10men+6boys=20days,
12m+4boys=18days, in what time
will 8m+8b do the work?
12m+4b=1/18
10m+6b=1/20
solving it we get: m=240, b=720
thus 8men + 8boys will do it in 22.5 days
5 DECEMBER 09
www.afterschoool.tk
www.afterschoool.tk
1/12+1/15 = 27/180
reverse it = 6.67 days.
5 DECEMBER 09
www.afterschoool.tk
5 DECEMBER 09
www.afterschoool.tk
5 DECEMBER 09
www.afterschoool.tk
1/6 +1/12 =
= 4 days
5 DECEMBER 09
www.afterschoool.tk
www.afterschoool.tk
A can do it in 25 days, B in 20
days. They work together for 5
days. A leaves. How much time
more is required?
Work done by A = 5/25 = 1/5
B has to do 4/5 , 20*4/5 =16
B has worked for 5 days, so 11 more days are
required.