You are on page 1of 423

d

Site:

0
Computer Code No. :

Location : Pune
W1
Default Date :
Revised on Date :

Item No. : FDAPL/WP/VIII/3


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Box type W/P to RCC raft, walls

Providing box type waterproofing treatment to RCC raft, wall, footings, columns, beams in basement by
fixing rough shahabad stone slabs of about 25 mm thickness in C:M. 1:3 with waterproofing layer in
between shahabad stone and slab bottom/ wall surfaces well pointed with cement plaster mixed with
waterproofing compound carefully well pressed and cured. The said treatment shall be carried out at
the hands of approved waterproofing agency.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Shahabad stone with 5% wastage
d) Waterproofing compound
2

Labours :
Masons for laying tiles & finishing
Unskilled labour

Centering & Shuttering


Nil

Others

Quantity

Unit

Rate per

Amount

1.28
0.04
1.05
0.60

Bags
Cum
Sqm.
Kg.

245.00
1060.00
82.50
40.00

313.60
42.40
86.63
24.00

0.15
0.30

No.
No.

150.00
80.00

22.50
24.00

0.00

0.00

0.00
TOTAL (A)
5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

513.13

on total (A)
on total (A)
on total (A)
TOTAL (B)

10.26
2.57
0.00
525.95

on total (B)

78.89

TOTAL

Say Rs.

604.85

605 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
Default Date :
W2
Revised on Date :

Item No. : FDAPL/WP/VIII/2


Description :

Unit :

Dec 30, 99
14-08-06
per Cum

Brickbat water proofing for toilets

Providing & laying brick bat coba of required thickness in C:M. 1:4 over the specified area including
rubbing and cleaning the base formwork if necessary giving proper slope compacting and curing etc.
complete, (in sunk portion of toilets) including providing and fixing 1" dia GI water escape pipe etc.
complete.
Sr.No.
1

4
5
6

Particulars
Assuming the thickness of 200mm
Materials :
a) Cement
b) Sand
c) Brickbats
d) Waterproofing compound
e) 1" dia. GI pipe

Quantity

Unit

Rate per

Amount

0.63
0.07
0.16
0.63
0.30

Bags
Cum
Cum
Kg.
Rmt.

245.00
1060.00
250.00
40.00
89.00

154.35
74.20
40.00
25.20
26.70

Labours :
Laying of brickbats & finishing
Mason
Helper

0.50
0.50

No.
No.

200.00
80.00

100.00
40.00

Others
Lift

1.00

Cum

17.75

17.75

TOTAL (A)

478.20
9.56
2.39
0.00

TOTAL (B)

490.16
73.52

TOTAL

563.68

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

Costing for 0.2 cum

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

2,818 /- Per

per Cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
Default Date :
W3
Revised on Date :

Item No. : FDAPL/WP/VIII/1


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Brickbat water proofing for terrace

Providing and laying cement bonded waterproofing treatment using brick bats fixed in concrete 1:2:4
in required slope and finishing top with neat cement punning, marking lines at 300 mm c/c including
providing and mixing waterproofing compound ( work to be carried out at the hands of approved
nominated sub contractors) including curing, testing against watertightness
Sr.No.

Particulars
Quantity
Assuming 1 sqm. Of area with 115 thk. Coba

Unit

Rate per

Amount

a) Cement
b) Sand
c) Metal
d) Brickbats
e) Waterproofing compound

0.40
0.03
0.03
0.08
0.43

Bags
Cum
Cum
Cum
Kg.

245.00
1060.00
340.00
250.00
40.00

98.74
31.80
10.20
20.00
17.20

Labours :
Laying of brickbats & finishing
Mason
Helper

0.40
0.40

No.
No.

200.00
80.00

80.00
32.00

Others
Lift

0.12

Cum

17.75

2.04

TOTAL (A)

291.98
5.84
1.46
0.00

TOTAL (B)

299.28
44.89

TOTAL

344.17

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

344 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : 35
Description :

Location : Pune
W4
Default Date :
Revision on Date :
Unit :

Dec 30, 99
14-08-06
per sqm

Chemical w/p for terrace, toilets

Providing and applying approved waterproofing chemical as per manufacturer's specifications to


terrace slab, toilet bottoms and sides, balconies etc wherever required with all labour and material
Sr.No.
Particulars
1 Materials :
Rate given by water proofing
agency

Labours :

Centering & Shuttering


Nil

Others

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Quantity

1.00

2.00%
0.50%
1.00%

15.00%

Unit

Sqm

Rate per

Amount

275.00

275.00

TOTAL (A)

275.00
5.50
1.38
2.75

TOTAL (B)

284.63
42.69

TOTAL

327.32

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

327 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/1


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

White wash

Providing and applying white wash to walls and ceilings , to concrete / brick /block/ stone surfaces
including preparing the surface by cleaning, including scaffolding of required type, all labour and
material complete.
Sr.No.
1

Particulars
Assuming 10sqm of area
Materials :
a) Slaked Lime
b) Ultramarine blue
c) Glue
d) Sodium chloride

Quantity

2.80
7.00
8.00
365.00

Unit

Kg.
Gram
Gram
Gram

Rate per

Amount

1.50
0.11
0.05
0.01

4.20
0.80
0.39
3.65

100.00
80.00

22.50
8.40

TOTAL (A)

39.95
0.80
0.20
0.00

TOTAL (B)

40.94
6.14

TOTAL

47.09

Labours :
For 10 sqm. Area , labour required
= (0.085+0.035) for first coat &
(0.07+.035)*2 for two coat
Lime washer
Helper

4
5
6

0.23
0.11

No.
No.

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit


For 10 sqm costing = 63/-

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

5 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/2


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Dry distemper

Providing and applying dry distemper of approved make, colour and shade to walls and ceilings , to
concrete / brick /block/ stone surfaces including preparing the surface by cleaning, including scaffolding
of required type, all labour and material complete.
Sr.No.
1

Particulars
Assuming 10sqm of area
Materials :
a) Dry distemper
b) Glue
d) Putty

Quantity

Unit

Rate per

Amount

1.35
80.00
0.20

Kg.
Gram
Kg.

67.00
0.05
40.95

90.45
3.91
8.19

0.37
0.09

No.
No.

150.00
80.00

54.75
7.20

TOTAL (A)

164.50
3.29
0.82
0.00

TOTAL (B)

168.61
25.29

Labours :
For 10 sqm. Area , labour required
= (0.22+0.05) for first coat &
(0.145+.04) for second coat
Painter
Helper

4
5
6

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

For 10 sqm costing = 290/-

TOTAL

Say Rs.

19 /- Per

193.90

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/3


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Oil bound distemper

Providing and applying oil bound distemper of approved make,colour and shade to walls and ceilings ,
to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks,
putty filling, rubbing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1

Particulars
Assuming 10sqm of area
Materials :
a) OBD
b) Primer
c) Glue
d) Whitning
e) Putty

Quantity

Unit

Rate per

Amount

1.50
0.85
80.00
1.00
0.20

Kg.
lts.
Gram
Kg.
Kg.

90.00
60.90
0.05
20.00
40.95

135.00
51.77
3.91
20.00
8.19

0.50
0.11

No.
No.

150.00
80.00

74.25
8.80

TOTAL (A)

301.91
6.04
1.51
0.00

TOTAL (B)

309.46
46.42

Labours :
For 10 sqm. Area , labour required
= (0.275+0.06) for first coat &
(0.22+.05) for second coat
Painter
Helper

4
5
6

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

For 10 sqm costing = 371.5/-

TOTAL
Say Rs.

36 /- Per

355.88
per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/4


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Synthetic enamel paint

Providing and applying synthetic enamel paint of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material
complete.
Sr.No.
1

Particulars
Assuming 10sqm of area
Materials :
a) Synthetic enamel
b) Primer
c) Glue
d) Whitning
e) Putty

Quantity

Unit

Rate per

Amount

1.50
0.85
80.00
1.00
0.20

Kg.
lts.
Gram
Kg.
Kg.

141.75
60.90
0.05
20.00
40.95

212.63
51.77
3.91
20.00
8.19

0.56
0.15

No.
No.

150.00
80.00

84.00
12.00

TOTAL (A)

392.49
7.85
1.96
0.00

TOTAL (B)

402.30

Labours :
For 10 sqm. Area , labour required
= (0.295+0.09) for first coat &
(0.265+.06) for second coat
Painter
Helper

4
5
6

Others

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

For 10 sqm costing = 482.95/-

60.34
TOTAL

Say Rs.

46 /- Per

462.64

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/6


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Lustre paint

Providing and applying lustre paint of approved make,colour and shade to walls and ceilings , to
concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks,
putty filling, rubbing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1

Particulars
Assuming 10sqm of area
Materials :
a) Luster paint
b) Primer
c) Glue
d) Whitning
e) Putty

Quantity

Unit

Rate per

Amount

1.50
0.85
80.00
1.00
0.30

Ltr.
lts.
Gram
Kg.
Kg.

218.75
60.90
0.05
20.00
40.95

328.13
51.77
3.91
20.00
12.29

0.85
0.30

No.
No.

150.00
80.00

127.88
23.76

TOTAL (A)

567.72
11.35
2.84
0.00

Labours :
For 10 sqm. Area , labour required
= (0.4+0.15) for first coat &
(0.375+.12) for second coat
Painter
Helper

4
5
6

Others

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

581.91
87.29

TOTAL

669.20

on total (B)

For 10 sqm costing = 623.93/-

Say Rs.

67 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/7


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Cement paint

Providing and applying cement paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and
material complete.
Sr.No.
1

Particulars
Assuming 10sqm of area
Materials :
a) Cement paint
b) Putty
Labours :
For 10 sqm. Area , labour required
= (0.25+0.15) for first coat &
(0.2+.1) for second coat
Painter
Helper
Unskilled

Others

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Quantity

Unit

Rate per

Amount

4.00
0.15

Kg.
Kg.

49.35
40.95

197.40
6.14

0.45
0.25
0.20

No.
No.
No.

150.00
80.00
80.00

67.50
20.00
16.00

TOTAL (A)

307.04
6.14
1.54
0.00

TOTAL (B)

314.72

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

For 10 sqm costing = 377.82/-

47.21
TOTAL

Say Rs.

36 /- Per

361.93

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/8


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Sandtex paint

Providing and applying sandtex paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling
the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and
material complete.
Sr.No.
1

4
5
6

Particulars
Assuming 10sqm of area
Materials :
a) Sandtex paint
b) Cement paint
c) Putty
Labours :
For 10 sqm. Area , labour required
= (0.3+0.1) for first coat & (0.25+.1)
for second coat
Painter
Helper
Unskilled

Quantity

Unit

Rate per

Amount

4.50
1.50
0.20

Kg.
Kg.
Kg.

86.36
49.35
40.95

388.63
74.03
8.19

0.65
0.20
0.20

No.
No.
No.

150.00
80.00
80.00

97.50
16.00
16.00

TOTAL (A)

600.35
12.01
3.00
0.00

TOTAL (B)

615.35
92.30

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

For 10 sqm costing = 761.5/-

TOTAL

Say Rs.

71 /- Per

707.66

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/9


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Antifungal paint

Providing and applying anti fungal paint of approved make,colour and shade to walls to concrete /
brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling,
rubbing , curing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1

4
5
6

Particulars
Assuming 10sqm of area
Materials :
a) Antifungal paint
b) Cement paint
c) Putty
Labours :
For 10 sqm. Area , labour required
= (0.3+0.1) for first coat & (0.25+.1)
for second coat
Painter
Helper
Unskilled

Quantity

Unit

Rate per

Amount

4.50
1.50
0.20

Kg.
Kg.
Kg.

123.38
49.35
40.95

555.19
74.03
8.19

0.65
0.30
0.20

No.
No.
No.

150.00
80.00
80.00

97.50
24.00
16.00

TOTAL (A)

774.90
15.50
3.87
0.00

TOTAL (B)

794.28

Others

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

For 10 sqm costing = 953.22/-

119.14
TOTAL

Say Rs.

91 /- Per

913.42
per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
W3
Revised on Date :

Item No. : FDAPL/PAINT/IX/5


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Plastic emulsion paint

Providing and applying plastic emulsion paint of approved make,colour and shade to walls and ceilings
, to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks,
putty filling, rubbing etc including scaffolding of required type, all labour and material complete.
Sr.No.
1

Particulars
Assuming 10sqm of area
Materials :
a) Plastic emulsion paint
b) Primer
c) Glue
d) Whitning
e) Putty

Quantity

Unit

Rate per

Amount

1.75
0.85
80.00
1.25
0.40

Kg.
lts.
Gram
Kg.
Kg.

205.15
60.90
0.05
20.00
40.95

359.01
51.77
3.91
25.00
16.38

0.80
0.40

No.
No.

150.00
80.00

120.00
32.00

TOTAL (A)

608.06
12.16
3.04
0.00

TOTAL (B)

623.27

Labours :
For 10 sqm. Area , labour required
= (0.425+0.25) for first coat &
(0.375+.15) for second coat
Painter
Helper

4
5
6

Others

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

For 10 sqm costing = 553.7/-

Say Rs.

TOTAL (B)

623.27
93.49

TOTAL

716.75

on total (B)

72 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

0.38
0.0152
1.2768

refer page 109 & 75

17.7

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/1


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

Ac trafford 6mm thk.sheets

Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.

Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) AC trafford sheets
72.77
(adding 100mm for side laps &
200mm for end lap & 5% for
wastage)

Amount

149.10

10849.26

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.30
64.00
0.30

Kg.
Nos.
Kg.

32.00
6.30
47.25

9.60
403.20
14.18

Labours :
For fixing the sheets

60.00

Sqm.

35.00

2100.00

0.00

0.00

TOTAL (A)

13376.24
267.52
0.00
66.88

TOTAL (B)

13710.64
2056.60

TOTAL

15767.24

Others
Nil

4
5
6

Rate per

Sqm.

b) Bitumen washers 3mm thk.

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit


Costing for 60 sqm. area

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

263 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/2


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Ac 6mm thk.ridges

Providing and fixing in positional AC ridges as required including all fixing accessories complete
Sr.No.
Particulars
1 Materials :
a) AC ridges
(adding 5% for wastage)

Rate per

Amount

Rmt.

94.50

99.23

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.02
2.00
0.02

Kg.
Nos.
Kg.

32.00
6.30
47.25

0.64
12.60
0.95

Labours :
For fixing the sheets

1.00

Rmt

25.00

25.00

0.00

0.00

TOTAL (A)

138.41
2.77
0.00
0.69

TOTAL (B)

141.87
21.28

TOTAL

163.15

Others
Nil

4
5
6

Unit

1.05

b) Bitumen washers 3mm thk.

Quantity

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

163 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/3


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

Ac trafford 6mm thk.sheets cladding

Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
Cladding, flashing etc.
Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) AC trafford sheets
69.30
(adding 100mm for side laps &
5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.

Labours :
For fixing the sheets

Rate per

Amount

Sqm.

149.10

10332.63

0.30
48.00
0.30

Kg.
Nos.
Kg.

32.00
6.30
47.25

9.60
302.40
14.18

1.00

Sqm.

42.00

42.00

0.00

0.00

TOTAL (A)

10700.81
214.02
0.00
53.50

TOTAL (B)

10968.33
1645.25

Others
Nil

4
5
6

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 60 sqm. area

TOTAL

Say Rs.

210 /- Per

12613.57

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/4


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Ac gutter

Providing and fixing in required slope AC gutter including fixing with MS flat brackets at 600 mm c/c of
required size, filling the joints with polysulphide sealants etc with all labour and material and testing
against watertightness. (MS bracket to be measured & paid separately)
Sr.No.
Particulars
1 Materials :
a) AC Gutter
(adding 5% for wastage)

Rate per

Amount

Rmt.

105.00

110.25

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.02
2.00
0.02

Kg.
Nos.
Kg.

32.00
6.30
47.25

0.64
12.60
0.95

Labours :
For fixing the sheets

1.00

Rmt

25.00

25.00

0.00

0.00

TOTAL (A)

149.44
2.99
0.00
0.75

Others
Nil

4
5
6

Unit

1.05

b) Bitumen washers 3mm thk.

Quantity

Tools & Plants Charges


Water charges
Electricity Charges

0.00

2.00%
0.00%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

153.17
22.98

TOTAL

176.15

on total (B)

Say Rs.

176 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/5


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

MS precoated sheets

Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc
complete with all labour and material.
Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :
a) MS precoated sheets
0.55mm
97.74
(adding 70mm for side laps &
200mm for end lap & 5% for
wastage)

Rate per

Amount

Sqm.

319.00

31180.50

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.38
80.00
0.38

Kg.
Nos.
Kg.

32.00
6.30
47.25

12.00
504.00
17.72

Labours :
For fixing the sheets

84.00

Sqm.

72.80

6115.20

0.00

0.00

b) Bitumen washers 3mm thk.

Unit

Others
Nil

0.00

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
0.50%

15.00%

TOTAL (A)

37829.41
756.59
0.00
189.15

TOTAL (B)

38775.15
5816.27

TOTAL

44591.42

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 84 sqm. area

Say Rs.

531 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/2


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

MS precoated ridges

Providing and fixing in position MS precoated ridges as required including all fixing accessories
complete
Sr.No.
Particulars
1 Materials :
a) MS precoated ridges
(adding 5% for wastage)

Unit

Rate per

Amount

1.05

Rmt.

181.50

190.58

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.02
2.00
0.02

Kg.
Nos.
Kg.

32.00
6.30
47.25

0.64
12.60
0.95

Labours :
For fixing the sheets

1.00

Rmt

55.00

55.00

b) Bitumen washers 3mm thk.

Quantity

Others

Nil

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

0.00

0.00

TOTAL (A)

259.76
5.20
0.00
1.30

TOTAL (B)

266.25
39.94

TOTAL

306.19

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

306 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/3


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

MS precoated .55mm thk.sheets cladding

Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc
complete with all labour and material. For Cladding
Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 2 = 30 sqm.
Materials :
a) MS precoated sheets
0.55mm
33.71
(adding 70mm for side laps &
5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.

0.23
48.00
0.23

Unit

Rate per

Amount

Sqm.

319.00

10751.90

Kg.
Nos.
Kg.

32.00
6.30
47.25

7.20
302.40
10.63

Labours :
For fixing the sheets

Sqm.

90.00

2880.00

0.00

0.00

TOTAL (A)

13952.13
279.04
0.00
69.76

TOTAL (B)

14300.93
2145.14

TOTAL

16446.07

Others
Nil

4
5
6

32.00

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 32 sqm. area

Say Rs.

514 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/4


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

MS precoated gutter

Providing and fixing in required slope precoated sheet gutter including fixing with MS flat brackets at
600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and
material and testing against watertightness. (MS bracket to be measured & paid separately)
Sr.No.
Particulars
1 Materials :
a) MS precoated Gutter
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.

Quantity

Unit

Rate per

Amount

1.05

Rmt.

216.15

226.96

0.02
2.00
0.02

Kg.
Nos.
Kg.

32.00
6.30
47.25

0.64
12.60
0.95

Labours :
For fixing the sheets

Rmt

90.00

90.00

0.00

0.00

TOTAL (A)

331.14
6.62
0.00
1.66

TOTAL (B)

339.42
50.91

TOTAL

390.33

Others
Nil

4
5
6

1.00

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

390 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/5


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

Alluminium sheets

Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.

Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :

Unit

Rate per

Amount

a) MS precoated sheets
0.55mm

97.74

Sqm.

415.80

40642.16

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.38
80.00
0.38

Kg.
Nos.
Kg.

32.00
6.30
47.25

12.00
504.00
17.72

Labours :
For fixing the sheets

84.00

Sqm.

72.80

6115.20

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

47291.08
945.82
0.00
236.46

TOTAL (B)

48473.36
7271.00

TOTAL

55744.36

(adding 70mm for side laps &


200mm for end lap & 5% for
wastage)
b) Bitumen washers 3mm thk.

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 84 sqm. area

Say Rs.

664 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/10


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Alluminium ridges

Providing and fixing in position aluminium ridges as required including all fixing accessories
complete

Sr.No.
Particulars
1 Materials :
a) MS precoated ridges
(adding 5% for wastage)

Rate per

Amount

Rmt.

236.50

248.33

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.02
2.00
0.02

Kg.
Nos.
Kg.

32.00
6.30
47.25

0.64
12.60
0.95

Labours :
For fixing the sheets

1.00

Rmt

55.00

55.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

317.51
6.35

Centering & Shuttering


Nil

Others
Nil

Unit

1.05

b) Bitumen washers 3mm thk.

Quantity

Tools & Plants Charges

0.00
0.00
0.00

2.00%

on total (A)

6
7

Water charges
Electricity Charges

Over head & Profit

0.00%
0.50%

15.00%

on total (A)
on total (A)

0.00
1.59
TOTAL (B)

325.45
48.82

TOTAL

374.26

on total (B)

Say Rs.

374 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/11


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

Alluminium sheets cladding

Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
cladding

Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 2 = 30 sqm.
Materials :
a) MS precoated sheets
0.55mm
33.71
(adding 70mm for side laps &
5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.

0.23
48.00
0.23

Unit

Rate per

Amount

Sqm.

415.80

14014.54

Kg.
Nos.
Kg.

32.00
6.30
47.25

7.20
302.40
10.63

Labours :
For fixing the sheets

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

32.00

Sqm.

90.00

2880.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

17214.77
344.30
0.00
86.07

TOTAL (B)

17645.14
2646.77

TOTAL

20291.91

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 30 sqm. area

Say Rs.

676 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/12


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Alluminium gutter

Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600
mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material
and testing against watertightness. (MS bracket to be measured & paid separately)

Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600
mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material
and testing against watertightness. (MS bracket to be measured & paid separately)

Sr.No.
Particulars
1 Materials :
a) MS precoated Gutter
(adding 5% for wastage)

Amount

302.50

317.63

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.02
2.00
0.02

Kg.
Nos.
Kg.

32.00
6.30
47.25

0.64
12.60
0.95

Labours :
For fixing the sheets

1.00

Rmt

90.00

90.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

421.81
8.44
0.00
2.11

TOTAL (B)

432.36
64.85

TOTAL

497.21

Centering & Shuttering


Nil

Others
Nil

Rate per

Rmt.

5
6
7

Unit

1.05

b) Bitumen washers 3mm thk.

Quantity

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

Say Rs.
Prepared by :

on total (A)
on total (A)
on total (A)

on total (B)

497 /- Per

per Rmt.

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/13


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

FRP sheets

Providing and fixing in position FRP sheet of 1.5 mm thick of Finoram or any other approved make at
all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and
material.

Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :
97.74
a) FRP sheets 1.5mm
(adding 70mm for side laps &
200mm for end lap & 5% for
wastage)

Rate per

Amount

Sqm.

423.50

41394.80

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.38
80.00
0.38

Kg.
Nos.
Kg.

32.00
6.30
47.25

12.00
504.00
17.72

Labours :
For fixing the sheets

84.00

Sqm.

72.80

6115.20

0.00

0.00

b) Bitumen washers 3mm thk.

Unit

Centering & Shuttering


Nil

Others
Nil

0.00

0.00
0.00

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
0.50%

15.00%

0.00
0.00

0.00
0.00

TOTAL (A)

48043.71
960.87
0.00
240.22

TOTAL (B)

49244.81
7386.72

TOTAL

56631.53

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 84 sqm. area

Say Rs.

674 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/14


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

FRP ridges

Providing and fixing in position FRP ridges as required including all fixing accessories complete

Sr.No.
Particulars
1 Materials :
a) MS precoated ridges
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
c) J hooks & nuts
d) GI flat washer 2mm thk.

Quantity

Unit

Rate per

Amount

1.05

Rmt.

154.00

161.70

0.02
2.00
0.02

Kg.
Nos.
Kg.

32.00
6.30
47.25

0.64
12.60
0.95

Labours :
For fixing the sheets

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

Rmt

48.05

48.05

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

223.93
4.48
0.00
1.12

TOTAL (B)

229.53
34.43

TOTAL

263.96

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

264 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/15


Description :

Unit :
FRP sheets cladding

Dec 30, 99
14-08-06
per Sqm.

Providing and fixing in position FRP sheet roofing with 1.5 mm thick sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
cladding

Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 2 = 30 sqm.
Materials :
a) MS precoated sheets
0.55mm
33.71
(adding 70mm for side laps &
5% for wastage)

14274.07

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.23
48.00
0.23

Kg.
Nos.
Kg.

32.00
6.30
47.25

7.20
302.40
10.63

Labours :
For fixing the sheets

32.00

Sqm.

90.00

2880.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

17474.30
349.49
0.00
87.37

TOTAL (B)

17911.16
2686.67

Centering & Shuttering


Nil

Others
Nil

Amount

423.50

5
6
7

Rate per

Sqm.

b) Bitumen washers 3mm thk.

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 30 sqm. area

TOTAL

Say Rs.

687 /- Per

20597.83

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/16


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

FRP gutter

Providing and fixing in required slope FRP gutter including fixing with MS flat brackets at 600 mm c/c
of required size, filling the joints with polysulphide sealants etc with all labour and material and testing
against watertightness. (MS bracket to be measured & paid separately)

Sr.No.
Particulars
1 Materials :
a) MS precoated Gutter
(adding 5% for wastage)

Unit

Rate per

Amount

1.05

Rmt.

209.00

219.45

c) J hooks & nuts


d) GI flat washer 2mm thk.
e) Polysulphide sealant

0.02
2.00
0.02
0.03

Kg.
Nos.
Kg.
Kg.

32.00
6.30
47.25
500.00

0.64
12.60
0.95
12.50

Labours :
For fixing the sheets

1.00

Rmt

105.00

105.00

b) Bitumen washers 3mm thk.

Quantity

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

351.14
7.02
0.00
1.76

TOTAL (B)

359.91
53.99

TOTAL

413.90

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

414 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/ROOF/X/13


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

Polycarbonate sheets

Providing and fixing in position polycarbonate sheet roof as per detail design and drawing with
minimum thickness of sheet as 2 mm of Lexan or any other approved make including making the
joints waterproof with all labour and material and accessories to complete the work.

Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 5.6 = 84 sqm.
Materials :
a) Polycabonate sheets 2mm

88.20

Unit

Sqm.

Rate per

1500.00

Amount

132300.00

add 5% for wastage


b) Bitumen washers 3mm thk.

c) J hooks & nuts


d) GI flat washer 2mm thk.

0.38
80.00
0.38

Kg.
Nos.
Kg.

32.00
6.30
47.25

12.00
504.00
17.72

Labours :
For fixing the sheets

84.00

Sqm.

72.80

6115.20

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

138948.92
2778.98
0.00
694.74

TOTAL (B)

142422.64
21363.40

TOTAL

163786.04

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 84 sqm. area

Say Rs.

1,950 /- Per

per Sqm.

16.5
4.2
1.21275
72.765
(sheets in row + 1) x no. of purlins
64 hooks

1100

1100

1014
950
0.9218181818 0.8636364

sheet width = 1.07m, length = 3.2


15*2*1.07*2.9*1.05
97.7445
(sheets in row + 1) x no. of purlins
area of sheets = 15*2*2.9*1.07 = 93.09
93.09
Purlin spacing = 1.2m
(sheets in row + 1) x no. of purlins
80 hooks

sheets required = 15*1.07*2*1.05


33.705

150.72
4.71
1.536

122.88

7.7

15.4

347908.2

160650

3080
757
73920 97.648613
2587777
2601726.8
538200
6075612
30378.06
15.4
1972.6012987
9863.0064935

Rate analysis
Site:

0
Computer Code No. :

Location :
F1

Pune
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/FLOOR/VI/2


Description :

Dec 30, 99
14-08-06
per sqm

Grey Mosaic Tile Flooring of 25cm x 25cm

Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 25 cm x 25 cm

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2

Quantity

Labours :
a) for fixing & joint grouting
b) for polishing (including 3 coats)

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

0.16
0.03
1.05
0.01

Bags
Cum
Sqm
Bags

245.00
1060.00
150.00
150.00

39.20
31.80
157.50
1.50

1.00
1.00

Sqm
Sqm

32.00
20.00

32.00
20.00

0.00

0.00

TOTAL (A)

282.00
5.64
1.41
1.41

TOTAL (B)

290.46
43.57

TOTAL

334.03

0.00

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

334 /- Per

per sqm

Prepared by :
Name : _________________________________
Rate analysis

Sign: ________________

Site:

0
Computer Code No. :

Location :
F1

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/2


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Grey Mosaic Tile Flooring of 30x30

Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 30 cm x 30cm

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2

Quantity

Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

0.16
0.05
1.05
0.01

Bags
Cum
Sqm
Bags

245.00
1060.00
220.00
150.00

39.20
53.00
231.00
1.50

1.00

Sqm

32.00

32.00

1.00

Sqm

20.00

20.00

0.00

0.00

TOTAL (A)

376.70
7.53
1.88
1.88

TOTAL (B)

388.00
58.20

TOTAL

446.20

0.00

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

446 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F1

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/2


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

White Mosaic Tile Flooring of 25x25

Providing & laying mosaic tile flooring of 20 to 25 mm thk. & size 25x25cm of White colour in required
positions & set in a bed of 1:6 cement mortor including neat cement float, filling the joint with
appropriate coloured cement slurry, curing, polishing etc. complete

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2

Quantity

Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)

3
4

5
6
7

Centering & Shuttering


Nil
Others
Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

0.16
0.03
1.05
0.55

Bags
Cum
Sqm
Kg

245.00
1060.00
244.00
30.00

39.20
31.80
256.20
16.50

1.00

Sqm

32.00

32.00

1.00

Sqm

20.00

20.00

0.00

0.00

TOTAL (A)

395.70
7.91
1.98
1.98

TOTAL (B)

407.57
61.14

TOTAL

468.71

0.00

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

469 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F1

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/2


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

White Mosaic Tile Flooring of 30 x 30

Providing,laying and fixing marble mosaic tiles in white cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 30 cm x 30 cm

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile ( as approved)
d) White/ coloured cement
2

Quantity

Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Rate per

Amount

0.16
0.05
1.05
0.55

Bags
Cum
Sqm
Kg

245.00
1060.00
350.00
30.00

39.20
53.00
367.50
16.50

1.00

Sqm

32.00

32.00

1.00

Sqm

20.00

20.00

0.00

0.00

TOTAL (A)

528.20
10.56
2.64
2.64

TOTAL (B)

544.05
81.61

TOTAL

625.65

0.00

2.00%
0.50%
0.50%

15.00%

Say Rs.
Prepared by :

Unit

on total (A)
on total (A)
on total (A)

on total (B)

626 /- Per

per sqm

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F2

Pune
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/FLOOR/VI/22


Description :

Dec 30, 99
14-08-06
per rmt

Grey Mosaic Tile Skirting of 125 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing filling the joints with cement slurry, polishing, cleaning complete - gray
mosaic tile skirting 125 mm high

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile skirting(as
approved)

Quantity

Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)

3
4

5
6
7

Centering & Shuttering


Nil
Others
Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

0.02
0.01

Bags
Cum.

1.05

Rate per

Amount

245.00
1060.00

4.90
10.60

rmt

23.00

24.15

1.00

rmt

10.00

10.00

1.00

rmt

9.00

9.00

0.00

0.00

TOTAL (A)

58.65
1.17
0.29
0.29

TOTAL (B)

60.41
9.06

TOTAL

69.47

0.00

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

69 /- Per

Say Rs.

per rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F2

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/23


Description :

Unit :

Dec 30, 99
14-08-06
per rmt

Grey Mosaic Tile Skirting of 150 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, polishing, cleaning, curing etc complete - gray mosaic tile skirting 150 mm
high

Sr.No.
Particulars
1 Materials :
a) Cement
b) Mosaic tile skirting(as
approved)
c) Mosaic tile skirting(as
approved)
2

Quantity

Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)

Centering & Shuttering


Nil

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Rate per

Amount

0.02

Bags

245.00

4.90

0.01

Cum

1060.00

10.60

1.05

rmt

32.00

33.60

1.00

rmt

10.00

10.00

1.00

rmt

9.00

9.00

0.00

0.00

TOTAL (A)

68.10
1.36
0.34
0.34

TOTAL (B)

70.14
10.52

0.00

Nil

5
6
7

Unit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL
Say Rs.

81 /- Per

80.66
per rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F2

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/24


Description :

Unit :

Dec 30, 99
14-08-06
per rmt

White Mosaic Tile Skirting of 125 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry,polishing, cleaning curing etc complete white mosaic tile skirting 125 mm high

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
b) Mosaic tile skirting(as
approved)
c) White/ coloured cement
2

Quantity

Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)

3
4

5
6
7

Centering & Shuttering


Nil
Others
Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

0.02
0.01

Bags
cum.

1.05
0.25

Rate per

Amount

245.00
1060.00

4.90
10.60

rmt
Kg

30.00
30.00

31.50
7.50

1.00

rmt

10.00

10.00

1.00

rmt

9.00

9.00

0.00

0.00

TOTAL (A)

73.50
1.47
0.37
0.37

TOTAL (B)

75.71
11.36

0.00

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

87 /- Per

87.06

per rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F2

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/25


Description :

Unit :

Dec 30, 99
14-08-06
per rmt

White Mosaic Tile Skirting of 150 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing,filling the joints with cement slurry, cleaning complete - white mosaic tile
skirting 150 mm high

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Mosaic tile skirting(as
approved)
d) White/ coloured cement
2

Quantity

Labours :
a) For fixing & joint grouting
b) for polishing (including 3 coats)

3
4

5
6
7

Centering & Shuttering


Nil
Others
Nil

Tools & Plants Charges


Water charges
Electricity Charges

Unit

0.02
0.01

Bags
Cum

1.05
0.25

Amount

245.00
1060.00

4.90
10.60

rmt
Kg

45.00
30.00

47.25
7.50

1.00

rmt

10.00

10.00

1.00

rmt

9.00

9.00

0.00

0.00

TOTAL (A)

89.25
1.79
0.45
0.45

TOTAL (B)

91.93

0.00

2.00%
0.50%
0.50%

Rate per

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

13.79
TOTAL

Say Rs.

106 /- Per

105.72

per rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F1

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/1


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

P/L IPS 50mm thk.

Provding and laying in position IPS flooring 50mm thick in proportion of 1:2:4 laid in proper line and
level including finishing the top surface with cement punning, curing, cleaning etc complete with all
labour and material.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal 12mm

3
4

5
6
7

Quantity

Labours :
a) for pouring
b) for finishing
c) for shuttering
Centering & Shuttering
Nil
Others
Nil

Tools & Plants Charges


Water charges
Electricity Charges

Unit

Amount

0.22
0.02
0.05

Bags
Cum
Cum

245.00
1060.00
340.00

53.90
23.85
15.30

1.00
1.00
1.00

Sqm
Sqm
Sqm

16.00
23.00
10.56

16.00
23.00
10.56

1.00

Sqm

4.00

4.00

0.00

0.00

TOTAL (A)

146.61
2.93
0.73
0.73

0.00

2.00%
0.50%
0.50%

Rate per

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

151.01
22.65

TOTAL

173.66

on total (B)

Say Rs.

174 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F3

Pune
Default Date :
Revised on Date :
Unit :

Item No. : 29
Description :

Dec 30, 99
14-08-06
per sqm

Ceramic Tile Flooring

Providing and laying ceramic tiles of approved quality of approved colour, size & thickness for flooring in
required position laid on a bed 30mm thk.in 1:6 cement mortor including cement float filling joints with
white/colour cement slurry cleaning curing etc. complete as shown in detailed drawing or as directed by
architect incharge.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tile (as approved)
d) white cement
2

Labours :
for flooring including fixing,
cleaning & curing etc. complete

Centering & Shuttering


Providing good Specified
material/
material / erection & dismantling

Others

Quantity

Unit

Rate per

Amount

0.16
0.05
1.05
0.55

Bags
Cum
Sqm
Kg

245.00
1060.00
380.00
30.00

39.20
53.00
399.00
16.50

1.00
0.00

Sqm

75.00
0.00

75.00
0.00

0.00

0.00

TOTAL (A)

582.70

0.00

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

15.00%

11.65
2.91
2.91
TOTAL (B)

600.18
90.03

TOTAL

690.21

on total (B)

690 /- Per

Say Rs.

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

Pune
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/FLOOR/VI/6


Description :

Dec 30, 99
14-08-06
per sqm

Marble Flooring

Providing, laying and fixing in position marble slabs for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand

3
4

Unit

Rate per

Amount

0.22
0.04

Bags
Cum

245.00
1060.00

53.90
42.40

d) White cement

1.05
0.22

Sqm
Kg

860.00
30.00

903.00
6.60

Labours :
a) for fixing & joint grouting
b) for polishing

1.00
1.00

Sqm
Sqm

100.00
129.00

100.00
129.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

1234.90

c) Marble (including 5% wastage)

Quantity

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

24.70
6.17
6.17
TOTAL (B)

1271.95
190.79

TOTAL

1462.74

1,463 /- Per

Say Rs.

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/35


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Marble Skirting

Providing and fixing in position dado of tiles / stone as per requirement, including fixing with C:M 1:4
backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete -marble stone

Sr.No.
Particulars
1 Materials :
a) Cement
b) Marble (including 10%
wastage)
c) White cement
d) Sand
2

3
4

5
6

Quantity

Unit

Rate per

Amount

0.22

Bags

245.00

53.90

1.10
1.00
0.01

Sqm
Kg
Cum

860.00
30.00
1060.00

946.00
30.00
10.60

Labours :
a) for fixing & joint grouting
b) for polishing

1.00
1.00

Sqm
Sqm

110.00
148.35

110.00
148.35

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

1298.85
25.98
6.49

Tools & Plants Charges


Water charges

2.00%
0.50%

on total (A)
on total (A)

Electricity Charges

Over head & Profit

0.50%

on total (A)

15.00%

6.49
TOTAL (B)

1337.82
200.67

TOTAL

1538.49

on total (B)

Costing per Sqm.

Say Rs.

154 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/7


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Kota Flooring

Providing, laying and fixing in required position machine cut machine polished Kotah stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Kota (including 5% wastage)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.22
0.04
1.05
0.35

Bags
Cum
Sqm
Kg

245.00
1060.00
290.52
30.00

53.90
42.40
305.05
10.50

Labours :
a) for fixing & polishing

1.00

Sqm

100.00

100.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

511.85
10.24
2.56
2.56

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

527.20
79.08

TOTAL

606.28

on total (B)

Say Rs.

606 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/27


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Kota Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, polishing, cleaning , curing etc complete
- kotah stone 100 mm height

Sr.No.
Particulars
1 Materials :
a) Cement
b) Kota (including 15% wastage)
c) White / coloured cement
d) Sand

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.34
1.15
1.10
0.01

Bags
Sqm
Kg
Cum

245.00
290.52
30.00
1060.00

83.30
334.10
33.00
10.60

Labours :
a) for fixing & polishing

1.00

Sqm

121.00

121.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

582.00
11.64
2.91
2.91

TOTAL (B)

599.46

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

599.46
89.92

TOTAL

689.38

on total (B)

Costing per sqm

Say Rs.

69 /- Per

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/9


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Tandoor Flooring

Providing, laying and fixing in required position machine cut machine polished Tandur stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Tandoor (including 5%
wastage)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.22
0.04

Bags
Cum

245.00
1060.00

53.90
42.40

1.05
0.35

Sqm
Kg

291.00
30.00

305.55
10.50

Labours :
a) for fixing & polishing

1.00

Sqm

86.00

86.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

498.35
9.97
2.49
2.49

TOTAL (B)

513.30

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

77.00
TOTAL

Say Rs.

590 /- Per

590.30

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/29


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt

Tandoor Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning , curing etc complete - tandur
stone 100 mm height

Sr.No.
Particulars
1 Materials :
a) Cement
b) Tandoor (including 15%
wastage)
c) White / coloured cement
d) Sand
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.34

Bags

245.00

83.30

1.15
0.35
0.01

Sqm
Kg
Cum

291.00
30.00
1060.00

334.65
10.50
10.60

Labours :
a) for fixing & polishing

1.00

Sqm

94.60

94.60

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

533.65
10.67
2.67
2.67

TOTAL (B)

549.66
82.45

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for each Sqm

TOTAL

Say Rs.

63 /- Per

632.11

per Rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/8


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Granite Flooring

Providing, laying and fixing in position granite stone for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand

Quantity

3
4

5
6
7

Rate per

Amount

0.22
0.04

Bags
Cum

245.00
1060.00

53.90
42.40

d) White / coloured cement

1.05
0.35

Sqm
Kg

1695.00
30.00

1779.75
10.50

Labours :
a) For fixing

1.00

Sqm

172.00

172.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

2058.55
41.17
10.29
10.29

TOTAL (B)

2120.31
318.05

c) Granite (including 5% wastage)

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

2,438 /- Per

2438.35

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/28


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Granite Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with white cement, cleaning, curing etc complete - granite
stone / tile 100 mm height

Sr.No.
Particulars
1 Materials :
a) Cement
b) Granite (including 15%
wastage)
c) White cement
d) Sand

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.34

Bags

245.00

83.30

1.15
0.35
0.01

Sqm
Kg
Cum

1695.00
30.00
1060.00

1949.25
10.50
10.60

Labours :
a) for fixing & polishing

1.00

Sqm

215.00

215.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

2268.65
45.37
11.34
11.34

TOTAL (B)

2336.71
350.51

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for each Ssqm

TOTAL

Say Rs.

269 /- Per

2687.22

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/11


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Rough Shahabad flooring

Providing, laying and fixing in required position machine cut rough shahabad stone flooring of required
size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement
float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Rough shahabad (including 5%
wastage)
d) White / coloured cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.22
0.04

Bags
Cum

245.00
1060.00

53.90
42.40

1.05
0.35

Sqm
Kg

75.00
3.00

78.75
1.05

Labours :
a) For fixing

1.00

Sqm

65.00

65.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

241.10
4.82
1.21
1.21

TOTAL (B)

248.33
37.25

TOTAL

285.58

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

286 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/10


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Polished Shahabad flooring

Providing, laying and fixing in required position machine cut machine polished shahabad stone flooring
of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Polished shahabad (including
5% wastege)
d) White / coloured cement
2

3
4

5
6
7

Quantity

Labours :
a) For fixing
Centering & Shuttering
Nil
Others
Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

0.22
0.04

Bags
Cum

245.00
1060.00

53.90
42.40

1.05
0.35

Sqm
Kg

110.00
30.00

115.50
10.50

1.00

Sqm

80.00

80.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

302.30
6.05
1.51
1.51

TOTAL (B)

311.37
46.71

0.00
0.00
0.00

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

358 /- Per

358.07

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/13


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Ceramic tiles flooring

Providing and fixing in position ceramic tile of various sizes such as 200 x 200 mm, 300 x 300 mm, 200
x 300 etc of approved make, color and shade on C:M 1:6 bedding including filling the joints with neat
cement slurry of matching colour, including cutting the tiles to required size, curing, cleaning etc
complete.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tiles(including 5%
wastage)
d) White / coloured cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.22
0.03

Bags
Cum

245.00
1060.00

53.90
34.45

1.05
0.25

Sqm
Kg

380.00
30.00

399.00
7.50

Labours :
a) For fixing

1.00

Sqm

75.00

75.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

569.85
11.40
2.85
2.85

TOTAL (B)

586.95
88.04

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

675 /- Per

674.99

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/13


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Ceramic tiles Dado

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete ceramic tiles of approved make and type and given height.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tiles(including 10%
wastage)
d) White / coloured cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.03

Bags
Cum

245.00
1060.00

68.60
26.50

1.10
0.30

Sqm
Kg

380.00
30.00

418.00
9.00

Labours :
a) For fixing

1.00

Sqm

90.00

90.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

612.10
12.24
3.06
3.06

TOTAL (B)

630.46
94.57

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

725 /- Per

725.03

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/33


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt

Ceramic tiles Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete ceramic tiles of approved make and type and colour 100 mm height

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Ceramic tiles(including 10%
wastege)
d) White / coloured cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.02

Bags
Cum

245.00
1060.00

68.60
15.90

1.07
1.00

Sqm
Kg

380.00
30.00

406.60
30.00

Labours :
a) For fixing

1.00

Sqm

80.00

80.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

601.10
12.02
3.01
3.01

TOTAL (B)

619.13
92.87

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing per Sqm.

TOTAL

Say Rs.

71 /- Per

712.00

per Rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/14


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Vitrified tiles flooring

Providing and fixing in position vitrified tile flooring of approved make,size and shade on bed of cement
mortar 1:6 in required line and level, filling the joints with white cement, cleaning etc complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Vetrified tiles(including 5%
wastage)
d) White / coloured cement
2

Quantity

Labours :
a) For fixing

Centering & Shuttering


Nil

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Rate per

Amount

0.20
0.03

Bags
Cum

245.00
1060.00

49.00
26.50

1.05
0.25

Sqm
Kg

800.00
30.00

840.00
7.50

1.00

Sqm

80.00

80.00

0.00

0.00

TOTAL (A)

1003.00
20.06
5.02
5.02

TOTAL (B)

1033.09
154.96

0.00

Nil

5
6
7

Unit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

1,188 /- Per

1188.05

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : 30
Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Vitrified tiles Dado

Providing and fixing in position vitrified tile flooring of approved make,size and shade in required line
and level, filling the joints with white cement, cleaning etc complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Vetrified tiles(including 10%
wastage)
d) White / coloured cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.02

Bags
Cum

245.00
1060.00

68.60
21.20

1.10
0.30

Sqm
Kg

800.00
0.00

880.00
0.00

Labours :
a) For fixing

1.00

Sqm

96.00

96.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

1065.80
21.32
5.33
5.33

TOTAL (B)

1097.77
164.67

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

1,262 /- Per

1262.44

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : 30
Description :

Unit :

Dec 30, 99
14-08-06
per Rmt.

Vitrified tiles Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete
-polished vitrified tile 100 mm height

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Vetrified tiles(including 10%
wastage)
d) White / coloured cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.02

Bags
Cum

245.00
1060.00

68.60
15.90

1.07
0.30

Sqm
Kg

800.00
30.00

856.00
9.00

Labours :
a) For fixing

1.00

Sqm

85.00

85.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

1034.50
20.69
5.17
5.17

TOTAL (B)

1065.54
159.83

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing per sqm

TOTAL

Say Rs.

1,225 /- Per

1225.37

per Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/16


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Designer tiles flooring

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade,
over bed of 1:6 mortar in proper line and level including finishing, compaction, filling joints cleaning etc
complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Designer tiles(including 5%
wastage)

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.18
0.04

Bags
Cum

245.00
1060.00

44.10
41.34

1.05

Sqm

430.40

451.92

Labours :
a) For fixing

1.00

Sqm

60.00

60.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

597.36
11.95
2.99
2.99

TOTAL (B)

615.28
92.29

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

708 /- Per

707.57

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/17


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Paving blocks flooring (regular)

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on
bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating
etc complete. ( of strength M20 - 65 mm thick)

Sr.No.
Particulars
1 Materials :

Quantity

a) Sand
b) Paver blocks (including 5%
wastege)
2

3
4

5
6
7

Unit

Rate per

Amount

0.05

Cum

1060.00

53.00

1.05

Sqm

242.10

254.21

Labours :
a) For fixing

1.00

Sqm

30.00

30.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

337.21
6.74
1.69
1.69

TOTAL (B)

347.32
52.10

TOTAL

399.42

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

399 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/18


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Paving blocks heavy duty (M40 & above)

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on
bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating
etc complete. ( of strength M40 - 65 mm thick)

Sr.No.
Particulars
1 Materials :

Quantity

a) Sand
b) Paver blocks (including 5%
wastage)

3
4

5
6
7

Unit

Rate per

Amount

0.05

Cum

1060.00

53.00

1.05

Sqm

386.00

405.30

Labours :
a) For fixing

1.00

Sqm

30.00

30.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

488.30
9.77
2.44
2.44

TOTAL (B)

502.95
75.44

TOTAL

578.39

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

578 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/19


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Chequered tiles flooring

Providing and laying chequered tiles in required position in proper line and level, on bed of C:M 1:6
including filling the joints with neat cement slurry, cleaning, curing etc complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Chequered tiles(including 5%
wastage)

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.21
0.04

Bags
Cum

245.00
1060.00

51.45
41.34

1.05

Sqm

102.00

107.10

Labours :
a) For fixing

1.00

Sqm

60.00

60.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

259.89
5.20
1.30
1.30

TOTAL (B)

267.69
40.15

TOTAL

307.84

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

308 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/42


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Kota for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing etc
complete -kotah stone

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Kota steps (including 5%
wastege)

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.04

Bags
Cum

245.00
620.00

68.60
24.80

1.05

Sqm

250.00

262.50

Labours :
a) for fixing & polishing

1.00

Sqm

400.00

400.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

755.90
15.12
3.78
3.78

TOTAL (B)

778.58
116.79

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

895 /- Per

895.36

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/40


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt

Marble for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing etc
complete -marble stone

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Marble steps (including 5%
wastage)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.04

Bags
Cum

245.00
1060.00

68.60
42.40

1.05
0.35

Sqm
Kg

1032.00
30.00

1083.60
10.50

Labours :
a) for fixing & polishing

1.00

Sqm

167.70

167.70

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

1372.80
27.46
6.86
6.86

TOTAL (B)

1413.98
212.10

TOTAL

1626.08

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit


Costing per sqm

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

163 /- Per

per Rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/41


Description :

Unit :

Dec 30, 99
14-08-06
per Rmt

Granite for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc
complete -granite stone of approved colour

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Granite steps (including 5%
wastage)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.04

Bags
Cum

245.00
1060.00

68.60
42.40

1.05
1.00

Sqm
Kg

2118.75
30.00

2224.69
30.00

Labours :
a) for fixing & polishing

1.00

Sqm

223.60

223.60

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

2589.29
51.79
12.95
12.95

TOTAL (B)

2666.97
400.04

TOTAL

3067.01

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit


Costing per sqm.

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

307 /- Per

per Rmt

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/43


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Tandoor for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing, curing etc
complete -tandur stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Tandoor steps (including 5%
wastage)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.22
0.04

Bags
Cum

245.00
1060.00

53.90
42.40

1.05
0.35

Sqm
Kg

378.30
30.00

397.22
10.50

Labours :
a) for fixing & polishing

1.00

Sqm

111.80

111.80

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

615.82
12.32
3.08
3.08

TOTAL (B)

634.29
95.14

TOTAL

729.43

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

costing per sqm.

Say Rs.

73 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/50

Unit :

Dec 30, 99
14-08-06
per sqm

Description :
Kota for sill & Jams
Providing and fixing in position window sills and jambs of stone as per requirement, including fixing with
C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing
etc complete -kotah stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Kota sill (including 10%
wastege)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.20
0.02

Bags
Cum

245.00
1060.00

49.00
21.20

1.10
1.00

Sqm
Kg

290.52
30.00

319.57
30.00

Labours :
a) for fixing & polishing

1.00

Sqm

132.00

132.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

551.77
11.04
2.76
2.76

TOTAL (B)

568.33
85.25

TOTAL

653.57

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

Say Rs.
Prepared by :

on total (A)
on total (A)
on total (A)

on total (B)

654 /- Per

per sqm

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/48

Unit :

Dec 30, 99
14-08-06
per sqm

Description :
Marble for Sills & jams
Providing and fixing in position window sills and jambs of stone as per requirement, including fixing with
C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing
etc complete -marble stone
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Marble sill (including 10%
wastage)
d) White cement

Quantity

Labours :
a) for fixing & polishing

Centering & Shuttering


Nil

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Amount

0.20
0.02

Bags
Cum

245.00
1060.00

49.00
21.20

1.10
1.00

Sqm
Kg

860.00
30.00

946.00
30.00

1.00

Sqm

132.00

132.00

0.00

0.00

TOTAL (A)

1178.20
23.56
5.89
5.89

TOTAL (B)

1213.55
182.03

TOTAL

1395.58

2.00%
0.50%
0.50%

15.00%

Say Rs.
Prepared by :

Rate per

0.00

Nil

5
6
7

Unit

on total (A)
on total (A)
on total (A)

on total (B)

1,396 /- Per

per sqm

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/49

Unit :

Dec 30, 99
14-08-06
per sqm

Description :
Granite for sills & Jams
Providing and fixing in position window sills and jambs stone as per requirement, including fixing with
C:M 1:4bedding, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc
complete -granite stone of approved colour
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Granite sill (including 10%
wastage)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.28
0.04

Bags
Cum

245.00
1060.00

68.60
42.40

1.10
1.00

Sqm
Kg

1695.00
30.00

1864.50
30.00

Labours :
a) for fixing & polishing

1.00

Sqm

258.00

258.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

2263.50
45.27
11.32
11.32

TOTAL (B)

2331.41
349.71

TOTAL

2681.12

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

2,681 /- Per

per sqm

Prepared by :
Name : _________________________________
Rate analysis

Sign: ________________

Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/51

Unit :

Dec 30, 99
14-08-06
per sqm

Description :
Tandoor for sills & jams
Providing and fixing in position window sills and jambs of stone as per requirement, including fixing
with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing,
curing etc complete -tandur stone

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Tandoor sill (including 10%
wastege)
d) White cement
2

Quantity

Labours :
a) for fixing & polishing

Centering & Shuttering


Nil

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Rate per

Amount

0.20
0.02

Bags
Cum

245.00
1060.00

49.00
21.20

1.10
0.35

Sqm
Kg

291.00
30.00

320.10
10.50

1.00

Sqm

113.52

113.52

0.00

0.00

TOTAL (A)

514.32
10.29
2.57
2.57

TOTAL (B)

529.75
79.46

TOTAL

609.21

0.00

Nil

5
6
7

Unit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

609 /- Per

per sqm

Prepared by :
Name : _________________________________
Rate analysis

Sign: ________________

Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/56

Unit :

Dec 30, 99
14-08-06
Rmt.

Description :
Granite Kitchen otta
Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top
Sr.No.
Particulars
Quantity
Considering the size of 3.0m x.75m
1 Materials :
a) Cement
2.55
b) Sand
0.03
c) Granite (including 10%
wastage)
3.71
d) Kaddappa (with 10% wastage)
e) White / colour cement
2

Unit

Rate per

Amount

Bags
Cum

245.00
1060.00

624.75
31.80

Sqm

1695.00

6293.54

3.82
0.35

Sqm
Kg

220.00
30.00

840.40
10.50

2.25

Sqm

1506.00

3388.50

4.42

Rmt.

246.00

1087.32

1.00

No.

400.00

400.00

0.00

0.00

TOTAL (A)

12676.81
253.54
63.38
63.38

TOTAL (B)

13057.11
1958.57

TOTAL

15015.68

Labours :
a) for fixing of Kadappa & granite
(considering labour rate @ 105/per rft length I.e = 105/- per 0.75
sft. Rate per sqm =
(105/.75)*10.76 = Rs. 1506
b) For moulding & edge polishing
c) For Cutout making for sink
fixing

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Total costing for 3 Rmt.


Say Rs.

5,005 /- Per

Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/57

Unit :

Dec 30, 99
14-08-06
Rmt.

Description :
Marble Kitchen otta
Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top- Marble stone
Sr.No.
Particulars
Quantity
Considering the size of 3.0m x.75m
1 Materials :
a) Cement
2.55
b) Sand
0.03
c) Marble (including 10%
wastage)
3.71
d) Kaddappa (with 10% wastage)
e) White / colour cement
2

Unit

Rate per

Amount

Bags
Cum

245.00
1060.00

624.75
31.80

Sqm

860.00

3193.18

3.82
0.35

Sqm
Kg

220.00
30.00

840.40
10.50

2.25

Sqm

1147.00

2580.75

4.57

Rmt.

196.80

900.00

1.00

No.

400.00

400.00

0.00

0.00

TOTAL (A)

8581.38
171.63
42.91
42.91

TOTAL (B)

8838.82
1325.82
10164.64

Labours :
a) for fixing of Kadappa & Marble
(considering labour rate @ 80/per rft length I.e = 80/- per 0.75
sft. Rate per sqm = (80/.75)*10.76
= Rs. 1147
b) For edge polishing
c) For Cutout making for sink
fixing

Others
Nil

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit


Total costing for 3 Rmt.

0.00

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)
TOTAL

Say Rs.

3,388 /- Per

Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/58

Unit :

Dec 30, 99
14-08-06
Rmt.

Description :
Kadappa Kitchen otta
Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top- Kadappa stone
Sr.No.
Particulars
Quantity
Considering the size of 3.0m x.75m
1 Materials :
a) Cement
2.55
b) Sand
0.03
c) Top & shelf kadappa (including
10% wastage)
3.80
d) Kaddappa Verticals & Facia
(with 10% wastage)
1.60
e) White / colour cement
0.35
2

Labours :
a) for fixing of Kadappa

Unit

Rate per

Amount

Bags
Cum

245.00
1060.00

624.75
31.80

Sqm

258.00

980.40

Sqm
Kg

220.00
30.00

352.00
10.50

2.25

Sqm

860.00

1935.00

4.57

Rmt.

82.00

375.00

1.00

No.

250.00

250.00

0.00

0.00

TOTAL (A)

4559.45
91.19
22.80
22.80

TOTAL (B)

4696.23
704.44

TOTAL

5400.67

(considering labour rate @ 60/per rft length I.e = 60/- per 0.75
sft. Rate per sqm = (60/.75)*10.76
= Rs. 717
b) For moulding & edge polishing
c) For Cutout making for sink
fixing
3

Others
Nil

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Total costing for 3 Rmt.


Say Rs.
Prepared by :

1,800 /- Per

Rmt.

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
F4

0
Default Date :
Revised on Date :

Item No. : FDAPL/FLOOR/VI/43


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Designer tiles for steps

Providing and fixing in position treads and risers of designer tiles as per requirement, including fixing
with C:M 1:4 backing, filling the joints with cement slurry, cleaning, etc complete -

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Designer Tiles (including 5%
wastage)
d) White cement
2

3
4

5
6
7

Quantity

Unit

Rate per

Amount

0.22
0.04

Bags
Cum

240.00
620.00

52.80
24.80

1.05
0.35

Sqm
Kg

780.00
30.00

819.00
10.50

Labours :
a) for fixing & polishing

1.00

Sqm

300.00

300.00

Centering & Shuttering


Nil
Others
Nil

0.00

0.00

0.00

TOTAL (A)

1207.10
-36.21
-6.04
-6.04

TOTAL (B)

1158.82
173.82

TOTAL

1332.64

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

-3.00%
-0.50%
-0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

costing per sqm.

Say Rs.

1,333 /- Per

per sqm

Rs 320/- per step

Prepared by :
Name : _________________________________

Sign: ________________

0.2 mason
0.5 labour

0.01

0.344
0.86
137.6

0.2
0.5
0.2
0.35

40
28
68

0.2
0.5

40
40

0.2
0.4

40
32

0.25
0.45
90

50
36

0.15
0.3

30
24

0.4
0.8

80
64
144
158.4
65.20

0.9
0.45

180
36

Rate analysis
Site:

0
Computer Code No. :

Location :
B1

Pune
Default Date :
Revised on Date :

Item No. : FDAPL/MAS/IV/2


Description :

Unit :

Dec 30, 99
14-08-06
per cum

UCR In plinth

Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation steps, platforms etc.below
plinth including curing , weepholes if required, including specials such as corners, quions, headers, through
stones etc. dewatering if required, racking out joints 10 mm deep etc. complete.

Sr.No.
Particulars
1 Materials :
a) Rubble
b) Cement
c) Sand

Quantity

Labours :
for U.C.R. masonry works

Centering & Shuttering


Nil

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

1.25
1.57
0.40

cum
Bags
cum

500.00
240.00
1060.00

625.00
376.80
424.00

1.00

cum

250.00

250.00

0.00

0.00

TOTAL (A)

1675.80
33.52
8.38
8.38

TOTAL (B)

1726.07
258.91

TOTAL

1984.99

0.00

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

1,985 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
B1

0
Default Date :
Revised on Date :

Item No. : FDAPL/MAS/IV/3


Description :

Unit :

14-08-06
per cum

Uncoursed rubble masonry in superstructure

Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation for compound wall, steps,
pillars , platforms etc. and wherever required including scaffolding, curing , weepholes if required, including
specials such as corners, quions, headers through stones etc. dewatering if required, racking out joints 10
mm deep etc. complete.

Sr.No.
Particulars
1 Materials :
a) Rubble
b) Cement
c) Sand

Quantity

Labours :
for U.C.R. masonry works

Centering & Shuttering


Nil

Others
Scaffolding

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

Unit

Rate per

Amount

1.25
1.57
0.40

cum
Bags
cum

500.00
245.00
1060.00

625.00
384.65
424.00

1.00

cum

252.00

252.00

1.00

Cum

20.00

20.00

TOTAL (A)

1705.65
34.11
8.53
8.53

TOTAL (B)

1756.82

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

263.52
TOTAL

Say Rs.

2,020 /- Per

2020.34

per cum

Rate analysis
Site:

0
Computer Code No. :

Location :
B1

0
Default Date :
Revised on Date :

Item No. : FDAPL/MAS/IV/1


Description :

Unit :

14-08-06
per cum

Brick masonary 35cm thk. Below plinth

Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in plinth for
steps, or any where as required including racking out joints 1.5 cm deep including scaffolding, curing etc.
complete.

Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand

Quantity

Centering & Shuttering


Nil

Others

Tools & Plants Charges


Water charges
Electricity Charges

Amount

Nos.
Bags
cum

2.25
245.00
1060.00

1125.00
416.50
275.60

1.00

cum

164.00

164.00

0.00

0.00

TOTAL (A)

1981.10
39.62
9.91
0.00

TOTAL (B)

2030.63

Nil

5
6
7

Rate per

500.00
1.70
0.26

Labours :
for brick masonry works

Unit

0.00

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

2030.63
304.59

TOTAL

2335.22

on total (B)

Say Rs.

2,335 /- Per

per cum

Rate analysis
Site:

0
Computer Code No. :

Location :
B1

0
Default Date :
Revised on Date :

Item No. : FDAPL/MAS/IV/4


Description :

Unit :

Dec 30, 99
14-08-06
per cum

Brick work 35cm thk. In superstructure

Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in
superstructure at all levels wherever required including raking out joints 1.5 cm deep including scaffolding,
curing etc. complete.

Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand

Labours :
for brick masonry works

Centering & Shuttering


Nil

Others
Add for scaffolding & sand screening
etc.

Quantity

Unit

Rate per

Amount

500.00
1.70
0.30

Nos.
Bags
cum

2.25
245.00
1060.00

1125.00
416.50
318.00

1.00

cum

164.00

164.00

1.00

cum

45.60

45.60

TOTAL (A)

2069.10

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

15.00%

41.38
10.35
0.00
TOTAL (B)

2120.83
318.12

TOTAL

2438.95

on total (B)

Say Rs.

2,439 /- Per

per cum

Rate analysis
Site:

0
Computer Code No. :

Location :
B2

Pune
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/MAS/IV/5


Description :

Dec 30, 99
14-08-06
per cum

Plinth Masonry 23cm thk

Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls,etc below plinth wherever required
including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand

Labours :
for Brick masonry works

Quantity

Unit

Rate per

Amount

500.00
0.90
0.05

No
Bags
cum

3.00
210.00
850.00

1500.00
189.00
42.50

1.00

sqm

38.00

38.00

0.00

0.00

Others
Nil

0.00

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

Say Rs.

TOTAL (A)

1769.50
35.39
8.85
0.00

TOTAL (B)

1813.74
272.06

TOTAL

2085.80

2,086 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
B2

0
Default Date :
Revised on Date :

Item No. : FDAPL/MAS/IV/6


Description :

Unit :

Dec 30, 99
14-08-06
per cum

BBM 23cm thk in superstructure

Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls in superstructure at all levers
wherever required including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand

Labours :
for Brick masonry works

Quantity

Unit

Rate per

Amount

500.00
0.90
0.05

No
Bags
cum

3.00
245.00
1060.00

1500.00
220.50
53.00

1.00

sqm

42.00

42.00

5
6
7

Others
Scaffolding / sand screening etc.

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

2.00%
0.50%
0.00%

sqm.

9.80

9.80

TOTAL (A)

1825.30
36.51
9.13
0.00

TOTAL (B)

1870.93
280.64

TOTAL

2151.57

on total (A)
on total (A)
on total (A)

15.00%

on total (B)

Say Rs.

2,152 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
B3

Pune
Default Date :
Revised on Date :

Item No. : FDAPL/MAS/IV/8


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

P/F 15cm thk. Brick Wall (C.M. 1:4)

Providing & constructing 6" thk, brick masonry using 'Thoklas' bricks in C.M. 1:4, at all levels wherever
required including raking out joints, scaffolding, curing etc,. All complete.

Sr.No.
Particulars
1 Materials :
a) Thokla Bricks (15cm thk.)

Quantity
48.00

Unit
No

Rate per
4.00

Amount
192.00

b) Cement
c) Sand

0.26
0.04

Bags
Cum

245.00
1060.00

63.70
42.40

Labours :
for Brick masonry works

1.00

Sqm

46.00

46.00

8.23

0.00

TOTAL (A)

344.10
6.88
1.72
0.00

TOTAL (B)

352.70
52.91

TOTAL

405.61

Centering & Shuttering


Nil

Others
Scaffolding / sand screening etc.

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

406 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
B4

Pune
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/MAS/IV/7


Description :

Dec 30, 99
14-08-06
per sqm

P/F 10cm thk. Brick Wall (C.M. 1:4)

Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick 1:2:4
p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking out
joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete mullion
with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete and
reinforcement will be paid in items of Columns and reinforcement respectively)

Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick 1:2:4
p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking out
joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete mullion
with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete and
reinforcement will be paid in items of Columns and reinforcement respectively)

Sr.No.
Particulars
1 Materials :
a) Bricks
b) Cement
c) Sand

Quantity

Centering & Shuttering


Nil

Others
Scaffolding / sand screening etc.

Rate per

Amount

58.00
0.17
0.03

No
Bags
Cum

3.00
245.00
1060.00

174.00
41.65
26.50

1.00

Sqm

41.50

41.50

1.00

Sqm.

7.70

7.70

TOTAL (A)

291.35
5.83
1.46
0.00

TOTAL (B)

298.63
44.80

TOTAL

343.43

Labours :
for Brick masonry works

Unit

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

Say Rs.

343 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
B1

0
Default Date :
Revised on Date :

Item No. : FDAPL/MAS/IV/9


Description :

Unit :
Coursed rubble masonary

Dec 30, 99
14-08-06
per cum

Providing & constructing coursed rubble masonry II sort in cement mortar 1:6 for foundation steps, platforms
etc.at all required levels including curing, scaffolding if required, weepholes if required, including specials
such as corners, quions, headers through stones etc. dewatering if required, raking out joints 10 mm deep
etc. complete.

Sr.No.
Particulars
1 Materials :
a) Rubble
b) Cement
c) Sand

Labours :
For coursed rubble masonary

Centering & Shuttering


Nil

Others
Scaffolding & sand screening

5
6
7

Quantity

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

1.25
1.75
0.31

cum
Bags
cum

500.00
245.00
1060.00

625.00
428.75
332.84

1.00

cum

253.22

253.22

1.00

Cum.

29.71

29.71

TOTAL (A)

1669.53
33.39
8.35
0.00

TOTAL (B)

1711.27
256.69

TOTAL

1967.96

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

1,968 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:
Computer Code No. :

Location :
B5

Default Date :

Revised on Date :
Item No. : FDAPL/MAS/IV/11
Description :

Unit :

14-08-06
per sqm

150mm thk. C.C. Solid block masonry

Providing & constructing 150 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..

Sr.No.
Particulars
1 Materials :
a) Concrete blocks
b) Cement
c) Sand

Centering & Shuttering


Nil

Others
Scaffolding / sand screening etc.

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

18.00
0.15
0.04

No
Bags
Cum

16.00
245.00
1060.00

288.00
36.02
42.40

1.00

Sqm

8.23

8.23

1.00

Job

8.23

8.23

TOTAL (A)

382.88
7.66
1.91
0.00

TOTAL (B)

392.45
58.87

TOTAL

451.31

Labours :
for C.C.block masonry works

5
6
7

Quantity

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

451 /- Per

per sqm

Prepared by :
Name : _________________________________
Rate analysis

Sign: ________________

Site:

0
Computer Code No. :

Location :
B5

Pune
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/MAS/IV/12


Description :

Dec 30, 99
14-08-06
per sqm

200mm thk. C.C. Solid block masonry

Providing & constructing 200 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..

Sr.No.
Particulars
1 Materials :
a) Concrete blocks
b) Cement
c) Sand

Quantity

Centering & Shuttering


Nil

Others
Scaffolding / sand screening etc.

Rate per

Amount

12.00
0.11
0.05

No
Bags
Cum

34.00
245.00
1060.00

408.00
26.95
53.00

1.00

Sqm

25.30

25.30

1.00
0.00

Job

8.76
0.00

8.76
0.00

TOTAL (A)

522.01
10.44
2.61
0.00

TOTAL (B)

535.06
80.26

TOTAL

615.32

Labours :
for C.C.block masonry works

Unit

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

Say Rs.

615 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:
Computer Code No. :

Location :
B5

Default Date :
Revised on Date :

Item No. : 22 /
Description :

Unit :

14-08-06
per sqm

100mm thk. Siporex block masonry

Providing 100mm thk siporex blocks of size 0.1 x 0.1 x 0.2 with c.m. 1:6,in super structure including striking
joints, taking out joints and scaffolding, curing etc. complete.

Sr.No.
Particulars
1 Materials :
a)Siporex blocks
b) Cement
c) Sand

Centering & Shuttering


Nil

Others
Scaffolding / sand screening etc.

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

24.00
0.15
0.04

No
Bags
Cum

60.00
245.00
1060.00

1440.00
36.02
42.40

1.00

Sqm

25.30

25.30

1.00

Sqm

7.70

7.70

TOTAL (A)

1551.42
31.03
7.76
0.00

TOTAL (B)

1590.20
238.53

TOTAL

1828.73

Labours :
for 100mm Siporex block masonry
works

5
6
7

Quantity

2.00%
0.50%
0.00%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

1,829 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

Err:509
Computer Code No. :

Location :
B5

Err:509
Default Date :
Revised on Date :

Item No. : 22 /
Description :

Unit :

Err:509
14-08-06
per sqm

150mm thk. Siporex block masonry

Providing 150mm thk siporex blocks of size 0.15 x 0.15 x 0.3 with c.m. 1:6,in super structure including
striking joints, taking out joints and scaffolding, curing etc. complete.

Sr.No.
Particulars
1 Materials :
a)Siporex blocks
b) Cement
c) Sand

Labours :
for 100mm Siporex block masonry
works

Centering & Shuttering


Nil

Others
Scaffolding / sand screening etc.

5
6

Quantity

Tools & Plants Charges


Water charges

2.00%
0.50%

Unit

Rate per

Amount

24.00
0.15
0.04
0.00
0.00
0.00

No
Bags
Cum

0.00
245.00
1060.00
0.00
0.00
0.00

0.00
36.02
42.40
0.00
0.00
0.00

1.00

Sqm

28.06

28.06

1.00

Sqm

8.23

8.23

TOTAL (A)

114.71
2.29
0.57

on total (A)
on total (A)

Electricity Charges

Over head & Profit

0.00%

on total (A)

15.00%

0.00
TOTAL (B)

117.57
17.64

TOTAL

135.21

on total (B)

Say Rs.

135 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
B5

0
Default Date :
Revised on Date :

Item No. : 22 / III 7


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

200mm thk. Siporex block masonry

Providing 200mm thk Siporex blocks of size 0.2x0.2x0.4 with c.m. 1:6,in super structure including striking
joints, taking out joints and scaffolding, curing etc. complete.

Sr.No.
Particulars
1 Materials :
a)Siporex blocks
b) Cement
c) Sand

Labours :
for 100mm Siporex block masonry
works

Centering & Shuttering


Nil

Quantity

Unit

Rate per

Amount

13.00
0.11
0.05

No
Bags
Cum

0.00
245.00
1060.00

0.00
26.95
53.00

1.00

Sqm

28.06

28.06

5
6
7

Others
Scaffolding / sand screening etc.

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

2.00%
0.50%
0.00%

15.00%

Say Rs.

Sqm

8.76

8.76

TOTAL (A)

116.77
2.34
0.58
0.00

TOTAL (B)

119.69
17.95

TOTAL

137.64

on total (A)
on total (A)
on total (A)

on total (B)

138 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

2.6315789
#REF!

0.304
1.7024

0.304
0.0608
1.7024
0.391552
0.04864 0.051072

WELCOME TO RATE ANALYSIS


Enter the data in yellow cells.
a) Site Name :

Location : Pune

b) Default date :

Revision on date :

c)
For MKS system click

MKS

For FPS system click

d) Tools & Plants & fixed Charges :

5.00%

e) Water Charges :

1.00%

f) Electricity Charges :

1.00%

g) PROFIT ( Over heads+ Profit) :

Instructions
Enter Data

10.00%

(Over head)

5.00%
( Profit )

Uneditable text
Clickable links

FPS

=
=

15.00%
(TOTAL)

Rate analysis
Site:

0
Computer Code No. :

Location :
C1

Item No. : FDAPL/PCC/II/3


Description :

Pune
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

P.C.C. (1 :2:4 )

Providing & laying PCC 1:2:4 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1.5")
d) Metal ( 3/4)"
2

5
6
7

Quantity

Labours :
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Errection & dismantling
Others
Mixer & Vibrator

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

6.20
0.47
0.48
0.48

Bags
cum
cum
cum

245.00
1060.00
575.00
500.00

1519.00
498.20
276.00
240.00

1.00
1.00
1.00

cum
cum
cum

120.00
7.50
57.50

120.00
7.50
57.50

1.00

cum

80.00

80.00

1.00

cum

25.00

25.00

TOTAL (A)

2823.20
56.46
0.28
0.00

TOTAL (B)

2879.95
431.99

TOTAL

3311.94

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

3,312 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C1

Item No. : FDAPL/PCC/II/1


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

P.C.C. (1 : 5 : 10 )

Providing & laying PCC 1:5:10 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1.5")
d) Metal ( 3/4)"

5
6
7

Quantity

Labours :
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Errection & dismantling
Others
Mixer & Vibrator

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

Unit

Rate per

Amount

2.74
0.49
0.48
0.48

Bags
cum
cum
cum

245.00
1060.00
575.00
500.00

671.30
519.40
276.00
240.00

1.00
1.00
1.00

cum
cum
cum

120.00
7.50
57.50

120.00
7.50
57.50

1.00

cum

80.00

80.00

1.00

cum

24.75

24.75

TOTAL (A)

1996.45
39.93
0.20
0.00

TOTAL (B)

2036.58

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

2036.58
305.49

TOTAL

2342.07

on total (B)

Say Rs.

2,342 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C2

Item No. : FDAPL/PCC/II/2


Description :

Pune
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

P.C.C. (1 : 4: 8 )

Providing & laying PCC 1:4:8 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1")
d) Metal ( 3/4)"
2

Labours :
for
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
erection & dismantling

4
Others

Quantity

Unit

Rate per

Amount

3.40
0.48
0.48
0.48

Bags
cum
cum
cum

245.00
1060.00
575.00
500.00

833.00
508.80
276.00
240.00

1.00
1.00
1.00

cum
cum
cum

120.00
7.50
57.50

120.00
7.50
57.50

1.00

cum

80.00

80.00

Mixer & Vibrator

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

2.00%
0.50%
0.50%

cum

24.75

24.75

TOTAL (A)

2147.55
42.95
10.74
10.74

TOTAL (B)

2211.98
331.80

TOTAL

2543.77

on total (A)
on total (A)
on total (A)

15.00%

Say Rs.

on total (B)

2,544 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C2

Item No. : FDAPL/PCC/II/6


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

Plum concrete with P.C.C. (1 : 4: 8 )

Providing and laying plum concrete of 1:4:8 mix using stone of size not more than 230 mm in size and
proportion of plum to concrete @ 35:65 including curing, formwork if required, etc complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal (1.5")
d) Metal ( 1)"
e) Rubble
2

Labours :
for
a)Mixing & Pouring
b)Levelling & finishing
c) Shuttering

Quantity

Unit

Rate per

Amount

2.21
0.31
0.31
0.31
0.46

Bags
cum
cum
cum
cum

240.00
1060.00
575.00
500.00
500.00

530.40
330.72
179.40
156.00
227.50

1.00
1.00
1.00

cum
cum
cum

275.00
7.50
57.50

275.00
7.50
57.50

Centering & Shuttering


Providing good Specified material/
erection & dismantling

1.00

cum

80.00

80.00

1.00

cum

24.75

24.75

TOTAL (A)

1868.77
37.38
9.34
9.34

TOTAL (B)

1924.83
288.72

TOTAL

2213.56

4
Others
Mixer & Vibrator

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

15.00%

Say Rs.

on total (B)

2,214 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C4

Item No. : FDAPL/RCC/III/1


Description :

Pune
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

C.C. M20 for Footing, raft

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"

Quantity
7.77
0.45
0.60
0.25

Unit
Bags
cum
cum
cum

Rate per
210.00
850.00
500.00
340.00

Amount
1631.70
382.50
300.00
85.00

5
6
7

Labours :
a) Mixing & Pouring (concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material
for erection & dismantling
Others
Mixer & Vibrator

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00
1.00
1.00

cum
cum
cum

107.20
16.50
86.25

107.20
16.50
86.25

1.00

cum

136.20

136.20

1.00

cum

24.75

24.75

TOTAL (A)

2770.10
55.40
13.85
13.85

TOTAL (B)

2853.20
427.98

TOTAL

3281.18

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

3,281 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:
Computer Code No. :
Item No. : FDAPL/RCC/III/2
Description :

Location :
C6

Default Date :
Revised on Date :
Unit :

14-08-06
per cum

C.C. M20 for Columns below plinth

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Columns upto plinth

steel/tor steel reinforcement) .---For Columns upto plinth

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

144.00
0.00
287.50

144.00
0.00
287.50

1.00

cum

820.00

820.00

1.00

cum

24.75

24.75

TOTAL (A)

4041.90
80.84
20.21
20.21

TOTAL (B)

4163.16
624.47

TOTAL

4787.63

Fixing & removing


4

5
6
7

Others
Mixer & Vibrator

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

4,788 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/RCC/III/3

Location :
C6

Pune
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

Description :

C.C. M20 for superstructure Columns

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Columns at all levels

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
erection & dismantling
Others
Mixer & Vibrator

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

176.00
0.00
359.38

176.00
0.00
359.38

1.00

cum

1040.00

1040.00

1.00

cum

24.75

24.75

TOTAL (A)

4365.78
87.32
21.83
21.83

TOTAL (B)

4496.75
674.51

TOTAL

5171.26

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

5,171 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

Location :

Pune

Computer Code No. :

Default Date :
Revised on Date :
Unit :

C8

Item No. : FDAPL/RCC/III/5


Description :

14-08-06
per cum

C.C. M20 for floor Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Floor beams

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b) Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

176.00
15.00
480.13

176.00
15.00
480.13

1.00

cum

992.25

992.25

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

4471.53
89.43
22.36
22.36

TOTAL (B)

4605.67
690.85

TOTAL

5296.52

2.00%
0.50%
0.50%

15.00%

Say Rs.
Prepared by :

Unit

on total (A)
on total (A)
on total (A)

on total (B)

5,297 /- Per

per cum

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C10

Item No. : FDAPL/RCC/III/9


Description :

Pune
Default Date :
Revised on Date :
Unit :

14-08-06
per cum

C.C. M20 for slab

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Floor slabs

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

6.80
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1666.00
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

160.00
15.00
310.50

160.00
15.00
310.50

1.00

cum

682.50

682.50

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

3738.50
74.77
18.69
18.69

TOTAL (B)

3850.66
577.60

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

4,428 /- Per

4428.25

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C11

Item No. : FDAPL/RCC/III/19


Description :

Pune
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

C.C. M20 for Staircase

Providing & casting M 200 for RCC staircase upto 17 cm riser 30 cm tread & 20 cm th waist slab but
excluding parapet as per detailed drawing & design at all levels with all leads & lift or as directed
including formwork, centering, scaffolding, machine mixing, & mixing , laying, levelling, vibrating and
finishing rough and broken surfaces with C.M. 1:2 including curing etc. complete (excluding steel
reinforcement)

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges

2.00%

Unit

Rate per

Amount

7.77
0.60
0.65
0.20

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
636.00
325.00
68.00

1.00
1.00
1.00
0.00

cum
cum
cum

190.00
17.50
621.00
0.00

190.00
17.50
621.00
0.00

1.00

cum

800.00

800.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

4603.65
92.07

on total (A)

6
7

Water charges
Electricity Charges

Over head & Profit

0.50%
0.50%

on total (A)
on total (A)

15.00%

23.02
0.00
TOTAL (B)

4718.74
707.81

TOTAL

5426.55

on total (B)

Say Rs.

5,427 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :

Item No. : FDAPL/RCC/III/17


Description :

Pune
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

RCC M20 for Pardi, fins

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For pardis,parapets and fins

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator

Quantity

Unit

Rate per

Amount

7.77
0.60
0.65
0.20

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
636.00
325.00
68.00

1.00
1.00
1.00
0.00
0.00
0.00
1.00

cum
cum
cum

cum

225.00
7.50
575.00
0.00
0.00
0.00
1520.00

225.00
7.50
575.00
0.00
0.00
0.00
1520.00

1.00

cum

24.75

24.75

Lifts

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

2.00%
0.50%
0.50%

cum

17.75

17.75

TOTAL (A)

5302.65
106.05
26.51
26.51325

TOTAL (B)

5461.73
819.26

TOTAL

6280.99

on total (A)
on total (A)
on total (A)

15.00%

Say Rs.

on total (B)

6,281 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C8

Item No. : FDAPL/RCC/III/4


Description :

0
Default Date :
Revised on Date :
Unit :

14-08-06
per cum

C.C. M20 for Plinth Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Plinth beams

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

Labours :
a) Mixing & Pouring (Concreting)

Quantity

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00

cum

176.00

176.00

5
6
7

b)Levelling & finishing


c) Shuttering

1.00
1.00

cum
cum

10.50
359.38

10.50
359.38

Centering & Shuttering


Providing good Specified material/
erection & dismantling

1.00

cum

750.00

750.00

1.00

cum

24.75

24.75

TOTAL (A)

4086.28
81.73
20.43
20.43

TOTAL (B)

4208.86
631.33

TOTAL

4840.19

Others
Mixer & Vibrator

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

15.00%

Say Rs.

on total (B)

4,840 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C8

Item No. : FDAPL/RCC/III/7&16


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 31, 99
per cum

C.C. M20 for lintels & chajjas

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For lintels & chajja

Sr.No.
Particulars
1 Materials :
a) Cement

Quantity
7.77

Unit
Bags

Rate per
245.00

Amount
1903.65

5
6
7

b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"

0.45
0.60
0.25

cum
cum
cum

1060.00
500.00
340.00

477.00
300.00
85.00

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

1.00
1.00
1.00

cum
cum
cum

240.00
10.50
575.00

240.00
10.50
575.00

1.00

cum

996.00

996.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

4629.65
92.59
23.15
23.15

TOTAL (B)

4768.54
715.28

TOTAL

5483.82

Centering & Shuttering


Providing good Specified material/
erection & dismantling
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

5,484 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/RCC/III/6
Description :

Location :
C8

0
Default Date :
Revised on Date :
Unit :

14-08-06
per cum

C.C. M20 for grid Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Grid beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Grid beams

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

240.00
10.50
575.00

240.00
10.50
575.00

1.00

cum

1344.00

1344.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

4977.65
99.55
24.89
24.89

TOTAL (B)

5126.98
769.05

TOTAL

5896.03

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

5,896 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

Location :

Computer Code No. :

Default Date :
Revised on Date :
Unit :

C8

Item No. : FDAPL/RCC/III/8


Description :

14-08-06
per cum

C.C. M20 for RCC walls

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For lift & Basement walls

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

176.00
0.00
460.00

176.00
0.00
460.00

1.00

cum

776.00

776.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

4220.15
84.40
21.10
21.10

TOTAL (B)

4346.75
652.01

TOTAL

4998.77

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

4,999 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C11

Item No. : FDAPL/RCC/III/15


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

M20 for folded Steps upto 150mm thk.

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For folded staircase slabs

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

240.00
37.50
931.50

240.00
37.50
931.50

1.00

cum

1224.00

1224.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

5241.15
104.82
26.21
26.21

TOTAL (B)

5398.38
809.76

TOTAL

6208.14

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

6,208 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C11

Item No. : FDAPL/RCC/III/28


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
Rmt.

P/F PVC sleeves 40mm dia. in concrete

Providing & fixing in corrent position.line, level 40 mm dia Finolex or equivalent PVC pipe in RCC
members such as columns, beams, slabs, paradi, chajjas etc. including fixing / typing with binding wire &
M.S. rod to secure in position during concrete including all lifts etc. complete.

Sr.No.
Particulars
1 Materials :
a) PVC pipe
b) Binding wire
2

5
6
7

Quantity

Labours :
a) Cutting & fixing sleeves

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

1.00
0.20

Rmt.
Kg.

51.75
40.00

51.75
8.00

1.00
0.00

Rmt.

55.90
0.00

55.90
0.00

TOTAL (A)

115.65
2.31
0.00
0.00

TOTAL (B)

117.96
17.69

TOTAL

135.66

2.00%
0.00%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

136 /- Per

Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C11

Item No. : FDAPL/RCC/III/12


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

M20 for sloping slabs

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For sloping slabs

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

200.00
19.50
412.97

200.00
19.50
412.97

1.00

cum

682.50

682.50

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

4123.12
82.46
20.62
20.62

TOTAL (B)

4246.81

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

637.02
TOTAL

Say Rs.

4,884 /- Per

4883.83

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C11

Item No. : FDAPL/RCC/III/11


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

M20 for cantilever slabs upto 2.0m span

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For cantilever slabs

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering


Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Quantity

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

160.00
10.50
363.29

160.00
10.50
363.29

1.00

cum

892.50

892.50

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

TOTAL (A)

4234.44
84.69
21.17
21.17

TOTAL (B)

4361.47
654.22

TOTAL

5015.69

on total (A)
on total (A)
on total (A)

15.00%

Say Rs.

on total (B)

5,016 /- Per

per cum

Prepared by :
Name : _________________________________

Site:

0
Computer Code No. :
Item No. : FDAPL/RCC/III/19
Description :

Sign: ________________

Rate analysis
Location : 0
Default Date :
C11
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

M20 for Copings & sills

Providing and laying in situ C.C. M-20 of trap metal for R.C.C.work of Copings & sills as per detailed
drawings and design or as directed including centering formwork, compacting using vibrator, curing and
roughening the surface if special finish is to be provided etc. complete. (excluding reinforcement &
fitter work).

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

Centering & Shuttering

Quantity

Unit

Rate per

Amount

7.77
0.45
0.60
0.25

Bags
cum
cum
cum

245.00
1060.00
500.00
340.00

1903.65
477.00
300.00
85.00

1.00
1.00
1.00

cum
cum
cum

212.80
66.00
621.00

212.80
66.00
621.00

Providing good Specified material/


Fixing & removing
4

5
6
7

Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

cum

1220.00

1220.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

4927.95
98.56
24.64
24.64

TOTAL (B)

5075.79
761.37

TOTAL

5837.16

2.00%
0.50%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

5,837 /- Per

per cum

Prepared by :
Name : _________________________________

E/O for providing M25 grade concrete instead of M20 grade


Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference =
x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =
E/O for providing M30 grade concrete instead of M20 grade
Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference =
x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =
E/O for providing M35 grade concrete instead of M20 grade
Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference =
x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =

Sign: ________________

E/O for providing M40 grade concrete instead of M20 grade


Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference =
x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =

Rate analysis
Site:

0
Computer Code No. :

Location :
C11

Item No. : FDAPL/RCC/III/29


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
Rmt.

Welding of bars to existing reinforcement

Welding the reinforcement bars to existing steel or as per the requirement including finishing the welding
work neatly, all labour and material etc complete.
Sr.No.
Particulars
1 Materials :
a) Welding rods
For one Rmt. Of welding
(Assuming that average 6 nos of 16mm
dia. Bars are welded for one end of
beam)

Quantity

Unit

Rate per

Amount

5.00

No.

2.34

11.70

0.03
0.03

No.
No.

150.00
100.00

4.50
3.00

15.49

Sft.

0.75

11.62

0.25

Hr.

31.25

7.81

TOTAL (A)

38.63

Welding rods used are of 4mm &


ESAB / Advani make
2

Labours :
a)Welder
b)Helper
One welder can do about 30rmt. Of
welding
Scaffolding
If required for welding at heights
Assuming the area of scaffolding to be
1.2m x1.2m

Others
Hire charges of welding machine
Assuming the hire charges rate of
250 /-for 8 hrs.

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
10.00%

15.00%

TOTAL (A)

38.63
0.77
0.00
3.86

TOTAL (B)

43.27
6.49

TOTAL

49.76

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

50 /- Per

Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C11

Item No. : FDAPL/RCC/III/30


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per sqm

Providing shalitex board expansion joint

Providing & fixing shalitex board expansion joint of 25mm thickness for beams, columns & slab

Sr.No.
Particulars
1 Materials :
a) Shalitex board
Add for wastage @ 5%

Labours :
a)carpenter
b)Helper
One pair of carp/helper can do about 2
columns as given below.

Quantity

Unit

Rate per

Amount

1.00
0.05

Sqm.
Sqm.

800.00
800.00

800.00
40.00

0.37
0.37

No.
No.

150.00
100.00

55.50
37.00

Assuming the size of column to be


450x230 & joint on 450mm face, Ht. Of
col.of about 3m. Area = 3 x 0.45 = 1.35
sqm.

5
6
7

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
0.50%

TOTAL (A)

932.50
18.65
0.00
4.66

TOTAL (B)

955.81
143.37

TOTAL

1099.18

on total (A)
on total (A)
on total (A)

15.00%

Say Rs.

on total (B)

1,099 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C10

Item No. : FDAPL/RCC/III/9


Description :

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand

0
Default Date :
Revised on Date :
Unit :

14-08-06
per cum

C.C. M20 for precast slab of 50 mm thick slab

Quantity
0.10
0.03

Unit
Bags
cum

Rate per
215.00
850.00

Amount
21.50
25.50

5
6
7

c) Metal ( 3/4)"
d) Metal ( 1/2)"

0.04
0.02

cum
cum

425.00
450.00

17.85
7.88

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering

0.07
0.07
0.07

cum
cum
cum

212.00
66.00
621.00

14.84
4.62
43.47

0.07

cum

1220.00

85.40

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

263.56
-7.91
-1.32
-1.32

TOTAL (B)

253.01
0.00

TOTAL

253.01

Centering & Shuttering


Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

-3.00%
-0.50%
-0.50%

0.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

253 /- Per

per cum

Prepared by :

OR Rs 15/ sqm

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/RCC/III/8
Description :

Location :
C8

0
Default Date :
Revised on Date :
Unit :

14-08-06
per cum

C.C. M50 for RCC walls

Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild

Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For lift & Basement walls

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

9.65
0.85
0.70
0.50

Bags
cum
cum
cum

210.00
1060.00
550.00
550.00

2026.50
901.00
385.00
275.00

1.00
1.00
1.00

cum
cum
cum

185.00
0.00
486.00

185.00
0.00
486.00

1.00

cum

776.00

776.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

5077.00
-152.31
-25.39
-25.39

TOTAL (B)

4873.92
731.09

TOTAL

5605.01

-3.00%
-0.50%
-0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

5,605 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C8

Item No. : FDAPL/RCC/III/8


Description :

0
Default Date :
Revised on Date :
Unit :

14-08-06
per cum

C.C. M30 for Concrete Road

Providing & laying M 30 (as per design mix) for Road work using machine crushed metal of approved
quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering
formwork, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2
c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (Concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material/
Fixing & removing
Others
Mixer & Vibrator
Lift

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

7.50
0.85
0.70
0.50

Bags
cum
cum
cum

210.00
1060.00
550.00
550.00

1575.00
901.00
385.00
275.00

1.00
1.00
1.00

cum
cum
cum

185.00
0.00
150.00

185.00
0.00
150.00

1.00

cum

365.00

365.00

1.00
1.00

cum
cum

24.75
17.75

24.75
17.75

TOTAL (A)

3878.50
-116.36
-19.39
-19.39

TOTAL (B)

3723.36
558.50

TOTAL

4281.86

-3.00%
-0.50%
-0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

4,282 /- Per

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location :
C4

Item No. : FDAPL/RCC/III/2


Description :

0
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per cum

C.C. M30 for Footing, raft

Providing & laying M 300 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing
rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild
steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Metal ( 3/4)"
d) Metal ( 1/2)"
2

5
6
7

Quantity

Labours :
a) Mixing & Pouring (concreting)
b)Levelling & finishing
c) Shuttering
Centering & Shuttering
Providing good Specified material
for erection & dismantling
Others
Mixer & Vibrator

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

Amount

8.50
0.45
0.60
0.25

Bags
cum
cum
cum

210.00
850.00
500.00
550.00

1785.00
382.50
300.00
137.50

1.00
1.00
1.00

cum
cum
cum

107.20
16.50
86.25

107.20
16.50
86.25

1.00

cum

136.20

136.20

1.00

cum

24.75

24.75

TOTAL (A)

2975.90
59.52
14.88
14.88

TOTAL (B)

3065.18
459.78

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

3,525 /- Per

3524.95

per cum

Prepared by :
Name : _________________________________

Sign: ________________

2.21
0.312
0.624
0.312
0.455

0.2763636
7.7381818
7.9703273

16.5
86.25

250
31.25
0.792
24.8
36
3.2175032 2.2844273
79.633205 56.539575
637.06564 452.3166
19749.035
0.309375
24.75
17.775
Assign 0.3 hrs

176
15
480.13

992.25

1165.5
254.25
270
100

160
15
310.5

682.5

24.75
17.75

3000.25
150.01
30.0025
30.0025
3210.27
481.54013

3691.81
0.8336939

18.75
12.5

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
Default Date :

Dec 30, 99

Revised on Date
Item No. :

Unit :

Description :

Sr.No.
Particulars
1 Materials :

2 Labours :

3 Centering & Shuttering

4 Others

Quantity

Unit

Rate per

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

TOTAL (A)
4 Tools & Plants Charges
5 Water charges
6 Electricity Charges

5.00%
1.00%
1.00%

on total (A)
on total (A)
on total (A)

7 Over head & Profit

15.00%

on total (B)

TOTAL (B)
TOTAL
Say Rs.

0 /-

Amount
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00

Per

Prepared by :
Name : _________________________________

Sign: ________________

Assumptions
Tools and plants fixed charges

3%

Eleciticity Charges

0.50%

Water Charges
Profit ( Overheads + Profit )

0.50%
15%

Summary of Rateanalysis (MKS system)


Default date :
Revision Date :
Item.
No.

Description

1 Excavation in soil and soft murum upto 1.5m depth


2 Excavation in Hard Murum & boulders
3 Excavation in Soft Rock
4 Excavation in Hard Rock by chiselling
5 Soling 230 thk below floor
6 Filling with selected murum obtained from excavati
7 Filling with outside murum
8 Fillind with sand
9 Antitrmite treatment
10 Carting away surplus xcavated work
11 Excavation in hard rock by blasting
12 P.C.C. (1 :2:4 )
13 P.C.C.(1: 5: 10 )
14 P.C.C. (1 : 4: 8 )
15 P.C.C.(1 :4: 8 ) Plum Concrete
16 C.C. M20 for Footing, raft
17 C.C. M20 for column below plinth
18 C.C. M20 for superstructure Columns
19 C.C. M20 for floor Beams
20 C.C. M20 for slab
21 C.C. M20 for Staircase
22 RCC M20 for Pardi, fins
23 C.C.M20 for plith Beam
24 C.C.M20 for lintels & Chajja
25 C.C.M20 for Grid Beam
26 C.C.M20 for RCC walls
27 M20 for folded Steps upto 150mm thk.
28 M20 for sloping slabs
29 M20 for cantilever slabs upto 2.0m span
30 M20 for Copings & sills
31 P/F PVC sleeves 40mm dia. in concrete
32 Welding of bars to existing reinforcement
33 Providing shalitex board expansion joint
34 Ac trafford 6mm thk.sheets
35 Ac 6mm thk.ridges
36 Ac trafford 6mm thk.sheets cladding
37 Ac gutter
38 MS precoated sheets
39 MS precoated ridges
40 MS precoated .55mm thk.sheets cladding
41 MS precoated gutter

01.03.06
09.12.06
Rate in
Unit
Rs.
per cum
per cum
per cum
per cum
per Sqm
per Cum
per Cum
per Cum
per Sqm
per Cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
per cum
Rmt.
Rmt.
per sqm
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.

90.02
106.61
289.25
777.03
192.72
63.96
248.75
1272.15
42.85
68.03
353.66
3311.94
2342.07
2543.77
2213.56
3281.18
4787.63
5171.26
5296.52
4428.25
5426.55
6280.99
4840.19
5483.82
5896.03
4998.77
6208.14
4883.83
5015.69
5837.16
135.66
49.76
1099.18
262.79
163.15
210.23
176.15
530.85
306.19
513.94
390.33

42 Alluminium sheets

Default date :
43 Alluminium ridges
44 Alluminium sheets cladding
45 Alluminium gutter
46 FRP sheets
47 FRP ridges
48 FRP sheets cladding
49 FRP gutter
50 Polycarbonate sheets
51 UCR In plinth
52 Uncoursed rubble masonry in superstructure
53 Brick masonary 35cm thk. Below plinth
54 Brick work 35cm thk. In superstructure
55 Plinth Masonry 23cm thk
56 BBM 23cm thk in superstructure
57 P/F 15cm thk. Brick Wall (C.M. 1:4)
58 P/F 10cm thk. Brick Wall (C.M. 1:4)
59 Coursed rubble masonary
60 150mm thk. C.C. Solid block masonry
61 200mm thk. C.C. Solid block masonry
62 100mm thk. Siporex block masonry
63 150mm thk. Siporex block masonry
64 200mm thk. Siporex block masonry
65 Ext. Plaster single coat mortor ratio (1:5)
66 External Plastering Double coat
67 Internal Neeru Plaster CM (1:4)-12mm thk.
68 Internal Neeru Plaster CM (1:4) - 20mm thk.
69 Waterproof plaster
70 Pointing to brick masonary
71 Pointing to Stone masonary
72 P/A POP plaster to walls
73 Back coat for dado work 1:4)
74 Grey Mosaic Tile Flooring of 25cm x 25cm
75 Grey Mosaic Tile Flooring of 30x30
76 White Mosaic Tile Flooring of 25x25
77 White Mosaic Tile Flooring of 30 x 30
78 Grey Mosaic Tile Skirting of 125 mm ht.
79 Grey Mosaic Tile Skirting of 150 mm ht.
80 White Mosaic Tile Skirting of 125 mm ht.
81 White Mosaic Tile Skirting of 150 mm ht.
82 P/L IPS 50mm thk.
83 Ceramic Tile Flooring
84 Marble Flooring
85 Marble Skirting
86 Kota Flooring
87 Kota Skirting
88 Tandoor Flooring
89 Tandoor Skirting
90 Granite Flooring
91 Granite Skirting
92 Rough Shahabad flooring
93 Polished Shahabad flooring
94 Ceramic tiles flooring
95 Ceramic tiles Dado
96 Ceramic tiles Skirting

per Sqm.

663.62

01.03.06
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per Rmt.
per Sqm.
per cum
per cum
per cum
per cum
per cum
per cum
per sqm
per sqm
per cum
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per sqm
per rmt
per rmt
per rmt
per rmt
per sqm
per sqm
per sqm
per Rmt.
per sqm
per Rmt.
per sqm
per Rmt
per sqm
per Rmt.
per sqm
per sqm
per sqm
per sqm
per Rmt

374.26
676.40
497.21
674.18
263.96
686.59
413.90
1949.83
1984.99
2020.34
2335.22
2438.95
2085.80
2151.57
405.61
343.43
1967.96
451.31
615.32
1828.73
135.21
137.64
136.15
166.52
111.94
135.99
268.20
63.90
89.84
0.00
93.98
334.03
446.20
468.71
625.65
69.47
80.66
87.06
105.72
173.66
690.21
1462.74
153.85
606.28
68.94
590.30
63.21
2438.35
268.72
285.58
358.07
674.99
725.03
71.20

97 Vitrified tiles flooring


98 Vitrified tiles Dado
99 Vitrified tiles Skirting

Default date :
100 Designer tiles flooring
101 Paving blocks flooring (regular)
102 Paving blocks heavy duty (M40 & above)
103 Chequered tiles flooring
104 Marble for steps
105 Kota for sill & Jams
106 Marble for Sills & jams
107 Granite for sills & Jams
108 Tandoor for sills & jams
109 Granite Kitchen otta
110 Marble Kitchen otta
111 Kadappa Kitchen otta
112 Box type W/P to RCC raft, walls
113 Brickbat water proofing for toilets
114 Brickbat water proofing for terrace
115 White wash
116 Dry distemper
117 Oil bound distemper
118 Synthetic enamel paint
119 Lustre paint
120 Cement paint
121 Sandtex paint
122 Antifungal paint
123 Plastic emulsion paint
124 Chemical w/p for terrace, toilets
125 Providing & fixing TW frame (4"x 2.5")
126 P/F Granite frame (170x20)
127 P/F Marble frame (170x20)
128 P/F flush shutter 35mm
129 P/F flush shutter 35mm (internal door)
130 P/F flush shutter 35mm (internal door)
131 P/F Laminate of appr. shade & colour
132 P/F MS powder coated fittings
133 P/F Alluminium fittings
134 P/F stainless steel fittings
135 P/F Brass fittings
136 P/F Night latch
137 P/F Automatic door closer
138 P/F eye piece
139 P/F MS powder coated grills & railing
140 P/F MS grills & railing with enamel paint
141 P/F MS Z section windows
142 Reinforcement works
143 Structural steel works
144 12mm dia. Fan hook
145 Chainlink fencing

per sqm
per sqm
per Rmt.

1188.05
1262.44
1225.37

01.03.06
per sqm
707.57
per sqm
399.42
per sqm
578.39
per sqm
307.84
per Rmt
162.61
per sqm
653.57
per sqm 1395.58
per sqm 2681.12
per sqm
609.21
Rmt. 5005.23
Rmt. 3388.21
Rmt. 1800.22
per sqm
604.85
per Cum 2818.39
per sqm
344.17
per sqm
4.71
per sqm
19.39
per sqm
35.59
per sqm
46.26
per sqm
66.92
per sqm
36.19
per sqm
70.77
per sqm
91.34
per sqm
71.68
per sqm
327.32
Rmt.
468.23
Rmt.
934.46
Rmt.
579.47
Sqmt. 1097.63
Sqmt. 1138.66
Sqmt. 1284.05
Sqmt.
432.01
Door.
135.56
Door.
268.17
Door.
268.17
Door.
268.17
Door.
70.73
Door.
70.73
Door.
35.36
Sqm. 1018.76
Sqm.
797.86
Sqm. 1274.64
MT 45499.46
per Sqm. 43578.09
per No.
31.75
per Sqm.
259.20

Standard rate of materials considered for rate analysis


PREPARED
Sr.
List of Materials
No.
1 Cement
2 Reinforcement steel CTD
3 Binding wire
4 Sand
5 Metal (18 to 20)mm
6 Metal (12mm)
7 Metal (25mm)
8 Bricks (230mm)
9 Bricks (150mm)
10 Bricks (100mm)
11 Concrete Blocks (20x20x40)cm
12 Concrete Blocks (15x15x30)cm
(M15 grade @ 2200/-)
13 Siporex blocks (10x10x20) cm
14 Siporex blocks (15x15x30) cm
15 Siporex blocks (20x20x40) cm
16 Brick Bats
17 Rubble
18 Murum
19 Neeru
20 Lime
21 White cement
22 M.M. Tile (White) 25cm X 25cm
23 M.M. Tile (White) 25cm X 12cm
24 M.M. Tile (White) 30cm X 30cm
25 M.M. Tile (White) 30cm X 15cm
26 M.M. Tile (Grey) 25cm X 25cm
27 M.M. Tile (Grey) 25cm X 12cm
28 M.M. Tile (Grey) 30cm X 30cm
29 M.M. Tile (Grey) 30cm X 15cm
30 Marble
31 Tandoor
32 Granite
33 Rough Shahabad
34 Polished Shahabad
35 Ceramic tiles(30cm X 30cm)colour
36 Glazed Tiles (15cm X 15cm) White
37 Vitrified rough tiles
38 Vitrified polished tiles
39 Designer tiles(25mm)
40 Paver blocks (regular) 60mm
41 Paver blocks (heavy duty)
42 Chequered tiles
43 Kota steps
44 Marble steps
45 Granite steps
46 Tandoor steps
47 Kaddappa one side polish (40mm)
48 Shahabad stone 25mm
49 Broken glazed tiles
50 Water proofing Compound
51 Shalitex board 25mm
52 Kotah stone cut to size
53 Sub frame
54 Main frame
55 Shutter members

Per Unit

Rate (inRs.)

Per Bag
Per MT
Per Kg
Per cum
Per cum
Per cum
Per cum
Per No
Per No
Per No
Per No

245.00
28000.00
40.00
1060.00
500.00
340.00
575.00
2.25
4.00
3.00
34.00

Per No
Per No
Per No
Per No
Per cum
Per cum
Per cum
Per Bag
Per Bag
Per Kg.
Per sqm
Per rmt
Per sqm
Per rmt
Per sqm
Per rmt
Per sqm
Per rmt
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per Kg.
Per Kg.
Per sqm
Sqm
Per Kg.
Per Kg.
Per Kg.

16.00

Page 259 of 423

250.00
500.00
120.00
50.00
55.00
30.00
244.00
30.00
350.00
45.00
150.00
23.00
220.00
32.00
860.00
291.00
1695.00
75.00
110.00
380.00
400.00
800.00
800.00
430.40
242.10
386.00
102.00
377.68
1032.00
2118.75
378.30
220.00
82.50
10.00
40.00
800
290.52

Remarks
53 grade O.P.Cement
18 gauge binding wire

each bag of 25kg.


each bag of 30kg.

Sr.
List of Materials
No.
56 a) Beadings
57 b) Glass
58 c) Gasket,wool piles
59 d) Concealed lock
60 PVC Pipe
61 Chlordane 20% emulsion
62 Blasting powder
63 Safety fuse
64 Detonating fuse
65 Detonator
66 Teak wood frame 4"x2.5"
67 MS Holdfast
68 Coal tar
69 Flush shutter 35mm (90/- per sft.)
70 Brass hinges 75mm
71 Brass hinges 100mm
72 Brass hinges 125mm
73 Brass screws25mm
74 Brass screws25mm
75 Laminate 1mm
76 Fevicol
77 MS tubular
78 Nails
79 MS Z sections (1.5 kg @ 30)
80 10mm sq. bars (.785 x 30)
81 4mm float glass
82 Lime
83 Ultramarine blue
84 Glue
85 Sodium chloride
86 Distemper
87 Whitning
88 Primer
89 Putty
90 Oil bound distemper
91 Synthetic enamel
92 Luster paint
93 Cement paint
94 Sandtex paint
95 Antifungal paint
96 Plastic emulsion
97 AC trafford 6mm thk.
98 Bitminous washers 3mm
99 GI flat washers 2mm
100 GI - 6mm J hooks
101 AC -ridges pair
102 AC Gutter
103 MS precoated sheets
104 MS precoated -ridges (0.6m width )
105 MS precoated Gutter
106 Alluminium sheets
107 Alluminium -ridges (0.6m width )
108 Alluminium Gutter
109 Structural steel
110 FRP
111 FRP -ridges (0.6m width )
112 FRP gutter
113 Chain link
114 Polycarbonate sheets

Per Unit

Rate (inRs.)

Per Kg.
Per sqm
Per m.
Per No
Ltr.
kg.
Rmt
Rmt
No
Cft.
No.
Kg.
Sqm.
No
No
No
No
No.
sqm.
Kg.
Kg.
Kg.
Rmt.
Rmt.
Sqm.
Kg.
Kg.
Kg.
Kg.
Kg.
kg.
Lts
Kg.
Kg.
Ltr.
Ltr.
Kg.
Kg.
kg.
ltr.
Sqm.
Kg.
Kg.
No.
Rmt.
Rmt.
Sqm.
Rmt.
Rmt.
Sqm.
Rmt.
Rmt.
Mt.
Sqm.
Rmt.
Rmt.
sqm.
sqm.
Page 260 of 423

51.75
66.15
78.75
4.725
6.5
8
1200
10
25
968
20
26
35
1.5
2
310
250
32
30
45
23.55
325
1.5
114.98
48.825
10
67
20
60.9
40.95
90.00
141.75
218.75
49.35
86.3625
123.375
205.15
149.1
32
47.25
6.3
94.5
105
319
181.5
216.15
415.8
236.5
302.5
30500
423.5
154
209
156
1400

Remarks

Sr.
No.
115
116

List of Materials

Per Unit

Click on the button for Labour rates

Rate (inRs.)

Labour Rate

Page 261 of 423

Remarks

THIRUPPATHI KANNAN

Page 262 of 423

4.71

150.72

1.71

153.9

136.8

156
Page 263 of 423

Page 264 of 423

Standard rate of Labour considered for rate analysis


Revised on Date :
14-08-06
Sr.No.

Description
1 Unskilled coolie (Male)
2 Unskilled coolie (Female)
3 Beldar mazdoor
4 Breaker Operator
5 Helper for Breaker operator
6 Rent for Pneumatic Breaker Needle (8 hr.)
Machinaries on Hire basis
7 Mixer
8 Lift
9 Vibrator
Mixing & pouring for
10 P.C.C.
11 footing M15 grade

Unit
per day
per day
per day
per day
per day
per day
Per cum
Per cum
Per cum

Rate
100.00
75.00
80.00
120.00
80.00
1040.00

Remarks

17.75 Rate is derived from average


17.75 out put of machine (cft) per
day
7.00

Per cum
Per cum

120.00
107.20

12 footing M20 grade


13 Columns M15 grade
14 Beams M15 grade
15 Slabs M15 grade
16 Columns M20 grade
17 Beams M20 grade
18 Slabs M20 grade
19 Staircase
20 Pardi works
Levelling & finishing for
21 P.C.C.
22 footing
23 Columns
24 Beams
25 Slabs
26 Staircase
27 Pardi works
Only Labour rate for Shuttering works
28 P.C.C.
29 Footing
30 Columns
31 Beams
32 Slabs
33 Staircase
34 Pardi works (15cm thk.)
Masonry & Plaster works
35 U.C.R. masonry works in plinth
36 U.C.R. masonry for c.wall pillars etc.
36 BBM 350thk. below plinth
37 23cm B.B.Masonry works
37 15cm Tokla Brick Masonry works
38 10cm B.B.Masonry works
38 15cm C.C.Block Masonry works
39 External plastering single coat
39 External plastering double coat
40 External plastering (Scaffolding Charges)
40 Internal plastering
41 Internal platering (Scaffolding Charges)
Tile Fixing / Polisher

Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum

107.20
176.00
176.00
150.00
176.00
176.00
160.00
190.00
225.00

Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum

7.50
16.50
0.00
15.00
15.00
17.50
7.50

Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum

57.50
86.25
359.38
480.13
310.50
621.00
575.00

Per cum
Per cum
Per cum
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm
Per sqm

165.00
252.00
164.00
33.48
40.00
41.50
25.30
45.00
47.60
6.64
36.00
4.00

42 Mosaic Tile fixing

Per sqm

32.00

Revised on Date :
Sr.No.
Description
43 Mosaic Tile Skirting fixing
43 Ceramic Tile fixing
44 Marble Flooring
44 Ceramic /Glazed dado Tile fixing
45 Mosaic Tile polishing (3 coats)
45 Mosaic Tile Skirting polishing
46 Marble floor Polishing (regular)
46 Marble skirting polishing
47 Marble skirting fixing
47 Kota floor fixing & polishing
48 Kota skirting fixing & polishing
48 Tandoor floor fixing & polishing
49 Tandoor skirting fixing & polishing
49 Rough shahabad
50 Polished shahabad
50 Vitrified tiles flooring
51 Vitrified tiles Dado
51 Granite floor fixing
52 Granite skirting fixing
52 Kota Steps fixing
53 Marble Steps fixing
53 Granite Steps fixing
54 Tandoor steps
54 Kota sill & jams fixing
55 Marble sill & jams fixing
55 Granite sill & jams fixing
56 Tandoor sill & jams
Water proofing Works for
57 Box type
58 Toilets / Bathroom (for 200mm sunk)
59 Terrace (roof)
60 Chemical waterproofing
Shuttering material charges
61 for P.C.C. works
62 for footing
63 for columns
64 for beams
65 for slabs
66 for Staircase
67 for pardi
68 Reinforcement Works
69 KOTAH STONE
70 Polishing of kotah stone
Door frame charges
71 Frame making
72 Powder coating (at 15/- per sft)
73 Enamel painting including red oxide
74 AC sheets fixing
75 MS precoated sheets fixing
76 FRP sheets
77 Alluminium sheets fixing
78
79
80
81

Unit
Per rmt

Rate
10.00

Per sqm
Per sqm
Per sqm
Per sqm
Per rmt
Per Sqm
Per Sqm
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.
Per Sqm.

75.00
100.00
90.00
20.00
9.00
129.00
148.35
110.00
100.00
110.00
86.00
94.60
65.00
80.00
80.00
96.00
172.00
215.00
130.00
167.70
223.60
111.80
132.00
132.00
258.00
113.52

Per sqm
Per sqm
Per sqm
Per sqm

325.00
170.00
125.00
130.00

Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per cum
Per MT
Per Sqm
Per Sqm

80.00
136.20
1040.00
992.25
682.50
800.00
1520.00
2000.00
100.00
60.00

Per Sqm
Per sqm.
Per sqm.
Per sqm.
Per sqm.
Per sqm.

161.40
35.00
35.00
72.80
72.80
72.80

14-08-06
Remarks

Revised on Date :
Sr.No.
Description
Unit
Rate
Click on the button for entering into "ITEM LIST FOR SELECTION"

14-08-06
Remarks
Item List

WELCOME TO ITEM SELECTION SHEET


Sr.N Computer
o.
code
0
Blank format
1
Earth work
2
Earth work
3
Earth work
4
Earth work
5
Earth work
6
Concreting
7
Concreting
8
Concreting
9
Concreting
10
Concreting
11
Concreting
12
Concreting
13
Concreting
14
Concreting
15
Concreting
16
Masonry
17
Masonry
18
Masonry
19
Masonry
20
Masonry
21
Plastering
22
Plastering
23
Plastering
24
Plastering
25
Flooring
26
Flooring
27
Flooring
28
Flooring
29
Dado
30
W/P
31
W/P
32
W/P
33
Re
34

ITEMS
Earth work in ordinary soil
Earth work in Shadu
Earth work in Murum
Earth work in Soft Rock
Earth work in Hard Rock
P.C.C. (1:3:6)
P.C.C. (1:4:8)
C.C. M15 for footing
C.C. M20 for footing
C.C. M15 for columns
C.C. M20 for columns
C.C. M15 for Beams
C.C. M20 for Beams
C.C. M15 for Slabs
C.C. M20 for Slabs
U.C.R. Masonry 15" thk.
B.B.Masonry 9" thk.
B.B.Masonry 6" thk.
B.B.Masonry 4" thk.
C.C. Block masonry 6" thk.
External Plastering Single coat
External Plastering Double coat
Internal Plastering with C.M.1:4
Internal Plastering with C.M.1:5
Mosaic Tile flooring
Mosaic Tile Skirting
Ceramic Tile flooring
Marble Flooring
Ceramic /Glazed tile Dado
Brickbat waterproofing for Toilet
Brickbat waterproofing for Terrace
Glazed china mosaic w/p for terrace
Reinforcement works
Summary of rate analysis

Selection
button
_1
E1
E2
E3
E4
E5
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
B1
B2
B3
B4
B5
P1
P2
P3
P4
F1
F2
F3
F4
D1
W/P1
W/P2
W/P3
R1
SR

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
Default Date :
Revised on Date :

Item No. : FDAPL/EX/I/1


Description :

Unit :

14-08-06
per cum

Excavation in soil and soft murum upto 1.5m depth

Excavation upto 1.5 M depth in ordinary soil or soft murum, old foundations etc. in pits, over areas and in
trenches by machinery or otherwise including removing the excavated materials upto a distance of 100 M
beyond building premises, stacking as directed dewatering manually or mechanically if required, shoring,
strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet
compaction etc. complete.

Sr.No.
Particulars
1 Materials :

Labours :
a) Unskilled coolie for excn.
b) Labour for backfilling
Assuming that one pair
to do excavation of 125 cft.

Centering & Shuttering


NIL

Others
Shoring
Dewatering

5
6
7
8

Tools & Plants Charges


Water charges
Electricity Charges
Over head & Profit

Quantity

Unit

Rate per

Amount

0.56
0.08

No
No

100.00
100.00

56.00
8.00

1.00
1.00

L/S
L/s

10.00
2.00

10.00
2.00

TOTAL (A)

76.00
1.52
0.38
0.38

TOTAL (B)

78.28
11.74

TOTAL

90.02

2.00%
0.50%
0.50%
15.00%

on total (A)
on total (A)
on total (A)
on total (B)

90 /- Per

Say Rs.

per cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
E3
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/EX/I/3

Description :

Dec 30, 99
14-08-06
per cum

Excavation in Hard Murum & boulders

Excavation upto 1.5 M depth in hard murum & boulders etc. in pits, over areas and in trenches by
machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond
building premises, stacking as directed dewatering manually or mechanically if required, shoring,
strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet
compaction etc. complete.

Sr.No.
Particulars
1 Materials :

Quantity

Unit

Rate per

Amount

NIL
2

Labours :
a) Unskilled coolie (Male)
( It is assumed that 1 m/c + 1 f/c
can excavate nearly 100cft of murum in a day with specified lead
and lift)
c) Add for backfilling & compaction

0.70

No

100.00

70.00

0.08

No

100.00

8.00

1.00
1.00

L/S
L/s

10.00
2.00

10.00
2.00

Centering & Shuttering


NIL

Others
Shoring
Dewatering

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

TOTAL (A)

90.00
1.80
0.45
0.45

TOTAL (B)

92.70
13.91

TOTAL

106.61

on total (A)
on total (A)
on total (A)

on total (B)

107 /- Per

Say Rs.

per cum

Prepared by :
Name : _________________________________

Site:

0
Computer Code No. :

Sign: ________________

Rate analysis
Location : Pune
E4
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/EX/I/5


Description :

Dec 30, 99
14-08-06
per cum

Excavation in Soft Rock

Excavation upto 1.5 M depth in soft rock in pits and trenches by machinery or otherwise including
removing the excavated materials upto a distance of 100 M beyond building premises,stacking as
directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for
foundation and necessary back filling in layers including dry and wet compaction etc. complete.
Sr.No.
Particulars
1 Materials :
Nil
2 Labours :
a) 1 Breaker Needle with breaker
operator
( It is assumed that with a breaker needle in a day we can excavate nearly 200cft and the same
with lead & lift as specified.)
i.e. For 1 cum. It requires
0.18 days of breaker
b) Unskilled coolie 2 nos. (Male)
For 150 cft ( 4.25cum) 2 persons
are required, therefore for one

Quantity

Unit

Rate per

Amount

0.18

Per day

1040.00

187.20

0.47

No

100.00

47.00

5
6
7

cum 0.71 person is required


Labour for backfilling
Centering & Shuttering
NIL
Others
Dewatering

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.08

No

100.00

8.00

1.00

L/s

2.00

2.00

TOTAL (A)

244.20
4.88
1.22
1.22

TOTAL (B)

251.53
37.73

TOTAL

289.25

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

289 /- Per

per cum

Prepared by :
Name : _________________________________

Site:

0
Computer Code No. :

Sign: ________________

Rate analysis
Location : Pune
E5
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/EX/I/8

Dec 30, 99
14-08-06
per cum

Description :
Excavation in Hard Rock by chiselling
Excavation upto 1.5 M depth in hard rock in pits and trenches by machinery or otherwise including
removing the excavated materials upto a distance of 100 M beyond building premises,stacking as
directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for
foundation and necessary back filling in layers including dry and wet compaction etc. complete.

Sr.No.
Particulars
1 Materials : NIL
2

Labours :
a)1 Breaker Needle with operator
( It is assumed that with a breaker needle in a day we can excav-ate nearly 65cft (1.84cum.)

Quantity

0.54

Unit

Per day

Rate per

1000.00

Amount

540.00

with lead & lift as specified.)


i.e. For 1 cum. It requires
0.54 days of breaker
c) Unskilled coolie (Male)
For 100 cft ( 2.83cum) 3 persons
are required, therefore for one
cum1.06 person for 1cum.
d) Backfilling
3

Centering & Shuttering


NIL

Others
Dewatering

1.06

No

100.00

106.00

0.08

No

100.00

8.00

1.00

L/s

2.00

2.00

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

TOTAL (A)
on total (A)
on total (A)
on total (A)
TOTAL (B)

Over head & Profit

15.00%

on total (B)
TOTAL
777 /- Per
per cum

Say Rs.
Prepared by :
Name : ________________________________

656.00
13.12
3.28
3.28
675.68
101.35
777.03

Sign : _______________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
E1
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/EX/I/15


Description :

Dec 30, 99
14-08-06
per Sqm

Soling 230thk. Below floor

Providing and laying 230 mm thick dry trap rubble soling in plinth including filling the interstices with
murum and stone chips, watering,compacting, ramming etc complete with all labour and material.

Sr.No.
Particulars
1 Materials :

Quantity

Unit

Rate per

Amount

a)Rubble
b)Murrum

Labours :
a) Unskilled coolie (Male)
b) Unskilled coolie (Female)
Assuming that one pair
to do 200 sft. (18.59 sqm.)Of soling
area

Centering & Shuttering


NIL

Others

0.30
0.02

Cum
Cum

500.00
120.00

149.50
2.40

0.05
0.05

No
No

100.00
100.00

5.40
5.40

0.00
0.00

0.00
0.00

TOTAL (A)

162.70
3.25
0.81
0.81

TOTAL (B)

167.58
25.14

TOTAL

192.72

0.00
0.00

NIL

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

Say Rs.

193 /- Per

per Sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/EX/I/12
Description :

Location : 0
E1
Default Date :
Revised on Date :
Unit :

Dec 30, 99
14-08-06
per Cum

Filling with selected murrum obtained from excavation

Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)

Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)

Sr.No.
Particulars
1 Materials :
NIL
NIL
2

Centering & Shuttering


NIL

Others (m/c compactor)


Hire charges at 10/- per hour

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Unit

Rate per

0.00

Labours :
a) Unskilled coolie (Male)
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours
Net labour required = (2 / 2.83)/8

5
6
7

Quantity

Amount

0.00

0.00

0.35

No

100.00

35.00

0.09

No

100.00

9.00

1.00

10.00

10.00

TOTAL (A)

54.00
1.08
0.27
0.27

TOTAL (B)

55.62
8.34

TOTAL

63.96

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

64 /- Per

per Cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
E1
Default Date :

Dec 30, 99

Revised on Date :
Unit :

Item No. : FDAPL/EX/I/13


Description :

14-08-06
per Cum

Filling with outside murrum

Providing & filling in plinth murrum brought from outside including spreading, levelling, watering, and
ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Sr.No.
Particulars
1 Materials :
a) Murrum

Quantity

Unit

Rate per

Amount

1.30

Cum

120.00

156.00

0.35

No

100.00

35.00

0.09

No

100.00

9.00

1.00

10.00

10.00

TOTAL (A)

210.00
4.20
1.05
1.05

TOTAL (B)

216.30
32.45

TOTAL

248.75

Assuming the difference of loose


volume & compacted volume = 30%
2

Labours :
a) Unskilled coolie (Male)
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours
Net labour required = (2 / 2.83)/8

Centering & Shuttering


NIL

Others (m/c compactor)


Hire charges at 10/- per hour

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

Say Rs.
Prepared by :

on total (A)
on total (A)
on total (A)

on total (B)

249 /- Per

per Cum

Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
E1
Default Date :
Revised on Date :
Unit :

Item No. : 1
Item No. : FDAPL/EX/I/14

Dec 30, 99
14-08-06
per Cum

Filling with sand

Providing & filling in plinth with approved sand including spreading, levelling, watering, and ramming (in
layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Sr.No.
Particulars
1 Materials :
a) Sand

Quantity

Unit

Rate per

Amount

1.20

Cum

850.00

1020.00

0.35

No

100.00

35.00

0.09

No

100.00

9.00

1.00

10.00

10.00

TOTAL (A)

1074.00
21.48
5.37
5.37

TOTAL (B)

1106.22
165.93

Assuming the difference of loose


volume & compacted volume = 20%
2

Labours :
a) Unskilled coolie (Male)
Assuming that one male coolie
to do 100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours
Net labour required = (2 / 2.83)/8

Centering & Shuttering


NIL

Others (m/c compactor)


Hire charges at 10/- per hour

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

1,272 /- Per

Say Rs.

1272.15

per Cum

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
E1
Default Date :
Revised on Date :

Item No. : FDAPL/EX/I/16


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm

Antitermite treatment

Providing & applying preconstructional anti termite treatment to bottom and sides of excavated surfaces
by approved agency (MODE of Measurement will be on plinth area basis.)

Sr.No.
Particulars
1 Materials :
Chemical

Quantity

Unit

Rate per

Amount

0.50

Ltr.

66.15

33.08

0.03

No

100.00

3.10

0.00

0.00

TOTAL (A)

36.18
0.72

Assuming the treatment with 10 ltr. Per


sqm. Of area & 0.5 ltr. Of chemical Per
10 ltr of water (i.e 5% concentration)
2

Labours :
a) Unskilled coolie (for spreading) for 1
hours for one footing of 4 sqm. Area
Net labour required = (1 / 4)/8

Centering & Shuttering


NIL

Others (m/c compactor)


0.00

Tools & Plants Charges

2.00%

on total (A)

6
7

Water charges
Electricity Charges

Over head & Profit

0.50%
0.50%

15.00%

on total (A)
on total (A)

0.18
0.18
TOTAL (B)

37.26
5.59

TOTAL

42.85

on total (B)

43 /- Per

Say Rs.

per Sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
E1
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/EX/I/17


Description :

Dec 30, 99
14-08-06
Cum

Carting away surplus excavated earth

Carting away the unwanted excavated,/ demolished material outside the premises and unloading and
spreading it as and where required as per the rules of local authority including loading, unloading, carting,
spreading etc complete.

Sr.No.
Particulars
1 Materials :
NIL
2

Labours :
a) Unskilled coolie 2 nos. do filling of
tractor (100cft) in 15 minutes
Net labour required = (0.5 / 2.83)

Quantity

Unit

Rate per

Amount
0.00

0.18

No

100.00

18.00

1.00

40.00

40.00

Centering & Shuttering


NIL

Others (m/c tractor)


Tractor hire charges at 40/- per trip

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.00%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

TOTAL (A)

58.00
1.16
0.00
0.00

TOTAL (B)

59.16
8.87

TOTAL

68.03

68

Say Rs.

per Cum

Prepared by :
Name : _________________________________

Site:

0
Computer Code No. :

Sign: ________________

Rate analysis
Location : 0
E5
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/EX/I/11

Dec 30, 99
14-08-06
per cum

Description :
Excavation in Hard Rock by blasting
Excavation in Hard Rock for foundation by blasting including removing the excavated material upto
a distance of 10m with normal lift upto 1.5m and stacking & spreading in such a way as to not
disturd any site activity or as directed. Dewatering Preparing the bed for foundation & necessary
back filling, watering including shoring & Shuttering etc. complete.

Sr.No.
Particulars
1 Materials :

Quantity

Unit

Rate per

Amount

0.7
2
2
8

Kg.
No
rmt
rmt

78.75
8
4.725
6.5

55.13
16.00
9.45
52

Per hole approx. 250 gm. Of blasting


powder & one detonator is required
a) Blasting powder
b) Detonator
c) Safety fuse
d) Detonating fuse
2

Labours :
a) Unskilled coolie (Male)
For 100 cft ( 2.83cum) 3 persons

1.06

No

100.00

106.00

are required, therefore for one


cum1.06 person for 1cum.

Centering & Shuttering


NIL

Others
Compressor for drilling holes

0.50

120

120.00

TOTAL (A)

298.58
5.97
1.49
1.49
307.53

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)
TOTAL (B)

Over head & Profit

15.00%

on total (B)

Say Rs.
Prepared by :
Name : ________________________________

60.00

46.13

TOTAL
354 /- Per
per cum

Sign : _______________

353.66

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/MISC/XI/2


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

Structural steel works

Providing, fabricating & erecting & fixing, cutting, bending, grinding, welding the structural steel work
consisting of m.s. plates I beams channels, angles, chequered plates, including fabricating as per
shop drawing including erection to required line and level and providing and fixing buts, bolts and
required appropriate washers etc. complete including painting

Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) Structural steel
1.05
(adding 5% for wastage)
155.00
b) Welding rods
c) Oxygen Gas
1.50
d) DA
0.50
c) Bolts, nuts & washers
1.00
d) Primer Painting
2.00
d) Enamel Painting
5.00

Labours :
For fabrication & errection
For painting

Centering & Shuttering


Nil

Others
Welding M/C

Unit

Rate per

Amount

Mt.

30500.00

32025.00

No.
Cyli.
Cyli.
Kg.
lts.
lts.

3.50
250.00
800.00
47.25
40.00
110.00

542.50
375.00
400.00
47.25
80.00
550.00

1.00
1.00

Mt.
Mt.

2250.00
450.00

2250.00
450.00

1.00

Day

250.00

250.00

TOTAL (A)

36969.75

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
0.50%

15.00%

TOTAL (A)

36969.75
739.40
0.00
184.85

TOTAL (B)

37893.99
5684.10

TOTAL

43578.09

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

43,578 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/MISC/XI/3


Description :

Unit :

Dec 30, 99
14-08-06
per No.

12mm dia. Fan hook

Providing & fixing and securing in position box type fan hooks of 12 mm diameter MS rods 30 cm
long as directed
Sr.No.
1

Particulars
Quantity
Assuming area of 15 x 4 = 60 sqm.
Materials :
a) MS rods 12mm
0.28
(adding 5% for wastage)
b) Sand
1.00
c) Binding wire
0.05

Labours :
For preparing the hook & fixing in
place
Fitter (0.5 hrs.)
Helper (0.5hrs.)
Others

0.06
0.06

Unit

Rate per

Amount

Kg.

27.50

7.71

L/s
Kg.

2.00
32.00

2.00
1.60

No.
No.

150.00
100.00

9.38
6.25

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
0.50%

15.00%

TOTAL (A)

26.93
0.54
0.00
0.13

TOTAL (B)

27.61
4.14

TOTAL

31.75

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

32 /- Per

per No.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
B1
Revised on Date :

Item No. : FDAPL/MISC/XI/5


Description :

Unit :

Dec 30, 99
14-08-06
per Sqm.

Chainlink fencing

Providing and erecting in position chain link fencing of GI 18 gauge, 50 mm opening size as required
including fixing the angle supports in bed blocks of C:M 1:3:6 at 2.4 m c/c, ms 6 mm dia at top, U
nails for fixing, etc complete with all labour and material. - 1.2 m high fencing ( Structural steel for
angles,flats will be paid separately)
Sr.No.
1

Particulars
Quantity
Consider lengthof 24 x 1.2 = 28.8 sqm.
Materials :
a) Chain link 18 guage
30.24
(adding 5% for wastage)
2.00
b) U nails
c) 6mm dia. Wire
12.40
d) Concrete 1:3:6
0.40

Sqm.

156.00

4717.44

Kg.
Kg.
Cum.

40.00
32.00
1979.00

80.00
396.80
783.68

Labours :
For excavation
For poles errecting (0.5 mason &
0.5 helpers)

Nos.
No.
No.

5
150.00
100.00

55.00
75.00
50.00

11
0.50
0.50

Unit

Rate per

Amount

For fixing chain link


(.5 mason & 1 helpers)
3

4
5
6

0.50
1.00

No.
No.

150.00
100.00

75.00
100.00

TOTAL (A)

6332.92
126.66
0.00
31.66

TOTAL (B)

6491.25
973.69

TOTAL

7464.93

Others

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Costing for 28.8 sqm.

Say Rs.

259 /- Per

per Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

300 mm
46.153846 per mt.
0.3 mm
153.84615 total rods
538.46154

28.8

12.4
33

CODE

NO

STANDARD ITEMS OF BOQ


BRIEF DESCRIPTION OF ITEMS

UNIT

SECTION I -Work Below Plinth


SNJ/EX/
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I

1 Excavation in soil and soft murum upto 1.5m depth


2 Excavation in soil and soft murum from 1.51 m to 3.0m depth
3 Excavation in hard murum and boulders upto 1.5 m depth
4 Excavation in hard murum and boulders from 1.51 to 3.0 m depth
5 Excavation in soft rock upto 1.5 m depth
6 Excavation in soft rock from 1.51 to 3.0 m depth
7 Excavation in soft rock from 3.1 m to 6.0 m depth
8 Excavation in hard rock upto 1.5m depth ( by chiselling)
9 Excavation in hard rock from 1.51m to 3m depth ( by chiselling)
10 Excavation in hard rock from 3.1m to 6.0m( by Chiselling)
11 Excavation in hard rock by blasting
12 Filling in plinth with selected murum obtained from excavation
13 Filling in plinth with murum brought from outside ( labour+material)

Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum

SNJ/EX/I
SNJ/EX/I
SNJ/EX/I
SNJ/EX/I

14 Filling in plinth sand


15 230 mm thick dry rubble soling in plinth
16 Providing preconstructional antitermite treatment to plinth
17 Carting away unwanted excavated material outside the premises

Cum
Sqm
Sqm
Cum

SECTION II-PCC Work


SNJ/PCC/II
SNJ/PCC/II
SNJ/PCC/II
SNJ/PCC/II
SNJ/PCC/II
SNJ/PCC/II

1 Providing and laying PCC 1:5:10 beddintg


2 Providing and laying PCC 1:4:8 bedding
3 Providing and laying PCC 1:3:6 bedding
4 Providing and laying PCC 1:2:4 bedding
5 Providing and laying PCC 1:1.5:3 bedding
6 Providing and laying 1:4:8 plum concrete

Cum
Cum
Cum
Cum
Cum
Cum

SECTION III-RCC Work


SNJ/RCC/III

1 Providing and casting RCC M20 for footings, foundations, combined


footings, eccentric footings, raft, pedastals,pile caps

SNJ/RCC/III

2 Providing and casting RCC M20 for columns ( of any size and shpe)upto Cum
plinth and in basement
3 Providing and casting RCC M20 for columns ( fo any size and shape) in Cum
superstructure at all levels
4 Providing and casting RCC M20 for plinth beams
Cum

SNJ/RCC/III
SNJ/RCC/III

Cum

SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III

5 Providing and casting RCC M20 for beams ( of any shape and size) at all Cum
levels
6 Providing and casting RCC M20 for beams in grid system
Cum
7 Providing and casting RCC M20 for lintels
Cum
8 Providing and casting RCC M20 for piles
9 Providing and casting RCC M20 for standard slab(thk upto 200 mm)
Cum

SNJ/RCC/III
SNJ/RCC/III

10 Providing and casting RCC M20 slab for loft


11 Providing and casting RCC M20 for cantilever slab upto 2.0 m span

Cum
Cum

SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III

12 Providing and casting RCC M20 for sloping slab


13 Providing and casting RCC M20 for pyramidal slab
14 Providing and casting RCC M20 for hordi slab
15 Providing and casting RCC M20 for folded slab upto thickness of 150mm

Cum
Cum
Cum
Cum

SNJ/RCC/III

16 Providing and casting RCC M20 for chajjas at any level , of projection
Cum
upto 0.75m
17 Providing and casting RCC M20 for pardies, parapets, fins, upstands of Cum
thickness upto 100 mm
18 Providing and casting RCC M20 for staircase steps and waist slab with Cum
riser upto 170 mm and tread upto 300 mm and waist slab thickness upto
200 mm.at all levels.

SNJ/RCC/III
SNJ/RCC/III

SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III
SNJ/RCC/III

19 Providing and constructing RCC M20 for coping at all levels


20 Providing and constructing RCC M20 for sills at all levels
21 Providing and constructing RCC walls in M20
22 Providing and constructing RCC M20 floor
23 Extra for addition or deduction in thickness of the structural members as
mentioned above , excluding form work
24 Less for providing concrete of grade M15 in lieu of M20
25 Extra for providing concrete of grade M25 in lieu of M20
26 Extra for providing concrete of grade M30 in lieu of M20
27 Extra for providing concrete of grade M35 in lieu of M20
28 Extra for providing concrete of grade M40 in lieu of M20
29 Providing, cutting, bending, laying reinfocement of mild steel, tor steel of
various diameters including binding wire
30 Welding of bars to existing reinforcement
31 Expansion joint for columns
32 Expansion joint for beams
33 Expansion joint for slab
34 Providing post tensioning of beams and slab
35 Providing anticorrosive treatment to reinforcement
SECTION IV-Stone /Brick masonry/Block/Siporex Masonry

Cum
Cum
Cum
Cum

Cum
Cum
Cum
Cum
Cum
MT
RM
RM
RM
RM
Sqm
MT

SNJ/MAS/IV

Cum

SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV

1 Providing and constructing 350 mm or above brick masorny below plinth


(C:M 1:6)
2 Providing and constructing UCR masonry in C: M 1:6 below plinth for
foundation
3 Providing and constructing UCR masonry in C:M 1:6 for compound wall,
steps, pillars in superstructure etc
4 Providing and constructing 350 mm thick BB masonry in superstructure
for steps, walls, pillars (C:M 1:4)
5 Providing and constructing 230 mm thick BB masonry for walls below
plinth (C:M1:6)
6 Providing and constructing 230 mm thick BB masorny for wall in
superstructure at all levels(C:M1:6)
7 Providing and constructing 115 mm thick BB masorny in super structure
at all levels (C:M 1:4)
8 Providing and constructing 150 mm thick BB masorny in super structure
at all levels (C:M 1:4)
9 Providing and constructing coursed rubble masonry
10 Providing and constructing 'Khandki' masonry
11 Providing and constructing 150 mm thk concrete block masonry
12 Providing and constructing 200 mm thk concrete block masonry

SNJ/MAS/IV
SNJ/MAS/IV

13 Providing and constructing siporex block masonry 100 mm thick


14 Providing and constructing siporex block masonry 150 mm thick

Sqm
Sqm

SNJ/MAS/IV

15 Providing and constructing siporex block masonry 200 mm thick

Sqm

SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV
SNJ/MAS/IV

Cum
Cum
Cum
Sqm
Sqm
Sqm
Sqm
Cum
Cum
Sqm
Sqm

SECTION V- PLASTERING AND POINTING


SNJ/PLAST/V

1 Providing and applying 12 mm thick internal cement plaster C:M 1:4

SNJ/PLAST/V

2 Providing and applying 20 mm thick sandface cement plaster C:M 1:5 in Sqm
one coat
3 Providing and applying 12mm back coat plaster behind dado C:M 1:4
Sqm

SNJ/PLAST/V
SNJ/PLAST/V

Sqm

Sqm

SNJ/PLAST/V
SNJ/PLAST/V
SNJ/PLAST/V

4 Providing and applying 20 mm thick sand faced cement plaster in two


coats first coat with 1:5 & second with 1:4
5 Provding and applying 25 mm thick plaster to toilet sunks and sides,
internally to water tanks with waterproofing compound
6 Providing and applying 20 mm thick rough cast plaster
7 Providing and applying pebble dash plaster
8 Providing and applying special finish RENOVO or other such plasters

SNJ/PLAST/V

9 Providing and making flush groove pointing to brick/block masonry

Sqm

SNJ/PLAST/V

Sqm
Sqm
Sqm
Sqm

SNJ/PLAST/V
SNJ/PLAST/V

10 Providing and making flush groove pointing to stone masonry


11 Providing and making sunk pointing to stone masonry

Sqm
Sqm

SECTION VI-FLOORING WORK


SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI

1 Providing and laying IPS floor 50 mm thick with ghotai


2 Providing and laying marble mosaic tile flooring 25cmx25cm size - grey
cement based
3 Providing and laying marble mosaic tile flooring 30cmx30cm size - grey
cement based
4 Providing and laying marble mosaic tile flooring 25cmx25cm size - white
cement based
5 Providing and laying marble mosaic tile flooring 30cmx30cm size - white
cement based
6 Providing and laying marble stone flooring
7 Providing and laying Kotah stone flooring
8 Providing and laying granite stone flooring
9 Providing and laying tandur stone flooring
10 Providing and laying polished shahabad flooring
11 Providing and laying rough shahabad flooring
12 Providing and laying Jaisalmer stone flooring
13 Providing and laying ceramic tile flooring
14 Providing and laying vitrified tile flooring
15 Providing and laying rough vitrified tile flooring
16 Providing and laying designer tiles - interlocking type
17 Provding and laying interlocking paving blocks
18 Provding and laying chequered tiles
19 Providing and laying marble mosaic tile skirting 125mm size - grey
cement based
20 Providing and laying marble mosaic tile skirting 150 mm size - grey
cement based
21 Providing and laying marble mosaic tile skirting 125mm size - white
cement based
22 Providing and laying marble mosaic tile skirting 150 mm size - white
cement based
23 Providing and laying marble stone skirting
24 Providing and laying Kotah stone skirting
25 Providing and laying granite stone skirting
26 Providing and laying tandur stone skirting
27 Providing and laying polished shahabad skirting
28 Providing and laying rough shahabad skirting
29 Providing and laying Jaisalmer stone skirting
30 Providing and laying ceramic tile skirting
31 Providing and laying vitrified tile skirting

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI
SNJ/FLOOR/VI

32 Providing and laying rough vitrified tile skirting


Sqm
33 Providing and laying ceramic tile dado
Sqm
34 Providing and laying marble stone dado
Sqm
35 Providing and laying Kotah stone dado
Sqm
36 Providing and laying granite stone dado
Sqm
37 Providing and laying tandur stone dado
Sqm
38 Providing and laying marble stone for treads and risers
Sqm
39 Providing and laying Kotah stone for treads and risers
Sqm
40 Providing and laying granite stone for treads and risers
Sqm
41 Providing and laying tandur stone for treadsand risers
Sqm
42 Providing and laying Jaisalmer stone for treads and risers
Sqm
43 Providing marble for window sills and jambs
Sqm
44 Provding kotah stone for window sills and jambs
Sqm
45 Providing granite stone for window sills and jambs
Sqm
46 Providing tandur stone for window sills and jambs
Sqm
47 Providing, making and erecting in position kitchen platform with following RM
specifications. Width of platform 2'3" and height 32" top
a. Kadappa slab 40 mm thick as base to granite stone slab.
b. Granite stone slab 20 mm thick with polishing,
c. Making hole for single bowl stainless steel sink with edge polishing to
cut surface of stones
d. One shelf of granite below platform
e. 2 no of vertical supports of kadappa stone with both side polish and
edge polish
f. 4" height granite fascia with edge polish
As per item no 56 above but with marble stone top slab

SNJ/FLOOR/VI
SNJ/FLOOR/VI

RM

As per item no 56 above but with polished kadappa top slab 50 mm RM


thick.
50 Providing and laying vitrified tile dado
Sqm
51 Provding and laying interlocking paving blocks (heavy duty)
Sqm

SECTION V :DOORS & WINDOWS

Providing and fixing in position door frames in correct line, level and
plumb of Teak Wood of size 4" x2.5" including applying coal tar to the
surface coming in contact with masorny including 6 no of MS hold fasts
fixed in concrete bedblocks in masonry ( 6"x6" size), MS rod at bottom to
keep the frame in position etc complete with all labour and material. door size 750mm x 2100 mm

RM

As per item no 1 above but for door size 900 x 2100 mm

RM

As per item no 1 above but for door size1000 x 2100 mm

RM

As per item no 1 above but for door size1200 x 2100 mm

RM

As per item no 1 above but for door size1500 x 2100 mm

RM

As per item no 01 but with granite door frame of size 170 mm x 20 mm


and extra patti for rebate formation for 35 mm thick shutter. Door size
750 x 2100 mm

RM

As per item no 6 above but for door size 900 x 2100 mm

RM

As per item no 6 above but for door size1000 x 2100 mm

RM

As per item no 6 above but for door size1200 x 2100 mm

RM

10

As per item no 6 above but for door size1500 x 2100 mm

RM

11

As per item no 01 but with marble door frame of size 170 mm x 20 mm


and extra patti for rebate formation for 35 mm thick shutter. Door size
750 x 2100 mm

RM

12

As per item no11 above but for door size 900 x 2100 mm

RM

13

As per item no 11 above but for door size1000 x 2100 mm

RM

14

As per item no 11 above but for door size1200 x 2100 mm

RM

15

As per item no11 above but for door size1500 x 2100 mm

RM

16

Providing and fixing in position flush block board door shutters 35 mm


thick including 25 mm lipping patti, both faces finished with commercial
teak ply, including fixing with 4 no of hinges, required screws etc Sq.M
complete. - single shutter - size of door - 750 x 2100 mm

17

As per item no 16 above but for door size of 900 x 2100 mm

Sq.M

18

As per item no 16 above but for door size of 1000 x 2100 mm

Sq.M

19

As per item no 16 above but for double shutter door of size 1200 x 2100

20

As per item no 16 above but for double shutter door of size 1500 x 2100

21

Providing and fixing laminate of approved colour and shade to doors


including all labour and material

22

Providing and fixing following MS powder coated fittings and fixtures for
doors
a. Aldrop 250 mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles

23

24

Sq.M

Sq.M

Sq.M

No
No
No
No
No
No

Providing and fixing following Aluminium fittings and fixtures for doors
a. Aldrop 250 mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles

No
No
No
No
No
No

Providing and fixing following stainless steel fittings and fixtures of D-line
or equivalent make for doors
a. Aldrop 250 mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper

No
No
No
No
No

25

f. D type handles

No

Providing and fixing following brass fittings and fixtures of D-line or


equivalent make for doors
a. Aldrop 250 mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles

No
No
No
No
No
No

26

Providing and fixing night latch of approved brand to door with all
hardware and accessories required

No

27

Providing and fixing in position automatic door closure of approved make


including all labour and material complete.

No

28

Providing and fixing peep hole / eye piece of approved make to doors
including all labour and material complete

29

Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws, 4 mm
thick clear float glass etc complete with all labour and material.- 2 track
sliding window

30

As per item no 29 above but with aluminium colour anodised sections


-do-

31

Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws,4 mm
thick clear float glass etc complete with all labour and material.- 3 track
sliding window with mosquito net

32

As per item no 31 above but with colour anodised aluminium sections


-do-

33

Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws, 6 mm
thick clear float glass etc complete with all labour and material.- 4 track
sliding window, with mosquito net

34

As per item no 33 above but with colour anodised aluminium sections


-do-

35

Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws,6 mm
thick clear float glass etc complete with all labour and material.- 5 track
sliding window, with mosquito net

36

As per item no 35 above but with colour anodised aluminium sections


-do-

37

Providing and fixing in position aluminium openable windows with


powder coated sections, with all accessories such as hinges, peg stays,
4 mm thick clear float glass, beading, EPDM gaskets, etc complete with
all labour and material

38

As per item no 37 above but with colour anodised sections -do-

39

Providing and fixing in position aluminium louvered windows with powder


coated sections as per detail design and drawing with all accessories
and 4 mm thick frosted glass for louvers etc complete.

40

Providing and fixing in position aluminium louvered windows with colour


anodised sections as per detail design and drawing with all accessories
and 4 mm thick frosted glass for louvers etc complete.

41

Providing and erecting in position fixed glazing with aluminium powder


coated sections as per detail design and drawing, including all
accessories such as polysulphide sealants, stainless steel clips, 12 mm
thick glass, all required scaffolding other labour and material complete
the item in all respects.

42

As per item no 31 above but with colour anodised aluminium sections

43

Providing, fabricating and fixing in position for grills & railings in Powder
coated MS tubular sections of all shapes and size, with weight upto 15
kg / sqm, as per detail design and drawing, all labour and material
complete.

44

Providing, fabricating and fixing in position for grills & railings in MS


tubular sections with enamel paint of all shapes and size, with weight
upto 15 kg / sqm, as per detail design and drawing, all labour and
material complete.

45

Providing and fixing in position MS glazed windows with Z section, 4 mm


thick clear float glass, 10 mm MS square bars at 120 mm c/c, reqired
springs, putty and two coats of oilpaint etc complete.

46

Providing and fixing in position Sintex door shutters to already fixed


granite frame for toilet doors with all accessories complete.

SECTION VIII - WATERPROOFING WORKS


SNJ/WP/VIII
SNJ/WP/VIII
SNJ/WP/VIII

1 Waterproofing of terrace with brick bat coba upto 115 mm thk


2 Waterproofing of toilet sunks with brick bat coba filling
3 Box type waterproofing for basement walls and wherever required

Sqm
Cum
Sqm

SNJ/WP/VIII

4 Chemical waterproofing to terrace and toilet sunks

Sqm

SECTION IX - PAINTING
SNJ/PAINT/IX
SNJ/PAINT/IX

1 White wash
2 Dry distemper

Sqm
Sqm

SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX
SNJ/PAINT/IX

3 Oil bound distemper


4 Synthetic enamel (oil paint)
5 Plastic emulsion
6 Lustre paint
7 Cement paint
8 Sandtex paint
9 Anti fungal paint such as ACE
10 Aluminium paint to structural steel

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

SECTION X - ROOFING WORK


SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X
SNJ/ROOF/X

1 AC sheet roofing
2 AC ridges
3 AC sheet cladding
4 AC flashig
5 AC gutters
6 Precoated sheet roofing
7 Precoated ridges
8 Precoated sheet cladding
9 Precoated sheet flashing
10 Precoated sheet gutters
11 Aluminium sheet roofing
12 Aluminium ridges
13 Aluminium sheet cladding
14 Aluminium flashings
15 Aluminium gutters
16 FRP sheet roof
17 FRP ridges
18 FRP sheet cladding
19 FRP sheet flashing
20 FRP gutters
21 Mangalor tiles with frame work
22 Pan tile roofing on exsting slab
23 FRP domes
24 Polycarbonate sheet domes/ roof covering

Sqm
RM
Sqm
Sqm
Sqm
Sqm
RM
Sqm
Sqm
Sqm
Sqm
RM
Sqm
Sqm
Sqm
Sqm
RM
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

SECTION XI - MISCELLANEOUS WORKS


SNJ/MISC/XI
SNJ/MISC/XI
SNJ/MISC/XI

1 Structural steel fabrication and erection wherever required for trusses,


stanchions, and such other industrial activities.
2 Box type fan hooks
3 Anchor fasteners

MT
No
No

SNJ/MISC/XI
SNJ/MISC/XI
SNJ/MISC/XI
SNJ/MISC/XI
SNJ/MISC/XI

4 Fabrication and erection of steel required for railings of balconies,


staircases, terraces etc with painting
5 ACP sheet cladding
6 Chain link fencing 4' height
7 Chain link fencing 8' height
8 Barbed wire fencing

Kg
Sqm
Sqm
Sqm
Sqm

Rate

90.02
99.02
106.61
117.27
289.25
318.18
350.00
777.03
854.74
940.21
353.66
63.96
248.75
1272.15
192.72
42.85
68.03

2342.07
2543.77
3311.94

2213.56

3281.18
4787.63
5171.26
4840.19

5296.52
5896.03
5483.82

4428.25
5483.82
5015.69
4883.83

6208.14
5483.82
6280.99

5426.55
5837.16
5837.16
4998.77

331.88

45499.46
49.76
1099.18
1099.18
1099.18

2335.22
1984.99
2020.34
2438.95
2085.80
2151.57
343.43
405.61
1967.96
451.31
615.32
1828.73
135.21
137.64

111.94
136.15
93.98
166.52
268.20

63.90

91.88
89.84

173.66
334.03
446.20
468.71
625.65
1462.74
606.28
2438.35
590.30
358.07
285.58
674.99
1188.05
1188.05
707.57
399.42
307.84
555.77
537.76
696.49
704.78
153.85
68.94
268.72
63.21

71.20
1225.37

1225.37
725.03

162.61
895.36
306.70
72.94
1395.58
653.57
2681.12
609.21
5005.23

3388.21

1800.22
1262.44
578.39

468.23

934.46

579.47

1097.63

1138.66
1284.05

432.01

1018.76

797.86

1274.64

344.17
2818.39
604.85
344.17

4.71
19.39

35.59
46.26
71.68
66.92
36.19
70.77
91.34

1.73
136.42
330.40

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
Default Date :
D1
Revised on Date:

Item No. : FDAPL/DW/VII/1

Unit :

Dec 30, 99
14-08-06
Rmt.

Description :
Providing & fixing TW frame (4"x 2.5")
Providing and fixing in position door frames in correct line, level and plumb of Teak Wood of size 4"
x2.5" including applying coal tar to the surface coming in contact with masorny including 6 no of MS hold
fasts fixed in concrete bedblocks in masonry ( 6"x 6" size), MS rod at bottom to keep the frame in
position etc complete with all labour and material. - door size 900mm x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand ( as approved)
c) MS Holdfast
d) Teak wood (4*2.5/144*17.83)*1.1 =
1.362
e) MS Tie rod 8mm
f) Coal tar
2

Quantity

Labours :
Carpenter for frame making
Helper for frame making
(0.5 carp + 0.2 help are required per cft
of frame making)
Mason for fixing of frame
Unskilled labour

Rate per

0.18
0.01
6.00

Bags
Cum
Nos.

245.00
1060.00
10.00

44.10
13.78
60.00

1.36
0.34
0.50

Cft
Kg.
Kg.

1200.00
27.50
25.00

1632.00
9.28
12.50

0.68
0.27

Nos.
Nos.

200.00
100.00

136.00
27.20

150.00
80.00

0.00
75.00
16.00

0.00

0.00

TOTAL (A)

2025.86
40.52
0.00
10.13

TOTAL (B)

2076.51
311.48

0.50
0.20

Nos.
Nos.

Amount

Others
Nil

4
5
6

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

Total costing for (0.9+2.1*2 = 5.1Rmt.)


Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)
TOTAL
468 /- Per
Rmt.

2387.98

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : FDAPL/DW/VII/1

Unit :

Dec 30, 99
14-08-06
Rmt.

Description :
P/F Granite frame (170x20)
As per item no 01 but with granite door frame of size 170 mm x 20 mm and extra patti for rebate
formation for 35 mm thick shutter. Door size 900x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand ( as approved)
c) MS Holdfast
d) Granite with 10% wastage
((0.9+.09*2+2.1*2+.05*2)*.17) +
((.86+2.08*2+.05*2)*(.17-.035)) = 1.606
x 1.1 = 1.77
e) MS Tie rod 8mm
f) White / colour cement
2

Quantity

Labours :
Labour rate for cutting, fixing &
moulding of frame

Rate per

Amount

0.18
0.01
6.00
1.77

Bags
Cum
Nos.
Sqm.

245.00
1060.00
10.00
1695.00

44.10
13.78
60.00
2995.07

0.34
0.25

Kg.
Kg.

27.50
30.00

9.28
7.50

1.77

Sqm.

516.00

913.32

0.00

0.00

TOTAL (A)

4043.04
80.86
0.00
20.22

TOTAL (B)

4144.12
621.62

TOTAL

4765.74

Others
Nil

4
5
6

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Total costing for (0.9+2.1*2 = 5.1 Rmt.)

Say Rs.

934 /- Per

Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1

Dec 30, 99

Revised on Date:
Item No. : FDAPL/DW/VII/3
Description :

14-08-06
Rmt.

Unit :
P/F Marble frame (170x20)

As per item no 01 but with marble door frame of size 170 mm x 20 mm and extra patti for rebate
formation for 35 mm thick shutter. Door size 900x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand ( as approved)
c) MS Holdfast
d) Marble with 10% wastage
((0.9+.09*2+2.1*2+.05*2)*.17) +
((.86+2.08*2+.05*2)*(.17-.035)) = 1.606
x 1.1 = 1.77
e) MS Tie rod 8mm
f) White / colour cement
2

Quantity

Labours :
Labour rate for cutting, fixing &
moulding of frame

Rate per

Amount

0.18
0.01
6.00
1.77

Bags
Cum
Nos.
Sqm.

245.00
1060.00
10.00
946.00

44.10
13.78
60.00
1671.58

0.34
0.25

Kg.
Kg.

27.50
30.00

9.28
7.50

1.77

Sqm.

396.00

700.92

0.00

0.00

TOTAL (A)

2507.16
50.14
0.00
12.54

TOTAL (B)

2569.84
385.48

TOTAL

2955.32

Others
Nil

4
5
6

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Total costing for (0.9+2.1*2 = 5.1 Rmt.)

Say Rs.

579 /- Per

Rmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/DW/VII/4

Location : 0
Default Date :
D1
Revised on Date:
Unit :

Dec 30, 99
14-08-06
Sqmt.

Description :

P/F flush shutter 35mm

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws
etc complete. - single shutter - size of door - 750 x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Shutter 35mm thk.
(2.055 x 0.66 = 1.356
b) Brass Hinges 75mm
c) Brass screws 25mm
2

Quantity

Unit

Rate per

1.36

Sqm.

968.00

1312.61

4.00
16.00

No
No

20.00
1.50

80.00
24.00

0.20
0.10

Nos.
Nos.

200.00
100.00

40.00
10.00

0.00

0.00

TOTAL (A)

1466.61
29.33
0.00
7.33

TOTAL (B)

1503.27
225.49

TOTAL

1728.76

Labours :
Carpenter for fixing shutter
Helper for fixing shutter
(0.2 carp + 0.2 help are required per cft
of frame making)
Others
Nil

5
6
7

Amount

0.00

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.00%
0.50%

Over head & Profit

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Total costing for (0.75*2.1 = 1.575 sqmt.)

Say Rs.

1,098 /- Per

Sqmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : 31
Description :

Location : 0
Default Date :
D1
Revised on Date:
Unit :
P/F flush shutter 35mm (internal door)

Dec 30, 99
14-08-06
Sqmt.

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws
etc complete. - single shutter - size of door - 900 x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Shutter 35mm thk.
(2.055 x 0.81 = 1.356)
b) Brass Hinges 100mm
c) Brass screws 25mm

Quantity

Unit

Rate per

1.67

Sqm.

968.00

1611.72

4.00
16.00

No
No

35.00
1.50

140.00
24.00

0.20
0.10

Nos.
Nos.

200.00
100.00

40.00
10.00

0.00

0.00

TOTAL (A)

1825.72
36.51
0.00
9.13

TOTAL (B)

1871.36
280.70

TOTAL

2152.07

Labours :
Carpenter for fixing shutter
Helper for fixing shutter

Amount

(0.2 carp + 0.2 help are required per cft


of frame making)
3
4

5
6
7

Centering & Shuttering


Nil
Others
Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Total costing for (0.9*2.1 = 1.89 sqmt.)

Say Rs.

1,139 /- Per

Sqmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/DW/VII/5
Description :

Location : 0
Default Date :
D1
Revised on Date:
Unit :
P/F flush shutter 35mm (internal door)

Dec 30, 99
14-08-06
Sqmt.

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 8 no of hinges, required screws
etc complete. - double shutter - size of door - 1500 x 2100 mm
Sr.No.
Particulars
1 Materials :
a) Shutter 35mm thk.
(2.055 x 1.41 = 1.356
b) Brass Hinges 125mm
c) Brass screws 50mm
2

Quantity

Unit

Rate per

2.89

Sqm.

1016.40

2937.40

8.00
32.00

No
No

35.00
2.00

280.00
64.00

0.50
0.50

Nos.
Nos.

200.00
100.00

100.00
50.00

0.00

0.00

TOTAL (A)

3431.40
68.63
0.00
17.16

TOTAL (B)

3517.18
527.58

TOTAL

4044.76

Labours :
Carpenter for fixing shutter
Helper for fixing shutter

Amount

(0.2 carp + 0.2 help are required per cft


of frame making)

Others
Nil

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Total costing for (1.5*2.1 = 2.52 sqmt.)

Say Rs.

1,284 /- Per

Sqmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/DW/VII/6
Description :

Location : 0
Default Date :
D1
Revised on Date:
Unit :

Dec 30, 99
14-08-06
Sqmt.

P/F Laminate of appr. shade & colour

Providing and fixing laminate of approved colour and shade to doors including all labour and material

Providing and fixing laminate of approved colour and shade to doors including all labour and material
Sr.No.
Particulars
1 Materials :
a) Laminate sheet of 1 mm thk.
b) Fevicol
c) Sundry material (plywood pieces &
0.5" nail)

Quantity

Labours :
Carpenter for fixing & polishing of
laminates
Helper

Unit

Rate per

Amount

1.00
0.05

Sqm.
Kg.

310.00
250.00

310.00
12.50

1.00

L/S

10.00

10.00

0.07
0.20

Nos.
Nos.

200.00
100.00

14.00
20.00

0.00

0.00

TOTAL (A)

366.50
7.33
0.00
1.83

TOTAL (B)

375.66
56.35

TOTAL

432.01

(0.2 carp + 0.2 help are required for


fixing the sheet of 4'x8' I.e = 2.88 sqm.)
& 0.25 help for polishing

Others
Nil

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

432 /- Per

Sqmt.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Door.

P/F MS powder coated fittings

Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop
250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop
250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.
Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws
2

Quantity

Unit

Rate per

1.00
1.00
1.00
1.00
1.00
2.00
24.00

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.

0.00

0.00
0.00
0.00

0.20
0.75

Nos.
Nos.

200.00
100.00

40.00
75.00

0.00

0.00

TOTAL (A)

115.00
2.30
0.00
0.58

TOTAL (B)

117.88
17.68

TOTAL

135.56

Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)

Others
Nil

5
6
7

Amount

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

136 /- Per

Door.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Door.

P/F Alluminium fittings

Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws

Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)

Quantity

Unit

Rate per

Amount

1.00
1.00
1.00
1.00
1.00
2.00
24.00

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.

112.50

112.50
0.00
0.00

0.20
0.75

Nos.
Nos.

200.00
100.00

40.00
75.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

227.50
4.55
0.00
1.14

TOTAL (B)

233.19
34.98

TOTAL

268.17

Centering & Shuttering


Nil

Others
4

5
6
7

Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

268 /- Per

Door.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Door.

P/F stainless steel fittings

Providing and fixing following stainless steel fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws

Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)

Quantity

Unit

Rate per

Amount

1.00
1.00
1.00
1.00
1.00
2.00
24.00

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.

112.50

112.50
0.00
0.00

0.20
0.75

Nos.
Nos.

200.00
100.00

40.00
75.00

0.00
0.00
0.00

0.00
0.00
0.00

Centering & Shuttering


Nil

Others
4

Nil

0.00
0.00
0.00

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.00%
0.50%

15.00%

TOTAL (A)

227.50
4.55
0.00
1.14

TOTAL (B)

233.19
34.98

TOTAL

268.17

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

268 /- Per

Door.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Door.

P/F Brass fittings

Providing and fixing following Brass fittings and fixtures for doors, including Aldrop 250mm, tadipatti,
towerbolts, PVC gattu, door stopper, D type handle.

Sr.No.
Particulars
1 Materials :
a. Aldrop 300 x 16mm size
b. Tadipatti
c. Tower bolts
d. PVC gattu
e. Door stopper
f. D type handles
g) Screws

Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)

Quantity

Unit

Rate per

Amount

1.00
1.00
1.00
1.00
1.00
2.00
24.00

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.

112.50

112.50
0.00
0.00

0.20
0.75

Nos.
Nos.

200.00
100.00

40.00
75.00

Centering & Shuttering


Nil

Others
4

5
6
7

Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

227.50
4.55
0.00
1.14

TOTAL (B)

233.19
34.98

TOTAL

268.17

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

268 /- Per

Door.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Door.

P/F Night latch

Providing and fixing night latch of approved brand to door with all hardware and accessories required

Sr.No.
Particulars
1 Materials :
a) Night Latch

Quantity
1.00

Unit
Nos.

Rate per

Amount
0.00

b) Screws

24.00

Nos.

0.20
0.20

Nos.
Nos.

Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.2 help are required for
fixing the latch for one door)

200.00
100.00

40.00
20.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

60.00
1.20
0.00
0.30

TOTAL (B)

61.50
9.23

TOTAL

70.73

Centering & Shuttering


Nil

Others
4

5
6
7

Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

71 /- Per

Door.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Door.

P/F Automatic door closer

Providing and fixing in position automatic door closure of approved make including all labour and
material complete.

Providing and fixing in position automatic door closure of approved make including all labour and
material complete.

Sr.No.
Particulars
1 Materials :
a) Automatic door closer (godrej or
equivalent)
b) Screws

Quantity

Unit

1.00
24.00

Nos.
Nos.

0.20
0.20

Nos.
Nos.

Labours :
Carpenter for fixing
Helper
(0.2 carp + 0.2 help are required for
fixing )

Rate per

Amount

0.00

200.00
100.00

40.00
20.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

60.00
1.20
0.00
0.30

TOTAL (B)

61.50
9.23

TOTAL

70.73

Centering & Shuttering


Nil

Others
4

5
6
7

Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

71 /- Per

Door.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Door.

P/F eye piece

Providing and fixing peep hole / eye piece of approved make to doors including all labour and material
complete

Sr.No.
Particulars
1 Materials :
a) Eye piece
b) Screws

Labours :
Carpenter for fixing
Helper
(0.1 carp + 0.1 help are required for
fixing the latch for one door)

Quantity

Unit

1.00
24.00

Nos.
Nos.

0.10
0.10

Nos.
Nos.

Rate per

Amount
0.00

200.00
100.00

20.00
10.00

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

30.00
0.60
0.00
0.15

TOTAL (B)

30.75
4.61

Centering & Shuttering


Nil

Others
4

5
6
7

Nil

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

TOTAL

Say Rs.

35 /- Per

35.36

Door.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31

Unit :

Dec 30, 99
14-08-06
Sqm.

Description :
P/F MS powder coated grills & railing
Providing, fabricating and fixing in position for grills & railings in Powder coated MS tubular sections of
all shapes and size, with weight upto 15 kg / sqm, as per detail design and drawing, all labour and
material complete.
Sr.No.
Particulars
1 Materials :
a) Steel sections
b) Nails
c) Cement
2

Labours :
For fabricating & fixing in position
Mason for finishing
For powder coating

Quantity

Unit

Rate per

Amount

15.00
0.20
0.05

Kg.
Kg.
Bag

32.00
32.00
245.00

480.00
6.40
12.25

15.00
0.10
1.27

Kg.
No.
Sqm.

8.00
200.00
161.40

120.00
20.00
205.62

1.00

L/s

20.00

20.00

0.00

0.00

TOTAL (A)

864.27
17.29
0.00
4.32

TOTAL (B)

885.88
132.88

TOTAL

1018.76

(Assuming ave. 40x40x1.5mm section


of medium wt. Surface area for 1.884
kg. = 0.16 sqm.)Surface area for 15kg.
= 1.274 sqm.
For paint touch up

Others
Nil

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

1,019 /- Per

Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
D1
Revised on Date:

Item No. : 31
Description :

Unit :

Dec 30, 99
14-08-06
Sqm.

P/F MS grills & railing with enamel paint

Providing, fabricating and fixing in position for grills & railings in MS tubular sections of all shapes and
size, with weight upto 15 kg / sqm, as per detail design and drawing, painted with one coat of zinc
chromate & two coats of enamel paint,all labour and material complete.
Sr.No.
Particulars
1 Materials :
a) Steel sections
b) Nails
c) Cement
2

Labours :
For fabricating & fixing in position
Mason for finishing
For enamel painting

Quantity

Unit

Rate per

Amount

15.00
0.20
0.05

Kg.
Kg.
Bag

32.00
32.00
245.00

480.00
6.40
12.25

15.00
0.10
1.27

Kg.
No.
Sqm.

8.00
200.00
30.00

120.00
20.00
38.22

0.00
0.00

0.00
0.00

TOTAL (A)

676.87
13.54
0.00
3.38

TOTAL (B)

693.79
104.07

TOTAL

797.86

(Assuming ave. 40x40x1.5mm section


of medium wt. Surface area for 1.884
kg. = 0.16 sqm.)Surface area for 15kg.
= 1.274 sqm.
3

Others
Nil

4
5
6

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

0.00
0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

798 /- Per

Sqm.

Prepared by :
Name : _________________________________

Site:

0
Computer Code No. :

Sign: ________________

Rate analysis
Location : 0
Default Date :
D1
Revised on Date:

Dec 30, 99
14-08-06
Sqm.

Item No. : 31
Unit :
Description :
P/F MS Z section windows
Providing and fixing in position MS glazed windows with Z section, 4 mm thick clear float glass, 10 mm
MS square bars at 120 mm c/c, required springs, putty and two coats of oilpaint etc complete.
Sr.No.
1

Particulars
Quantity
Assuming the window size to be = 1.2 x 1.2m
Materials :
9.60
a) MS Zsections (25mm)
8.00
b) 10mm Sq. bars
c) 4mm thk. Float glass (with 5%
wastage)
1.44
4.00
d) MS holdfast
e)
0.10
f) Nails
g) Cement
0.05
h) Fittings (stopper, handle, pin hinges
I.e = 26+10+20)
1.00
0.80
I) Putty
Labours :
For fabricating & fixing in position
(9.6*1.53+8*.785 = 14.2 kg.
Mason for finishing
For enamel painting
For fixing glass
(0.22 glazier reqd. for each Sqm.)

Rate per

Amount

Rmt.
Rmt.

45.00
23.55

432.00
188.40

Sqm.
Nos

325.00
20.00

468.00
80.00

Kg.
Bag

32.00
78.75

3.20
3.94

L/s
Kg.

56.00
20.00

56.00
16.00

Kg.
No.
Sqm.
No.

10.00
200.00
30.00
150.00

209.68
20.00
32.40
47.52

0.00

0.00

TOTAL (A)

1557.14
31.14
0.00
7.79

TOTAL (B)

1596.07
239.41

TOTAL

1835.48

Others
Nil

5
6
7

20.97
0.10
1.08
0.32

Unit

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit


Total costing for 1.2 x 1.2m

0.00

2.00%
0.00%
0.50%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

1,275 /- Per

Sqm.

Prepared by :
Name : _________________________________

Sign: ________________

backup calculation

Item / description
PCC (1:3:6)
Labour
For pouring
Male coolie
Female coolie

Mason for finishing


Carpenter for shuttering ( 2sqm per cum.)
Helper for shuttering
Add for deshuttering @ 25%

Qty.

Rate

Amount

0.75
0.75

80
80

60
60
120

0.05

150

7.5

0.2
0.2

130
100

26
20
11.5
57.5

Material cost of shuttering


Area of shuttering = 2 sqm. Per cum of concrete,
for each Sqm. Cost = 23.5 / .65 = 36.15 add 4 rs.
For nails & oil etc.

80

RCC M20 for footings


Assuming Size of 1.5x1.5x.4
Labour
For pouring
Male coolie
Female coolie

0.67
0.67

80
80

53.6
53.6
107.2

Mason for finishing

0.11

150

16.5

Page 1

Remarks

One carpenter can do 10 sqm. Per day


One helper can do 10 sqm. Per day
2.2 sqm
Assuming 75mm thk. For 2x2 size ftg.
Con = 2.15*2.15*.075 = 0.35 shutt. =
2.15*4*.075 = .65
0.0192
For wooden runner
(2.15x4*3.28*4*4/144)*225 = (705) / 30 =
23.5 rs. Per 0.65 sqm.
2.6m
4x3Wooden runner at 225/- per cft. =
(4*3/144)*8*5*225/939.1392
78.2616
152.4528

1.6
Conc. = 1.5*1.5*.4 = 0.9cum
shutt = 1.5 * 4 *.4 = 2.4
shutt / cum = 2.4/0.9 =2.67
0.9
One mason can do finishing of 9 cum. ( 10
ftgs. )

backup calculation

Carpenter for shuttering (approx = 3.0 sqm)


Helper for shuttering
Add for deshuttering @ 25%

0.3
0.3

130
100

39
30
17.25
86.25

One carpenter can do 10 sqm. Per day


One helper can do 10 sqm. Per day
0.3

Material cost of shuttering

Area of shuttering = 3 sqm. Per cum of concrete,


for each Sqm. Cost = 45.4/136.2

1000 rs. For plywood + 750 rs. For wooden


runner = (1000+750)/2.88 = 608 rs. Per
Sqm. With 20 uses cost per sqm = 608/20 =
30.4, Add 5/- for supports & 10/-. For nails
& oil etc. Total = 30.4+5+10 =45.4
4x3Wooden runner at 225/- per cft. =
(4*3/144)*8*5*225/-

RCC M20 for Columns superstrucure


Assuming col. Of 600x230
Labour
For pouring
Male coolie
Female coolie

Mason for finishing


Carpenter for shuttering (10 sqm. Shutt / cum)
Helper for shuttering
Add for deshuttering @ 25%

1.1
1.1

80
80

88
88
176

150

1.25
1.25

130
100

162.5
125
71.875
359.375

Material cost of shuttering

One carpenter can do 8 sqm. Per day


One helper can do 8 sqm. Per day

4.98

Page 2

backup calculation

Area of shuttering = 10 sqm. Per cum of concrete,


for each Sqm. Cost = 93.9 + 10/- for wirenails &
shuttering oil

1040

1000 rs. (for plywood) + 900 rs. (for wooden


runner) = (1000+900)/2.88 = 659 rs. Per
Sqm. + Rs.4 for supports + 24Rs. For chavis
4x3Wooden runner at 225/- per cft. =
(4*3/144)*8*6*225/(65.9+4+24)

RCC M20 for Columns below plinth


assuming column size of 600*230
Labour
For pouring
Male coolie
Female coolie

0.0833333333
900

0.9
0.9

80
80

72
72
144

Mason for finishing

150

Carpenter for shuttering (10sqm / cum. Of conc.)


Helper for shuttering
Add for deshuttering @ 25%

1
1

130
100

130
100
57.5
287.5

One mason can do finishing of 12 cum. (4


ftgs. )
One carpenter can do 10 sqm. Per day
One helper can do 10 sqm. Per day

Material cost of shuttering

1000 rs. (for plywood) + 900 rs. (for wooden


runner) = (1000+900)/2.88 = 659 rs. Per
Sqm. Assuming 15 uses rate per use =
43.9/- add Rs.4 for supports + 24Rs. for
chavis. Total = 43.9+4+24 = 71.9/-

Area of shuttering = 10 sqm. Per cum of concrete,


for each Sqm. Cost = 71.9 + 10/- for wirenails &
shuttering oil
820

6713.599

4x3Wooden runner at 225/- per cft. =


(4*3/144)*8*4*225/-

671.3599
44.75732667

Page 3

backup calculation

RCC M20 for beams


Labour
For pouring
Male coolie
Female coolie

1.1
1.1

80
80

88
88
176

Mason for finishing

0.1

150

15

1.67
1.67

130
100

217.1
167
96.025
480.125

Carpenter for shuttering (10sqm percum.)


Helper for shuttering
Add for deshuttering @ 25%

One mason can do finishing of 10 cum.


One carpenter can do 6 sqm. Per day
One helper can do 6 sqm. Per day

Material cost of shuttering

1000 rs. (for plywood) + 1200 rs. (for


wooden runner) = (1000+1200)/2.88 = 763
rs. Per Sqm. With 12 repetetion rate per
sqm = 63.58, add Rs.5 for supports + 16 Rs.
For chavis Total = 63.5+5+16 = 84.5

Area of shuttering = 10.5 sqm. Per cum of


concrete, for each Sqm. Cost =97.3, add 10/- for
shuttering oil & nails, total = 84.5+10 =94.5
992.25

4x3Wooden runner at 225/- per cft. =


(4*3/144)*8*8*225/- =1200/4*4 chavis of 4 feet in length (4 nos). with
25uses, cost = ((4*4*4*4/144)*225) /25
RCC M20 for Plinth & tie beams
Labour
For pouring
Male coolie
Female coolie

Mason for finishing

63.5833333333
84.5
1.1
1.1

80
80

88
88
176

0.07

150

10.5

Page 4

One mason can do finishing of 15 cum.

backup calculation

Carpenter for shuttering ( 10sqm per cum.)


Helper for shuttering
Add for deshuttering @ 25%

1.25
1.25

130
100

162.5
125
71.875
359.375

One carpenter can do 8 sqm. Per day


One helper can do 8 sqm. Per day

Material cost of shuttering

1000 rs. (for plywood) + 1200 rs. (for


wooden runner) = (1000+900)/2.88 = 659rs.
Per Sqm. With 15 repetetion rate per sqm =
43.9, add Rs.5 for supports + 16 Rs. For
chavis Total = 44+5+16 = 65

Area of shuttering = 10 sqm. Per cum of concrete,


for each Sqm. Cost =65, add 10/- for shuttering oil
& nails, total = 65+10 =75
750

4x3Wooden runner at 225/- per cft. =


(4*3/144)*8*6*225/- =1200/RCC M20 for lintel beams
Labour
For pouring
Male coolie
Female coolie

Mason for finishing


Carpenter for shuttering ( 12sqm per cum.)
Helper for shuttering
Add for deshuttering @ 25%

1.5
1.5

80
80

120
120
240

0.07

150

10.5

2
2

130
100

260
200
115
575

One mason can do finishing of 15 cum.


1.75
One carpenter can do 6 sqm. Per day
One helper can do 6 sqm. Per day

Material cost of shuttering


Area of shuttering = 12sqm. Per cum of concrete,
for each Sqm. Cost = 731 / 10 =73, add 10/- for
shuttering oil & nails

996

Page 5

1000 rs. For plywood + 900 rs. For wooden


runner = (1000+900)/2.88 = 659 rs. Per
Sqm. + 2x(120/10) for 2 no. for supports
Total = (659+72)

backup calculation

4x3Wooden runner at 225/- per cft. =


(4*3/144)*8*6*225/731
RCC M20 for grid beams
Labour
For pouring
Male coolie
Female coolie

Mason for finishing


Carpenter for shuttering ( 12qm per cum.)
Helper for shuttering
Add for deshuttering @ 25%

1.5
1.5

80
80

120
120
240

0.07

150

10.5

2
2

130
100

260
200
115
575

0.0666666667
One mason can do finishing of 15 cum.
1.75
One carpenter can do 6 sqm. Per day
One helper can do 6 sqm. Per day

Material cost of shuttering


Area of shuttering = 12sqm. Per cum of concrete,
for each Sqm. Cost = 102 , add 10/- for shuttering
oil & nails
1344

1000 rs. For plywood + 1200 rs. For


wooden runner = (1000+1200)/2.88 = 764
rs. Assuming 12uses rate Per Sqm. = 63.6,
Add 8/- for supports + 30rs for chavis Total =
(63.6+8+30)
4x3Wooden runner at 225/- per cft. =
(4*3/144)*8*8*225/- & Chavis 4' long 6 nos
with 20 uses (4*4*4/144*225*6/20)

RCC M20 for lift walls


Labour
For pouring
Male coolie
Female coolie

Mason for finishing


Carpenter for shuttering ( 8sqm per cum.)

1.1
1.1

80
80

88
88
176

150

1.6

130

208

Page 6

One mason can do finishing of 15 cum.


1.6
One carpenter can do 5 sqm. Per day

backup calculation

Helper for shuttering


Add for deshuttering @ 25%

1.6

100

160
92
460

One helper can do 5 sqm. Per day

Material cost of shuttering


Area of shuttering = 8sqm. Per cum of concrete,
for each Sqm. Cost = 87, add 10/-for shuttering oil
& nails
776

1000 rs. For plywood + 900 rs. For wooden


runner = (1000+900)/2.88 = 659 rs.
Assuming 12 uses rate Per Sqm. = 54.91,
Add 8/- for supports + 24rs for chavis Total =
(55+8+24)
4x3Wooden runner at 225/- per cft. =
(4*3/144)*8*6*225/-

RCC M20 for slab


Labour
For pouring
Male coolie
Female coolie

1
1

80
80

80
80
160

Mason for finishing

0.1

150

15

1
1

130
100

130
100
80.5
310.5

Carpenter for shuttering ( 7sqm per cum.)


Helper for shuttering
Add for deshuttering @ 35%

One mason can do finishing of 10cum.


1.75
One carpenter can do 7 sqm. Per day
One helper can do 7 sqm. Per day

Material cost of shuttering


Area of shuttering = 7sqm. Per cum of concrete,
for each Sqm. Cost = 87.5 , add 10/- for shuttering
oil & nails
682.5
RCC M20 for parapet fins drop walls upto
125mm thk.
Labour
For pouring
Male coolie

1.5

80

Page 7

120

Hire charges for plate = 20/- per month, we


have two uses per month, i.e rate per sqm =
20, add for wooden runners 4x4 @ 3no.
per sqm.(37.5/-), add for ballies at
2.5*120/10(30) = 20+37.5+30 = 87.5/-

backup calculation

Female coolie

Mason for finishing


Carpenter for shuttering ( 16sqm per cum.)
Helper for shuttering
Add for deshuttering @ 25%

1.5

80

120
240

0.05

150

7.5

2
2

130
100

260
200
115
575

One mason can do finishing of 20cum.


1.75
One carpenter can do 8 sqm. Per day
One helper can do 8 sqm. Per day

Material cost of shuttering


Area of shuttering = 16sqm. Per cum of concrete,
for each Sqm. Cost = 85 , add 10/- for shuttering
oil & nails
1520

RCC M20 forStaircases regular(with waist slab upto 175mm)


Labour
For pouring
Male coolie
1.25
Female coolie
1.25

Mason for finishing


Carpenter for shuttering ( 8sqm per cum.)
Helper for shuttering
Add for deshuttering @ 35%

1000 rs. For plywood + 900 rs. For wooden


runner = (1000+900)/2.88 = 659 rs. With 12
uses rate per Sqm. =54.91 Add 6/- for
supports + 24rs for chavis Total = (55+6+24)
= 85

80
80

100
100
200

0.25

150

37.5

One mason can do finishing of 4cum.

2
2

130
100

260
200
161
621

One carpenter can do 4 sqm. Per day


One helper can do 4 sqm. Per day

Material cost of shuttering


Area of shuttering = 8sqm. Per cum of concrete,
for each Sqm. Cost = 89 , add 11/- for shuttering
oil & nails
800

Page 8

1000 rs. For plywood + 1200 rs. For


wooden runner = (1000+1200)/2.88 = 764
rs. Per Sqm. + 8x(120/10) for 8 no. for
supports + 32rs for chavis Total =
(764+96+32)

backup calculation

892
763.8888888889
RCC M20 for folded Staircases (with thickness upto 150mm)
Labour
For pouring
Male coolie
1.5
Female coolie
1.5

Mason for finishing


Carpenter for shuttering (12sqm per cum.)
Helper for shuttering
Add for deshuttering @ 35%

80
80

120
120
240

0.25

150

37.5

One mason can do finishing of 4cum.

3
3

130
100

390
300
241.5
931.5

One carpenter can do 4 sqm. Per day


One helper can do 4 sqm. Per day

Material cost of shuttering


Area of shuttering = 12sqm. Per cum of concrete,
for each Sqm. Cost = 91 , add 11/- for shuttering
oil & nails
1224

1000 rs. For plywood + 1200 rs. For


wooden runner = (1000+1200)/2.88 = 764
rs. Per Sqm. + 8x(120/10) for 8 no. for
supports + 48rs for chavis Total =
(764+96+48)
908

Reinforcement steel cutting, bending & fixing


Labour for 1Mt. Of steel
Fitter
Helper
Foremen
Add for straightning & transportation @ 25%

8
8
0.2

110
100
175

880
800
35
428.75
2143.75

For ave. 125 kg. Of steel we require one


pair of F/H

Providing & fixing PVC sleeve of 40mm dia.


Material cost of sleeves
Labour

0.4347826087

Page 9

backup calculation

Carpenter

0.43

130

55.9
55.9

One carpenter can do 10 sleeves of 230mm


length i.e total = 2.3m
13.75

Providing & fixing UCR masonary in plinth


1.25 times rubble required than the actual
Labour
mason
Unskilled labour (2 nos)

0.46

150

69

1.2

80

96
165

0.2355712603
4.245
0.1766784452
One mason pair to do 150cft. (I.e.4.245cum)
of UCR

Providing & fixing UCR masonary for Compound wall etc.


1.25 times rubble required than the actual
Labour
mason
Unskilled labour ( 2 nos per mason)
Add for corner stones &

0.46

150

69

1.2

80

96
87

252

87.7192982456
One mason pair to do 150cft. (I.e.4.245
cum) of UCR
add for corner stones preparation ,
assuming 3.0m length & 1.5m height, corner
stones required 30nos @ 5/- for (.38*3*1.5 =
1.71 cum. I.e 150/1.71 = 87rs. Per cum.

Providing & laying 350mm thk. Below plinth


500 nos. bricks required for one cum of
194.34628975 BBM.
2.3206

Page 10

backup calculation

Labour
mason
Unskilled labour ( 2 nos per mason)

0.56

150

84

80

80
164

1.2195121951
3.5375
One mason pair to do 125ft. (I.e.3.53 cum)
of BBM

Providing & laying 350mm thk. In superstructure


500 nos. bricks required for one cum of
BBM.
Labour
mason
Unskilled labour ( 2 nos per mason)

Scaffolding / sand screening etc.

0.35

150

52.5

0.7

80

56
108.5

0.57

80

45.6

One mason pair to do 200cft. (I.e.5.66 cum)


of BBM
Unskilled labour 2 nos. for 1 hour for 10
sqm area ( 3.5cum.)

Providing & laying 230mm thk. Below plinth


500 nos. bricks required for one cum of
BBM.
Labour
mason

0.108

150

16.2

Unskilled labour ( 2 nos per mason)

0.216

80

17.28
33.48

One mason pair to do 150cft. (I.e.4.25 cum


= 18.5 sqm.) of BBM

Providing & fixing 230thk. BBM in superstructure


500 nos. of bricks per cum. Of masonary
Labour
mason

0.162

150

24.3

Unskilled labour ( 2 nos per mason)

0.216

80

17.28

Page 11

One mason pair to do 150cft. (I.e.4.25 cum


= 18.5 sqm.) of BBM

backup calculation

41.58

Scaffolding etc.

0.083

80

6.64

Sand screening

0.0552

53

2.9
9.6

Unskilled labour 2 nos. for 1 hour for 3 sqm


area
For 1sqm. I.e .23 x .2 = 0.046 cum of sand
required. (150 per brass)

Providing & fixing 115 thk.BBM in superstructure


500 nos. of bricks per cum. Of masonary
Labour
mason

0.17

150

25.5

0.2

80

16
41.5

Scaffolding etc.

0.083

80

6.64

Sand screening

0.02

53

1.1
7.7

Unskilled labour (2 nos)

One mason pair & 3 male coolie to do


12sqm.. Of BBM
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e .1 x .2 = 0.02 cum of sand
required. (150 per brass)

Providing & fixing 150 thk.BBM in superstructure


48nos. Of bricks of 230*150*75 are required
for 1sqm.
Labour
mason

0.2

150

30

Unskilled labour (2 nos)

0.2

80

16
46

Scaffolding etc.

0.083

80

6.64

Sand screening

0.03

53

1.6

Page 12

One mason pair & 3 male coolie to do


10sqm.. Of BBM
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e .15 x .2 = 0.03 cum of sand
required. (rate 150/- per brass)

0.03

backup calculation

8.2

Providing & laying coursed rubble masonary


1.25 times rubble required than the actual
Labour
mason
Unskilled labour ( 2 nos per mason)
Add for corner stones
add for face dressing of stones

0.46

150

69

0.7

80

56
87

0.24

175.00

41.22

253.22
Scaffolding etc.

0.083

80

6.64

Sand screening

0.07

53

3.7
10.4
29.7

One mason pair to do 150cft. (I.e.4.52 cum)


of rubble masonary
One mason can do 150 cft. Of face dressing
For corner stones preparation , assuming
3.0m length & 1.5m height, corner stones
required 30nos @ 5/- for (.38*3*1.5 = 1.71
cum. I.e 150/1.71 = 87rs. Per cum.
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e .35 x .2 = 0.07 cum of sand
required. (150 per brass)
Rate per cum.

Providing & fixing 150 thk.hollow block


24nos. Of blocks of 150*150*300 are
required for 1sqm.
Labour
mason

0.11

150

16.5

Unskilled labour (2 nos)

0.11

80

8.8
25.3

Page 13

One mason pair & 2 male coolie to do


18sqm.. Of BBM (2 brass)

18.58736059

backup calculation

Scaffolding etc.

0.083

80

6.64

Sand screening

0.03

53

1.6
8.2

Unskilled labour 2 nos. for 1 hour for 3 sqm


area
For 1sqm. I.e .15 x .2 = 0.03 cum of sand
required. (150 per brass)

Providing & fixing 200 thk.hollow block


13nos. Of blocks of 200*200*400 are
required for 1sqm.
Labour
mason

0.11

150

16.5

Unskilled labour (2 nos)

0.11

80

8.8
25.3

Scaffolding etc.

0.083

80

6.64

Sand screening

0.04

53

2.1
8.8

One mason pair & 2 male coolie to do


18sqm.. Of BBM
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e .2 x .2 = 0.04 cum of sand
required. (150 per brass)

Providing & fixing 100 thk.Siporex block


24nos. Of blocks of 150*150*300 are
required for 1sqm.
Labour
mason

0.11

150

16.5

Unskilled labour (2 nos)

0.11

80

8.8
25.3

Scaffolding etc.

0.083

80

6.64

Sand screening

0.02

53

1.1
7.7

Page 14

One mason pair & 2 male coolie to do


18sqm.. Of BBM (2 brass)
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e .1 x .2 = 0.02 cum of sand
required. (150 per brass)

0.193

backup calculation

Providing & fixing 150 thk.Siporex block


24nos. Of blocks of 150*150*300 are
required for 1sqm.
Labour
mason

0.122

150

18.3

Unskilled labour (2 nos)

0.122

80

9.76
28.06

Scaffolding etc.

0.083

80

6.64

Sand screening

0.03

53

1.6
8.2

One mason pair & 2 male coolie to do


18sqm.. Of BBM (150 sft. = 16.4 Sqm.)
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e .15 x .2 = 0.03 cum of sand
required. (150 per brass)

Providing & fixing 200 thk.Siporex block


13nos. Of blocks of 200*200*400 are
required for 1sqm.
Labour
mason

0.122

150

18.3

Unskilled labour (2 nos)

0.122

80

9.76
28.06

Scaffolding etc.

0.083

80

6.64

Sand screening

0.04

53

2.1
8.8

Providing & laying 12mmthk. Internal neeru plaster

Labour
mason

0.1

200

Page 15

20

One mason pair & 2 male coolie to do


18sqm.. Of BBM (150 sft. = 16.4 Sqm.)
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e .2 x .2 = 0.04 cum of sand
required. (150 per brass)
18.75

backup calculation

Unskilled labour (2 nos)

Scaffolding etc.

Sand screening

0.2

80

16
36

0.083

80

6.64

0.012

53

0.6
7.3

One mason can do 10 sqm. Of plaster


Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e 1 x .012 = 0.012 cum of sand
required. (150 per brass I.e. 53 / cum)

Providing & laying 25mmthk. Double coat plaster


19mm of Ist coat in 1:5 & 6mm 2nd coat of
1:4
Labour
mason

0.13

200

26

Unskilled labour (2 nos)

0.27

80

21.6
47.6

Scaffolding etc.

0.083

80

6.64

Sand screening

0.025

53

1.3
8.0

One mason can do 7to 8 sqm. Of plaster &


unskilled labour @2 per mason
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e 1 x .025 = 0.025 cum of sand
required. (150 per brass)

Providing & laying waterproof plaster for toiletsun/sides & Tanks


19mm of Ist coat in 1:4 & 6mm Final coat of
cement
Labour
mason

0.2

225

45

Unskilled labour (2 nos)

0.27

80

21.6

Unskilled labour (2 nos)

0.2

80

16
82.6

0.083

80

6.64

Scaffolding etc.

Page 16

One mason can do 5 sqm. Of plaster &


unskilled labour @2 per mason
Unskilled labour at 2 nos can clean upto
10sqm. Area for receiving plaster
Unskilled labour 2 nos. for 1 hour for 3 sqm
area

backup calculation

Sand screening

0.025

53

1.3
8.0

Labour
mason

0.1

225

22.5

Unskilled labour (2 nos)

0.1

80

Unskilled labour (2 nos)

0.05

80

4
34.5

Scaffolding etc.

0.083

80

6.64

Sand screening

0.008

53

0.4
7.1

0.1

225

22.5

Unskilled labour (2 nos)

0.13

80

10.4

Unskilled labour (2 nos)

0.05

80

4
36.9

Scaffolding etc.

0.083

80

6.64

Sand screening

0.008

53

0.4
7.1

For 1sqm. I.e 1 x .025 = 0.025 cum of sand


required. (150 per brass)

Providing & laying sunk pointing to brickwork

One mason can do 10 sqm. Of pointing &


unskilled labour @1 per mason
Unskilled labour at 1 nos can clean upto
20sqm. Area for receiving poitnting
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of
sand required. (150 per brass)

Providing & laying sunk pointing to Stone masonary


Labour
mason

One mason can do 7.5 sqm. Of pointing &


unskilled labour @1 per mason
Unskilled labour at 1 nos can clean upto
20sqm. Area for receiving poitnting
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of
sand required. (150 per brass)

Providing & laying 20mmthk. single coat plaster


20mm one coat in 1:5

Page 17

backup calculation

Labour
mason

0.1

200

20

0.27

80

21.6
41.6

Scaffolding etc.

0.083

80

6.64

Sand screening

0.02

53

1.1
7.7

0.07
0.2

200
80

14
16
30

Scaffolding etc.

0.083

80

6.64

Sand screening

0.012

53

0.6
7.3

Unskilled labour (2 nos)

One mason can do 10 sqm. Of plaster &


unskilled labour @2 per mason
Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e (1 x .02) = 0.02 cum of sand
required. (150 per brass)

Providing & laying 12mmthk.backcoat to dado works

Labour
mason
Unskilled labour (2 nos)

One mason can do 15 sqm. Of plaster


Unskilled labour 2 nos. for 1 hour for 3 sqm
area
For 1sqm. I.e (1 x .012) = 0.012 cum of
sand required. (150 per brass)

Providing & laying POP over walls & ceiling


20mm one coat in 1:5
Labour
mason

0.1

225

22.5

Unskilled labour (2 nos)

0.1

80

8
30.5

Scaffolding / sand screening etc.

0.1

80

Providing & laying 230thk. Soling

Page 18

One mason can do 10 sqm. Of plaster &


unskilled labour @1 per mason
Unskilled labour 1 nos. for 0.5 hour for 4.35
sqm area ( 1 / .23 = 4.35 sqm.)

backup calculation

20mm one coat in 1:5


Labour
mason

0.1

225

22.5

Unskilled labour (2 nos)

0.1

80

8
30.5

Scaffolding / sand screening etc.

0.1

80

Male coolie
Female coolie

1.25
1.25

80
80

100
100
200

Mason for finishing

0.13

150

19.5

Carpenter for shuttering ( 8sqm per cum.)


Helper for shuttering
Add for deshuttering @ 35%

1.33
1.33

130
100

172.9
133
107.065
412.965

One mason can do 10 sqm. Of plaster &


unskilled labour @1 per mason
Unskilled labour 1 nos. for 0.5 hour for 4.35
sqm area ( 1 / .23 = 4.35 sqm.)

RCC M20 for sloping slab


Labour
For pouring
Assuming that one pair of labour to 0.8 cum
of slab concreting
1.25

Two masons can do finishing of 150 sqm. Of


slab
One carpenter can do 6 sqm. Per day
One helper can do 6 sqm. Per day

Material cost of shuttering

682.5

Hire charges for plate = 20/- per month, we


have two uses per month, i.e rate per sqm =
20, add for wooden runners 4x4 @ 3no.
per sqm.(37.5/-), add for ballies at
2.5*120/10(30) = 20+37.5+30 = 87.5/-

80

Assuming that one pair of labour to 1 cum of


slab concreting

Area of shuttering = 7sqm. Per cum of concrete,


for each Sqm. Cost = 87.5 , add 10/- for shuttering
oil & nails

RCC M20 for Cantilever slabs upto 2.0m span


Labour
For pouring
Male coolie

80

Page 19

backup calculation

Female coolie

80

80
160

Mason for finishing

0.07

150

10.5

Carpenter for shuttering ( 7 sqm per cum.)


Helper for shuttering
Add for deshuttering @ 35%

1.17
1.17

130
100

152.1
117
94.185
363.285

1.25

Two masons can do finishing of 200 sqm. Of


slab of 150mm thk.
One carpenter can do 6 sqm. Per day
One helper can do 6 sqm. Per day

Material cost of shuttering


Area of shuttering = 7 sqm. Per cum of concrete,
for each Sqm. Cost = 117.5 , add 10/- for
shuttering oil & nails
892.5

Hire charges for plate = 20/- per month, we


have two uses per month, i.e rate per sqm =
20, add for wooden runners 4x4 @ 3no.
per sqm.(37.5/-), add for ballies at
(2.5*120)*2/10 i.e. Rs.(60) = 20+37.5+60 =
117.5/117.5

RCC M20 forCopings & sills


Labour
For pouring
Male coolie
Female coolie

1.33
1.33

80
80

106.4
106.4
212.8

Mason for finishing

0.44

150

66

2
2

130
100

260
200
161
621

Carpenter for shuttering (20sqm per cum.)


Helper for shuttering
Add for deshuttering @ 35%
Material cost of shuttering

Page 20

20
66.6666666667
Size of coping = 0.15 x .10
Assuming that one pair of labour to 50 Rmt
of Coping
1.3333333333

one masons can do finishing of 100 Rmt. Of


coping
One carpenter can do 10 sqm. Per day
One helper can do 10 sqm. Per day

backup calculation

Area of shuttering =13 sqm. Per cum of concrete,


for each Sqm. Cost = 764 / 15 = 50.93 , add 10/for shuttering oil & nails

1220

1000 rs. For plywood + 1200 rs. For


wooden runner = (1000+1200)/2.88 = 764
rs. Per Sqm.
50.9333333333

IPS 50mm thk.


Labour
For pouring

Male coolie
Female coolie

0.1
0.1

80
80

8
8
16

Mason for finishing


Mason helper

0.1
0.1

150
80

15
8
23

Carpenter for shuttering ( 7 sqm per cum.)

0.034

130

4.42

Helper for shuttering


Add for deshuttering @ 35%

0.034

100

3.4
2.737
10.557

Material cost of shuttering


Area of shuttering = 0.1sqm. Per sqm of IPS Cost
of shutt =23.35 x.1 = 2.35, add 1/- for shuttering
oil & nails

IPS 50mm thk.


Labour
For pouring

Page 21

Assuming that one pair of labour to 10 sqm


of IPS (4 panels of 2.5 sqm I.e. =1.58x1.58)

one masons can do finishing of above 4


panels of 10 sqm.

One carpenter can do shuttering of about


6.0sqm per day
One carpenter can do shuttering of about
6.0sqm per day
area = 4x1.58x3x.05 = .948 sqm.
Shutt per sqm of IPS = 1.264/10 = 0.0948
Wooden runners of 4"x3" of 2.0m long cost
= (4x3/144)*1.58*3.28*12*225 = 467/-, with
20uses = 23.35

backup calculation

Male coolie
Female coolie

0.1
0.1

80
80

8
8
16

Mason for finishing


Mason helper

0.1
0.1

150
80

15
8
23

For Kitchen Otta ;


Assuming the size of Kitchen otta = 3.0m x 0.75m x 0.810m Ht.
Material cost
Kaddappa
Base
2.46
vertical support
1.215
Granite
3.675
top
2.34
Facia in length & Ht.
0.376
Granite shelf (1.5x.75)
1.125
3.85
4.0425
4.2299125

Assuming that one pair of labour to 10 sqm


of IPS (4 panels of 2.5 sqm I.e. =1.58x1.58)

one masons can do finishing of above 4


panels of 10 sqm.

812.8

220.00
220.00

541.2
267.3

1695.00
1695.00
1695.00

3973.72
637.32
1906.88

Box type waterproofing


Labour
For laying shahabad over mortar bed of 40mm

Male coolie
Mason

0.1
0.1

80
80

8
8
16

Mason for finishing


Mason helper

0.1
0.1

150
80

15
8

Page 22

Assuming that one pair of labour to 10 sqm


of IPS (4 panels of 2.5 sqm I.e. =1.58x1.58)

one masons can do finishing of above 4


panels of 10 sqm.

backup calculation

23

Page 23

backup calculation

ply
battem

ballies

1.34

Page 24

backup calculation

0.375

1.5625

Page 25

backup calculation

Page 26

backup calculation

2.0875

Page 27

backup calculation

Page 28

backup calculation

Page 29

backup calculation

2.00

1.25

Page 30

backup calculation

Page 31

backup calculation

Page 32

backup calculation

Page 33

backup calculation

Page 34

backup calculation

Page 35

backup calculation

Page 36

backup calculation

Page 37

backup calculation

Page 38

backup calculation

Page 39

backup calculation

Page 40

backup calculation

Page 41

backup calculation

Page 42

backup calculation

Page 43

backup calculation

Page 44

backup calculation

Page 45

backup calculation

Page 46

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
P1
Default Date :
Revised on Date :

Item No. : 23
Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Ext. Plaster single coat mortor ratio (1:5)

Providing sand faced plaster externally in cement mortor in all position for a coat of 15 to 20mm thk. in
c.m. 1:5 finishing the surface taking out grains and curing for twenty one days scaffolding etc. complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand

Labours :
for Plastering

Centering & Shuttering


Nil

Others
Scaffolding & sand screening
charges

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

Quantity

Unit

Rate per

Amount

0.16
0.03

Bags
Cum

215.00
1060.00

34.40
31.80

1.00

Sqm

41.60

41.60

1.00

Sqm

7.70

7.70

TOTAL (A)

115.50
2.31
0.58
0.00

TOTAL (B)

118.39
17.76

TOTAL

136.15

2.00%
0.50%
0.00%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

136 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
P2
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/PLAST/V/4


Description :

Dec 30, 99
14-08-06
per sqm

External Plastering Double coat

Providing & applying 23 mm av. Th 1:3 c.m. sand faced plaster in 2 coats (base coat of 15 mm th and
finishing coat of 8 mm th) to concrete & brick surfaces, risers or otherwise including mixing plasticizers &
waterproofing compound supplied free as directed as including curing, scaffolding, corners, & edges,
bands, splays, grroves, drips, offsets (for which no extra payment will be made) curing etc. complete.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand

Labours :
for Plastering

Quantity

Unit

Rate per

Amount

0.22
0.03

Bags
Cum

245.00
1060.00

53.90
31.80

1.00

Sqm

47.60

47.60

1.00

Sqm

7.97

7.97

TOTAL (A)

141.27
2.83
0.71
0.00

Centering & Shuttering


Nil

5
6
7

Others
Scaffolding & sand screening
charges

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.50%
0.00%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

TOTAL (B)

144.80
21.72

TOTAL

166.52

on total (B)

Say Rs.

167 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
P3
Default Date :
Revised on Date :

Item No. : FDAPL/PLAST/V/2


Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Internal Neeru Plaster CM (1:4)-12mm thk.

Providing & applying av. 12 mm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets
etc. for which which no extra payment will be made.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Neeru

Labours :
for Plastering

Quantity

Unit

Rate per

Amount

0.13
0.01
0.10

Bags
Cum
Bags

245.00
1060.00
50.00

31.85
14.84
5.00

1.00

Sqm

36.00

36.00

1.00

Sqm

7.28

7.28

Centering & Shuttering


Nil

Others
Scaffolding charges

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

TOTAL (A)

94.97
1.90
0.47
0.00

TOTAL (B)

97.34
14.60

TOTAL

111.94

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

112 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : Pune
P4
Default Date :
Revised on Date :
Unit :

Item No. : FDAPL/PLAST/V/1


Description :

Dec 30, 99
14-08-06
per sqm

Internal Neeru Plaster CM (1:4) - 20mm thk.

Providing & applying av. 2 cm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets
etc. for which which no extra payment will be made.

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Neeru

Labours :
for Plastering work

Centering & Shuttering

Quantity

Unit

Rate per

Amount

0.17
0.02
0.10

Bags
Cum
Bags

245.00
1060.00
50.00

41.65
25.44
5.00

1.00

Sqm

36.00

36.00

5
6
7

Others
Scaffolding charges

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

2.00%
0.50%
0.00%

15.00%

Sqm

7.28

7.28

TOTAL (A)

115.37
2.31
0.58
0.00

TOTAL (B)

118.25
17.74

TOTAL

135.99

on total (A)
on total (A)
on total (A)

on total (B)

136 /- Per

Say Rs.

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
P2
Default Date :
Revised on Date :

14-08-06

ITEM NO - FDAPL/PLAST/V/10
Unit :
Description :

per sqm

Waterproof plaster

Extra for providing chemical admixtures in plastering for waterproofing as per manufacturer's
specifications.( Pidilite / Laticrete / Roffee/ Fosroc or any other approved make)

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand
c) Waterproofing compound

Quantity
0.34
0.03
0.34

Unit
Bags
Cum
Kg.

Rate per
245.00
1060.00
40.00

Amount
83.30
31.80
13.60

Labours :
for Plastering

Centering & Shuttering


Nil

Others
Sand screening & material shifting

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

Sqm

90.86

90.86

1.00

Sqm

7.97

7.97

TOTAL (A)

227.53
4.55
1.14
0.00

TOTAL (B)

233.21
34.98

TOTAL

268.20

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

268 /- Per

Say Rs.

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
P2
Default Date :
Revised on Date :

Item no - FDAPL/PLAST/V/8

Unit :

Dec 30, 99
14-08-06
per sqm

Description :
Pointing to brick masonary
Providing and making flush groove pointing to brick / block / stone masonry in C:M 1:3 including
scaffolding, curing, cleaning complete with all labour and material.

Sr.No.
Particulars
1 Materials :

Quantity

Unit

Rate per

Amount

a) Cement
b) Sand

0.03
0.01

Bags
Cum

245.00
1060.00

7.35
5.30

Labours :
for Pointing

1.00

Sqm

34.50

34.50

1.00

Sqm

7.06

7.06

TOTAL (A)

54.21
1.08
0.27
0.00

TOTAL (B)

55.57
8.34

TOTAL

63.90

Centering & Shuttering


Nil

5
6
7

Others
Sand screening & scaffolding

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

on total (A)
on total (A)
on total (A)

on total (B)

Say Rs.

64 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
P2
Default Date :
Revised on Date :
Unit :

Item No. : 24 / IV 6
Description :

Pointing to Stone masonary

14-08-06
per sqm

Providing and making sunk


pointing to brick or stone masonry
in C:M 1:3 including scaffolding,
curing, cleaning etc complete with
all labour and material.
Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand

Quantity
0.11
0.01

Unit

Rate per

Bags
Cum

245.00
1060.00
0.00
0.00
0.00
0.00

26.95
5.30
0.00
0.00
0.00
0.00

1.00
0.00
0.00
0.00

Sqm

36.90
0.00
0.00
0.00

36.90
0.00
0.00
0.00

1.00
0.00
0.00

Sqm

7.06
0.00
0.00

7.06
0.00
0.00

TOTAL (A)

76.21
1.52
0.38
0.00

TOTAL (B)

78.12
11.72

TOTAL

89.84

0.00
0.00
0.00
2

Labours :
for Pointing

Amount

Centering & Shuttering


Nil

5
6
7

Others
Sand screening & scaffolding

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

2.00%
0.50%
0.00%

15.00%

Say Rs.

on total (A)
on total (A)
on total (A)

on total (B)

90 /- Per

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
P4
Default Date :
Revised on Date :

Item No. : 26 / IV 10
Description :

Unit :

Dec 30, 99
14-08-06
per sqm

P/A POP plaster to walls

Providing POP plaster to walls

Sr.No.
Particulars
1 Materials :
a) POP

Labours :
for POP work

Centering & Shuttering

Others
Scaffolding charges

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Quantity

Unit

Rate per

Amount

0.13
0.00
0.00
0.00
0.00
0.00

Bags
Cum
Bags

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

1.00
0.00
0.00
0.00

Sqm

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

1.00
0.00
0.00

Sqm

0.00
0.00
0.00

0.00
0.00
0.00

TOTAL (A)

0.00
0.00
0.00
0.00

TOTAL (B)

0.00

2.00%
0.50%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

0.00%

on total (B)

0.00
TOTAL

0 /- Per

Say Rs.

0.00

per sqm

Prepared by :
Name : _________________________________

Sign: ________________

Rate analysis
Site:

0
Computer Code No. :

Location : 0
Default Date :
P4
Revised on Date :

Item No. : 26
Description :

Unit :

Dec 30, 99
14-08-06
per sqm

Back coat for dado work 1:4)

Providing & applying av. 12 cm thick 1:4 C.M. plaster without Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets
etc. for which which no extra payment will be made.(behind tile dado)

Sr.No.
Particulars
1 Materials :
a) Cement
b) Sand

Labours :
for Plastering work

Centering & Shuttering

Others

Quantity

Unit

Rate per

Amount

0.13
0.01

Bags
Cum

245.00
1060.00

31.85
10.60

1.00

Sqm

30.00

30.00

Scaffolding charges

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

Over head & Profit

1.00

2.00%
0.50%
0.00%

15.00%

Say Rs.

Sqm

7.28

7.28

TOTAL (A)

79.73
1.59
0.40
0.00

TOTAL (B)

81.72
12.26

TOTAL

93.98

on total (A)
on total (A)
on total (A)

on total (B)

94 /- Per

per sqm

0.013

0.304
0.00608
0.17024
0.02432
0.1354

0.034

Rate analysis
Site:

0
Computer Code No. :
Item No. : FDAPL/RCC/III/22
Description :

Location : Pune
Default Date :
R1
Revised on Date :
Unit :

14-08-06
MT

Reinforcement works

Providing and laying in position reinforcemnt steel of various diameters incluidng cutting
bending, binding with binding wire for all RCC work like footings, columns, beams, slabs,
paradise staircases, chajjas, walls, etc. as per RCC Specialist's design & drawing details
with necessary bending, laying, binding, with binding wire, etc. complete. Rate to include all
lead & lift.

Sr.No.
Particulars
1 Materials :
a) Reinforcement steel
b) Binding wire

Labours :
for reinforcement works including
cutting, bending, binding etc.
including T & P etc. complete.

Centering & Shuttering


Nil

Others

Quantity

Unit

Rate per

1.00
12.00

MT
Kg

36000.00
38.00

36000.00
456.00

1.00

MT

2143.75

2143.75

TOTAL (A)

38599.75
772.00
0.00
193.00

TOTAL (B)

39564.74
5934.71

5
6
7

Tools & Plants Charges


Water charges
Electricity Charges

2.00%
0.00%
0.50%

on total (A)
on total (A)
on total (A)

Over head & Profit

15.00%

on total (B)

Amount

TOTAL

Say Rs.

45,499 /- Per

45499.46

MT

Prepared by :
Name : _________________________________

Sign: ________________

Site Name : 0
Location : Pune
SINGLE LINE ESTIMATION
Sr.No.

Description

1 Excavation in soil and soft murum upto 1.5


2 Err:509
3 Excavation in Hard Murum & boulders
4 Excavation in Soft Rock
5 Excavation in Hard Rock by chiselling
6 P.C.C. (1 :2:4 )
7 P.C.C. (1 : 4: 8 )
8 Err:509
9 C.C. M20 for Footing, raft
10 Err:509
11 C.C. M20 for superstructure Columns
12 Err:509
13 C.C. M20 for floor Beams
14 Err:509
15 C.C. M20 for slab
16 C.C. M20 for Staircase
17 RCC M20 for Pardi, fins
18 UCR In plinth
19 Brick masonary 35cm thk. Below plinth
20 Brick work 35cm thk. In superstructure
21 Plinth Masonry 23cm thk
22 Err:509
23 Ext. Plaster single coat mortor ratio (1:5)
24 External Plastering Double coat
25 Internal Neeru Plaster CM (1:4)-12mm thk.
26 Err:509
27 Grey Mosaic Tile Flooring of 25cm x 25cm
28 Err:509
29 Err:509
30 Err:509
31 Err:509
32 Brickbat water proofing for toilets
33 Brickbat water proofing for terrace
34 Chemical w/p for terrace, toilets
35 Reinforcement works
36 Structural steel works
37 12mm dia. Fan hook
38 Chainlink fencing
39
0
40
41
0
42
0
43
44
45
46
47
48
49
50

Unit
per cum
Err:509
per cum
per cum
per cum
per cum
per cum
Err:509
per cum
Err:509
per cum
Err:509
per cum
Err:509
per cum
per cum
per cum
per cum
per cum
per cum
Err:509
Err:509
per sqm
per sqm
per sqm
Err:509
per sqm
Err:509
Err:509
Err:509
Err:509
per Cum
per sqm
per sqm
MT
per Sqm.
per No.
per Sqm.
0
0.03
0.005
0.005

Quantity

Rate

0
90
0.00 Err:509
0.00
107
0.00
289
0.00
777
0.00
3312
0.00
2544
0.00 Err:509
0.00
3281
0.00 Err:509
0.00
5171
0.00 Err:509
0.00
5297
0.00 Err:509
0.00
4428
0.00
5427
0.00
6281
0.00
1985
0.00
2335
0.00
2439
0.00
2086
0.00 Err:509
0.00
136
0.00
167
0.00
112
0.00 Err:509
0.00
334
0.00 Err:509
0.00 Err:509
0.00 Err:509
0.00 Err:509
0.00
2818
0.00
344
0.00
327
0.00
45499
0.00
43578
0.00
32
0.00
259
0.00
0
0.00
0
0
0

Total :

0
Pune
SINGLE LINE ESTIMATION
Amount
0.00
Err:509
0.00
0.00
0.00
0.00
0.00
Err:509
0.00
Err:509
0.00
Err:509
0.00
Err:509
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Err:509
0.00
0.00
0.00
Err:509
0.00
Err:509
Err:509
Err:509
Err:509
0.00
0.00
0.00
0.00
0.00
0.00

Err:509

You might also like