Professional Documents
Culture Documents
06 A Cost Control
06 A Cost Control
Cost Management : an
overview
Constraints
Control Costs
MONITORING &
CONTROLLING PROCESSES
Determine
Budget
PLANNING
PROCESSES
INITIATING
PROCESSES
CLOSING
PROCESSES
EXECUTING
PROCESSES
Estimate Costs
Determine Budgets
Cost Control
Cost Control
CC. Concept
Strategic
FORECAST
PLANNING
Strategic
FORECAST
IMPLEMENTATION
Monitoring
Monitoring
Monitoring
#1
Earned Value
Earned Value
Cumulative Value
Planned Value
Budget at
Completio
n (BAC)
Actual
Cost
Earned Value
Data Date
Time
Cost Variance CV = EV - AC
(+) = under budget
(-) = over budget
Schedule Variance SV = EV - PV
(+) = ahead schedule
(-) = behind schedule
EV. CV and SV
Cumulative Value
Planned Value
Actual
Cost
Cost Variance =
EV - AC
Budget at
Completio
n (BAC)
Schedule Variance =
EV - PV
Earned Value
Data Date
Time
EV
Performance
Above Plan
AC
BCWP
ACWP
Performance
Below Plan
2.5
1.5
1.5
0.5
1
0.5
1
1.5
2.5
1.5
0.5
0.5
1
EV. Example #1
Selamat!
Saya
memberi
Anda
kontrak
Pembangun
an Jalan Rel
baru
hmm... Sepanjang
5km, dalam 5
bulan, maka akan
selesai dengan
total biaya $5,000
Bulan 1
Bulan 2
Bulan 3
PV = $1,000 PV = $1,000 PV = $1,000
Bulan 4
Bulan 5
PV = $1,000 PV = $1,000
Month
Cost ($)
% complete
1,000
20%
2
1,000
40%
3
1,000
60%
4
1,000
80%
5
1,000
100%
PV
Bulan 1
Bulan 2
PV = $1,000PV = $1,000
Illustration Summary
1
Month
Cost ($)
1,000
% complete
2
1,000
20%
40%
3
1,000
60%
4
1,000
80%
5
1,000
PV
100%
CONTROL POINT
at Control Point :
PV = $2,000
EV = $1,000
Actual Progress
AC = $2,400
= 20%
Progress
Status
Cost
Actual Cost Spent = $2,400 Status
The Measurenment
Cost Variance CV = EV - AC
Schedule Variance SV = EV - PV
SV = $1,000 - $2,000 = - $1,000
(-) = behind schedule
#2
Forecasting
Forecasting
Forecasting:
F. Estimate to Complete
New estimates:
ETC = ETCbottom-up
ETC = BAC - EV
F. Estimate at Completion
New estimates:
EAC = AC + ETCbottom-up
#3
To-Complete Performance
Index
To-Complete Performance
Index
TCPI is the calculated projection of
cost performance that must be
achieved on the remaining work to
meet a specified management goal,
such as the BAC or the EAC.
TCPI
as the work remaining (BAC
minus EV) devided by the funds
remaining (BAC minus AC, or EAC
minus AC)
Formula TCPI = [ BAC - EV ] / [ BAC AC ]
Or TCPI = [ BAC - EV ] / [ EAC - AC ]
To-Complete Performance
Index
Terima Kasih
Semoga Bermanfaat