You are on page 1of 26

Delhi Metro

A Project Management Bench Mark


Presentation
By

Kumar Keshav
Director (Project &Planning), DMRC
23rd June, 2011

Delhi Metro Rail Corporation (DMRC)


Set up in May95 under the Indian Companies
Act.
A joint venture between the Federal
Government of India and the Provincial
Government of Delhi State, with equal equity.
DMRC has the responsibility for construction
and operation of Delhi Metro.

Delhi Metro Rail Corporation (DMRC)

A Master Plan had been drawn up for Delhi Metro


expansion, consisting of 12 lines, covering 420
kms. to be completed by 2021 in four Phases.
Works started on Phase I on 1st October, 1998 and
completed in December, 2005.
Phase-I 65 kms. Cost US $ 2.5 billion. Completed in 7
years and 3 months (2 years & 9 months ahead of
schedule)

Delhi Metro Rail Corporation (DMRC)

Phase-II covers 124 kms. This also includes a high


speed Metro connection from centre of the city to
the new airport in 18 minutes.
Phase-II works commenced in January 2006 and
completed in October, 2010 5 months ahead of
schedule.
Phase-III will consist of about 104 km at a cost of
US $ 8.6 billion. The first contract for Phase-III has
since been awarded.
4

Funding of the Metro


20% of the cost is borne by the Federal Government.
20% of the cost is borne by the State Government.
About 50 60% of the cost through JICA Loan.
5% of the cost
Development.

by

DMRC

through

Property

Operation Highlights
2500 train trips with 200 train sets on 6 lines.
Each train used to consist of 4 coaches. Trains
progressively being lengthened to 6 coaches and
finally to 8 coaches.
Average daily ridership - About 16.5 lakh
passengers with average lead of 14 kms.
Frequency during peak hours 2 m 30 sec.
System
fully Barrier Free for Physically
challenged.
DMRC has introduced feeder bus short loop services

Punctuality measured with a least count of 60 Sec.


and average punctuality percentage is above 99%.
6

Financial Success of Delhi Metro


Fare : From Rs. 8/- (17 cents) to Rs. 30/- (65 cents) fare structure lowest in the world except Kolkata.
The system making operational profit from Day-1.
Delhi Metro receives no subsidy from the two
Governments.
We are able to meet the operating and maintenance
expenditure fully.
In addition we are servicing and repaying the loans
taken from JICA.
20% of DMRCs revenue is from Non-operational
sources mainly real estate development and
advertisements.

Challenges in Implementation
Delhi Metro Project is the biggest urban intervention
since Independence.
Project is to be executed in very difficult urban
environment.
Being in the capital city all actions under close
scrutiny of VVIPs.
Project approved on completion cost.
The Project implementation period extremely
compressed and strict completion targets.
Metro being constructed to world class standards with
frontline technologies.

Challenges

The sensitivities of the city to be respected during


construction No hardship or inconvenience to
the public Calcutta Experience.
Each days delay in completion of project costs
DMRC Rs. 2.3 Cr (Rs. 1.4 Cr by way of escalation
and Rs.90 lakh by loss of revenues).

Constraints in Project
Implementation

Large scale land acquisition in the city

Tree cutting permission


- Substantial No. of trees are transplanted.
- For every tree cut, compulsory afforestation of 10
trees is undertaken.
Utility diversions for Telecom, Electrical, Sewerage &
Water pipe lines
Special permissions such as for Ridge (Reserve
Forest) Land, from Archaeological Survey of India ,
National Monument Authority

How Challenges have been met

Work Culture & Organizational Values of DMRC


1. Punctuality.
2. Integrity highest premium
3. Professional Competence.
4. Physical Fitness.
5. Quick Decision Making
6. High Discipline and loyalty to the Organization.
7. Prompt response to the needs of the Public
and Contractors.

Dynamic Management Style


Corporate Mission and Corporate Culture
A slim but effective organization - No ineffective
layers such as clerks, peons
Reverse Time clocks.
Democracy in management Weekly HOD
meetings and Monthly Dy. HOD meetings.
Discourage paper oriented work replies to
outsiders within 10 days.
Predominant use of information systems.
High premium for integrity in the organisation

Dynamic Management Style


Ample delegation of powers accountability with
delegation
Redefined the role of Finance Finance equally
accountable with executive.
Officers encouraged to take decisions on the spot.
The fear of Audit and Vigilance not allowed to cramp
the style.
Leading from the front and not pushing from the rear.
- Top Management readily available for decisions.

Management based on trust

Project Monitoring at all Stages

Tendering & Award of work


General philosophy success of the project depends
upon success of the contractors.
Tenders from Pre-qualified list of bidders
A unique filtering criterion evolved for prequalification
covering vital items of technical & financial capabilities
of the tenderers
Objective evaluation criteria based on scoring system
The tender conditions finalized keeping in view the JBIC
Procurement guidelines, FIDIC document and Indian
Contract Act .
Full powers for dealing with the tenders within organization

Tenders are decided fast so that no lobbying is


possible.

Monitoring during execution


Contractors prepare detailed Base line work
schedule for execution including duration of
activities and identification of critical activities/path
Close monitoring of work schedule, mobilization of
Manpower, Machinery & Plant and Materials
Weakly meetings with Contractors for planning the
work and solving their problems.
Practical approach to solve the genuine problems
of contractors.
Failing contractors are enabled to perform by
timely assistance.
Streamlined prompt payment procedure and quick
decision-making.

Monitoring during execution

Stringent penalties for failures to deliver.


Prompt resolution of claims.
Round the clock supervision guaranteed
Strict independent quality & safety audit.
Monthly progress presentations by the
contractors
DMRC directly handles works pertaining to other
Government and Civic Departments to speed up.
Have been able to establish that we are different
than the normal executing agencies and mean
business.

Interface Management
Interface Management
- Access dates and Key dates listed in
contract document itself.
The important items which require interface with other
contractors are clearly identified and indicated in
contracts.
Other contractors with whom the contractor has to
interface are also clearly defined.

Monitoring during Testing & Commissioning


Each activity of testing identified and duration of
all these activities pre-determined
Trials conducted as per schedule pre-determined
jointly by System Contracts
Service trial schedules also laid out in advance
Sufficient time provided before actual
commissioning

Training and motivation of employees


A rigid screening process for inducting staff and
officers.
Training and exposure in the appropriate areas.
Management objectives and philosophy clearly
shared with executives and staff.
Chief Executive and Top Managers themselves set
an examples.
Immediate appreciation and reward for good work
done but no castigation for failures.
No witch hunting for genuine mistakes.
Officers encouraged to take quick decisions . Tendency to
push decisions to higher levels curbed.

Public relations initiative


Works planned and managed with the least
inconvenience to the public.
Press regularly briefed on the progress and
programmes.
Community interaction at difficult work sites.
Proper barricading and good house keeping.
Proper signages, security men to guide traffic.
Special measures taken to protect the environment.
Control on noise levels and vibrations during
work.
Washing tyres of vehicles.
Performance is our best publicity. Have
been able to establish credibility with the
public by delivery on time.

Benefits of Delhi Metro


A study by CRRI has brought out benefits of Delhi
Metro Phase-I and worked out EIRR = 19.96%.
Thus the entire cost of Phase-I recovered by the city
of Delhi in 5yrs by 2010.

DMRC: An organisation with a


difference..

Thanks
DMRC Ltd.
Metro Bhawan,
Fire Brigade Lane,
Barakhamba Road,
New Delhi - 110 001.

SHAHD
ARA
MANSA
ROVAR
PARK
JHILMIL

H
AR

D
AN
N
A BT
IS

R
HA
I
V

VI

M
EX AY
T. UR

JAM
NA IA
GA
JOK
R
V HA

IHA LA
R
H J
ARAS
OL
AV
IHA
R

JO
O I KHASHRAM
AL
V II
AP
O IND
H
KH P ISHW A
LA UN
RIAGA R
R

SRINIVASPURI

SA
R

IT
A

VI

PANCHSHEEL
PARK
CHIRAG DELHI
G. K. ENCLAVE

NEHRU
PLACE

SO
U
EX T H
TN

OJI
NI
NA
GA
R

R.
PU K.
RA
M

KA

ARJAN GARH

SA
R

AM
A

BA
G
H

TI

B
PL HIK
AC AJ
E IK
MU
NI
R

VA
VIH SANT
AR

GURU D
RONAC
HARYA

SIKAND
ARPUR

SULTANPUR
GHITORNI

DILSHA
D GARD
EN

LAXMI
NAGAR
NIRMAN
VIHAR
PREET
VIHAR
KARKAR
DUMA

YAMUNA
BANK

SEELAM
PUR

SHASTR
I PARK

AZAR
TIS H

H
NGAS

A
PULB

R
PRATAP NAGA

RL
OK
SHASTR
I NAGAR

IN
DE

KIRTI N
AGAR

SHADIP
UR
PA
TE
LN
AG
RA
AR
JE N
DR
AP
KA
L
RO
L
BA
G
H

KU
A

LA

M
O

HA
U

I.G
AIR .D.
T POR
D

PO
RT

AI
R

M G RO
AD

DWARKA SEC 21

HUDA CITY CENTRE

RAJOUR
I GARD
EN
RAMESH
NAGAR
MOTI N
AGAR

SUBHAS
NAGAR
TAGORE
GARDEN

TILAK N
AGAR

NAGAR
WEST

UTTAM
NAGAR
EAST
JANAKP
URI WES
T
JANAKP
URI EAST

NAWAD
A

UTTAM

DWARK
A MOR

13
PALA
KA
C2
-1
AR
SE
M
W
A
EC
D
K
1
S
1
AR
KA
CW
E
R
S
D
A
KA
10
DW
CAR
W
SE
8
9
D
A
C
K
CSE
SE
AR
A
A
K
K
DW
AR
AR
DW
DW

IFFCO CHOWK

MN

DABRI
MOR

YAMUNA
VIHAR

AG
PR

14
CSE

CRI
PU
AK
N
JA
2B
DHSRATH
PURI

RD K
K W
B HO
C
J IV
RA

DWARKA

GA
R

IP

U
R

C.
AL
18
IM
AR
H
AD I
NA
P
GIN
LA
AR
RPG
SH
CE
UIRR
NA
JAJ
HAA

MU
ND
KA
RA
J DH
AN
IP
AR
K
NA
NG
LO
IR
NA
LY.
NG
ST
LO
N
I
SU
RA
JM
AL
ST
UD
AD
YO
IU M
GN
A
PE
GA
ER
R
AG
AR
HI
PA
SC
H IM
RI
VIH
TH
AR
PA
AL
SC
RO
W
A
HIM
HI
NI
VIH
W
AR RO
E
HI
ST
E
MA
NI
DIP
EA
PIT
UR
ST
AM
BA
SH
PU
IVA
D
RA
KO
JI P
LI
RO
HA
AR
T
K
H
EN
I
NI
C
N S PLA LAV
SE
CE
E
SH

L
R
YA
AD
DE
LA
GA
SHALIMAR
AZ MO
YA
NA
ID
B
BAGH S
V
A
GT
M
WA
BH
PR
VIS
SA
AV YA
N
H
I
A
S
H
MAUJPUR
A
KE
ESE
NH
VID
LINER
KA R
L
G
I
M
R N
V
JAFFRABAD
SHAKURPU
CI SH RE
ASHO
KA MTEE
K
A
H
SG
WEL
PARK
KA TE
COM
I
E
JAB
GA
AR
PUN H SRS
BHOLANATH NAG
LAL
M
G
CH
ANDNI CHOW QUILA
ESI BA
HA
K
MARG
AR
L
I
NAG
N
ITA
US
ARJU
HOSP
CHAWRI BA
A
AL
K I
ZAR
SH
JAMA
I
B
N
DL S
VA
MASJID
R I`
JAGATPURI
PU
R K ASH
DELHI
YA
RAM
A
L
MA
GATE
A
W
AM
IT
IP EXTN N
H
DE
O
RD
AN
E
US
HO
A
H
I
ND
J
M
I D NAGAR
MA
H
VINO
U
I
R
S
K
2
AD
OW
AK
HA
IN A
ST
CH
VI
IND
RA
JI
EL
J
R
T
I
A
R
l
NA
A
tra
A
A
Cen
P
U
IV
H
PRA
NA
ST H
AY
SHSECCen
EL TT
TT tral
PA
TRILOKPURI
M
A
1 D AN
TT BHAWAN
R
TH
SEC
A
C
OG
N
UDY
VIH
DHAULA
KUAN
UR
AI
NGAR
MAY
K
R
H
AN MA
NA
RKET
OK
15
ph-1
H
R
RACE COURSE
O
AS
T
HA
ZARAT
C
16
IUM
W
TAD
R
18
SE
NE
O
JLN S
A NIZAMUDDIN
R
A
T
R
JOR BAGH
O
C
U
ID
T
P
E
C
S
NO
NG
R
A
SE
INA
JA
AGA
ID
A
AT N
NOIDA CITY CENTRE
LAJP
NO OID
N
S
GOLF
COURSE
M
I
AI
D
HAN
K OLC
Y
ARMO
LON
P
O
BOTANICAL
GARDEN
C
N
SH
BOTANICAL
EE
E
AILA
DELHI AEROCITY
K
GR
S
AMITY NOID
A
L
A
P AC
A
L
H
U
R
K
.
GARDEN
SO
NEH
I.TAUZ
JA
DIR
I.H
MAN
E
AR
LKAJI
T
G
A
A
K
A
N
ST
VIYA
NE
MAL
HA
MO
SAKET
AD
AB
AK
HL
G
U
T
QUTAB MINAR
R
RPU
DA
CHHATARPUR
BA

JANAKPURI
WEST

P UR
ND
U
K
MUPUR TOWN

KALINDI
KUNJ

You might also like