You are on page 1of 32

METHODS OF PRESTRESSING

IN CONCRETE

PRESTENSIONING & POSTTENSIONING

PRESTRESSED CONCRETE
PRINCIPLE Using high tensile strength

steel alloys producing permanent precompression in areas subjected to Tension.


A portion of tensile stress is counteracted

thereby reducing the cross-sectional area of


the steel reinforcement .
METHODS :-

a) Pretensioning
b)Post-tensioning

PRETENSIONING :- Placing of concrete

around reinforcing tendons that have been


stressed to the desired degree.
POST-TENSIONING :- Reinforcing tendons

are stretched by jacks whilst keeping them in


serted in voids left pre-hand during curing of
concrete.
These spaces are then pumped full of grout to

bond steel tightly to the concrete.


STEEL BARS BEING
STRETCHED BY JACKS

POST - TENSIONING
WHAT IS POST-TENSIONING?
Post-tensioning-

is a method of reinforcing
(strengthening) concrete or other materials with highstrength steel strands called tendons.

Post-tensioning

allows construction that would


otherwise be impossible due to either site
constraints or architectural requirements.

Requires specialized knowledge and expertise to

fabricate, assemble and install.


After

adequate curing of concrete, reinforcing


tendons (placed in side the voids of the structure)
are tensioned/stretched by jacks on the sides &
grouts filled with appropriate mix.

Applications

a) Structural members beams,


bridge-deck panels, Roof Slabs, Concrete Silos
Etc.

POST TENSIONING METHOD

BENEFITS

Concrete is very strong in compression but


weak in tension,\

This deflection will cause the bottom of the beam

to elongate slightly & cause cracking.


Steel reinforcing bars (rebar) are typically

embedded in the concrete as tensile


reinforcement to limit the crack widths.
Rebar is what is called passive reinforcement

however; it does not carry any force until the


concrete has already deflected enough to crack.

Post-tensioning tendons, on the other hand, are


considered active reinforcing.

Because it is prestressed, the steel is effective

as reinforcement even though the concrete may


not be cracked .
Post-tensioned structures can be designed to

have minimal deflection and cracking, even


under full load.

Post Tensioned Structure

ADVANTAGES/APPLICATIONS
Post-tensioning allows longer clear spans, thinner

slabs, fewer beams and more slender, dramatic


elements.

This innovative form is result of


post tensioning.

Thinner slabs mean less concrete is required. It

means a lower overall building height for the same


floor-to-floor height.
Post-tensioning can thus allow a significant

reduction in building weight versus a conventional


concrete building with the same number of floors
reducing the foundation load and can be a major
advantage in seismic areas.
A lower building height can also translate to

considerable savings in mechanical systems and


faade costs.
Another advantage of post-tensioning is that beams

and slabs can be continuous, i.e. a single beam can


run continuously from one end of the building to
the other.
Reduces occurrence of cracks .
Freezing & thawing durability is higher than non

prestressed concrete.

Bridge decks

Post-tensioning is the system of choice for parking structures

since it allows a high degree of flexibility in the column layout,


span lengths and ramp configurations.

In areas where there are expansive clays or soils with low


bearing capacity, post-tensioned slabs-on-ground and mat
foundations reduce problems with cracking and differential
settlement.

Post-tensioning allows bridges to be built to very


demanding geometry requirements, including complex
curves, and significant grade changes.

Post-tensioning also allows extremely long span bridges to be


constructed without the use of temporary intermediate
supports. This minimizes the impact on the environment
and avoids disruption to water or road traffic below.

In stadiums, post-tensioning allows long clear spans and very


creative architecture. \

Post-tensioning can also be used to produce virtually crack-free


concrete for water-tanks.

The high tensile strength & precision of placement gives


maximum efficiency in size & weight of structural members.

Applications of various prestressed techniques enable quick


assembly of standard units such as bridge members,building
frames, bridge decks providing cost-time savings.

In slab-on-ground construction, unbonded tendons


are typically prefabricated at a plant and delivered to
the construction site, ready to install.

The tendons are laid out in the forms in accordance


with installation drawings that .

After the concrete is placed and has reached its


required

CONSTRUCTION
strength, usually between 3000 and 3500 psi
(pounds per
square inch), the tendons are stressed and
anchored.

The tendons, like rubber bands, want to return to


their original length but are prevented from doing so
by the anchorages.

The fact the tendons are kept in a permanently


stressed
(elongated) state causes a compressive force to act
on the
concrete.

The compression that results from the post-tensioning


counteracts the tensile forces created by subsequent
applied loading (cars, people, the weight of the
beam itself when the shoring is removed).

This significantly increases the load-carrying capacity


of the concrete.

Since post-tensioned concrete is cast in place at the


job site, there is almost no limit to the shapes that can
be formed.

Limitations of Prestressing
The limitations of prestressed concrete are few and really
depend only upon the imagination of the designer and the
terms of his brief. The only real limitation where
prestressing is a possible solution may be the cost of
providing moulds for runs of limited quantity of small
numbers of non-standard units.

Method of post-tensioning
Wedges tensioned by
Tendons

jacks
TENDONS

PRESTRESSED CONCRETE
Prestressed concrete, invented by Eugene

Frevssinet in 1928 is a method for overcoming


concretes natural weakness in tension . It can
be used to produce beams , floors or bridges
with a longer span than is practical with
ordinary reinforced concrete.
It can be accomplished in three ways: pretensioned concrete, and bonded or unbonded.

Pre-tensioned concrete

Pre-tensioned concrete is cast around already tensioned


tendons.
This method produces a good bond between the tendon
and concrete, which both protects the tendon from
corrosion and allows for direct transfer of tension.
The cured concrete adheres and bonds to the bars and
when the tension is released it is transferred to the
concrete as compression by static friction.
However, it requires stout anchoring points between
which the tendon is to be stretched and the tendons are
usually in a straight line.
Thus, most pretensioned concrete elements are
prefabricated in a factory and must be transported to the
construction site, which limits their size.
Pre-tensioned elements may be balcony elements, lintels
, floor slabs, beams or foundation piles.

Bonded post-tensioned concrete


Bonded post-tensioned concrete is the descriptive term for a

method of applying compression after pouring concrete and


the curing process (in situ).
The concrete is cast around a plastic, steel or aluminium

curved duct, to follow the area where otherwise tension would


occur in the concrete element.
A set of tendons are fished through the duct and the concrete is

poured. Once the concrete has hardened, the tendons are


tensioned by hydraulic jacks.
When the tendons have stretched sufficiently, according to the

design specifications they are wedged in position and maintain


tension after the jacks are removed, transferring pressure to
the concrete.
The duct is then grouted to protect the tendons from corrosion.

This method is commonly used to create monolithic slabs for


house construction in locations where expansive soils create
problems for the typical perimeter foundation.
All stresses from seasonal expansion and contraction of the

underlying soil are taken into the entire tensioned slab, which
supports the building without significant flexure. Post-stressing
is also used in the construction of various bridges.
The advantages of this system over unbonded post-tensioning

are

DECK STEEL LAYING

Large reduction in traditional reinforcement

requirements as tendons cannot destress in


accidents.
Tendons can be easily 'weaved' allowing a
more efficient design approach.
Higher ultimate strength due to bond
generated between the strand and concrete.
No long term issues with maintaining the
integrity of the anchor/dead end.

Unbonded post-tensioned
concrete
Unbonded post-tensioned concrete differs

from bonded post-tensioning by providing


each individual cable permanent freedom of
movement relative to the concrete.
To achieve this, each individual tendon is
coated with a grease (generally lithium
based) and covered by a plastic sheathing
formed in an extrusion process.
The transfer of tension to the concrete is
achieved by the steel cable acting against
steel anchors in the perimeter of the slab.
The main disadvantage over bonded posttensioning is the fact that a cable can
destress itself and burst out of the slab if
damaged (such as during repair on the slab).
The advantages of this system over bonded
post-tensioning are:

External Prestressing

This refers to the case where prestressing tendons are


placed outside the concrete section and the
prestressing force is transferred to a structural member
through end anchorages or deviators. Advantages of
external prestressing include the possibility of
monitoring and replacing tendons, ease in concreting
and hence better concrete quality and the use of
narrower webs. External prestressing is being
increasingly used in the construction of new bridges
and is a primary method for the strengthening and
rehabilitation of existing structures.

At NUS, a three-year project on the application of


external prestressing in structural strengthening has
been completed, and this has resulted in design charts
being developed for such applications. Works were
also carried out on the use of fibre-reinforced polymer
(FRP) reinforcement as external tendons in both
simply supported and continuous beams.

APPLICATIONS
Fallingwater is comprised of a series of concrete cantilever
trays 30-ft. above a waterfall. Previous efforts failed to
permanently address excessive deflections of the cantilever
and repair the cracks. After a thorough design review, the
owner and engineer selected an external post-tensioning
solution for its durability, aesthetics and structural
unobtrusiveness.
Construction plans called for strengthening of three support
girders spanning in the north-south direction with multistrand
post-tensioning tendons consisting of multiple 0.5 diameter
strands.
Thirteen strand tendons were placed on each side of two
girders. One 10-strand tendon was placed on the western side
of the third girder (access on the eastern side of this girder
was not available). Eight monostrand tendons, 0.6 diameter,
were slated for the east-west direction.
The monostrand tendons were stressed in the east-west
direction and then the multistrand tendons were stressed in
the north-south direction and grouted with a high quality, lowbleed cementitious grout mixture.
VSLs scope of work also included welding steel cover plates,
attaching structural steel channels, injecting epoxy grout,
doweling reinforced cast in place concrete blocks and the
installation of near surface mounted carbon fiber rods.
Challenged with maintaining Fallingwaters original setting,
furnishings and artwork, the project was successfully
completed in six months.

The lower and upper terraces cantilever


over the stream below. The temporary
structural steel shoring was placed beneath
the main level terrace.

Frank Lloyd Wright's Fallingwater


Mill Run, Pennsylvania

Cline Avenue Bridge


Gary, Indiana

The Cline Avenue Bridge (SR 912) is a predominately cast-in-place post-tensioned


structure located in Gary, Indiana. The bridge mainline is over 6,000 LF, has two
adjacent segments nearly 35 feet wide each, and contains four connecting ramps. An
inspection and analysis team was assembled to perform a thorough investigation of
the bridge. The team concentrated on the existing post-tensioning system and interior
and exterior concrete cracks. The engineer retained VSL to assist with the inspection
of the tendons.

VSL approached the Cline Avenue project with a guideline that outlines a statistically
sound method of sampling the tendons. A statistical sample pool (which consisted of
the mainline structure and the ramps) was defined by referencing the American
National Standard Institutes (ANSI) guideline Sampling Procedures and Tables for
Inspection by Attributes as published by the American Society for Quality Control
(1993).

The probable void locations throughout the structures mainline segments and ramps
were initially identified by VSL to appropriately distribute the sampling population.
Such areas consisted of high points, areas approaching and leaving the high points,
and couplers.

Using non-destructive Ground Penetrating Radar (GPR) and field layout drawings,
VSL located existing post-tensioning tendons. Once the layout was performed,
specific tendons throughout the bridge and ramp structures were sampled by drilling
into the duct and exposing the tendon for visual inspection. The use of a borescope
allowed for detailed visual inspection of the tendon and also captured video footage
to share with the owner and the engineer. After review of each inspection, VSL placed
epoxy in the borescope hole to protect the tendons from air and moisture intrusion.
When voids were encountered, the project team observed and documented the
condition of the strand based on the PCI Journal guideline, Evaluation of Degree of
Rusting on Prestressed Concrete Strand. VSL used vacuum grouting technology to
fill the void, thereby protecting the previously exposed strand.

The tendon inspection data was analyzed with other findings (such as crack survey
findings) to determine what type of rehabilitation was required. VSLs goal to establish
a statistically sound sample of physically inspected tendons that provided valid data
as to the current state of the existing PT system was accomplished
Grouting of void using VSLs specialized vacuum grouting equipment

85th Street Bridge


Valley Center, Kansas

The 85th Street North Bridge is a seven span post-tensioned


haunched slab bridge with a typical span of 26 meters for the
middle five spans, and 20 meters at the ends. This 170 meter
long bridge accommodates two lanes of traffic reaching over
the Wichita Valley Center Floodway. VSL post-tensioning
systems utilized for this project include 5-19 longitudinal
tendons as well as 6-4 transverse tendons.

Post-tensioned haunched slab bridges are noted for ease of


construction. Once the geometry of the bridge falsework has
been obtained, prefabricated spacer frames are set into
place. The spacer frames serve as templates for profiling the
longitudinal post-tensioning tendons and aid in the placement
of the remaining conventional reinforcement. Transverse
tendons maintain mid-depth placement along the geometry
of the haunched slab and provide the minimum precompression over the length of the structure.

The fi nished product has several advantages over


conventionally reinforced concrete. Dead loads are balanced
by the use of longitudinal post-tensioning reducing the
sustained loading and associated creep. Corrosion
resistance is increased due to the encapsulation of the posttensioning reinforcement. Through the use of transverse
post-tensioning, added compression improves the longevity
of the structure by adding resistance to de-icing methods
such as salt and magnesium chloride. Post-tensioned
haunched slab bridges allow for a larger span to depth ratio
than that of conventionally reinforced haunched slab bridges.
The labor and material savings on mild reinforcement is
Overlooking the 85th Street Bridge prior to concrete placement
another clear advantage to using post-tensioning for this
application.

Colorado Convention Center


Expansion
Denver, Colorado

The Colorado Convention Center Expansion


project is a 1.4 million square foot expansion of
the existing facility. This was a multi-level
project, which included a 1,000-car attached
parking garage.

The garage above the street was constructed


using precast tees and columns with a cast-inplace topping slab. In order to maintain regular
spacing for the columns in the precast section
of the garage and still maintain an
unobstructed path for the road and light rail,
large post-tensioned transfer girders were
required to support several of the columns
above. The transfer girders allowed for the
placement of columns required for the precast
design despite the restricted column locations
at the street level.

Post-tensioning the transfer girders resulted in


smaller dimensions than a conventional
reinforced concrete design, an important factor
given the girders are over 7 feet high and up to
7 feet wide and a larger section would not fit
within the space constraints of the building.
The girders could not be stressed until after the
precast garage was fully erected and the
topping slab poured on the truck dock.
Temporary columns were placed under the
girders to support the load until stressing.

The effective post-tensioning force required for


the beams ranged from 2176 to 5457 kips. A
multistrand bonded system was installed

The Seward Silo project involved the post-tensioning of three


interconnected ash silos that are part of the Seward Re-Powering
Project in Seward, Pennsylvania. The overall project involved the
construction of a new, state-of-the-art 208 MW power plant designed to
burn low-grade coal that can not be burned in ordinary coal plants. This
is a design-build project with Drake-Fluor Daniel as the
owner/construction manager until the completed plant is turned over to
Reliant Energy, the ultimate owner.

T.E. Ibberson Company was contracted to build three 187-6 tall,


interconnected, in-line silos; two 82-4 diameter fly ash silos and one
64-8 diameter bed ash silo. The silos were built using the slip-form
method of construction and are believed to be the first interconnected
silos in the world built using post-tensioning as the primary
circumferential reinforcement.

VSLs work was performed from November 2003 through February


2004, during the second coldest winter on record locally. Significant
snowfall and subzero temperatures made progress challenging, yet with
a strong focus on safety, both cold-related and otherwise, the job was
completed with no incidents. The job required close coordination
between the various trades working in close proximity and constant
communication between parties working above and below VSLs work
locations to phase the work to avoid having personnel under an active
work zone.

The strand installation, stressing and grouting operations were


completed successfully, with cold-weather grouting made possible
through a variety of heating methods.

Seward Silo

THE BICYCLE WHEEL


Bicycle wheel as we know it today - each is

associated with an application of prestressing to


a structural system.
The first and most obvious is the tensioned

spokes - the rider's weight is carried from the


forks to the ground not by hanging off the top
spokes, but by reducing the pretension in the
lower spokes - only a couple of spokes are
carrying the load at any one time.

The second is the pneumatic tyre, where the


compressive load is carried to the ground by
reducing the tension in the sidewall. The air
pressure in the tyre does not change when the
load is applied.

The final prestressing system is the tyre cord,


which is shorter than the perimeter of the rim.
The cord is thus in tension, holding the tyre on
the rim, which enables the pretension in the
sidewalls to be reacted

EQUIPMENTS : T6Z-08 Air Powered Grout Pump


Pumps cement grout only, no sand. 32 Gallon Mixing

Tank. Mixes up to 2 sacks of material at once and allows


for grout to be pumped during mixing or mixed without
pumping.

Approximate
size

50" long
30.5" high
52" wide

Weight

560 lbs.

Production Rate

8 gallons per
minute
at 150 psi

Colloidal Grout Plant

The heavy duty, high volume Colloidal Grout Plant is favored for precision
post-tension grouting. The unit features a high speed shear mixer that
thoroughly wets each particle and discharges the mixed material into a 13
cubic foot capacity agitating holding tank. A direct coupled progressing
cavity pump delivers slurries at a rate of up to 20 gpm and pressures of up
to 261 psi. The unit easily mixes and pumps slurries of Portland cement,
fly ash, bentonite, and lime flour. All controls are conveniently located on
the operator platform for easy one-man control.
Pump

Pump Type

31.6 progressing
cavity

Output/Pressure

variable up to 20
gpm, 261 psi

Mix Tank

13.0 CF with
bottom clean out

Mixing Pump

2 x 3 x 6 diffusertype centrifugal

Holding Tank

13.0 paddle
agitating

Drive Power

Air

300 CFM, 100 psi

Physical
Specifications

Dimensions

96" L x 60" W x 63"


H

Colloidal Mixer

eight

1800-2800 lbs.

T7Z Hydraulic Jacks

Used for testing and pre-stressing anchor bolts. Available


with up to 5-1/8" center hole. Unit comes with ram, pump,
gauge, hoses, jack stand, high strength coupling, high
strength test rod, plate, hex nut and knocker wrench.
Calibrations are available upon request.

Note: Jack pull rods should have a higher capacity than the
anchor rod.

T80 Post-Tensioning Jacks

With the T80 series the enclosed bearing

housing contains a geared socket drive to


tighten the bolt hex nut during tensioning. Test
jack housing will accommodate up to a 9
deep pocket.

T80 Post-Tensioning Jacks

T8Z-18 Hydraulic Torque Wrench

The hydraulic torque wrench is used for tensioning


anchors in tight fitting locations where it would be difficult
to use an hydraulic jack. The wrench is also
recommended for use when setting the large diameter
Spin-Lock anchors. The torque wrenches are light weight
and can achieve a maximum of 8,000 ft-lbs. Torque
Tensioning charts Williams products can be found here.

Maximum
Torque

Length

Height

Weight

5,590
ft./lbs.
(773 kg/M)

11.11"
(279 mm)

4.49"
(114 kg)

16.75 lbs.
(7.6 kg)

8,000 ft.lbs.
(1,006
kg/M)

12.57"
(319 kg)

5.09"
(129 kg)

24.95 lbs.
(11.3 kg)

T8Z Torque Wrench

For applying torque to the anchor bolt

when setting the anchor. Torque


Tensioning charts Williams products can
be found here.

T8Z-04 Torque Multiplier (4:1)


For use with T8Z Torque Wrench. Other sizes
available

Size

GA 186

Square Square Maximu


Drive
Drive
m
Input Output Torque

1"

1-1/2"

4,000
(ft. lbs.)

Bolt
Diameter

Square
Drive Size

Capacity
(ft. lbs.)

*1/2"-1"

3/4"

0-500

1/2"-1"

3/4"

0-600

*1-1/8"-2"

1"

0-1,000

T1Z & T2Z Long Fitting Tool Adapters


For driving hex nuts and setting tools,

typically with our Spin-Lock anchor


systems. Works with torque wrench or
impact gun.
Available with 1" or 1-1/2" square drive.
Please specify square drive for
compatability with your equipment.

2Z Regular Socket T1Z Deep Socket

K3F-26 Long Fitting Wrench Adapter


For applying torque to recessed anchor nuts that are under tension
when using hydraulic jacks. Available in all anchor sizes.

Corrosion Protection
Methods of Corrosion Protection
Typical
Thickness

Relative
Cost
(4=highest)

Lead Time

Can be
applied to
accessories
?

3-4 mils

2-4 weeks

yes

Epoxy
Coating

7-12 mils

2-3 weeks

yes

Pre-Grouted
Bars

2", 3" or 4"


tubing

2 weeks

no

Extruded
Polyethylene
Coating

23-25 mils

2-4 weeks

no

Corrosion
Inhibiting
Compound

N.A.

2-4 weeks

yes

Corrosion
Protection
Type

Abrasion
Resistance
(4=best)

Hot Dip
Galvanizing

Methods of Corrosion
Protection

Epoxy Coating
Fusion bonded epoxy coating of steel bars to help prevent
corrosion has been successfully employed in many applications
because of the chemical stability of epoxy resins. Epoxy coated
bars and fasteners should be done in accordance with ASTM A775 or ASTM 934. Coating thickness is generally specified
between 7 to 12 mils. Epoxy coated bars and components are
subject to damage if dragged on the ground or mishandled.
Heavy plates and nuts are often galvanized even though the bar
may be epoxy coated since they are difficult to protect against
abrasion in the field. Epoxy coating patch kits are often used in
the field for repairing nicked or scratched epoxy surfaces.

Pre-Grouted Bars
Cement Grout filled corrugated polyethylene tubing is often used to
provide an additional barrier against corrosion attack in highly
aggressive soils. These anchors are often referred to as MCP or
Multiple Corrosion Protection anchors. The steel bars are wrapped
with an internal centralizer then placed inside of the polyethylene tube
where they are then factory pre-grouted. When specifying couplings
with MCP ground anchors, verify coupling locations with a Williams
representative.

Hot Dip Galvanizing

Zinc serves as a sacrificial metal corroding preferentially to the


steel. Galvanized bars have excellent bond characteristics to
grout or concrete and do not require as much care in handling as
epoxy coated bars. However, galvanization of anchor rods is more
expensive than epoxy coating and often has greater lead time.
Hot dip galvanizing bars and fasteners should be done in
accordance with ASTM A-153. Typical galvanized coating
thickness for steel bars and components is between 3 and 4 mils.
150 KSI high strength steel bars should always be
mechanically cleaned (never acid washed) to avoid problems
associated with hydrogen embrittlement.

Extruded Polyethylene
Williams strand tendons contain an extruded high density
polyethylene sheathing around each individual strand in the
free-stressing portion of the anchorage. The sheathing is
minimum 60 mils thick and applied once the 7-wire strand
has been coated with a corrosion inhibiting compound.
Extruded polyethylene sheathing provides a moisture tight
barrier for corrosion protection and allows the strand to
elongate freely throughout the free-stressing length during
the prestressing operation

Corrosion Inhibiting Wax or Grease with Sheath


Williams corrosion inhibiting compounds can be placed in the free
stressing sleeves, in the end caps, or in the trumpet areas.
Often bars are greased/waxed and PVC is slipped over the
greased/waxed bar prior to shipping. Each are of an organic
compound with either a grease or wax base. They provide the
appropriate polar moisture displacement and have corrosion
inhibiting additives with self-healing properties. They can be
pumped or applied manually. Corrosion inhibiting compounds
stay permanently viscous, chemically stable and non-reactive
with the prestressing steel, duct materials or grout. Both
compounds meet PTI standards for Corrosion Inhibiting Coating.

Coal Tar Epoxy


Coal tar epoxy has shown to be abrasion resistant,
economical and durable. This product when specified
should meet or exceed the requirements of (a) Corp of
Engineers C-200, C200a and (b) AWWA C-210-92 for
exterior. Typically the thickness is between 8 and 24
mils. Make sure that the surfaces of the bar are clean
and dry before coating.

Heat Shrink Tubing

Heat Shrink Tubing provides a corrosion


protected seal when connecting smooth or
corrugated segments.

Epoxy Coating Patch Kits


Epoxy Coating Patch Kits are available upon request.
Anchor Head Protection
The most important section of a ground anchor that needs adequate
corrosion protection is the portion of the anchor exposed to air/oxygen.
This is typically defined as the "anchor head", which generally consists of a
steel bearing plate, a hex nut and washer for a bar system, or a wedge
plate and wedges for a strand system. For permanent ground anchors it is
best to galvanize the hex nut and plates even if the bar is epoxy coated.
Galvanized components, if scratched during shipping, are less likely to Fiber Reinforced Strand
cause corrosion concerns than scratched epoxy coated components. The Nylon Cap
End Cap
end of the steel bar protruding out from the hex nut is often protected by
the use of a plastic or steel end cap packed with grease or cement grout.
Williams offers several different types of PVC and metal end caps to
Steel Tube Welded on
provide corrosion protection at otherwise exposed anchor ends.
Flange with Threaded
Screw Connections

ScrewOn
PVC
Cap

Field Splice for Bars


Continuous corrosion protection can even be
accomplished for the MCP Pregrouted anchors
manufactured from Williams Form Engineering. To
achieve the equivalent levels of corrosion protection
the coupled sections of bar anchors can be wrapped
in a grease impregnated tape that is further protected
with heat shrink sleeving. This scheme is acceptable
by most governing agencies and is specified in the
PTI Recommendations for Prestresed Rock and Soil
Anchors.

You might also like