
Kg
1695.00
30.00
1864.50
30.00
Labours :
a) for fixing & polishing
1.00
Sqm
258.00
258.00
0.00
0.00
0.00
TOTAL (A)
2263.50
45.27
11.32
11.32
TOTAL (B)
2331.41
349.71
TOTAL
2681.12
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
2,681 /- Per
per sqm
Prepared by :
Name : _________________________________
Rate analysis
Sign: ________________
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Description :
Tandoor for sills & jams
Providing and fixing in position window sills and jambs of stone as per requirement, including fixing
with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing,
curing etc complete -tandur stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Tandoor sill (including 10%
wastege)
d) White cement
2
Quantity
Labours :
a) for fixing & polishing
Others
Rate per
Amount
0.20
0.02
Bags
Cum
245.00
1060.00
49.00
21.20
1.10
0.35
Sqm
Kg
291.00
30.00
320.10
10.50
1.00
Sqm
113.52
113.52
0.00
0.00
TOTAL (A)
514.32
10.29
2.57
2.57
TOTAL (B)
529.75
79.46
TOTAL
609.21
0.00
Nil
5
6
7
Unit
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
609 /- Per
per sqm
Prepared by :
Name : _________________________________
Rate analysis
Sign: ________________
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
Rmt.
Description :
Granite Kitchen otta
Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top
Sr.No.
Particulars
Quantity
Considering the size of 3.0m x.75m
1 Materials :
a) Cement
2.55
b) Sand
0.03
c) Granite (including 10%
wastage)
3.71
d) Kaddappa (with 10% wastage)
e) White / colour cement
2
Unit
Rate per
Amount
Bags
Cum
245.00
1060.00
624.75
31.80
Sqm
1695.00
6293.54
3.82
0.35
Sqm
Kg
220.00
30.00
840.40
10.50
2.25
Sqm
1506.00
3388.50
4.42
Rmt.
246.00
1087.32
1.00
No.
400.00
400.00
0.00
0.00
TOTAL (A)
12676.81
253.54
63.38
63.38
TOTAL (B)
13057.11
1958.57
TOTAL
15015.68
Labours :
a) for fixing of Kadappa & granite
(considering labour rate @ 105/per rft length I.e = 105/- per 0.75
sft. Rate per sqm =
(105/.75)*10.76 = Rs. 1506
b) For moulding & edge polishing
c) For Cutout making for sink
fixing
Others
Nil
5
6
7
0.00
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
5,005 /- Per
Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
Rmt.
Description :
Marble Kitchen otta
Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top- Marble stone
Sr.No.
Particulars
Quantity
Considering the size of 3.0m x.75m
1 Materials :
a) Cement
2.55
b) Sand
0.03
c) Marble (including 10%
wastage)
3.71
d) Kaddappa (with 10% wastage)
e) White / colour cement
2
Unit
Rate per
Amount
Bags
Cum
245.00
1060.00
624.75
31.80
Sqm
860.00
3193.18
3.82
0.35
Sqm
Kg
220.00
30.00
840.40
10.50
2.25
Sqm
1147.00
2580.75
4.57
Rmt.
196.80
900.00
1.00
No.
400.00
400.00
0.00
0.00
TOTAL (A)
8581.38
171.63
42.91
42.91
TOTAL (B)
8838.82
1325.82
10164.64
Labours :
a) for fixing of Kadappa & Marble
(considering labour rate @ 80/per rft length I.e = 80/- per 0.75
sft. Rate per sqm = (80/.75)*10.76
= Rs. 1147
b) For edge polishing
c) For Cutout making for sink
fixing
Others
Nil
4
5
6
0.00
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
3,388 /- Per
Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
Rmt.
Description :
Kadappa Kitchen otta
Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top- Kadappa stone
Sr.No.
Particulars
Quantity
Considering the size of 3.0m x.75m
1 Materials :
a) Cement
2.55
b) Sand
0.03
c) Top & shelf kadappa (including
10% wastage)
3.80
d) Kaddappa Verticals & Facia
(with 10% wastage)
1.60
e) White / colour cement
0.35
2
Labours :
a) for fixing of Kadappa
Unit
Rate per
Amount
Bags
Cum
245.00
1060.00
624.75
31.80
Sqm
258.00
980.40
Sqm
Kg
220.00
30.00
352.00
10.50
2.25
Sqm
860.00
1935.00
4.57
Rmt.
82.00
375.00
1.00
No.
250.00
250.00
0.00
0.00
TOTAL (A)
4559.45
91.19
22.80
22.80
TOTAL (B)
4696.23
704.44
TOTAL
5400.67
(considering labour rate @ 60/per rft length I.e = 60/- per 0.75
sft. Rate per sqm = (60/.75)*10.76
= Rs. 717
b) For moulding & edge polishing
c) For Cutout making for sink
fixing
3
Others
Nil
4
5
6
0.00
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
1,800 /- Per
Rmt.
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
F4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing and fixing in position treads and risers of designer tiles as per requirement, including fixing
with C:M 1:4 backing, filling the joints with cement slurry, cleaning, etc complete -
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Designer Tiles (including 5%
wastage)
d) White cement
2
3
4
5
6
7
Quantity
Unit
Rate per
Amount
0.22
0.04
Bags
Cum
240.00
620.00
52.80
24.80
1.05
0.35
Sqm
Kg
780.00
30.00
819.00
10.50
Labours :
a) for fixing & polishing
1.00
Sqm
300.00
300.00
0.00
0.00
0.00
TOTAL (A)
1207.10
-36.21
-6.04
-6.04
TOTAL (B)
1158.82
173.82
TOTAL
1332.64
-3.00%
-0.50%
-0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,333 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
0.2 mason
0.5 labour
0.01
0.344
0.86
137.6
0.2
0.5
0.2
0.35
40
28
68
0.2
0.5
40
40
0.2
0.4
40
32
0.25
0.45
90
50
36
0.15
0.3
30
24
0.4
0.8
80
64
144
158.4
65.20
0.9
0.45
180
36
Rate analysis
Site:
0
Computer Code No. :
Location :
B1
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
UCR In plinth
Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation steps, platforms etc.below
plinth including curing , weepholes if required, including specials such as corners, quions, headers, through
stones etc. dewatering if required, racking out joints 10 mm deep etc. complete.
Sr.No.
Particulars
1 Materials :
a) Rubble
b) Cement
c) Sand
Quantity
Labours :
for U.C.R. masonry works
Others
Nil
5
6
7
Unit
Rate per
Amount
1.25
1.57
0.40
cum
Bags
cum
500.00
240.00
1060.00
625.00
376.80
424.00
1.00
cum
250.00
250.00
0.00
0.00
TOTAL (A)
1675.80
33.52
8.38
8.38
TOTAL (B)
1726.07
258.91
TOTAL
1984.99
0.00
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
1,985 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
B1
0
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation for compound wall, steps,
pillars , platforms etc. and wherever required including scaffolding, curing , weepholes if required, including
specials such as corners, quions, headers through stones etc. dewatering if required, racking out joints 10
mm deep etc. complete.
Sr.No.
Particulars
1 Materials :
a) Rubble
b) Cement
c) Sand
Quantity
Labours :
for U.C.R. masonry works
Others
Scaffolding
5
6
7
2.00%
0.50%
0.50%
Unit
Rate per
Amount
1.25
1.57
0.40
cum
Bags
cum
500.00
245.00
1060.00
625.00
384.65
424.00
1.00
cum
252.00
252.00
1.00
Cum
20.00
20.00
TOTAL (A)
1705.65
34.11
8.53
8.53
TOTAL (B)
1756.82
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
263.52
TOTAL
Say Rs.
2,020 /- Per
2020.34
per cum
Rate analysis
Site:
0
Computer Code No. :
Location :
B1
0
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in plinth for
steps, or any where as required including racking out joints 1.5 cm deep including scaffolding, curing etc.
complete.
Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand
Quantity
Others
Amount
Nos.
Bags
cum
2.25
245.00
1060.00
1125.00
416.50
275.60
1.00
cum
164.00
164.00
0.00
0.00
TOTAL (A)
1981.10
39.62
9.91
0.00
TOTAL (B)
2030.63
Nil
5
6
7
Rate per
500.00
1.70
0.26
Labours :
for brick masonry works
Unit
0.00
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
2030.63
304.59
TOTAL
2335.22
on total (B)
Say Rs.
2,335 /- Per
per cum
Rate analysis
Site:
0
Computer Code No. :
Location :
B1
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in
superstructure at all levels wherever required including raking out joints 1.5 cm deep including scaffolding,
curing etc. complete.
Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand
Labours :
for brick masonry works
Others
Add for scaffolding & sand screening
etc.
Quantity
Unit
Rate per
Amount
500.00
1.70
0.30
Nos.
Bags
cum
2.25
245.00
1060.00
1125.00
416.50
318.00
1.00
cum
164.00
164.00
1.00
cum
45.60
45.60
TOTAL (A)
2069.10
5
6
7
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
41.38
10.35
0.00
TOTAL (B)
2120.83
318.12
TOTAL
2438.95
on total (B)
Say Rs.
2,439 /- Per
per cum
Rate analysis
Site:
0
Computer Code No. :
Location :
B2
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls,etc below plinth wherever required
including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.
Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand
Labours :
for Brick masonry works
Quantity
Unit
Rate per
Amount
500.00
0.90
0.05
No
Bags
cum
3.00
210.00
850.00
1500.00
189.00
42.50
1.00
sqm
38.00
38.00
0.00
0.00
Others
Nil
0.00
5
6
7
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
Say Rs.
TOTAL (A)
1769.50
35.39
8.85
0.00
TOTAL (B)
1813.74
272.06
TOTAL
2085.80
2,086 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
B2
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls in superstructure at all levers
wherever required including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.
Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand
Labours :
for Brick masonry works
Quantity
Unit
Rate per
Amount
500.00
0.90
0.05
No
Bags
cum
3.00
245.00
1060.00
1500.00
220.50
53.00
1.00
sqm
42.00
42.00
5
6
7
Others
Scaffolding / sand screening etc.
1.00
2.00%
0.50%
0.00%
sqm.
9.80
9.80
TOTAL (A)
1825.30
36.51
9.13
0.00
TOTAL (B)
1870.93
280.64
TOTAL
2151.57
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
Say Rs.
2,152 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
B3
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & constructing 6" thk, brick masonry using 'Thoklas' bricks in C.M. 1:4, at all levels wherever
required including raking out joints, scaffolding, curing etc,. All complete.
Sr.No.
Particulars
1 Materials :
a) Thokla Bricks (15cm thk.)
Quantity
48.00
Unit
No
Rate per
4.00
Amount
192.00
b) Cement
c) Sand
0.26
0.04
Bags
Cum
245.00
1060.00
63.70
42.40
Labours :
for Brick masonry works
1.00
Sqm
46.00
46.00
8.23
0.00
TOTAL (A)
344.10
6.88
1.72
0.00
TOTAL (B)
352.70
52.91
TOTAL
405.61
Others
Scaffolding / sand screening etc.
5
6
7
0.00
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
406 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
B4
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick 1:2:4
p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking out
joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete mullion
with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete and
reinforcement will be paid in items of Columns and reinforcement respectively)
Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick 1:2:4
p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking out
joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete mullion
with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete and
reinforcement will be paid in items of Columns and reinforcement respectively)
Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand
Quantity
Others
Scaffolding / sand screening etc.
Rate per
Amount
58.00
0.17
0.03
No
Bags
Cum
3.00
245.00
1060.00
174.00
41.65
26.50
1.00
Sqm
41.50
41.50
1.00
Sqm.
7.70
7.70
TOTAL (A)
291.35
5.83
1.46
0.00
TOTAL (B)
298.63
44.80
TOTAL
343.43
Labours :
for Brick masonry works
Unit
5
6
7
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
Say Rs.
343 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
B1
0
Default Date :
Revised on Date :
Unit :
Coursed rubble masonary
Dec 30, 99
14-08-06
per cum
Providing & constructing coursed rubble masonry II sort in cement mortar 1:6 for foundation steps, platforms
etc.at all required levels including curing, scaffolding if required, weepholes if required, including specials
such as corners, quions, headers through stones etc. dewatering if required, raking out joints 10 mm deep
etc. complete.
Sr.No.
Particulars
1 Materials :
a) Rubble
b) Cement
c) Sand
Labours :
For coursed rubble masonary
Others
Scaffolding & sand screening
5
6
7
Quantity
Unit
Rate per
Amount
1.25
1.75
0.31
cum
Bags
cum
500.00
245.00
1060.00
625.00
428.75
332.84
1.00
cum
253.22
253.22
1.00
Cum.
29.71
29.71
TOTAL (A)
1669.53
33.39
8.35
0.00
TOTAL (B)
1711.27
256.69
TOTAL
1967.96
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,968 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
Computer Code No. :
Location :
B5
Default Date :
Revised on Date :
Item No. : FDAPL/MAS/IV/11
Description :
Unit :
14-08-06
per sqm
Providing & constructing 150 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..
Sr.No.
Particulars
1 Materials :
a) Concrete blocks
b) Cement
c) Sand
Others
Scaffolding / sand screening etc.
Unit
Rate per
Amount
18.00
0.15
0.04
No
Bags
Cum
16.00
245.00
1060.00
288.00
36.02
42.40
1.00
Sqm
8.23
8.23
1.00
Job
8.23
8.23
TOTAL (A)
382.88
7.66
1.91
0.00
TOTAL (B)
392.45
58.87
TOTAL
451.31
Labours :
for C.C.block masonry works
5
6
7
Quantity
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
451 /- Per
per sqm
Prepared by :
Name : _________________________________
Rate analysis
Sign: ________________
Site:
0
Computer Code No. :
Location :
B5
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & constructing 200 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..
Sr.No.
Particulars
1 Materials :
a) Concrete blocks
b) Cement
c) Sand
Quantity
Others
Scaffolding / sand screening etc.
Rate per
Amount
12.00
0.11
0.05
No
Bags
Cum
34.00
245.00
1060.00
408.00
26.95
53.00
1.00
Sqm
25.30
25.30
1.00
0.00
Job
8.76
0.00
8.76
0.00
TOTAL (A)
522.01
10.44
2.61
0.00
TOTAL (B)
535.06
80.26
TOTAL
615.32
Labours :
for C.C.block masonry works
Unit
5
6
7
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
Say Rs.
615 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
Computer Code No. :
Location :
B5
Default Date :
Revised on Date :
Item No. : 22 /
Description :
Unit :
14-08-06
per sqm
Providing 100mm thk siporex blocks of size 0.1 x 0.1 x 0.2 with c.m. 1:6,in super structure including striking
joints, taking out joints and scaffolding, curing etc. complete.
Sr.No.
Particulars
1 Materials :
a)Siporex blocks
b) Cement
c) Sand
Others
Scaffolding / sand screening etc.
Unit
Rate per
Amount
24.00
0.15
0.04
No
Bags
Cum
60.00
245.00
1060.00
1440.00
36.02
42.40
1.00
Sqm
25.30
25.30
1.00
Sqm
7.70
7.70
TOTAL (A)
1551.42
31.03
7.76
0.00
TOTAL (B)
1590.20
238.53
TOTAL
1828.73
Labours :
for 100mm Siporex block masonry
works
5
6
7
Quantity
2.00%
0.50%
0.00%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
1,829 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
Err:509
Computer Code No. :
Location :
B5
Err:509
Default Date :
Revised on Date :
Item No. : 22 /
Description :
Unit :
Err:509
14-08-06
per sqm
Providing 150mm thk siporex blocks of size 0.15 x 0.15 x 0.3 with c.m. 1:6,in super structure including
striking joints, taking out joints and scaffolding, curing etc. complete.
Sr.No.
Particulars
1 Materials :
a)Siporex blocks
b) Cement
c) Sand
Labours :
for 100mm Siporex block masonry
works
Others
Scaffolding / sand screening etc.
5
6
Quantity
2.00%
0.50%
Unit
Rate per
Amount
24.00
0.15
0.04
0.00
0.00
0.00
No
Bags
Cum
0.00
245.00
1060.00
0.00
0.00
0.00
0.00
36.02
42.40
0.00
0.00
0.00
1.00
Sqm
28.06
28.06
1.00
Sqm
8.23
8.23
TOTAL (A)
114.71
2.29
0.57
on total (A)
on total (A)
Electricity Charges
0.00%
on total (A)
15.00%
0.00
TOTAL (B)
117.57
17.64
TOTAL
135.21
on total (B)
Say Rs.
135 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
B5
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing 200mm thk Siporex blocks of size 0.2x0.2x0.4 with c.m. 1:6,in super structure including striking
joints, taking out joints and scaffolding, curing etc. complete.
Sr.No.
Particulars
1 Materials :
a)Siporex blocks
b) Cement
c) Sand
Labours :
for 100mm Siporex block masonry
works
Quantity
Unit
Rate per
Amount
13.00
0.11
0.05
No
Bags
Cum
0.00
245.00
1060.00
0.00
26.95
53.00
1.00
Sqm
28.06
28.06
5
6
7
Others
Scaffolding / sand screening etc.
1.00
2.00%
0.50%
0.00%
15.00%
Say Rs.
Sqm
8.76
8.76
TOTAL (A)
116.77
2.34
0.58
0.00
TOTAL (B)
119.69
17.95
TOTAL
137.64
on total (A)
on total (A)
on total (A)
on total (B)
138 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
2.6315789
#REF!
0.304
1.7024
0.304
0.0608
1.7024
0.391552
0.04864 0.051072
Location : Pune
b) Default date :
Revision on date :
c)
For MKS system click
MKS
5.00%
e) Water Charges :
1.00%
f) Electricity Charges :
1.00%
Instructions
Enter Data
10.00%
(Over head)
5.00%
( Profit )
Uneditable text
Clickable links
FPS
=
=
15.00%
(TOTAL)
Rate analysis
Site:
0
Computer Code No. :
Location :
C1
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
P.C.C. (1 :2:4 )
Providing & laying PCC 1:2:4 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1.5")
d) Metal ( 3/4)"
2
5
6
7
Quantity
Labours :
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering
Unit
Rate per
Amount
6.20
0.47
0.48
0.48
Bags
cum
cum
cum
245.00
1060.00
575.00
500.00
1519.00
498.20
276.00
240.00
1.00
1.00
1.00
cum
cum
cum
120.00
7.50
57.50
120.00
7.50
57.50
1.00
cum
80.00
80.00
1.00
cum
25.00
25.00
TOTAL (A)
2823.20
56.46
0.28
0.00
TOTAL (B)
2879.95
431.99
TOTAL
3311.94
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
3,312 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C1
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
P.C.C. (1 : 5 : 10 )
Providing & laying PCC 1:5:10 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1.5")
d) Metal ( 3/4)"
5
6
7
Quantity
Labours :
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering
2.00%
0.50%
0.50%
Unit
Rate per
Amount
2.74
0.49
0.48
0.48
Bags
cum
cum
cum
245.00
1060.00
575.00
500.00
671.30
519.40
276.00
240.00
1.00
1.00
1.00
cum
cum
cum
120.00
7.50
57.50
120.00
7.50
57.50
1.00
cum
80.00
80.00
1.00
cum
24.75
24.75
TOTAL (A)
1996.45
39.93
0.20
0.00
TOTAL (B)
2036.58
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
2036.58
305.49
TOTAL
2342.07
on total (B)
Say Rs.
2,342 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C2
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
P.C.C. (1 : 4: 8 )
Providing & laying PCC 1:4:8 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1")
d) Metal ( 3/4)"
2
Labours :
for
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering
4
Others
Quantity
Unit
Rate per
Amount
3.40
0.48
0.48
0.48
Bags
cum
cum
cum
245.00
1060.00
575.00
500.00
833.00
508.80
276.00
240.00
1.00
1.00
1.00
cum
cum
cum
120.00
7.50
57.50
120.00
7.50
57.50
1.00
cum
80.00
80.00
5
6
7
1.00
2.00%
0.50%
0.50%
cum
24.75
24.75
TOTAL (A)
2147.55
42.95
10.74
10.74
TOTAL (B)
2211.98
331.80
TOTAL
2543.77
on total (A)
on total (A)
on total (A)
15.00%
Say Rs.
on total (B)
2,544 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C2
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing and laying plum concrete of 1:4:8 mix using stone of size not more than 230 mm in size and
proportion of plum to concrete @ 35:65 including curing, formwork if required, etc complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1.5")
d) Metal ( 1)"
e) Rubble
2
Labours :
for
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering
Quantity
Unit
Rate per
Amount
2.21
0.31
0.31
0.31
0.46
Bags
cum
cum
cum
cum
240.00
1060.00
575.00
500.00
500.00
530.40
330.72
179.40
156.00
227.50
1.00
1.00
1.00
cum
cum
cum
275.00
7.50
57.50
275.00
7.50
57.50
1.00
cum
80.00
80.00
1.00
cum
24.75
24.75
TOTAL (A)
1868.77
37.38
9.34
9.34
TOTAL (B)
1924.83
288.72
TOTAL
2213.56
4
Others
Mixer & Vibrator
5
6
7
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
Say Rs.
on total (B)
2,214 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C4
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
Quantity
7.77
0.45
0.60
0.25
Unit
Bags
cum
cum
cum
Rate per
210.00
850.00
500.00
340.00
Amount
1631.70
382.50
300.00
85.00
5
6
7
Labours :
a) Mixing & Pouring (concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material
for erection & dismantling
Others
Mixer & Vibrator
1.00
1.00
1.00
cum
cum
cum
107.20
16.50
86.25
107.20
16.50
86.25
1.00
cum
136.20
136.20
1.00
cum
24.75
24.75
TOTAL (A)
2770.10
55.40
13.85
13.85
TOTAL (B)
2853.20
427.98
TOTAL
3281.18
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
3,281 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
Computer Code No. :
Item No. : FDAPL/RCC/III/2
Description :
Location :
C6
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Columns upto plinth
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
144.00
0.00
287.50
144.00
0.00
287.50
1.00
cum
820.00
820.00
1.00
cum
24.75
24.75
TOTAL (A)
4041.90
80.84
20.21
20.21
TOTAL (B)
4163.16
624.47
TOTAL
4787.63
5
6
7
Others
Mixer & Vibrator
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
4,788 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/RCC/III/3
Location :
C6
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Description :
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Columns at all levels
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
erection & dismantling
Others
Mixer & Vibrator
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
176.00
0.00
359.38
176.00
0.00
359.38
1.00
cum
1040.00
1040.00
1.00
cum
24.75
24.75
TOTAL (A)
4365.78
87.32
21.83
21.83
TOTAL (B)
4496.75
674.51
TOTAL
5171.26
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
5,171 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
Location :
Pune
Default Date :
Revised on Date :
Unit :
C8
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Floor beams
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b) Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
176.00
15.00
480.13
176.00
15.00
480.13
1.00
cum
992.25
992.25
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
4471.53
89.43
22.36
22.36
TOTAL (B)
4605.67
690.85
TOTAL
5296.52
2.00%
0.50%
0.50%
15.00%
Say Rs.
Prepared by :
Unit
on total (A)
on total (A)
on total (A)
on total (B)
5,297 /- Per
per cum
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C10
Pune
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Floor slabs
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Unit
Rate per
Amount
6.80
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1666.00
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
160.00
15.00
310.50
160.00
15.00
310.50
1.00
cum
682.50
682.50
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
3738.50
74.77
18.69
18.69
TOTAL (B)
3850.66
577.60
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
4,428 /- Per
4428.25
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C11
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & casting M 200 for RCC staircase upto 17 cm riser 30 cm tread & 20 cm th waist slab but
excluding parapet as per detailed drawing & design at all levels with all leads & lift or as directed
including formwork, centering, scaffolding, machine mixing, & mixing , laying, levelling, vibrating and
finishing rough and broken surfaces with C.M. 1:2 including curing etc. complete (excluding steel
reinforcement)
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
2.00%
Unit
Rate per
Amount
7.77
0.60
0.65
0.20
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
636.00
325.00
68.00
1.00
1.00
1.00
0.00
cum
cum
cum
190.00
17.50
621.00
0.00
190.00
17.50
621.00
0.00
1.00
cum
800.00
800.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
4603.65
92.07
on total (A)
6
7
Water charges
Electricity Charges
0.50%
0.50%
on total (A)
on total (A)
15.00%
23.02
0.00
TOTAL (B)
4718.74
707.81
TOTAL
5426.55
on total (B)
Say Rs.
5,427 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
Pune
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For pardis,parapets and fins
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Quantity
Unit
Rate per
Amount
7.77
0.60
0.65
0.20
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
636.00
325.00
68.00
1.00
1.00
1.00
0.00
0.00
0.00
1.00
cum
cum
cum
cum
225.00
7.50
575.00
0.00
0.00
0.00
1520.00
225.00
7.50
575.00
0.00
0.00
0.00
1520.00
1.00
cum
24.75
24.75
Lifts
5
6
7
1.00
2.00%
0.50%
0.50%
cum
17.75
17.75
TOTAL (A)
5302.65
106.05
26.51
26.51325
TOTAL (B)
5461.73
819.26
TOTAL
6280.99
on total (A)
on total (A)
on total (A)
15.00%
Say Rs.
on total (B)
6,281 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C8
0
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Plinth beams
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
Labours :
a) Mixing & Pouring (Concreting)
Quantity
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
cum
176.00
176.00
5
6
7
1.00
1.00
cum
cum
10.50
359.38
10.50
359.38
1.00
cum
750.00
750.00
1.00
cum
24.75
24.75
TOTAL (A)
4086.28
81.73
20.43
20.43
TOTAL (B)
4208.86
631.33
TOTAL
4840.19
Others
Mixer & Vibrator
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
Say Rs.
on total (B)
4,840 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C8
0
Default Date :
Revised on Date :
Unit :
Dec 31, 99
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For lintels & chajja
Sr.No.
Particulars
1 Materials :
a) Cement
Quantity
7.77
Unit
Bags
Rate per
245.00
Amount
1903.65
5
6
7
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
0.45
0.60
0.25
cum
cum
cum
1060.00
500.00
340.00
477.00
300.00
85.00
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
1.00
1.00
1.00
cum
cum
cum
240.00
10.50
575.00
240.00
10.50
575.00
1.00
cum
996.00
996.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
4629.65
92.59
23.15
23.15
TOTAL (B)
4768.54
715.28
TOTAL
5483.82
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
5,484 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/RCC/III/6
Description :
Location :
C8
0
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Grid beams
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Grid beams
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
240.00
10.50
575.00
240.00
10.50
575.00
1.00
cum
1344.00
1344.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
4977.65
99.55
24.89
24.89
TOTAL (B)
5126.98
769.05
TOTAL
5896.03
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
5,896 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
Location :
Default Date :
Revised on Date :
Unit :
C8
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For lift & Basement walls
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
176.00
0.00
460.00
176.00
0.00
460.00
1.00
cum
776.00
776.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
4220.15
84.40
21.10
21.10
TOTAL (B)
4346.75
652.01
TOTAL
4998.77
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
4,999 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C11
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For folded staircase slabs
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
240.00
37.50
931.50
240.00
37.50
931.50
1.00
cum
1224.00
1224.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
5241.15
104.82
26.21
26.21
TOTAL (B)
5398.38
809.76
TOTAL
6208.14
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
6,208 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C11
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
Rmt.
Providing & fixing in corrent position.line, level 40 mm dia Finolex or equivalent PVC pipe in RCC
members such as columns, beams, slabs, paradi, chajjas etc. including fixing / typing with binding wire &
M.S. rod to secure in position during concrete including all lifts etc. complete.
Sr.No.
Particulars
1 Materials :
a) PVC pipe
b) Binding wire
2
5
6
7
Quantity
Labours :
a) Cutting & fixing sleeves
Unit
Rate per
Amount
1.00
0.20
Rmt.
Kg.
51.75
40.00
51.75
8.00
1.00
0.00
Rmt.
55.90
0.00
55.90
0.00
TOTAL (A)
115.65
2.31
0.00
0.00
TOTAL (B)
117.96
17.69
TOTAL
135.66
2.00%
0.00%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
136 /- Per
Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C11
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For sloping slabs
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift
2.00%
0.50%
0.50%
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
200.00
19.50
412.97
200.00
19.50
412.97
1.00
cum
682.50
682.50
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
4123.12
82.46
20.62
20.62
TOTAL (B)
4246.81
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
637.02
TOTAL
Say Rs.
4,884 /- Per
4883.83
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C11
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For cantilever slabs
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Quantity
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
160.00
10.50
363.29
160.00
10.50
363.29
1.00
cum
892.50
892.50
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
5
6
7
2.00%
0.50%
0.50%
TOTAL (A)
4234.44
84.69
21.17
21.17
TOTAL (B)
4361.47
654.22
TOTAL
5015.69
on total (A)
on total (A)
on total (A)
15.00%
Say Rs.
on total (B)
5,016 /- Per
per cum
Prepared by :
Name : _________________________________
Site:
0
Computer Code No. :
Item No. : FDAPL/RCC/III/19
Description :
Sign: ________________
Rate analysis
Location : 0
Default Date :
C11
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing and laying in situ C.C. M-20 of trap metal for R.C.C.work of Copings & sills as per detailed
drawings and design or as directed including centering formwork, compacting using vibrator, curing and
roughening the surface if special finish is to be provided etc. complete. (excluding reinforcement &
fitter work).
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Quantity
Unit
Rate per
Amount
7.77
0.45
0.60
0.25
Bags
cum
cum
cum
245.00
1060.00
500.00
340.00
1903.65
477.00
300.00
85.00
1.00
1.00
1.00
cum
cum
cum
212.80
66.00
621.00
212.80
66.00
621.00
5
6
7
Others
Mixer & Vibrator
Lift
1.00
cum
1220.00
1220.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
4927.95
98.56
24.64
24.64
TOTAL (B)
5075.79
761.37
TOTAL
5837.16
2.00%
0.50%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
5,837 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C11
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
Rmt.
Welding the reinforcement bars to existing steel or as per the requirement including finishing the welding
work neatly, all labour and material etc complete.
Sr.No.
Particulars
1 Materials :
a) Welding rods
For one Rmt. Of welding
(Assuming that average 6 nos of 16mm
dia. Bars are welded for one end of
beam)
Quantity
Unit
Rate per
Amount
5.00
No.
2.34
11.70
0.03
0.03
No.
No.
150.00
100.00
4.50
3.00
15.49
Sft.
0.75
11.62
0.25
Hr.
31.25
7.81
TOTAL (A)
38.63
Labours :
a)Welder
b)Helper
One welder can do about 30rmt. Of
welding
Scaffolding
If required for welding at heights
Assuming the area of scaffolding to be
1.2m x1.2m
Others
Hire charges of welding machine
Assuming the hire charges rate of
250 /-for 8 hrs.
5
6
7
2.00%
0.00%
10.00%
15.00%
TOTAL (A)
38.63
0.77
0.00
3.86
TOTAL (B)
43.27
6.49
TOTAL
49.76
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
50 /- Per
Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C11
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & fixing shalitex board expansion joint of 25mm thickness for beams, columns & slab
Sr.No.
Particulars
1 Materials :
a) Shalitex board
Add for wastage @ 5%
Labours :
a)carpenter
b)Helper
One pair of carp/helper can do about 2
columns as given below.
Quantity
Unit
Rate per
Amount
1.00
0.05
Sqm.
Sqm.
800.00
800.00
800.00
40.00
0.37
0.37
No.
No.
150.00
100.00
55.50
37.00
5
6
7
Others
2.00%
0.00%
0.50%
TOTAL (A)
932.50
18.65
0.00
4.66
TOTAL (B)
955.81
143.37
TOTAL
1099.18
on total (A)
on total (A)
on total (A)
15.00%
Say Rs.
on total (B)
1,099 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C10
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
0
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Quantity
0.10
0.03
Unit
Bags
cum
Rate per
215.00
850.00
Amount
21.50
25.50
5
6
7
c) Metal ( 3/4)"
d) Metal ( 1/2)"
0.04
0.02
cum
cum
425.00
450.00
17.85
7.88
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
0.07
0.07
0.07
cum
cum
cum
212.00
66.00
621.00
14.84
4.62
43.47
0.07
cum
1220.00
85.40
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
263.56
-7.91
-1.32
-1.32
TOTAL (B)
253.01
0.00
TOTAL
253.01
-3.00%
-0.50%
-0.50%
0.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
253 /- Per
per cum
Prepared by :
OR Rs 15/ sqm
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/RCC/III/8
Description :
Location :
C8
0
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For lift & Basement walls
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift
Unit
Rate per
Amount
9.65
0.85
0.70
0.50
Bags
cum
cum
cum
210.00
1060.00
550.00
550.00
2026.50
901.00
385.00
275.00
1.00
1.00
1.00
cum
cum
cum
185.00
0.00
486.00
185.00
0.00
486.00
1.00
cum
776.00
776.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
5077.00
-152.31
-25.39
-25.39
TOTAL (B)
4873.92
731.09
TOTAL
5605.01
-3.00%
-0.50%
-0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
5,605 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C8
0
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Providing & laying M 30 (as per design mix) for Road work using machine crushed metal of approved
quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering
formwork, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2
c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift
Unit
Rate per
Amount
7.50
0.85
0.70
0.50
Bags
cum
cum
cum
210.00
1060.00
550.00
550.00
1575.00
901.00
385.00
275.00
1.00
1.00
1.00
cum
cum
cum
185.00
0.00
150.00
185.00
0.00
150.00
1.00
cum
365.00
365.00
1.00
1.00
cum
cum
24.75
17.75
24.75
17.75
TOTAL (A)
3878.50
-116.36
-19.39
-19.39
TOTAL (B)
3723.36
558.50
TOTAL
4281.86
-3.00%
-0.50%
-0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
4,282 /- Per
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location :
C4
0
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Providing & laying M 300 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2
5
6
7
Quantity
Labours :
a) Mixing & Pouring (concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material
for erection & dismantling
Others
Mixer & Vibrator
Unit
Rate per
Amount
8.50
0.45
0.60
0.25
Bags
cum
cum
cum
210.00
850.00
500.00
550.00
1785.00
382.50
300.00
137.50
1.00
1.00
1.00
cum
cum
cum
107.20
16.50
86.25
107.20
16.50
86.25
1.00
cum
136.20
136.20
1.00
cum
24.75
24.75
TOTAL (A)
2975.90
59.52
14.88
14.88
TOTAL (B)
3065.18
459.78
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
3,525 /- Per
3524.95
per cum
Prepared by :
Name : _________________________________
Sign: ________________
2.21
0.312
0.624
0.312
0.455
0.2763636
7.7381818
7.9703273
16.5
86.25
250
31.25
0.792
24.8
36
3.2175032 2.2844273
79.633205 56.539575
637.06564 452.3166
19749.035
0.309375
24.75
17.775
Assign 0.3 hrs
176
15
480.13
992.25
1165.5
254.25
270
100
160
15
310.5
682.5
24.75
17.75
3000.25
150.01
30.0025
30.0025
3210.27
481.54013
3691.81
0.8336939
18.75
12.5
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
Default Date :
Dec 30, 99
Revised on Date
Item No. :
Unit :
Description :
Sr.No.
Particulars
1 Materials :
2 Labours :
4 Others
Quantity
Unit
Rate per
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
4 Tools & Plants Charges
5 Water charges
6 Electricity Charges
5.00%
1.00%
1.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
TOTAL (B)
TOTAL
Say Rs.
0 /-
Amount
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
Per
Prepared by :
Name : _________________________________
Sign: ________________
Assumptions
Tools and plants fixed charges
3%
Eleciticity Charges
0.50%
Water Charges
Profit ( Overheads + Profit )
0.50%
15%
Description
01.03.06
09.12.06
Rate in
Unit
Rs.
per cum
per cum
per cum
per cum
per Sqm
per Cum
per Cum
per Cum
per Sqm
per Cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
Rmt.
Rmt.
per sqm
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.
90.02
106.61
289.25
777.03
192.72
63.96
248.75
1272.15
42.85
68.03
353.66
3311.94
2342.07
2543.77
2213.56
3281.18
4787.63
5171.26
5296.52
4428.25
5426.55
6280.99
4840.19
5483.82
5896.03
4998.77
6208.14
4883.83
5015.69
5837.16
135.66
49.76
1099.18
262.79
163.15
210.23
176.15
530.85
306.19
513.94
390.33
42 Alluminium sheets
Default date :
43 Alluminium ridges
44 Alluminium sheets cladding
45 Alluminium gutter
46 FRP sheets
47 FRP ridges
48 FRP sheets cladding
49 FRP gutter
50 Polycarbonate sheets
51 UCR In plinth
52 Uncoursed rubble masonry in superstructure
53 Brick masonary 35cm thk. Below plinth
54 Brick work 35cm thk. In superstructure
55 Plinth Masonry 23cm thk
56 BBM 23cm thk in superstructure
57 P/F 15cm thk. Brick Wall (C.M. 1:4)
58 P/F 10cm thk. Brick Wall (C.M. 1:4)
59 Coursed rubble masonary
60 150mm thk. C.C. Solid block masonry
61 200mm thk. C.C. Solid block masonry
62 100mm thk. Siporex block masonry
63 150mm thk. Siporex block masonry
64 200mm thk. Siporex block masonry
65 Ext. Plaster single coat mortor ratio (1:5)
66 External Plastering Double coat
67 Internal Neeru Plaster CM (1:4)-12mm thk.
68 Internal Neeru Plaster CM (1:4) - 20mm thk.
69 Waterproof plaster
70 Pointing to brick masonary
71 Pointing to Stone masonary
72 P/A POP plaster to walls
73 Back coat for dado work 1:4)
74 Grey Mosaic Tile Flooring of 25cm x 25cm
75 Grey Mosaic Tile Flooring of 30x30
76 White Mosaic Tile Flooring of 25x25
77 White Mosaic Tile Flooring of 30 x 30
78 Grey Mosaic Tile Skirting of 125 mm ht.
79 Grey Mosaic Tile Skirting of 150 mm ht.
80 White Mosaic Tile Skirting of 125 mm ht.
81 White Mosaic Tile Skirting of 150 mm ht.
82 P/L IPS 50mm thk.
83 Ceramic Tile Flooring
84 Marble Flooring
85 Marble Skirting
86 Kota Flooring
87 Kota Skirting
88 Tandoor Flooring
89 Tandoor Skirting
90 Granite Flooring
91 Granite Skirting
92 Rough Shahabad flooring
93 Polished Shahabad flooring
94 Ceramic tiles flooring
95 Ceramic tiles Dado
96 Ceramic tiles Skirting
per Sqm.
663.62
01.03.06
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per cum
per cum
per cum
per cum
per cum
per cum
per sqm
per sqm
per cum
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per rmt
per rmt
per rmt
per rmt
per sqm
per sqm
per sqm
per Rmt.
per sqm
per Rmt.
per sqm
per Rmt
per sqm
per Rmt.
per sqm
per sqm
per sqm
per sqm
per Rmt
374.26
676.40
497.21
674.18
263.96
686.59
413.90
1949.83
1984.99
2020.34
2335.22
2438.95
2085.80
2151.57
405.61
343.43
1967.96
451.31
615.32
1828.73
135.21
137.64
136.15
166.52
111.94
135.99
268.20
63.90
89.84
0.00
93.98
334.03
446.20
468.71
625.65
69.47
80.66
87.06
105.72
173.66
690.21
1462.74
153.85
606.28
68.94
590.30
63.21
2438.35
268.72
285.58
358.07
674.99
725.03
71.20
Default date :
100 Designer tiles flooring
101 Paving blocks flooring (regular)
102 Paving blocks heavy duty (M40 & above)
103 Chequered tiles flooring
104 Marble for steps
105 Kota for sill & Jams
106 Marble for Sills & jams
107 Granite for sills & Jams
108 Tandoor for sills & jams
109 Granite Kitchen otta
110 Marble Kitchen otta
111 Kadappa Kitchen otta
112 Box type W/P to RCC raft, walls
113 Brickbat water proofing for toilets
114 Brickbat water proofing for terrace
115 White wash
116 Dry distemper
117 Oil bound distemper
118 Synthetic enamel paint
119 Lustre paint
120 Cement paint
121 Sandtex paint
122 Antifungal paint
123 Plastic emulsion paint
124 Chemical w/p for terrace, toilets
125 Providing & fixing TW frame (4"x 2.5")
126 P/F Granite frame (170x20)
127 P/F Marble frame (170x20)
128 P/F flush shutter 35mm
129 P/F flush shutter 35mm (internal door)
130 P/F flush shutter 35mm (internal door)
131 P/F Laminate of appr. shade & colour
132 P/F MS powder coated fittings
133 P/F Alluminium fittings
134 P/F stainless steel fittings
135 P/F Brass fittings
136 P/F Night latch
137 P/F Automatic door closer
138 P/F eye piece
139 P/F MS powder coated grills & railing
140 P/F MS grills & railing with enamel paint
141 P/F MS Z section windows
142 Reinforcement works
143 Structural steel works
144 12mm dia. Fan hook
145 Chainlink fencing
per sqm
per sqm
per Rmt.
1188.05
1262.44
1225.37
01.03.06
per sqm
707.57
per sqm
399.42
per sqm
578.39
per sqm
307.84
per Rmt
162.61
per sqm
653.57
per sqm 1395.58
per sqm 2681.12
per sqm
609.21
Rmt. 5005.23
Rmt. 3388.21
Rmt. 1800.22
per sqm
604.85
per Cum 2818.39
per sqm
344.17
per sqm
4.71
per sqm
19.39
per sqm
35.59
per sqm
46.26
per sqm
66.92
per sqm
36.19
per sqm
70.77
per sqm
91.34
per sqm
71.68
per sqm
327.32
Rmt.
468.23
Rmt.
934.46
Rmt.
579.47
Sqmt. 1097.63
Sqmt. 1138.66
Sqmt. 1284.05
Sqmt.
432.01
Door.
135.56
Door.
268.17
Door.
268.17
Door.
268.17
Door.
70.73
Door.
70.73
Door.
35.36
Sqm. 1018.76
Sqm.
797.86
Sqm. 1274.64
MT 45499.46
per Sqm. 43578.09
per No.
31.75
per Sqm.
259.20
Per Unit
Rate (inRs.)
Per Bag
Per MT
Per Kg
Per cum
Per cum
Per cum
Per cum
Per No
Per No
Per No
Per No
245.00
28000.00
40.00
1060.00
500.00
340.00
575.00
2.25
4.00
3.00
34.00
Per No
Per No
Per No
Per No
Per cum
Per cum
Per cum
Per Bag
Per Bag
Per Kg.
Per sqm
Per rmt
Per sqm
Per rmt
Per sqm
Per rmt
Per sqm
Per rmt
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per Kg.
Per Kg.
Per sqm
Sqm
Per Kg.
Per Kg.
Per Kg.
16.00
250.00
500.00
120.00
50.00
55.00
30.00
244.00
30.00
350.00
45.00
150.00
23.00
220.00
32.00
860.00
291.00
1695.00
75.00
110.00
380.00
400.00
800.00
800.00
430.40
242.10
386.00
102.00
377.68
1032.00
2118.75
378.30
220.00
82.50
10.00
40.00
800
290.52
Remarks
53 grade O.P.Cement
18 gauge binding wire
Sr.
List of Materials
No.
56 a) Beadings
57 b) Glass
58 c) Gasket,wool piles
59 d) Concealed lock
60 PVC Pipe
61 Chlordane 20% emulsion
62 Blasting powder
63 Safety fuse
64 Detonating fuse
65 Detonator
66 Teak wood frame 4"x2.5"
67 MS Holdfast
68 Coal tar
69 Flush shutter 35mm (90/- per sft.)
70 Brass hinges 75mm
71 Brass hinges 100mm
72 Brass hinges 125mm
73 Brass screws25mm
74 Brass screws25mm
75 Laminate 1mm
76 Fevicol
77 MS tubular
78 Nails
79 MS Z sections (1.5 kg @ 30)
80 10mm sq. bars (.785 x 30)
81 4mm float glass
82 Lime
83 Ultramarine blue
84 Glue
85 Sodium chloride
86 Distemper
87 Whitning
88 Primer
89 Putty
90 Oil bound distemper
91 Synthetic enamel
92 Luster paint
93 Cement paint
94 Sandtex paint
95 Antifungal paint
96 Plastic emulsion
97 AC trafford 6mm thk.
98 Bitminous washers 3mm
99 GI flat washers 2mm
100 GI - 6mm J hooks
101 AC -ridges pair
102 AC Gutter
103 MS precoated sheets
104 MS precoated -ridges (0.6m width )
105 MS precoated Gutter
106 Alluminium sheets
107 Alluminium -ridges (0.6m width )
108 Alluminium Gutter
109 Structural steel
110 FRP
111 FRP -ridges (0.6m width )
112 FRP gutter
113 Chain link
114 Polycarbonate sheets
Per Unit
Rate (inRs.)
Per Kg.
Per sqm
Per m.
Per No
Ltr.
kg.
Rmt
Rmt
No
Cft.
No.
Kg.
Sqm.
No
No
No
No
No.
sqm.
Kg.
Kg.
Kg.
Rmt.
Rmt.
Sqm.
Kg.
Kg.
Kg.
Kg.
Kg.
kg.
Lts
Kg.
Kg.
Ltr.
Ltr.
Kg.
Kg.
kg.
ltr.
Sqm.
Kg.
Kg.
No.
Rmt.
Rmt.
Sqm.
Rmt.
Rmt.
Sqm.
Rmt.
Rmt.
Mt.
Sqm.
Rmt.
Rmt.
sqm.
sqm.
Page 260 of 423
51.75
66.15
78.75
4.725
6.5
8
1200
10
25
968
20
26
35
1.5
2
310
250
32
30
45
23.55
325
1.5
114.98
48.825
10
67
20
60.9
40.95
90.00
141.75
218.75
49.35
86.3625
123.375
205.15
149.1
32
47.25
6.3
94.5
105
319
181.5
216.15
415.8
236.5
302.5
30500
423.5
154
209
156
1400
Remarks
Sr.
No.
115
116
List of Materials
Per Unit
Rate (inRs.)
Labour Rate
Remarks
THIRUPPATHI KANNAN
4.71
150.72
1.71
153.9
136.8
156
Page 263 of 423
Description
1 Unskilled coolie (Male)
2 Unskilled coolie (Female)
3 Beldar mazdoor
4 Breaker Operator
5 Helper for Breaker operator
6 Rent for Pneumatic Breaker Needle (8 hr.)
Machinaries on Hire basis
7 Mixer
8 Lift
9 Vibrator
Mixing & pouring for
10 P.C.C.
11 footing M15 grade
Unit
per day
per day
per day
per day
per day
per day
Per cum
Per cum
Per cum
Rate
100.00
75.00
80.00
120.00
80.00
1040.00
Remarks
Per cum
Per cum
120.00
107.20
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
107.20
176.00
176.00
150.00
176.00
176.00
160.00
190.00
225.00
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
7.50
16.50
0.00
15.00
15.00
17.50
7.50
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
57.50
86.25
359.38
480.13
310.50
621.00
575.00
Per cum
Per cum
Per cum
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
165.00
252.00
164.00
33.48
40.00
41.50
25.30
45.00
47.60
6.64
36.00
4.00
Per sqm
32.00
Revised on Date :
Sr.No.
Description
43 Mosaic Tile Skirting fixing
43 Ceramic Tile fixing
44 Marble Flooring
44 Ceramic /Glazed dado Tile fixing
45 Mosaic Tile polishing (3 coats)
45 Mosaic Tile Skirting polishing
46 Marble floor Polishing (regular)
46 Marble skirting polishing
47 Marble skirting fixing
47 Kota floor fixing & polishing
48 Kota skirting fixing & polishing
48 Tandoor floor fixing & polishing
49 Tandoor skirting fixing & polishing
49 Rough shahabad
50 Polished shahabad
50 Vitrified tiles flooring
51 Vitrified tiles Dado
51 Granite floor fixing
52 Granite skirting fixing
52 Kota Steps fixing
53 Marble Steps fixing
53 Granite Steps fixing
54 Tandoor steps
54 Kota sill & jams fixing
55 Marble sill & jams fixing
55 Granite sill & jams fixing
56 Tandoor sill & jams
Water proofing Works for
57 Box type
58 Toilets / Bathroom (for 200mm sunk)
59 Terrace (roof)
60 Chemical waterproofing
Shuttering material charges
61 for P.C.C. works
62 for footing
63 for columns
64 for beams
65 for slabs
66 for Staircase
67 for pardi
68 Reinforcement Works
69 KOTAH STONE
70 Polishing of kotah stone
Door frame charges
71 Frame making
72 Powder coating (at 15/- per sft)
73 Enamel painting including red oxide
74 AC sheets fixing
75 MS precoated sheets fixing
76 FRP sheets
77 Alluminium sheets fixing
78
79
80
81
Unit
Per rmt
Rate
10.00
Per sqm
Per sqm
Per sqm
Per sqm
Per rmt
Per Sqm
Per Sqm
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
75.00
100.00
90.00
20.00
9.00
129.00
148.35
110.00
100.00
110.00
86.00
94.60
65.00
80.00
80.00
96.00
172.00
215.00
130.00
167.70
223.60
111.80
132.00
132.00
258.00
113.52
Per sqm
Per sqm
Per sqm
Per sqm
325.00
170.00
125.00
130.00
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per MT
Per Sqm
Per Sqm
80.00
136.20
1040.00
992.25
682.50
800.00
1520.00
2000.00
100.00
60.00
Per Sqm
Per sqm.
Per sqm.
Per sqm.
Per sqm.
Per sqm.
161.40
35.00
35.00
72.80
72.80
72.80
14-08-06
Remarks
Revised on Date :
Sr.No.
Description
Unit
Rate
Click on the button for entering into "ITEM LIST FOR SELECTION"
14-08-06
Remarks
Item List
ITEMS
Earth work in ordinary soil
Earth work in Shadu
Earth work in Murum
Earth work in Soft Rock
Earth work in Hard Rock
P.C.C. (1:3:6)
P.C.C. (1:4:8)
C.C. M15 for footing
C.C. M20 for footing
C.C. M15 for columns
C.C. M20 for columns
C.C. M15 for Beams
C.C. M20 for Beams
C.C. M15 for Slabs
C.C. M20 for Slabs
U.C.R. Masonry 15" thk.
B.B.Masonry 9" thk.
B.B.Masonry 6" thk.
B.B.Masonry 4" thk.
C.C. Block masonry 6" thk.
External Plastering Single coat
External Plastering Double coat
Internal Plastering with C.M.1:4
Internal Plastering with C.M.1:5
Mosaic Tile flooring
Mosaic Tile Skirting
Ceramic Tile flooring
Marble Flooring
Ceramic /Glazed tile Dado
Brickbat waterproofing for Toilet
Brickbat waterproofing for Terrace
Glazed china mosaic w/p for terrace
Reinforcement works
Summary of rate analysis
Selection
button
_1
E1
E2
E3
E4
E5
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
B1
B2
B3
B4
B5
P1
P2
P3
P4
F1
F2
F3
F4
D1
W/P1
W/P2
W/P3
R1
SR
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
Default Date :
Revised on Date :
Unit :
14-08-06
per cum
Excavation upto 1.5 M depth in ordinary soil or soft murum, old foundations etc. in pits, over areas and in
trenches by machinery or otherwise including removing the excavated materials upto a distance of 100 M
beyond building premises, stacking as directed dewatering manually or mechanically if required, shoring,
strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet
compaction etc. complete.
Sr.No.
Particulars
1 Materials :
Labours :
a) Unskilled coolie for excn.
b) Labour for backfilling
Assuming that one pair
to do excavation of 125 cft.
Others
Shoring
Dewatering
5
6
7
8
Quantity
Unit
Rate per
Amount
0.56
0.08
No
No
100.00
100.00
56.00
8.00
1.00
1.00
L/S
L/s
10.00
2.00
10.00
2.00
TOTAL (A)
76.00
1.52
0.38
0.38
TOTAL (B)
78.28
11.74
TOTAL
90.02
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
90 /- Per
Say Rs.
per cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
E3
Default Date :
Revised on Date :
Unit :
Description :
Dec 30, 99
14-08-06
per cum
Excavation upto 1.5 M depth in hard murum & boulders etc. in pits, over areas and in trenches by
machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond
building premises, stacking as directed dewatering manually or mechanically if required, shoring,
strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet
compaction etc. complete.
Sr.No.
Particulars
1 Materials :
Quantity
Unit
Rate per
Amount
NIL
2
Labours :
a) Unskilled coolie (Male)
( It is assumed that 1 m/c + 1 f/c
can excavate nearly 100cft of murum in a day with specified lead
and lift)
c) Add for backfilling & compaction
0.70
No
100.00
70.00
0.08
No
100.00
8.00
1.00
1.00
L/S
L/s
10.00
2.00
10.00
2.00
Others
Shoring
Dewatering
5
6
7
2.00%
0.50%
0.50%
15.00%
TOTAL (A)
90.00
1.80
0.45
0.45
TOTAL (B)
92.70
13.91
TOTAL
106.61
on total (A)
on total (A)
on total (A)
on total (B)
107 /- Per
Say Rs.
per cum
Prepared by :
Name : _________________________________
Site:
0
Computer Code No. :
Sign: ________________
Rate analysis
Location : Pune
E4
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Excavation upto 1.5 M depth in soft rock in pits and trenches by machinery or otherwise including
removing the excavated materials upto a distance of 100 M beyond building premises,stacking as
directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for
foundation and necessary back filling in layers including dry and wet compaction etc. complete.
Sr.No.
Particulars
1 Materials :
Nil
2 Labours :
a) 1 Breaker Needle with breaker
operator
( It is assumed that with a breaker needle in a day we can excavate nearly 200cft and the same
with lead & lift as specified.)
i.e. For 1 cum. It requires
0.18 days of breaker
b) Unskilled coolie 2 nos. (Male)
For 150 cft ( 4.25cum) 2 persons
are required, therefore for one
Quantity
Unit
Rate per
Amount
0.18
Per day
1040.00
187.20
0.47
No
100.00
47.00
5
6
7
0.08
No
100.00
8.00
1.00
L/s
2.00
2.00
TOTAL (A)
244.20
4.88
1.22
1.22
TOTAL (B)
251.53
37.73
TOTAL
289.25
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
289 /- Per
per cum
Prepared by :
Name : _________________________________
Site:
0
Computer Code No. :
Sign: ________________
Rate analysis
Location : Pune
E5
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Description :
Excavation in Hard Rock by chiselling
Excavation upto 1.5 M depth in hard rock in pits and trenches by machinery or otherwise including
removing the excavated materials upto a distance of 100 M beyond building premises,stacking as
directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for
foundation and necessary back filling in layers including dry and wet compaction etc. complete.
Sr.No.
Particulars
1 Materials : NIL
2
Labours :
a)1 Breaker Needle with operator
( It is assumed that with a breaker needle in a day we can excav-ate nearly 65cft (1.84cum.)
Quantity
0.54
Unit
Per day
Rate per
1000.00
Amount
540.00
Others
Dewatering
1.06
No
100.00
106.00
0.08
No
100.00
8.00
1.00
L/s
2.00
2.00
5
6
7
2.00%
0.50%
0.50%
TOTAL (A)
on total (A)
on total (A)
on total (A)
TOTAL (B)
15.00%
on total (B)
TOTAL
777 /- Per
per cum
Say Rs.
Prepared by :
Name : ________________________________
656.00
13.12
3.28
3.28
675.68
101.35
777.03
Sign : _______________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
E1
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm
Providing and laying 230 mm thick dry trap rubble soling in plinth including filling the interstices with
murum and stone chips, watering,compacting, ramming etc complete with all labour and material.
Sr.No.
Particulars
1 Materials :
Quantity
Unit
Rate per
Amount
a)Rubble
b)Murrum
Labours :
a) Unskilled coolie (Male)
b) Unskilled coolie (Female)
Assuming that one pair
to do 200 sft. (18.59 sqm.)Of soling
area
Others
0.30
0.02
Cum
Cum
500.00
120.00
149.50
2.40
0.05
0.05
No
No
100.00
100.00
5.40
5.40
0.00
0.00
0.00
0.00
TOTAL (A)
162.70
3.25
0.81
0.81
TOTAL (B)
167.58
25.14
TOTAL
192.72
0.00
0.00
NIL
5
6
7
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
Say Rs.
193 /- Per
per Sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/EX/I/12
Description :
Location : 0
E1
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Cum
Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)
Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)
Sr.No.
Particulars
1 Materials :
NIL
NIL
2
Unit
Rate per
0.00
Labours :
a) Unskilled coolie (Male)
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours
Net labour required = (2 / 2.83)/8
5
6
7
Quantity
Amount
0.00
0.00
0.35
No
100.00
35.00
0.09
No
100.00
9.00
1.00
10.00
10.00
TOTAL (A)
54.00
1.08
0.27
0.27
TOTAL (B)
55.62
8.34
TOTAL
63.96
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
64 /- Per
per Cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
E1
Default Date :
Dec 30, 99
Revised on Date :
Unit :
14-08-06
per Cum
Providing & filling in plinth murrum brought from outside including spreading, levelling, watering, and
ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)
Sr.No.
Particulars
1 Materials :
a) Murrum
Quantity
Unit
Rate per
Amount
1.30
Cum
120.00
156.00
0.35
No
100.00
35.00
0.09
No
100.00
9.00
1.00
10.00
10.00
TOTAL (A)
210.00
4.20
1.05
1.05
TOTAL (B)
216.30
32.45
TOTAL
248.75
Labours :
a) Unskilled coolie (Male)
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours
Net labour required = (2 / 2.83)/8
5
6
7
2.00%
0.50%
0.50%
15.00%
Say Rs.
Prepared by :
on total (A)
on total (A)
on total (A)
on total (B)
249 /- Per
per Cum
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
E1
Default Date :
Revised on Date :
Unit :
Item No. : 1
Item No. : FDAPL/EX/I/14
Dec 30, 99
14-08-06
per Cum
Providing & filling in plinth with approved sand including spreading, levelling, watering, and ramming (in
layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)
Sr.No.
Particulars
1 Materials :
a) Sand
Quantity
Unit
Rate per
Amount
1.20
Cum
850.00
1020.00
0.35
No
100.00
35.00
0.09
No
100.00
9.00
1.00
10.00
10.00
TOTAL (A)
1074.00
21.48
5.37
5.37
TOTAL (B)
1106.22
165.93
Labours :
a) Unskilled coolie (Male)
Assuming that one male coolie
to do 100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours
Net labour required = (2 / 2.83)/8
5
6
7
2.00%
0.50%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
1,272 /- Per
Say Rs.
1272.15
per Cum
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
E1
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm
Antitermite treatment
Providing & applying preconstructional anti termite treatment to bottom and sides of excavated surfaces
by approved agency (MODE of Measurement will be on plinth area basis.)
Sr.No.
Particulars
1 Materials :
Chemical
Quantity
Unit
Rate per
Amount
0.50
Ltr.
66.15
33.08
0.03
No
100.00
3.10
0.00
0.00
TOTAL (A)
36.18
0.72
Labours :
a) Unskilled coolie (for spreading) for 1
hours for one footing of 4 sqm. Area
Net labour required = (1 / 4)/8
2.00%
on total (A)
6
7
Water charges
Electricity Charges
0.50%
0.50%
15.00%
on total (A)
on total (A)
0.18
0.18
TOTAL (B)
37.26
5.59
TOTAL
42.85
on total (B)
43 /- Per
Say Rs.
per Sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
E1
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
Cum
Carting away the unwanted excavated,/ demolished material outside the premises and unloading and
spreading it as and where required as per the rules of local authority including loading, unloading, carting,
spreading etc complete.
Sr.No.
Particulars
1 Materials :
NIL
2
Labours :
a) Unskilled coolie 2 nos. do filling of
tractor (100cft) in 15 minutes
Net labour required = (0.5 / 2.83)
Quantity
Unit
Rate per
Amount
0.00
0.18
No
100.00
18.00
1.00
40.00
40.00
5
6
7
2.00%
0.00%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
TOTAL (A)
58.00
1.16
0.00
0.00
TOTAL (B)
59.16
8.87
TOTAL
68.03
68
Say Rs.
per Cum
Prepared by :
Name : _________________________________
Site:
0
Computer Code No. :
Sign: ________________
Rate analysis
Location : 0
E5
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per cum
Description :
Excavation in Hard Rock by blasting
Excavation in Hard Rock for foundation by blasting including removing the excavated material upto
a distance of 10m with normal lift upto 1.5m and stacking & spreading in such a way as to not
disturd any site activity or as directed. Dewatering Preparing the bed for foundation & necessary
back filling, watering including shoring & Shuttering etc. complete.
Sr.No.
Particulars
1 Materials :
Quantity
Unit
Rate per
Amount
0.7
2
2
8
Kg.
No
rmt
rmt
78.75
8
4.725
6.5
55.13
16.00
9.45
52
Labours :
a) Unskilled coolie (Male)
For 100 cft ( 2.83cum) 3 persons
1.06
No
100.00
106.00
Others
Compressor for drilling holes
0.50
120
120.00
TOTAL (A)
298.58
5.97
1.49
1.49
307.53
5
6
7
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
TOTAL (B)
15.00%
on total (B)
Say Rs.
Prepared by :
Name : ________________________________
60.00
46.13
TOTAL
354 /- Per
per cum
Sign : _______________
353.66
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Providing, fabricating & erecting & fixing, cutting, bending, grinding, welding the structural steel work
consisting of m.s. plates I beams channels, angles, chequered plates, including fabricating as per
shop drawing including erection to required line and level and providing and fixing buts, bolts and
required appropriate washers etc. complete including painting
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) Structural steel
1.05
(adding 5% for wastage)
155.00
b) Welding rods
c) Oxygen Gas
1.50
d) DA
0.50
c) Bolts, nuts & washers
1.00
d) Primer Painting
2.00
d) Enamel Painting
5.00
Labours :
For fabrication & errection
For painting
Others
Welding M/C
Unit
Rate per
Amount
Mt.
30500.00
32025.00
No.
Cyli.
Cyli.
Kg.
lts.
lts.
3.50
250.00
800.00
47.25
40.00
110.00
542.50
375.00
400.00
47.25
80.00
550.00
1.00
1.00
Mt.
Mt.
2250.00
450.00
2250.00
450.00
1.00
Day
250.00
250.00
TOTAL (A)
36969.75
5
6
7
2.00%
0.00%
0.50%
15.00%
TOTAL (A)
36969.75
739.40
0.00
184.85
TOTAL (B)
37893.99
5684.10
TOTAL
43578.09
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
43,578 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per No.
Providing & fixing and securing in position box type fan hooks of 12 mm diameter MS rods 30 cm
long as directed
Sr.No.
1
Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) MS rods 12mm
0.28
(adding 5% for wastage)
b) Sand
1.00
c) Binding wire
0.05
Labours :
For preparing the hook & fixing in
place
Fitter (0.5 hrs.)
Helper (0.5hrs.)
Others
0.06
0.06
Unit
Rate per
Amount
Kg.
27.50
7.71
L/s
Kg.
2.00
32.00
2.00
1.60
No.
No.
150.00
100.00
9.38
6.25
4
5
6
2.00%
0.00%
0.50%
15.00%
TOTAL (A)
26.93
0.54
0.00
0.13
TOTAL (B)
27.61
4.14
TOTAL
31.75
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
32 /- Per
per No.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
B1
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per Sqm.
Chainlink fencing
Providing and erecting in position chain link fencing of GI 18 gauge, 50 mm opening size as required
including fixing the angle supports in bed blocks of C:M 1:3:6 at 2.4 m c/c, ms 6 mm dia at top, U
nails for fixing, etc complete with all labour and material. - 1.2 m high fencing ( Structural steel for
angles,flats will be paid separately)
Sr.No.
1
Particulars
Quantity
Consider lengthof 24 x 1.2 = 28.8 sqm.
Materials :
a) Chain link 18 guage
30.24
(adding 5% for wastage)
2.00
b) U nails
c) 6mm dia. Wire
12.40
d) Concrete 1:3:6
0.40
Sqm.
156.00
4717.44
Kg.
Kg.
Cum.
40.00
32.00
1979.00
80.00
396.80
783.68
Labours :
For excavation
For poles errecting (0.5 mason &
0.5 helpers)
Nos.
No.
No.
5
150.00
100.00
55.00
75.00
50.00
11
0.50
0.50
Unit
Rate per
Amount
4
5
6
0.50
1.00
No.
No.
150.00
100.00
75.00
100.00
TOTAL (A)
6332.92
126.66
0.00
31.66
TOTAL (B)
6491.25
973.69
TOTAL
7464.93
Others
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
259 /- Per
per Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
300 mm
46.153846 per mt.
0.3 mm
153.84615 total rods
538.46154
28.8
12.4
33
CODE
NO
UNIT
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
Cum
Sqm
Sqm
Cum
Cum
Cum
Cum
Cum
Cum
Cum
SNJ/RCC/III
2 Providing and casting RCC M20 for columns ( of any size and shpe)upto Cum
plinth and in basement
3 Providing and casting RCC M20 for columns ( fo any size and shape) in Cum
superstructure at all levels
4 Providing and casting RCC M20 for plinth beams
Cum
SNJ/RCC/III
SNJ/RCC/III
Cum
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
5 Providing and casting RCC M20 for beams ( of any shape and size) at all Cum
levels
6 Providing and casting RCC M20 for beams in grid system
Cum
7 Providing and casting RCC M20 for lintels
Cum
8 Providing and casting RCC M20 for piles
9 Providing and casting RCC M20 for standard slab(thk upto 200 mm)
Cum
SNJ/RCC/III
SNJ/RCC/III
Cum
Cum
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
Cum
Cum
Cum
Cum
SNJ/RCC/III
16 Providing and casting RCC M20 for chajjas at any level , of projection
Cum
upto 0.75m
17 Providing and casting RCC M20 for pardies, parapets, fins, upstands of Cum
thickness upto 100 mm
18 Providing and casting RCC M20 for staircase steps and waist slab with Cum
riser upto 170 mm and tread upto 300 mm and waist slab thickness upto
200 mm.at all levels.
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
MT
RM
RM
RM
RM
Sqm
MT
SNJ/MAS/IV
Cum
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
Sqm
Sqm
SNJ/MAS/IV
Sqm
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
Cum
Cum
Cum
Sqm
Sqm
Sqm
Sqm
Cum
Cum
Sqm
Sqm
SNJ/PLAST/V
2 Providing and applying 20 mm thick sandface cement plaster C:M 1:5 in Sqm
one coat
3 Providing and applying 12mm back coat plaster behind dado C:M 1:4
Sqm
SNJ/PLAST/V
SNJ/PLAST/V
Sqm
Sqm
SNJ/PLAST/V
SNJ/PLAST/V
SNJ/PLAST/V
SNJ/PLAST/V
Sqm
SNJ/PLAST/V
Sqm
Sqm
Sqm
Sqm
SNJ/PLAST/V
SNJ/PLAST/V
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
RM
Providing and fixing in position door frames in correct line, level and
plumb of Teak Wood of size 4" x2.5" including applying coal tar to the
surface coming in contact with masorny including 6 no of MS hold fasts
fixed in concrete bedblocks in masonry ( 6"x6" size), MS rod at bottom to
keep the frame in position etc complete with all labour and material. door size 750mm x 2100 mm
RM
RM
RM
RM
RM
RM
RM
RM
RM
10
RM
11
RM
12
As per item no11 above but for door size 900 x 2100 mm
RM
13
RM
14
RM
15
RM
16
17
Sq.M
18
Sq.M
19
As per item no 16 above but for double shutter door of size 1200 x 2100
20
As per item no 16 above but for double shutter door of size 1500 x 2100
21
22
Providing and fixing following MS powder coated fittings and fixtures for
doors
a. Aldrop 250 mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
23
24
Sq.M
Sq.M
Sq.M
No
No
No
No
No
No
Providing and fixing following Aluminium fittings and fixtures for doors
a. Aldrop 250 mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
No
No
No
No
No
No
Providing and fixing following stainless steel fittings and fixtures of D-line
or equivalent make for doors
a. Aldrop 250 mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
No
No
No
No
No
25
f. D type handles
No
No
No
No
No
No
No
26
Providing and fixing night latch of approved brand to door with all
hardware and accessories required
No
27
No
28
Providing and fixing peep hole / eye piece of approved make to doors
including all labour and material complete
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
Providing, fabricating and fixing in position for grills & railings in Powder
coated MS tubular sections of all shapes and size, with weight upto 15
kg / sqm, as per detail design and drawing, all labour and material
complete.
44
45
46
Sqm
Cum
Sqm
SNJ/WP/VIII
Sqm
SECTION IX - PAINTING
SNJ/PAINT/IX
SNJ/PAINT/IX
1 White wash
2 Dry distemper
Sqm
Sqm
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
1 AC sheet roofing
2 AC ridges
3 AC sheet cladding
4 AC flashig
5 AC gutters
6 Precoated sheet roofing
7 Precoated ridges
8 Precoated sheet cladding
9 Precoated sheet flashing
10 Precoated sheet gutters
11 Aluminium sheet roofing
12 Aluminium ridges
13 Aluminium sheet cladding
14 Aluminium flashings
15 Aluminium gutters
16 FRP sheet roof
17 FRP ridges
18 FRP sheet cladding
19 FRP sheet flashing
20 FRP gutters
21 Mangalor tiles with frame work
22 Pan tile roofing on exsting slab
23 FRP domes
24 Polycarbonate sheet domes/ roof covering
Sqm
RM
Sqm
Sqm
Sqm
Sqm
RM
Sqm
Sqm
Sqm
Sqm
RM
Sqm
Sqm
Sqm
Sqm
RM
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
MT
No
No
SNJ/MISC/XI
SNJ/MISC/XI
SNJ/MISC/XI
SNJ/MISC/XI
SNJ/MISC/XI
Kg
Sqm
Sqm
Sqm
Sqm
Rate
90.02
99.02
106.61
117.27
289.25
318.18
350.00
777.03
854.74
940.21
353.66
63.96
248.75
1272.15
192.72
42.85
68.03
2342.07
2543.77
3311.94
2213.56
3281.18
4787.63
5171.26
4840.19
5296.52
5896.03
5483.82
4428.25
5483.82
5015.69
4883.83
6208.14
5483.82
6280.99
5426.55
5837.16
5837.16
4998.77
331.88
45499.46
49.76
1099.18
1099.18
1099.18
2335.22
1984.99
2020.34
2438.95
2085.80
2151.57
343.43
405.61
1967.96
451.31
615.32
1828.73
135.21
137.64
111.94
136.15
93.98
166.52
268.20
63.90
91.88
89.84
173.66
334.03
446.20
468.71
625.65
1462.74
606.28
2438.35
590.30
358.07
285.58
674.99
1188.05
1188.05
707.57
399.42
307.84
555.77
537.76
696.49
704.78
153.85
68.94
268.72
63.21
71.20
1225.37
1225.37
725.03
162.61
895.36
306.70
72.94
1395.58
653.57
2681.12
609.21
5005.23
3388.21
1800.22
1262.44
578.39
468.23
934.46
579.47
1097.63
1138.66
1284.05
432.01
1018.76
797.86
1274.64
344.17
2818.39
604.85
344.17
4.71
19.39
35.59
46.26
71.68
66.92
36.19
70.77
91.34
1.73
136.42
330.40
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
Default Date :
D1
Revised on Date:
Unit :
Dec 30, 99
14-08-06
Rmt.
Description :
Providing & fixing TW frame (4"x 2.5")
Providing and fixing in position door frames in correct line, level and plumb of Teak Wood of size 4"
x2.5" including applying coal tar to the surface coming in contact with masorny including 6 no of MS hold
fasts fixed in concrete bedblocks in masonry ( 6"x 6" size), MS rod at bottom to keep the frame in
position etc complete with all labour and material. - door size 900mm x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand ( as approved)
c) MS Holdfast
d) Teak wood (4*2.5/144*17.83)*1.1 =
1.362
e) MS Tie rod 8mm
f) Coal tar
2
Quantity
Labours :
Carpenter for frame making
Helper for frame making
(0.5 carp + 0.2 help are required per cft
of frame making)
Mason for fixing of frame
Unskilled labour
Rate per
0.18
0.01
6.00
Bags
Cum
Nos.
245.00
1060.00
10.00
44.10
13.78
60.00
1.36
0.34
0.50
Cft
Kg.
Kg.
1200.00
27.50
25.00
1632.00
9.28
12.50
0.68
0.27
Nos.
Nos.
200.00
100.00
136.00
27.20
150.00
80.00
0.00
75.00
16.00
0.00
0.00
TOTAL (A)
2025.86
40.52
0.00
10.13
TOTAL (B)
2076.51
311.48
0.50
0.20
Nos.
Nos.
Amount
Others
Nil
4
5
6
Unit
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
468 /- Per
Rmt.
2387.98
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Unit :
Dec 30, 99
14-08-06
Rmt.
Description :
P/F Granite frame (170x20)
As per item no 01 but with granite door frame of size 170 mm x 20 mm and extra patti for rebate
formation for 35 mm thick shutter. Door size 900x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand ( as approved)
c) MS Holdfast
d) Granite with 10% wastage
((0.9+.09*2+2.1*2+.05*2)*.17) +
((.86+2.08*2+.05*2)*(.17-.035)) = 1.606
x 1.1 = 1.77
e) MS Tie rod 8mm
f) White / colour cement
2
Quantity
Labours :
Labour rate for cutting, fixing &
moulding of frame
Rate per
Amount
0.18
0.01
6.00
1.77
Bags
Cum
Nos.
Sqm.
245.00
1060.00
10.00
1695.00
44.10
13.78
60.00
2995.07
0.34
0.25
Kg.
Kg.
27.50
30.00
9.28
7.50
1.77
Sqm.
516.00
913.32
0.00
0.00
TOTAL (A)
4043.04
80.86
0.00
20.22
TOTAL (B)
4144.12
621.62
TOTAL
4765.74
Others
Nil
4
5
6
Unit
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
934 /- Per
Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Dec 30, 99
Revised on Date:
Item No. : FDAPL/DW/VII/3
Description :
14-08-06
Rmt.
Unit :
P/F Marble frame (170x20)
As per item no 01 but with marble door frame of size 170 mm x 20 mm and extra patti for rebate
formation for 35 mm thick shutter. Door size 900x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand ( as approved)
c) MS Holdfast
d) Marble with 10% wastage
((0.9+.09*2+2.1*2+.05*2)*.17) +
((.86+2.08*2+.05*2)*(.17-.035)) = 1.606
x 1.1 = 1.77
e) MS Tie rod 8mm
f) White / colour cement
2
Quantity
Labours :
Labour rate for cutting, fixing &
moulding of frame
Rate per
Amount
0.18
0.01
6.00
1.77
Bags
Cum
Nos.
Sqm.
245.00
1060.00
10.00
946.00
44.10
13.78
60.00
1671.58
0.34
0.25
Kg.
Kg.
27.50
30.00
9.28
7.50
1.77
Sqm.
396.00
700.92
0.00
0.00
TOTAL (A)
2507.16
50.14
0.00
12.54
TOTAL (B)
2569.84
385.48
TOTAL
2955.32
Others
Nil
4
5
6
Unit
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
579 /- Per
Rmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/DW/VII/4
Location : 0
Default Date :
D1
Revised on Date:
Unit :
Dec 30, 99
14-08-06
Sqmt.
Description :
Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws
etc complete. - single shutter - size of door - 750 x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Shutter 35mm thk.
(2.055 x 0.66 = 1.356
b) Brass Hinges 75mm
c) Brass screws 25mm
2
Quantity
Unit
Rate per
1.36
Sqm.
968.00
1312.61
4.00
16.00
No
No
20.00
1.50
80.00
24.00
0.20
0.10
Nos.
Nos.
200.00
100.00
40.00
10.00
0.00
0.00
TOTAL (A)
1466.61
29.33
0.00
7.33
TOTAL (B)
1503.27
225.49
TOTAL
1728.76
Labours :
Carpenter for fixing shutter
Helper for fixing shutter
(0.2 carp + 0.2 help are required per cft
of frame making)
Others
Nil
5
6
7
Amount
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,098 /- Per
Sqmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : 31
Description :
Location : 0
Default Date :
D1
Revised on Date:
Unit :
P/F flush shutter 35mm (internal door)
Dec 30, 99
14-08-06
Sqmt.
Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws
etc complete. - single shutter - size of door - 900 x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Shutter 35mm thk.
(2.055 x 0.81 = 1.356)
b) Brass Hinges 100mm
c) Brass screws 25mm
Quantity
Unit
Rate per
1.67
Sqm.
968.00
1611.72
4.00
16.00
No
No
35.00
1.50
140.00
24.00
0.20
0.10
Nos.
Nos.
200.00
100.00
40.00
10.00
0.00
0.00
TOTAL (A)
1825.72
36.51
0.00
9.13
TOTAL (B)
1871.36
280.70
TOTAL
2152.07
Labours :
Carpenter for fixing shutter
Helper for fixing shutter
Amount
5
6
7
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,139 /- Per
Sqmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/DW/VII/5
Description :
Location : 0
Default Date :
D1
Revised on Date:
Unit :
P/F flush shutter 35mm (internal door)
Dec 30, 99
14-08-06
Sqmt.
Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 8 no of hinges, required screws
etc complete. - double shutter - size of door - 1500 x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Shutter 35mm thk.
(2.055 x 1.41 = 1.356
b) Brass Hinges 125mm
c) Brass screws 50mm
2
Quantity
Unit
Rate per
2.89
Sqm.
1016.40
2937.40
8.00
32.00
No
No
35.00
2.00
280.00
64.00
0.50
0.50
Nos.
Nos.
200.00
100.00
100.00
50.00
0.00
0.00
TOTAL (A)
3431.40
68.63
0.00
17.16
TOTAL (B)
3517.18
527.58
TOTAL
4044.76
Labours :
Carpenter for fixing shutter
Helper for fixing shutter
Amount
Others
Nil
4
5
6
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,284 /- Per
Sqmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/DW/VII/6
Description :
Location : 0
Default Date :
D1
Revised on Date:
Unit :
Dec 30, 99
14-08-06
Sqmt.
Providing and fixing laminate of approved colour and shade to doors including all labour and material
Providing and fixing laminate of approved colour and shade to doors including all labour and material
Sr.No.
Particulars
1 Materials :
a) Laminate sheet of 1 mm thk.
b) Fevicol
c) Sundry material (plywood pieces &
0.5" nail)
Quantity
Labours :
Carpenter for fixing & polishing of
laminates
Helper
Unit
Rate per
Amount
1.00
0.05
Sqm.
Kg.
310.00
250.00
310.00
12.50
1.00
L/S
10.00
10.00
0.07
0.20
Nos.
Nos.
200.00
100.00
14.00
20.00
0.00
0.00
TOTAL (A)
366.50
7.33
0.00
1.83
TOTAL (B)
375.66
56.35
TOTAL
432.01
Others
Nil
4
5
6
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
432 /- Per
Sqmt.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Door.
Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop
250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop
250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws
2
Quantity
Unit
Rate per
1.00
1.00
1.00
1.00
1.00
2.00
24.00
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
0.00
0.00
0.00
0.00
0.20
0.75
Nos.
Nos.
200.00
100.00
40.00
75.00
0.00
0.00
TOTAL (A)
115.00
2.30
0.00
0.58
TOTAL (B)
117.88
17.68
TOTAL
135.56
Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Others
Nil
5
6
7
Amount
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
136 /- Per
Door.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Door.
Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws
Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Quantity
Unit
Rate per
Amount
1.00
1.00
1.00
1.00
1.00
2.00
24.00
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
112.50
112.50
0.00
0.00
0.20
0.75
Nos.
Nos.
200.00
100.00
40.00
75.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
227.50
4.55
0.00
1.14
TOTAL (B)
233.19
34.98
TOTAL
268.17
Others
4
5
6
7
Nil
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
268 /- Per
Door.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Door.
Providing and fixing following stainless steel fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws
Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Quantity
Unit
Rate per
Amount
1.00
1.00
1.00
1.00
1.00
2.00
24.00
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
112.50
112.50
0.00
0.00
0.20
0.75
Nos.
Nos.
200.00
100.00
40.00
75.00
0.00
0.00
0.00
0.00
0.00
0.00
Others
4
Nil
0.00
0.00
0.00
5
6
7
2.00%
0.00%
0.50%
15.00%
TOTAL (A)
227.50
4.55
0.00
1.14
TOTAL (B)
233.19
34.98
TOTAL
268.17
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
268 /- Per
Door.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Door.
Providing and fixing following Brass fittings and fixtures for doors, including Aldrop 250mm, tadipatti,
towerbolts, PVC gattu, door stopper, D type handle.
Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws
Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Quantity
Unit
Rate per
Amount
1.00
1.00
1.00
1.00
1.00
2.00
24.00
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
112.50
112.50
0.00
0.00
0.20
0.75
Nos.
Nos.
200.00
100.00
40.00
75.00
Others
4
5
6
7
Nil
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
227.50
4.55
0.00
1.14
TOTAL (B)
233.19
34.98
TOTAL
268.17
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
268 /- Per
Door.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Door.
Providing and fixing night latch of approved brand to door with all hardware and accessories required
Sr.No.
Particulars
1 Materials :
a) Night Latch
Quantity
1.00
Unit
Nos.
Rate per
Amount
0.00
b) Screws
24.00
Nos.
0.20
0.20
Nos.
Nos.
Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.2 help are required for
fixing the latch for one door)
200.00
100.00
40.00
20.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
60.00
1.20
0.00
0.30
TOTAL (B)
61.50
9.23
TOTAL
70.73
Others
4
5
6
7
Nil
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
71 /- Per
Door.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Door.
Providing and fixing in position automatic door closure of approved make including all labour and
material complete.
Providing and fixing in position automatic door closure of approved make including all labour and
material complete.
Sr.No.
Particulars
1 Materials :
a) Automatic door closer (godrej or
equivalent)
b) Screws
Quantity
Unit
1.00
24.00
Nos.
Nos.
0.20
0.20
Nos.
Nos.
Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.2 help are required for
fixing )
Rate per
Amount
0.00
200.00
100.00
40.00
20.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
60.00
1.20
0.00
0.30
TOTAL (B)
61.50
9.23
TOTAL
70.73
Others
4
5
6
7
Nil
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
71 /- Per
Door.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Door.
Providing and fixing peep hole / eye piece of approved make to doors including all labour and material
complete
Sr.No.
Particulars
1 Materials :
a) Eye piece
b) Screws
Labours :
Carpenter for fixing
Helper
(0.1 carp + 0.1 help are required for
fixing the latch for one door)
Quantity
Unit
1.00
24.00
Nos.
Nos.
0.10
0.10
Nos.
Nos.
Rate per
Amount
0.00
200.00
100.00
20.00
10.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
30.00
0.60
0.00
0.15
TOTAL (B)
30.75
4.61
Others
4
5
6
7
Nil
0.00
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
TOTAL
Say Rs.
35 /- Per
35.36
Door.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Unit :
Dec 30, 99
14-08-06
Sqm.
Description :
P/F MS powder coated grills & railing
Providing, fabricating and fixing in position for grills & railings in Powder coated MS tubular sections of
all shapes and size, with weight upto 15 kg / sqm, as per detail design and drawing, all labour and
material complete.
Sr.No.
Particulars
1 Materials :
a) Steel sections
b) Nails
c) Cement
2
Labours :
For fabricating & fixing in position
Mason for finishing
For powder coating
Quantity
Unit
Rate per
Amount
15.00
0.20
0.05
Kg.
Kg.
Bag
32.00
32.00
245.00
480.00
6.40
12.25
15.00
0.10
1.27
Kg.
No.
Sqm.
8.00
200.00
161.40
120.00
20.00
205.62
1.00
L/s
20.00
20.00
0.00
0.00
TOTAL (A)
864.27
17.29
0.00
4.32
TOTAL (B)
885.88
132.88
TOTAL
1018.76
Others
Nil
5
6
7
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,019 /- Per
Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
D1
Revised on Date:
Item No. : 31
Description :
Unit :
Dec 30, 99
14-08-06
Sqm.
Providing, fabricating and fixing in position for grills & railings in MS tubular sections of all shapes and
size, with weight upto 15 kg / sqm, as per detail design and drawing, painted with one coat of zinc
chromate & two coats of enamel paint,all labour and material complete.
Sr.No.
Particulars
1 Materials :
a) Steel sections
b) Nails
c) Cement
2
Labours :
For fabricating & fixing in position
Mason for finishing
For enamel painting
Quantity
Unit
Rate per
Amount
15.00
0.20
0.05
Kg.
Kg.
Bag
32.00
32.00
245.00
480.00
6.40
12.25
15.00
0.10
1.27
Kg.
No.
Sqm.
8.00
200.00
30.00
120.00
20.00
38.22
0.00
0.00
0.00
0.00
TOTAL (A)
676.87
13.54
0.00
3.38
TOTAL (B)
693.79
104.07
TOTAL
797.86
Others
Nil
4
5
6
0.00
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
798 /- Per
Sqm.
Prepared by :
Name : _________________________________
Site:
0
Computer Code No. :
Sign: ________________
Rate analysis
Location : 0
Default Date :
D1
Revised on Date:
Dec 30, 99
14-08-06
Sqm.
Item No. : 31
Unit :
Description :
P/F MS Z section windows
Providing and fixing in position MS glazed windows with Z section, 4 mm thick clear float glass, 10 mm
MS square bars at 120 mm c/c, required springs, putty and two coats of oilpaint etc complete.
Sr.No.
1
Particulars
Quantity
Assuming the window size to be = 1.2 x 1.2m
Materials :
9.60
a) MS Zsections (25mm)
8.00
b) 10mm Sq. bars
c) 4mm thk. Float glass (with 5%
wastage)
1.44
4.00
d) MS holdfast
e)
0.10
f) Nails
g) Cement
0.05
h) Fittings (stopper, handle, pin hinges
I.e = 26+10+20)
1.00
0.80
I) Putty
Labours :
For fabricating & fixing in position
(9.6*1.53+8*.785 = 14.2 kg.
Mason for finishing
For enamel painting
For fixing glass
(0.22 glazier reqd. for each Sqm.)
Rate per
Amount
Rmt.
Rmt.
45.00
23.55
432.00
188.40
Sqm.
Nos
325.00
20.00
468.00
80.00
Kg.
Bag
32.00
78.75
3.20
3.94
L/s
Kg.
56.00
20.00
56.00
16.00
Kg.
No.
Sqm.
No.
10.00
200.00
30.00
150.00
209.68
20.00
32.40
47.52
0.00
0.00
TOTAL (A)
1557.14
31.14
0.00
7.79
TOTAL (B)
1596.07
239.41
TOTAL
1835.48
Others
Nil
5
6
7
20.97
0.10
1.08
0.32
Unit
0.00
2.00%
0.00%
0.50%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
1,275 /- Per
Sqm.
Prepared by :
Name : _________________________________
Sign: ________________
backup calculation
Item / description
PCC (1:3:6)
Labour
For pouring
Male coolie
Female coolie
Qty.
Rate
Amount
0.75
0.75
80
80
60
60
120
0.05
150
7.5
0.2
0.2
130
100
26
20
11.5
57.5
80
0.67
0.67
80
80
53.6
53.6
107.2
0.11
150
16.5
Page 1
Remarks
1.6
Conc. = 1.5*1.5*.4 = 0.9cum
shutt = 1.5 * 4 *.4 = 2.4
shutt / cum = 2.4/0.9 =2.67
0.9
One mason can do finishing of 9 cum. ( 10
ftgs. )
backup calculation
0.3
0.3
130
100
39
30
17.25
86.25
1.1
1.1
80
80
88
88
176
150
1.25
1.25
130
100
162.5
125
71.875
359.375
4.98
Page 2
backup calculation
1040
0.0833333333
900
0.9
0.9
80
80
72
72
144
150
1
1
130
100
130
100
57.5
287.5
6713.599
671.3599
44.75732667
Page 3
backup calculation
1.1
1.1
80
80
88
88
176
0.1
150
15
1.67
1.67
130
100
217.1
167
96.025
480.125
63.5833333333
84.5
1.1
1.1
80
80
88
88
176
0.07
150
10.5
Page 4
backup calculation
1.25
1.25
130
100
162.5
125
71.875
359.375
1.5
1.5
80
80
120
120
240
0.07
150
10.5
2
2
130
100
260
200
115
575
996
Page 5
backup calculation
1.5
1.5
80
80
120
120
240
0.07
150
10.5
2
2
130
100
260
200
115
575
0.0666666667
One mason can do finishing of 15 cum.
1.75
One carpenter can do 6 sqm. Per day
One helper can do 6 sqm. Per day
1.1
1.1
80
80
88
88
176
150
1.6
130
208
Page 6
backup calculation
1.6
100
160
92
460
1
1
80
80
80
80
160
0.1
150
15
1
1
130
100
130
100
80.5
310.5
1.5
80
Page 7
120
backup calculation
Female coolie
1.5
80
120
240
0.05
150
7.5
2
2
130
100
260
200
115
575
80
80
100
100
200
0.25
150
37.5
2
2
130
100
260
200
161
621
Page 8
backup calculation
892
763.8888888889
RCC M20 for folded Staircases (with thickness upto 150mm)
Labour
For pouring
Male coolie
1.5
Female coolie
1.5
80
80
120
120
240
0.25
150
37.5
3
3
130
100
390
300
241.5
931.5
8
8
0.2
110
100
175
880
800
35
428.75
2143.75
0.4347826087
Page 9
backup calculation
Carpenter
0.43
130
55.9
55.9
0.46
150
69
1.2
80
96
165
0.2355712603
4.245
0.1766784452
One mason pair to do 150cft. (I.e.4.245cum)
of UCR
0.46
150
69
1.2
80
96
87
252
87.7192982456
One mason pair to do 150cft. (I.e.4.245
cum) of UCR
add for corner stones preparation ,
assuming 3.0m length & 1.5m height, corner
stones required 30nos @ 5/- for (.38*3*1.5 =
1.71 cum. I.e 150/1.71 = 87rs. Per cum.
Page 10
backup calculation
Labour
mason
Unskilled labour ( 2 nos per mason)
0.56
150
84
80
80
164
1.2195121951
3.5375
One mason pair to do 125ft. (I.e.3.53 cum)
of BBM
0.35
150
52.5
0.7
80
56
108.5
0.57
80
45.6
0.108
150
16.2
0.216
80
17.28
33.48
0.162
150
24.3
0.216
80
17.28
Page 11
backup calculation
41.58
Scaffolding etc.
0.083
80
6.64
Sand screening
0.0552
53
2.9
9.6
0.17
150
25.5
0.2
80
16
41.5
Scaffolding etc.
0.083
80
6.64
Sand screening
0.02
53
1.1
7.7
0.2
150
30
0.2
80
16
46
Scaffolding etc.
0.083
80
6.64
Sand screening
0.03
53
1.6
Page 12
0.03
backup calculation
8.2
0.46
150
69
0.7
80
56
87
0.24
175.00
41.22
253.22
Scaffolding etc.
0.083
80
6.64
Sand screening
0.07
53
3.7
10.4
29.7
0.11
150
16.5
0.11
80
8.8
25.3
Page 13
18.58736059
backup calculation
Scaffolding etc.
0.083
80
6.64
Sand screening
0.03
53
1.6
8.2
0.11
150
16.5
0.11
80
8.8
25.3
Scaffolding etc.
0.083
80
6.64
Sand screening
0.04
53
2.1
8.8
0.11
150
16.5
0.11
80
8.8
25.3
Scaffolding etc.
0.083
80
6.64
Sand screening
0.02
53
1.1
7.7
Page 14
0.193
backup calculation
0.122
150
18.3
0.122
80
9.76
28.06
Scaffolding etc.
0.083
80
6.64
Sand screening
0.03
53
1.6
8.2
0.122
150
18.3
0.122
80
9.76
28.06
Scaffolding etc.
0.083
80
6.64
Sand screening
0.04
53
2.1
8.8
Labour
mason
0.1
200
Page 15
20
backup calculation
Scaffolding etc.
Sand screening
0.2
80
16
36
0.083
80
6.64
0.012
53
0.6
7.3
0.13
200
26
0.27
80
21.6
47.6
Scaffolding etc.
0.083
80
6.64
Sand screening
0.025
53
1.3
8.0
0.2
225
45
0.27
80
21.6
0.2
80
16
82.6
0.083
80
6.64
Scaffolding etc.
Page 16
backup calculation
Sand screening
0.025
53
1.3
8.0
Labour
mason
0.1
225
22.5
0.1
80
0.05
80
4
34.5
Scaffolding etc.
0.083
80
6.64
Sand screening
0.008
53
0.4
7.1
0.1
225
22.5
0.13
80
10.4
0.05
80
4
36.9
Scaffolding etc.
0.083
80
6.64
Sand screening
0.008
53
0.4
7.1
Page 17
backup calculation
Labour
mason
0.1
200
20
0.27
80
21.6
41.6
Scaffolding etc.
0.083
80
6.64
Sand screening
0.02
53
1.1
7.7
0.07
0.2
200
80
14
16
30
Scaffolding etc.
0.083
80
6.64
Sand screening
0.012
53
0.6
7.3
Labour
mason
Unskilled labour (2 nos)
0.1
225
22.5
0.1
80
8
30.5
0.1
80
Page 18
backup calculation
0.1
225
22.5
0.1
80
8
30.5
0.1
80
Male coolie
Female coolie
1.25
1.25
80
80
100
100
200
0.13
150
19.5
1.33
1.33
130
100
172.9
133
107.065
412.965
682.5
80
80
Page 19
backup calculation
Female coolie
80
80
160
0.07
150
10.5
1.17
1.17
130
100
152.1
117
94.185
363.285
1.25
1.33
1.33
80
80
106.4
106.4
212.8
0.44
150
66
2
2
130
100
260
200
161
621
Page 20
20
66.6666666667
Size of coping = 0.15 x .10
Assuming that one pair of labour to 50 Rmt
of Coping
1.3333333333
backup calculation
1220
Male coolie
Female coolie
0.1
0.1
80
80
8
8
16
0.1
0.1
150
80
15
8
23
0.034
130
4.42
0.034
100
3.4
2.737
10.557
Page 21
backup calculation
Male coolie
Female coolie
0.1
0.1
80
80
8
8
16
0.1
0.1
150
80
15
8
23
812.8
220.00
220.00
541.2
267.3
1695.00
1695.00
1695.00
3973.72
637.32
1906.88
Male coolie
Mason
0.1
0.1
80
80
8
8
16
0.1
0.1
150
80
15
8
Page 22
backup calculation
23
Page 23
backup calculation
ply
battem
ballies
1.34
Page 24
backup calculation
0.375
1.5625
Page 25
backup calculation
Page 26
backup calculation
2.0875
Page 27
backup calculation
Page 28
backup calculation
Page 29
backup calculation
2.00
1.25
Page 30
backup calculation
Page 31
backup calculation
Page 32
backup calculation
Page 33
backup calculation
Page 34
backup calculation
Page 35
backup calculation
Page 36
backup calculation
Page 37
backup calculation
Page 38
backup calculation
Page 39
backup calculation
Page 40
backup calculation
Page 41
backup calculation
Page 42
backup calculation
Page 43
backup calculation
Page 44
backup calculation
Page 45
backup calculation
Page 46
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
P1
Default Date :
Revised on Date :
Item No. : 23
Description :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing sand faced plaster externally in cement mortor in all position for a coat of 15 to 20mm thk. in
c.m. 1:5 finishing the surface taking out grains and curing for twenty one days scaffolding etc. complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
Labours :
for Plastering
Others
Scaffolding & sand screening
charges
5
6
7
Quantity
Unit
Rate per
Amount
0.16
0.03
Bags
Cum
215.00
1060.00
34.40
31.80
1.00
Sqm
41.60
41.60
1.00
Sqm
7.70
7.70
TOTAL (A)
115.50
2.31
0.58
0.00
TOTAL (B)
118.39
17.76
TOTAL
136.15
2.00%
0.50%
0.00%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
136 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
P2
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & applying 23 mm av. Th 1:3 c.m. sand faced plaster in 2 coats (base coat of 15 mm th and
finishing coat of 8 mm th) to concrete & brick surfaces, risers or otherwise including mixing plasticizers &
waterproofing compound supplied free as directed as including curing, scaffolding, corners, & edges,
bands, splays, grroves, drips, offsets (for which no extra payment will be made) curing etc. complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
Labours :
for Plastering
Quantity
Unit
Rate per
Amount
0.22
0.03
Bags
Cum
245.00
1060.00
53.90
31.80
1.00
Sqm
47.60
47.60
1.00
Sqm
7.97
7.97
TOTAL (A)
141.27
2.83
0.71
0.00
5
6
7
Others
Scaffolding & sand screening
charges
2.00%
0.50%
0.00%
on total (A)
on total (A)
on total (A)
15.00%
TOTAL (B)
144.80
21.72
TOTAL
166.52
on total (B)
Say Rs.
167 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
P3
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & applying av. 12 mm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets
etc. for which which no extra payment will be made.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Neeru
Labours :
for Plastering
Quantity
Unit
Rate per
Amount
0.13
0.01
0.10
Bags
Cum
Bags
245.00
1060.00
50.00
31.85
14.84
5.00
1.00
Sqm
36.00
36.00
1.00
Sqm
7.28
7.28
Others
Scaffolding charges
5
6
7
2.00%
0.50%
0.00%
15.00%
TOTAL (A)
94.97
1.90
0.47
0.00
TOTAL (B)
97.34
14.60
TOTAL
111.94
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
112 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : Pune
P4
Default Date :
Revised on Date :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & applying av. 2 cm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets
etc. for which which no extra payment will be made.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Neeru
Labours :
for Plastering work
Quantity
Unit
Rate per
Amount
0.17
0.02
0.10
Bags
Cum
Bags
245.00
1060.00
50.00
41.65
25.44
5.00
1.00
Sqm
36.00
36.00
5
6
7
Others
Scaffolding charges
1.00
2.00%
0.50%
0.00%
15.00%
Sqm
7.28
7.28
TOTAL (A)
115.37
2.31
0.58
0.00
TOTAL (B)
118.25
17.74
TOTAL
135.99
on total (A)
on total (A)
on total (A)
on total (B)
136 /- Per
Say Rs.
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
P2
Default Date :
Revised on Date :
14-08-06
ITEM NO - FDAPL/PLAST/V/10
Unit :
Description :
per sqm
Waterproof plaster
Extra for providing chemical admixtures in plastering for waterproofing as per manufacturer's
specifications.( Pidilite / Laticrete / Roffee/ Fosroc or any other approved make)
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Waterproofing compound
Quantity
0.34
0.03
0.34
Unit
Bags
Cum
Kg.
Rate per
245.00
1060.00
40.00
Amount
83.30
31.80
13.60
Labours :
for Plastering
Others
Sand screening & material shifting
5
6
7
1.00
Sqm
90.86
90.86
1.00
Sqm
7.97
7.97
TOTAL (A)
227.53
4.55
1.14
0.00
TOTAL (B)
233.21
34.98
TOTAL
268.20
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
268 /- Per
Say Rs.
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
P2
Default Date :
Revised on Date :
Item no - FDAPL/PLAST/V/8
Unit :
Dec 30, 99
14-08-06
per sqm
Description :
Pointing to brick masonary
Providing and making flush groove pointing to brick / block / stone masonry in C:M 1:3 including
scaffolding, curing, cleaning complete with all labour and material.
Sr.No.
Particulars
1 Materials :
Quantity
Unit
Rate per
Amount
a) Cement
b) Sand
0.03
0.01
Bags
Cum
245.00
1060.00
7.35
5.30
Labours :
for Pointing
1.00
Sqm
34.50
34.50
1.00
Sqm
7.06
7.06
TOTAL (A)
54.21
1.08
0.27
0.00
TOTAL (B)
55.57
8.34
TOTAL
63.90
5
6
7
Others
Sand screening & scaffolding
2.00%
0.50%
0.00%
15.00%
on total (A)
on total (A)
on total (A)
on total (B)
Say Rs.
64 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
P2
Default Date :
Revised on Date :
Unit :
Item No. : 24 / IV 6
Description :
14-08-06
per sqm
Quantity
0.11
0.01
Unit
Rate per
Bags
Cum
245.00
1060.00
0.00
0.00
0.00
0.00
26.95
5.30
0.00
0.00
0.00
0.00
1.00
0.00
0.00
0.00
Sqm
36.90
0.00
0.00
0.00
36.90
0.00
0.00
0.00
1.00
0.00
0.00
Sqm
7.06
0.00
0.00
7.06
0.00
0.00
TOTAL (A)
76.21
1.52
0.38
0.00
TOTAL (B)
78.12
11.72
TOTAL
89.84
0.00
0.00
0.00
2
Labours :
for Pointing
Amount
5
6
7
Others
Sand screening & scaffolding
2.00%
0.50%
0.00%
15.00%
Say Rs.
on total (A)
on total (A)
on total (A)
on total (B)
90 /- Per
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
P4
Default Date :
Revised on Date :
Item No. : 26 / IV 10
Description :
Unit :
Dec 30, 99
14-08-06
per sqm
Sr.No.
Particulars
1 Materials :
a) POP
Labours :
for POP work
Others
Scaffolding charges
5
6
7
Quantity
Unit
Rate per
Amount
0.13
0.00
0.00
0.00
0.00
0.00
Bags
Cum
Bags
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.00
0.00
0.00
0.00
Sqm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.00
0.00
0.00
Sqm
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL (A)
0.00
0.00
0.00
0.00
TOTAL (B)
0.00
2.00%
0.50%
0.50%
on total (A)
on total (A)
on total (A)
0.00%
on total (B)
0.00
TOTAL
0 /- Per
Say Rs.
0.00
per sqm
Prepared by :
Name : _________________________________
Sign: ________________
Rate analysis
Site:
0
Computer Code No. :
Location : 0
Default Date :
P4
Revised on Date :
Item No. : 26
Description :
Unit :
Dec 30, 99
14-08-06
per sqm
Providing & applying av. 12 cm thick 1:4 C.M. plaster without Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets
etc. for which which no extra payment will be made.(behind tile dado)
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
Labours :
for Plastering work
Others
Quantity
Unit
Rate per
Amount
0.13
0.01
Bags
Cum
245.00
1060.00
31.85
10.60
1.00
Sqm
30.00
30.00
Scaffolding charges
5
6
7
1.00
2.00%
0.50%
0.00%
15.00%
Say Rs.
Sqm
7.28
7.28
TOTAL (A)
79.73
1.59
0.40
0.00
TOTAL (B)
81.72
12.26
TOTAL
93.98
on total (A)
on total (A)
on total (A)
on total (B)
94 /- Per
per sqm
0.013
0.304
0.00608
0.17024
0.02432
0.1354
0.034
Rate analysis
Site:
0
Computer Code No. :
Item No. : FDAPL/RCC/III/22
Description :
Location : Pune
Default Date :
R1
Revised on Date :
Unit :
14-08-06
MT
Reinforcement works
Providing and laying in position reinforcemnt steel of various diameters incluidng cutting
bending, binding with binding wire for all RCC work like footings, columns, beams, slabs,
paradise staircases, chajjas, walls, etc. as per RCC Specialist's design & drawing details
with necessary bending, laying, binding, with binding wire, etc. complete. Rate to include all
lead & lift.
Sr.No.
Particulars
1 Materials :
a) Reinforcement steel
b) Binding wire
Labours :
for reinforcement works including
cutting, bending, binding etc.
including T & P etc. complete.
Others
Quantity
Unit
Rate per
1.00
12.00
MT
Kg
36000.00
38.00
36000.00
456.00
1.00
MT
2143.75
2143.75
TOTAL (A)
38599.75
772.00
0.00
193.00
TOTAL (B)
39564.74
5934.71
5
6
7
2.00%
0.00%
0.50%
on total (A)
on total (A)
on total (A)
15.00%
on total (B)
Amount
TOTAL
Say Rs.
45,499 /- Per
45499.46
MT
Prepared by :
Name : _________________________________
Sign: ________________
Site Name : 0
Location : Pune
SINGLE LINE ESTIMATION
Sr.No.
Description
Unit
per cum
Err:509
per cum
per cum
per cum
per cum
per cum
Err:509
per cum
Err:509
per cum
Err:509
per cum
Err:509
per cum
per cum
per cum
per cum
per cum
per cum
Err:509
Err:509
per sqm
per sqm
per sqm
Err:509
per sqm
Err:509
Err:509
Err:509
Err:509
per Cum
per sqm
per sqm
MT
per Sqm.
per No.
per Sqm.
0
0.03
0.005
0.005
Quantity
Rate
0
90
0.00 Err:509
0.00
107
0.00
289
0.00
777
0.00
3312
0.00
2544
0.00 Err:509
0.00
3281
0.00 Err:509
0.00
5171
0.00 Err:509
0.00
5297
0.00 Err:509
0.00
4428
0.00
5427
0.00
6281
0.00
1985
0.00
2335
0.00
2439
0.00
2086
0.00 Err:509
0.00
136
0.00
167
0.00
112
0.00 Err:509
0.00
334
0.00 Err:509
0.00 Err:509
0.00 Err:509
0.00 Err:509
0.00
2818
0.00
344
0.00
327
0.00
45499
0.00
43578
0.00
32
0.00
259
0.00
0
0.00
0
0
0
Total :
0
Pune
SINGLE LINE ESTIMATION
Amount
0.00
Err:509
0.00
0.00
0.00
0.00
0.00
Err:509
0.00
Err:509
0.00
Err:509
0.00
Err:509
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Err:509
0.00
0.00
0.00
Err:509
0.00
Err:509
Err:509
Err:509
Err:509
0.00
0.00
0.00
0.00
0.00
0.00
Err:509