You are on page 1of 89

Discipline:

Engineering

Category:

Procedure

Structures Inspection Procedure


ETE-09-02
Applicability
ARTC Network Wide

Document Status
Version

Date Reviewed

Prepared by

Reviewed by

Endorsed

Approved

1.4

10 Feb 14

National Bridges
& Structures
Engineer

Stakeholders

GM Technical
Standards

Operations Safety
& Environment
Review Group
8/09/2014

Amendment Record
Version

Date Reviewed

Clause

1.0

08 Dec 09

Originally published as ETN-09-01 Structures Inspection Manual


version 1.0 Working Draft. Reissued as a Procedure.

1.1

18 Jun 10

Banner added regarding mandatory requirements in other


documents and alternative interpretations.

1.2

31 Oct 11

Appendices

Description of Amendment

Updates to Appendix B, E, F & P.


Minor editorial change to remove CRN applicability box.

1.3

12 Nov 12

Appendix B

Updated with pre-approved amendment (Nov 2011) to remove CRN


related lines & data following hand over of CRN Network effective
15 January 2012.

1.4

10 Feb 14

Various

Updated inspection process for Bridge Wood panels, Fibre


Composite products, Expanda & Rotaloc pvc pipes / liners and
Redundant Structures.

Australian Rail Track Corporation Limited 2014


Disclaimer:
This document has been prepared by ARTC for internal use and may not be relied on by any other party without ARTCs prior written consent. Use
of this document shall be subject to the terms of the relevant contract with ARTC.
ARTC and its employees shall have no liability to unauthorised users of the information for any loss, damage, cost or expense incurred or arising by
reason of an unauthorised user using or relying upon the information in this document, whether caused by error, negligence, omission or
misrepresentation in this document.

This document is uncontrolled when printed.

Authorised users of this document should visit ARTCs intranet or extranet (www.artc.com.au) to access the latest version of this document.

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Contents

Contents
1

Introduction ........................................................................................... 6
1.1

Purpose ............................................................................................ 6

1.2

Scope ............................................................................................... 6

1.3

Procedure Owner ............................................................................... 6

1.4

Responsibilities .................................................................................. 6

1.5

Reference Documents ......................................................................... 7

Structures Management System ............................................................. 7

Inventory ................................................................................................ 8

3.1

Introduction ...................................................................................... 8

3.2

Inventory Information ........................................................................ 8

Engineering Inspection ......................................................................... 10


4.1

Inspection Procedure .........................................................................10


4.1.1 Pre Inspection Investigation .....................................................10
4.1.2 As-New Load Rating .............................................................. 10
4.1.3 Fatigue Assessment .................................................................11
4.1.4 Preparation for Inspection ........................................................ 11
4.1.5 Detailed Inspection .................................................................11
4.1.6 Site Measurements ..................................................................13
4.1.7 As-Is Load Rating .................................................................13
4.1.8 Bridge Management Strategies .................................................14

4.2

Data Recording .................................................................................14


4.2.1 Inventory and photographic record ............................................15
4.2.2 Condition Rating .....................................................................15
4.2.3 Assessment of Outstanding Defects ...........................................15
4.2.4 New Defects ...........................................................................16
4.2.5 Load Rating ............................................................................16
4.2.6 Fatigue Assessment .................................................................16
4.2.7 Inspection Frequency .............................................................. 17
4.2.8 Timber Bore Results ................................................................ 17

4.3

Inspection Review .............................................................................17


4.3.1 Defects ..................................................................................17
4.3.2 Mitigation/Maintenance Work ....................................................17
4.3.3 Engineering Inspection Report ..................................................17
4.3.4 Overall Review of Inspection Report ..........................................18

5
Version 1.4

Visual Inspection .................................................................................. 19


Date of last revision: 10 Feb 14
This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 2 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

5.1

Contents

Inspection Procedure .........................................................................19


5.1.1 Pre Inspection Investigation .....................................................19
5.1.2 Preparation for Inspection ........................................................ 19
5.1.3 Visual Inspection .....................................................................19

5.2

Data Recording .................................................................................21

5.3

Inspection Review .............................................................................21


5.3.1 Defects ..................................................................................21
5.3.2 Mitigation/Maintenance Work ....................................................21
5.3.3 Overall Review of Inspection Report ..........................................22

Special Inspection ................................................................................ 23


6.1

Inspection Procedure .........................................................................23

Track Patrol .......................................................................................... 24


7.1

Inspection Procedure .........................................................................24

7.2

Data Recording .................................................................................24

Appendix A Structures Management System Inventory Attributes..... 25

Appendix B Asset Register Attributes Controlled Values ................. 28

10

Appendix C Structural Elements ......................................................... 33

11

Appendix D Element Location ............................................................ 45

12

Appendix E Inspection of Steel Structural Elements .......................... 47


12.1 Steel Degradation .............................................................................47
12.2 Inspection Methods ...........................................................................47
12.3 Element Inspection ...........................................................................48
12.4 Broad Flange Beam ...........................................................................49
12.5 Element Condition Assessment Guidelines ............................................50
12.6 Additional Inspection Requirements.....................................................51

13

Appendix F Inspection of Timber Structural Elements ....................... 53


13.1 BridgeWood Decking .........................................................................53
13.2 Timber degradation ...........................................................................53
13.3 Inspection methods ...........................................................................53
13.4 Inspection procedure .........................................................................54
13.5 Element Condition Assessment Guidelines ............................................56

14

Appendix G Inspection of Concrete Structural Elements .................... 57


14.1 Concrete Degradation ........................................................................57
14.2 Inspection Methods ...........................................................................57
14.3 Locations ......................................................................................... 58

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 3 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Contents

14.4 Element Condition Assessment Guidelines ............................................58


14.4.1 Reinforced Concrete Elements ..................................................58
14.4.2 Prestressed Concrete Beams ....................................................59
15

Appendix H Inspection of Fibre Composite Structural Elements ........ 60


15.1 Fibre Composite Degradation.............................................................. 60
15.1.1 Inspection ..............................................................................60
15.2 Inspection Methods ...........................................................................60
15.3 Locations ......................................................................................... 61
15.4 Element Condition Assessment Guidelines ............................................61
15.4.1 Fibre Composite Elements ........................................................ 61

16

Appendix I Inspection of Interflow Expanda & Rotaloc Pipes ............ 63


16.1 General ........................................................................................... 63
16.2 Expanda & Rotaloc Degradation .......................................................... 63
16.2.1 Inspection ..............................................................................63
16.3 Inspection Methods ...........................................................................63
16.4 Locations ......................................................................................... 64
16.5 Element Condition Assessment Guidelines ............................................65
16.5.1 Expanda & Rotaloc Pipes .......................................................... 65

17

Appendix J Inspection of Masonry Structural Elements ..................... 66


17.1 Overview ......................................................................................... 66
17.2 Defects Caused by Structural Distress .................................................66
17.3 Defects arising due to the nature of the material ..................................67
17.4 Defects instigated by external agents ..................................................67
17.5 Element Condition Assessment Guidelines ............................................67

18

Appendix K Inspection of Tunnels....................................................... 68

19

Appendix L Inspection of Substructure Elements ............................... 69


19.1 Introduction .....................................................................................69
19.2 Inspection procedures .......................................................................69

20

Appendix M Inspection of Underwater Structural Elements ............... 71


20.1 Introduction .....................................................................................71
20.2 Frequency ........................................................................................ 71
20.3 Methods of Underwater Inspection ...................................................... 71
20.4 Diving Inspection Intensity Levels ....................................................... 72
20.5 Types of Inspection ...........................................................................73
20.6 Qualifications of Diver-Inspectors ........................................................ 73

21
Version 1.4

Appendix N Inspection of Miscellaneous Structures ........................... 74


Date of last revision: 10 Feb 14
This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 4 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Contents

22

Appendix O Inspection of Redundant Structures ............................... 75

23

Appendix P Engineering Inspection Process Flow Chart .................... 76

24

Appendix Q Visual Inspection Process Flow Chart ............................. 79

25

Appendix R Determination of Condition Rating .................................. 81


25.1 Introduction .....................................................................................81
25.2 Measurement ...................................................................................81

26

Appendix S Load Rating of Bridges and Culverts ................................ 83


26.1 Introduction .....................................................................................83
26.2 Load Rating Results...........................................................................83
26.3 Train Load Effects .............................................................................83
26.4 Speed Restriction ..............................................................................83
26.5 Fatigue Rating ..................................................................................84
26.6 Wind & Sway Bracing ........................................................................84
26.7 Train Consists...................................................................................86
26.8 Road Vehicles ...................................................................................88

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 5 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Introduction

Mandatory requirements also exist in other documents.


Where alternative interpretations occur, the Manager Standards shall be informed so the
ambiguity can be removed. Pending removal of the ambiguity the interpretation with the safest
outcome shall be adopted.

Introduction

1.1

Purpose
This document forms an integral part of Structures Inspection Standard ETE0901 and
describes the system and processes for inspecting structures on the Australian Rail Track
Corporations (ARTC) network.

1.2

Scope
Section 9 of the ARTC Code of Practice identifies the minimum requirements for the inspection
of structures.
This Structures Inspection Procedure applies to all structures under ARTCs responsibility and
provides guidance for the processes for undertaking the following inspections:

Engineering Inspections;

Visual Inspections;

Special Inspections;

Track Patrol Inspections.

The systematic inspection of structures forms the basis of good asset management practice. The
outcomes from the inspection process are used to:
i.

Provide data on the current condition, performance and environment of a structure


including the severity and extent of defects. The data enables those responsible for
managing structures on ARTCs network to assess if a structure is currently safe for use
and fit for purpose, and provides sufficient data for actions to be planned where structures
do not meet these requirements.

ii.

Provide analyses, assessments and processes where there is a change in condition, cause
of deterioration, rate of deterioration, maintenance requirements, effectiveness of
maintenance and structural capacity.

iii. Provide data for asset management planning in order to deliver an acceptable level of
service.
iv. Compile, verify and maintain inventory data for all structures under ARTC responsibility.
Section 3 of this Procedure describes the inventory data that should be held in the
Structures Management System 1.

1.3

Procedure Owner
The Manager Standards is the Procedure Owner and is the initial point of contact for all queries
relating to this Procedure.

1.4

Responsibilities
The National Bridges & Structures Engineer is responsible for the implementation of this
Procedure.

The Structures Management System refers to ARTCs computerised Bridge Management System, known as the BMS. Refer to the BMS
User Manual for specific use of the system in each state.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 6 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

1.5

Structures Management System

Reference Documents
The following documents are supported by this Procedure:

ARTC Track & Civil Code of Practice Section 9 Structures

ETG-09-01 Structures Inventory

ETE-09-01 Structures Inspection.

Structures Management System


For effectiveness of structure management, it is important that data associated with an asset is
as complete as possible, of high quality and consistent with other data collected on the network.
To ensure the completeness of the data, the Structures Management System provides a means
for recording, storing and accessing critical data for all structures on the network. A flowchart of
the processes of the Bridge Management System (BMS) is provided in Figure 1 below.

Figure 1 Structures Management System Processes

To ensure the data is of high quality and auditable, access to the Structures Management
System is restricted to approved users only to input and amend inventory, inspection and
maintenance information.
For consistency of data structure, reporting, descriptions and processes are described in this
Procedure for the following categories:
Inventory
The requirements for inventory data are provided in Section 3 of this Procedure.
Inspection
The purpose and methodologies of these inspections are detailed in Sections 4 to 7 of this
Procedure.
Maintenance
The processes for scheduling corrective and preventive maintenance work are included in the
inspection methodologies in Sections 4 to 7 of this Procedure.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 7 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Inventory

3.1

Introduction

Inventory

The Structures Management System holds asset inventory, condition and performance data with
the objective of providing up-to-date information that can be used to determine the current
condition of structural elements and the overall performance of structures. In addition, the
Structures Management System provides the basis for providing a range of network wide
reports on different structures and structure types.

3.2

Inventory Information
The Structures Management System must have a minimum set of inventory information for
each structure on the network in order for it to provide sufficient functionality to all involved in
the management of structures. Appendix A provides a schedule of inventory attributes
required to be populated in the Structures Management System.
Corporate Asset Management System
In NSW, there are a number of the higher level attributes that are controlled and maintained in
Ellipse, ARTCs Corporate Asset Management System. The schedule in Appendix A identifies
these attributes controlled in Ellipse. Where there is a change in the value of these attributes,
the change must be made in Ellipse. These changes will be automatically reflected into the
Structures Management System.
In other states all inventory attributes are controlled and maintained in the Structures
Management System only.
Controlled Attribute Lists
A number of the attributes have been allocated a controlled set of values with the objective of
providing consistency in inventory information across the network. A schedule of controlled
values for each subject inventory attribute is provided in the Appendix B.
Structural Elements
Structure inspection procedures, reporting, maintenance scheduling and monitoring of condition
mainly focus on structural elements. The elements used for the majority of structures on the
network have been predefined in Appendix C.
Appendix C also provides further guidance for the identification of the predefined elements on
typical structures.
The elements are further divided into the following six material groups describing the material
from which they are constructed:

Steel - including cast and wrought iron elements / components;

Precast concrete;

Cast-in-situ concrete;

Timber;

Masonry including brickwork and stonework;

Other including but not limited to gravel, neoprene, bitumen, cork, malthoid and
aluminium.

To achieve consistent and comparable results, the inspector must use the unique element
and/or element number documented in Appendix C to identify defects and condition rate each
part of the structure being inspected.
Location
The process of identifying the location of an element that has the defect should be defined as
follows:

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 8 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Inventory

For underbridges, and any other structure with spans parallel to the track, all
descriptions are based on the start of a structure, which is the end with the lowest
Kilometrage using the following abbreviations:
A Abutment;
S Span;
P Pier.

All elements should be numbered from the Downside (left hand side when facing direction
of increasing kilometrage) progressing to the Upside (right hand side).

For Overbridges, culverts and any other structure with spans perpendicular to the track
the numbering system should be the same as for an underbridge with the start of a
structure located on the Down Side of the track.

All elements should be numbered from the highest Kilometrage (left hand side when facing
the Up side rail) side progressing to the lowest Kilometrage (right hand side) side.
An example of the numbering/description system is provided in Appendix D.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 9 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Engineering Inspection

Engineering Inspection
The purpose and scope of an Engineering Inspection is provided in the Standard ETE-09-01
Structures Inspection.
Further general information for specific types of structures is provided in Appendices E to L, as
listed below:
Appendix E

Inspection of Steel Structural Elements;

Appendix F

Inspection of Timber Structural Elements;

Appendix G

Inspection of Concrete Structural Elements;

Appendix H

Inspection of Masonry Structural Elements;

Appendix I

Inspection of Tunnels;

Appendix J

Inspection of Substructure Elements;

Appendix K

Inspection of Underwater Structural Elements;

Appendix L

Inspection of Miscellaneous Structures.

These appendices provide general guidance only and it is expected the Structures Engineer will
use appropriate engineering judgement and experience when recommending actions from an
Engineering Inspection.

4.1

Inspection Procedure
The process of undertaking an Engineering Inspection is shown in a flowchart in Appendix M.

4.1.1

Pre Inspection Investigation


Prior to undertaking an Engineering Inspection the Structures Engineer should review the
available relevant historical information for the structure, including:
i.

Available inspection and engineering investigation reports;

ii.

Maintenance history;

iii. Outstanding defects and proposed Major Periodic Maintenance;


iv. Defects identified for future observation from previous inspections;
v.

Structural issues that have been recorded since the last inspection;

vi. As-New and As-Is load rating and load effects from current traffic from previous
inspections and/or investigations;
vii. Current train operating configurations;
viii. Train loading history and previous fatigue assessments;
ix. Underwater Inspections (including assessing the need to undertake a further underwater
inspection as part of this Engineering Inspection).

4.1.2

As-New Load Rating


Where a structure does not have an As-New load rating in terms of LA design railway loading
or T44 design road vehicle loading in accordance with AS 5100/7 and construction drawings are
available the rating should be calculated prior to undertaking the on-site inspection, so that
there is a better understanding of the structurally critical elements. The drawing dimensions
should later be confirmed by site measurements and rating results corrected as necessary.
The load assessment should identify:

Version 1.4

The capacity of each primary and secondary element;

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 10 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Engineering Inspection

The equivalent train load effects for each primary and secondary element for each
nominated train consist.

The load rating should be determined in accordance with the document Load Rating of Bridges
and Culverts, which is included in Appendix P.

4.1.3

Fatigue Assessment
Prior to undertaking the on-site inspection, the fatigue assessment should be updated to include
the train loading history for the period since the last fatigue assessment, so there is a better
understanding of the critical elements that have reached or are approaching the end of their
theoretical remaining fatigue lives.
Fatigue assessment for road bridges and culverts are not required unless otherwise included in
the scope of work.

4.1.4

Preparation for Inspection


In preparation for the inspection, the Structures Engineer should liaise with the local Structures
Representative and/or the Structures Inspector to ensure the appropriate arrangements are in
place to undertake the inspection, including:

Track protection;

Inspection access arrangements;

Safety equipment;

Arrangements with relevant authorities/stakeholders.

The Structures Engineer must prepare a Safety Plan and submit to the Structures
Representative for approval.

4.1.5

Detailed Inspection
The detailed inspection should cover all elements of the structure, including below ground and
water level where appropriate. The individual elements of the bridge should be visually
examined either with the naked eye or through the use of appropriate equipment such as
mirrors, telescopic equipment or video recording in order to identify structural defects.
The Structures Engineer should undertake the following work:
Review of Structure Inventory Records
The Structures Engineer is required to review the existing inventory information currently held
in the Structures Management System for the structure and identify:

Additional information to make the inventory data complete;

Modifications to correct errors, or changes arising from maintenance work, to the


existing information.

For each structure, the following photographic records that form part of the inventory
information are required:
1) A view along the deck system;
2) One or two views (depending on the size of the structure) showing the elevation of the
structure;
3) One or two representative photographs of more complex structures such as trusses.
The Structures Engineer should review the existing photographs in the Structures Management
System for that structure, and take additional photographs if currently inadequate or there has
been a substantive change.
Following the inspection, the Structures Engineer should advise the Structures Representative of
any required changes to the inventory. The Structures Representative should review the
proposed changes and arrange for the changes to be made in the Structures Management
System.
Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 11 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Engineering Inspection

Record the Exposure Rating of Elements


The Structures Engineer should identify the exposure classification in the immediate proximity
of each structural element in accordance with Section 5.2 of ETE-09-01.
Condition Rating of Elements
The Structures Engineer should make an assessment of the condition of each standard element
and the extent over which that condition applies in accordance with Section 5.3 of ETE-09-01.
The Structures Engineer should compare the condition of each element with the above general
description and those provided in Appendices E to L of this Procedure. These descriptions
cannot cover every situation and the Structures Engineer is expected to exercise judgement
based on knowledge and experience in association with the above general descriptions, to
identify the appropriate condition state applying to each element in the field.
The extent of each condition state affecting an element should be measured as a percentage of
the whole element. That is the percentages in each condition state (1, 2, 3 and 4) must add up
100%. The unit of measurement adopted for each element is provided in Appendix C and this
should be used as a basis for determining and measuring the percentage of each condition state
affecting the whole element. The methodology of determining the measurement of condition
rating is further described in Appendix O.
Assessment of Previously Reported Defects and Monitor
At the start of the inspection procedure, the Structures Engineer should review the status of the
previously reported defects. Depending on the rate of deterioration of the defect the Structures
Engineer should either record:

No Change -

The original defect category and repair priority (where appropriate) allocated
to the defect does not change.

Re-Assess -

The defect is reassessed and a new defect category and repair priority
recorded.

Remove -

The defect is not considered to be an issue any longer and is therefore not
required to have any further monitoring at the next inspection.

Completed -

If a defect has been repaired but is still identified as an outstanding defect,


the Structures Representative should be notified.

Outstanding - If a defect has been reported as repaired but is still outstanding, the
Structures Representative should be notified.

New Defect Identification


Generally for each element with a Condition State 3 or 4, additional information concerning the
defect(s) on that element should be recorded including:

Type of element;

Location of element;

Assessment of Defect Category A- D and M;

The Defect Type from the controlled list of defect types (refer Appendix B);

For Defect Categories A-D, assign a Repair Priority and specific date for rectification
(refer Table 1 below);

For Defect Categories A and B, impose an immediate mitigation strategy as deemed necessary;

Defect size;

A brief description of the defect. Where the defect is likely to cause a loss in capacity of
an element provide an estimate of reduction in cross sectional area and rate of
degradation;

Photographic records are required of all critical defects. Typically this should include, but
not be limited to, defects located on elements with condition rating 4. Where defects are
repeated, only typical defects photographs are required.

The Structures Engineer should take


documented in Table 8 in ETE-09-01.
Version 1.4

into

account

the

required

response

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

timeframes

Page 12 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Engineering Inspection

Establishing the cause of an observed defect is crucial to determining the severity of a defect. If
the Structures Engineer is unable to determine the mechanism responsible for the cause of a
defect, further input should be sought from a specialist engineer. If the cause of a defect cannot
be identified and the level of risk cannot be determined, further investigation should be
recommended.
Repair Priority
All defects should be allocated a repair priority as shown in Table 1 below:
Repair Priority Code

Rectification Period

E Emergency

Rectification work to commence within 24 hours.

3 Priority 3

An actual Date for Rectification should be nominated but should be:

not less than 90 days from Date of Inspection;

not greater than the date for the next inspection.


Table 1: Repair Priority Codes

Note:

Repair priority codes 1 (<7 days) and 2 (<28 days), in accordance with Asset
Maintenance Works Management Procedure (EGP-10-01) are not applicable for
structures maintenance work due to insufficient timeframes to undertake remedial
action, and therefore not utilised to prioritise maintenance work.

Specific Requirements for Engineering Inspections


In addition to the inspection requirements outlined above for all structures, it is necessary to
undertake specific inspection and/or testing as listed below in Table 2:
Structure Type
Steel and
Structures

Wrought

Iron

Timber Structures

Substructures submerged in
permanent water

Inspections/ Testing

Procedure Reference

Paint condition rating;

Appendix E

Magnetic Particle and Dye Penetrant


testing.

Boring of Elements;

Underground Inspections.

Underwater Inspection

Appendix F

Appendix J

Table 2 Additional Inspection Requirements

4.1.6

Site Measurements
Site measurements should be undertaken to either confirm drawing dimensions or when
drawings are not available, to ensure accurate dimensions of elements are available for load
rating.

4.1.7

As-Is Load Rating


Where the condition of an element has deteriorated to the extent that its As-New load
carrying capacity has been affected, a new rating for the element should be determined for the
As-Is condition.
Where elements have a capacity of less than 300LA for railway structures, and T44 for road
bridges, the following information should be recorded for each deficient element:

Version 1.4

Location;

Description of Deficiency;
Date of last revision: 10 Feb 14
This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 13 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

4.1.8

Engineering Inspection

Member Rating;

Capacity Ratio;

Speed Restriction for current traffic where railway bridge or culvert has inadequate load
carrying capacity (to provide a capacity ratio of 1.0);

Load limit expressed in terms of R (rigid) and T articulated vehicles for road bridges
where capacity is less than T44 design load.

Bridge Management Strategies


Following completion of the fieldwork and As-Is load rating, the Structures Engineer should
develop recommendations for:
Corrective Maintenance
Maintenance work or mitigation measures to defects that represent either an immediate risk to
train operations or an unacceptable risk to train operations before the next scheduled
Engineering Inspection. The work must be implemented by the specified rectification date.
Preventive Maintenance
Rehabilitation work likely to be required beyond the timeframe of the next engineering
inspection. The rehabilitation work should be grouped into similar type of work that can be
addressed during a single Major Periodic Maintenance (MPM) activity. Usually the work would be
limited to Defect Category M defects and strengthening of deficient elements, but may include
Category A-D defects if the rectification dates coincide with the MPM program.
The recommendations for MPM work should take into account work already programmed for
that structure.
Category M Defects
The Category M defects requiring further observation at the next inspection should be identified.
Special Inspections
The Structures Engineer may recommend that Special Inspections are undertaken to monitor
specific defects. Where a Special Inspection is currently being undertaken, the Structures
Engineer may recommend a change in the frequency of the Inspection if appropriate or
recommend the inspections are no longer required.
Engineering and Visual Inspections
The Structures Engineer may recommend an increase in the frequency of Engineering and / or
Visual Inspections where deemed necessary.
The Structures Engineer should take into account the overall condition of the structure and the
criticality of the line when developing the recommendations.

4.2

Data Recording
All information obtained during the Engineering Inspection must be entered directly into the
Structures Management System. All defects should contain a clear and concise scope of work to
allow forward planning and costing. The information includes:
i.

Inventory and photographic records;

ii.

Condition/Paint Rating;

iii. Outstanding Defects;


iv. New Defects;
v.

Load Rating (including all calculations);

vi. Fatigue Assessment (including all calculations);


vii. Maintenance Works;
viii. General Information and Inspection Frequency;

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 14 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Engineering Inspection

ix. Timber Boring Results.


For item i., inventory and photographic records, the Structures Engineer does not have
permission to change such information in the Structures Management System. The engineer
should seek changes in accordance with Section 4.1.5 of this Procedure.

4.2.1

Inventory and photographic record


The information should include all of the required inventory attributes as identified in Section 3,
where appropriate for that structure.
The Structures Engineer should provide the Structures Representative with the following
information:

Attribute information where there is currently no information;

Information where there are changes required;

Where there is a controlled value to the attribute, the Structures Engineer can only recommend
the controlled values nominated in Appendix B.
The Structures Representative should arrange for the information to be included in the
Structures Management System.

4.2.2

Condition Rating
The following information is to be recorded:
i.

List all elements of the structure (by their unique number reference) as per Appendix C;

ii.

Exposure classification for each element;

iii. Condition state of each element;


iv. Paint Condition Rating for Steel Bridges.

4.2.3

Assessment of Outstanding Defects


The Structures Engineer should record if:

The defect has not changed

There is no requirement to provide any further information.

The defect needs to be re-assessed

There is a requirement to provide the following further information:

Defect Category;

Defect Type;

Repair priority for Category A-D defects only;

Rectification Date for Category A-D defects only;

Allocated MPM (if appropriate);

Quantity;

Description.

The defect should be Closed

The defect no longer needs to be assessed. Provide a reason to the cause of why
assessment is no longer necessary and the defect can then be closed out.

The defect has been repaired

The defect has been repaired but was not recorded as being fixed in the Structures
Management System. The Structures Engineer should advise the Structures Representative
who should investigate further and arrange for the close out of the defect in BMS in Victoria
and SA/WA or in Work Management System (WMS) in NSW, if appropriate.
Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 15 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Engineering Inspection

Closure of such a defect in BMS will NOT result in its closure in WMS.

The defect is still Outstanding

The defect was identified as repaired, but was found to be still outstanding upon inspection.
The defect should be re-identified as for a new defect, including a description stating the
defect had been closed in error.

4.2.4

New Defects
The information should list all new defects and issues requiring remedial work or on-going
observation. All defects must have clear and concise scope of work. The Structures Engineer
should record

4.2.5

Element Name;

Location;

Defect Category;

Defect Type;

Description.

Quantity;

Recommended rectification work;

Repair priority for Category A-D defects only;

Rectification Date for Category A-D defects only);

Allocate to an MPM (if appropriate).

Load Rating
The Structures Engineer should list:

Load rating in the As-New and As-Is conditions;

Load effect from the current train consists;

The elements with less than 300LA As-Is load capacity (or T44 for overbridge):
Location;
Member Rating;
Capacity in As-New and As-Is condition;
Dynamic Load Allowance (where applicable);
Speed Restriction for current traffic where railway bridge or culvert has inadequate load
carrying capacity (to provide a capacity ratio of 1.0);
Load limit for road bridges where capacity is less than T44.

4.2.6

Fatigue Assessment
The information should list for elements with a theoretical remaining fatigue life of less than 20
years:
Element;
Location;
Accumulated Damage;
Theoretical Remaining Fatigue Life.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 16 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

4.2.7

Engineering Inspection

Inspection Frequency
The Structures Engineer should record the recommended frequency and date of inspection for
the next:

4.2.8

Engineering Inspection (if less than the mandatory frequency);

Visual Inspection (if less than the mandatory frequency);

Special Inspection(s) if required.

Timber Bore Results


The inspector should record timber bore results for each element that has been drilled in
accordance with Appendix F:

The location;

The size of piping to each bore.

Where appropriate, the type of decay should be recorded as part of the defect description.

4.3

Inspection Review

4.3.1

Defects
The Structures Representative should assess all reported Category Defects A-D, and Category
Defects M where requested by the Structures Engineer within the required timeframes.
Where the Structures Representative has concerns over the defect category allocation,
associated repair priority and/or associated rectification date of a defect, in the first instance the
issue should be discussed with the Structures Engineer. If it is agreed that the Structures
Representative should vary the assessment of the defect, the Structures Engineer should
provide written confirmation of the agreed change(s) that should be filed with the inspection
records.
If the Structures Representative and the Structures Engineer cannot reach an acceptable course
of action, the matter should be referred to the National Bridges & Structures Engineer for
further review. If, following the review, it is agreed that the Structures Representative should
vary the assessment of the deficiency; the National Bridges & Structures Engineer should
provide written confirmation of the change(s), which should be filed with the inspection record.

4.3.2

Mitigation/Maintenance Work
Corrective Maintenance
The Structures Representative should allocate the corrective maintenance work to be actioned
in accordance with the repair priorities agreed above. The Structures Representative should also
arrange any short term mitigation actions recommended by the Structures Engineer.
If it is planned to undertake corrective maintenance work as part of an MPM the proposed date
for completing the MPM must be before the agreed date for rectification of the defect.
Preventive Maintenance
For preventive maintenance work, the Structures Representative should develop MPM strategies
for the structure taking into account the recommendations of the Structures Engineer.

4.3.3

Engineering Inspection Report


The Structures Engineer should submit a draft engineering report containing a summary of
critical defects, deficient elements, speed restrictions, load ratings, fatigue assessments,
recommended inspection frequencies and short term mitigation actions within the timeframes
identified in the Inspection Standard, ETE0901.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 17 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Engineering Inspection

The Structures Representative should arrange for the review of the draft report with the
National Bridges & Structures Engineer and discuss as required with the Structures Engineer
with the objective of accepting the details for the final report.

4.3.4

Overall Review of Inspection Report


Following successful resolution of all of the above issues, the Structures Engineer should upload
the report, including all ratings, calculations, etc., into the Structures Management System.
The Structures Representative should mark the engineering inspection report as accepted for
inclusion in the Structures Management System and ensure any requirement for special
inspections, speed restrictions, etc. are actioned.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 18 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Visual Inspection

Visual Inspection
The purpose and scope of a Visual Inspection is provided in the Standard ETE-09-01 Structures
Inspection.
Further general information for specific types of structures is provided in Appendices E to K,
as listed below:
Appendix E

Inspection of Steel Structural Elements;

Appendix F

Inspection of Timber Structural Elements;

Appendix G

Inspection of Concrete Structural Elements;

Appendix H

Inspection of Masonry Structural Elements;

Appendix I

Inspection of Tunnels;

Appendix J

Inspection of Substructure Elements;

Appendix K

Inspection of Underwater Structural Elements;

Appendix L

Inspection of Miscellaneous Structures.

These appendices provide general guidance only and it is expected the Structures Inspector will
use appropriate judgement and experience when recommending actions from a Visual
Inspection.

5.1

Inspection Procedure
The process of undertaking a Visual Inspection is shown in the flowchart in Appendix N.

5.1.1

Pre Inspection Investigation


Prior to undertaking a Visual Inspection the Structures Inspector should review the available
relevant historical information for the structure, including:

5.1.2

Available inspection, engineering and any investigation reports;

Maintenance history;

Outstanding defects and planned Major Periodic Maintenance;

Deficiencies identified for future observation;

Structural issues that have been recorded since the last inspection.

Preparation for Inspection


In preparation for the Inspection, the Structures Inspector should liaise with the Structures
Representative to ensure the appropriate arrangements are in place to undertake the
Inspection, including:

5.1.3

Track protection;

Inspection access arrangements;

Safety equipment;

Arrangements with relevant authorities/stakeholders.

Visual Inspection
A Visual Inspection covers all elements of the structure above ground and water level.
Inspections below ground and water level and non- destructive testing, such as MPI, Dye
Penetrant or timber boring, may be necessary for specific structures from time to time. The
individual elements of the bridge should be visually examined either with the naked eye or

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 19 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Visual Inspection

through the use of appropriate equipment such as mirrors, telescopic equipment or video
recording in order to identify structural defects.
Review of Structure Inventory Records
The Structures Inspector is required to review the existing inventory information currently held
in the Structures Management System for the structure and identify either:
Additional information to make the inventory data complete;
Modifications to correct errors, or changes arising from maintenance work, to the existing
information.
For each structure, the following photographic records that form part of the inventory
information are required:

A view along the deck system;

One or two views (depending on the size of the structure) showing the elevation of the
structure;

One or two representative photographs of more complex structures such as trusses.

The Structures Inspector should review the existing photographs in the Structures Management
System for that structure, and take additional photographs if currently inadequate or there has
been a substantive change.
Following the inspection, the Structures Inspector should advise the Structures Representative
of any required changes to the inventory. The Structures Representative should review the
proposed changes and arrange for the changes to be made in the Structures Management
System or Ellipse.
Assessment of Previously Reported Defects and Monitor
At the start of inspection procedure, the Structures Inspector should review the status of the
previously reported defects, including those require monitoring. Depending on the rate of
deterioration of the defect the Structures Inspector should either record:

No Change -

The original deficiency category and repair priority (where appropriate)


allocated to the deficiency does not change.

Re-Assess -

The deficiency is reassessed and a new deficiency category and repair


priority recorded.

Completed -

If a defect has been repaired but is still identified as an outstanding defect,


the Structures Representative should be notified to have it closed out in BMS
in Victoria and SA/WA or in Work Management System (WMS) in NSW, if
appropriate. Closure of such a defect in BMS will NOT result in its closure in
WMS.

Outstanding - If a defect has been reported as repaired but is still outstanding, the
Structures Representative should be notified.

New Deficiency Identification


When the Structures Inspector identifies a new defect, the following information should be
recorded:

Version 1.4

Type of element;

Location of element;

Assessment of Defect Category A- D and M;

The Defect Type from the controlled list of defect types (refer Appendix B);

For Defect Categories A-D, assign a Repair Priority and a specific date for rectification
(refer Table 1);

For Defect Categories A and B, impose an immediate mitigation strategy as deemed


necessary.

Defect size;

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 20 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Visual Inspection

A brief description of the defect. Where the defect is likely to cause a reduction in
strength provide estimate of reduction in cross sectional area of structural element or
loss of structural adequacy.

Photographic records of all critical defects. Where defects are repeated, only typical
defects photographs are required.

It should be noted for Category A to C defects the Structures Inspector should communicate
urgently with the Structures Representative to implement immediate mitigation strategies and
arrange further assessment within the prescribed timeframes. All verbally agreed actions should
be documented in the inspection report.
For Category M, Monitor, the Structures Inspector can allocate the defect:

5.2

To the Structures Representative to review, or

For re-assessment at the next inspection.

Data Recording
All information except for Inventory and Photographic record obtained during the Visual
Inspection should be entered directly into the Structures Management System. All defects
should contain a clear and concise scope of work to allow forward planning and costing.
Refer to the nominated section for further details:
i.

Outstanding Defects

Section 4.2.3

ii.

New Defects

Section 4.2.4

5.3

Inspection Review

5.3.1

Defects
The Structures Representative should review, within the specified timeframes:

All Category A to D defects;

All Category M defects where the Structures Inspector has requested further review;

The Structures Representative has authorisation to change the defect category, repair
priority and rectification date reported by the Structures Inspector. The Inspectors
original assessment must be kept on record.

Where the Structures Representative has concerns over specific defects further advice may be
sought from either the Structures Engineer who undertook the last Engineering Inspection or
from the National Bridges & Structures Engineer. Where written advice has been provided, the
advice should be filed with the inspection report.

5.3.2

Mitigation/Maintenance Work
Corrective Maintenance
The Structures Representative should allocate the corrective maintenance work to be actioned
in accordance with the agreed repair priorities and rectification dates. The Structures
Representative should also arrange for any short term mitigation actions to be implemented.
If it is planned to undertake corrective maintenance work as part of an MPM; the date for
completing the MPM must be before the rectification date for the defect.
Preventive Maintenance
For preventive maintenance work, the Structures Representative should review the outcomes of
the Visual Inspection against the proposed MPM works for the structure and make modifications
as required.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 21 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

5.3.3

Visual Inspection

Overall Review of Inspection Report


Following successful resolution of all of the above issues the Structures Representative should
mark the Visual Inspection report as accepted for inclusion in the Structures Management
System.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 22 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Special Inspection

Special Inspection
The purpose and scope of a Special Inspection is provided in Standard ETE-09-01 Structures
Inspection.

6.1

Inspection Procedure
Special Inspections should generally be carried out in accordance with Section 5.1 of this
Procedure.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 23 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Track Patrol

Track Patrol
The purpose and scope of a Track Patrol inspection is provided in Standard ETE-09-01
Structures Inspection.

7.1

Inspection Procedure
Track Patrols should be carried out in accordance with ARTC Code of Practice (Track & Civil).

7.2

Data Recording
All defects should be reported to the Structures Representative, who should arrange for
assessment and input into the Structures Management System.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 24 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix A Structures Management System Inventory Attributes

Appendix A Structures Management System


Inventory Attributes
Attribute

Controlled Values

1. Structure Identification
1

Asset class

Yes 1

1.1

State

Yes

1.2

Region

Yes1

1.3

Line

Yes1

1.4

Line segment

No1

1.5

Line class

Yes

1.6

Kilometrage

No1

1.7

Line Class

Yes

1.8

Direction

Yes1

1.9

Asset Number

No1

1.11

Network

Yes

1.12

Service status

Yes1

1.13

Date of Construction

No1

2. Structure Information
2.1

Structure Type

Yes1

2.2

Structure Name

No1

2.3

Bridge owner

Yes

2.4

Bridge Maintainer

Yes

2.5

Span Type Material

Yes1

2.6

Span Type Structure

Yes

2.7

Deck type

Yes

2.8

Deck material type

Yes

2.9

Structure configuration)

No

3. Structure Configuration
3.1

No of Spans

No

3.2

Span Length

No

3.3

No of cells (Culverts only)

No

3.4

Cell width/diameter (Culverts only)

No

3.5

Cell height (Culverts only)

No

4. Access Information
4.1

Rail Level to Invert Level

No

4.2

Land Owner

No

4.3

Phone Number

No

5. Geometry Details

Version 1.4

5.1

Posted vertical clearance

No

5.2

Actual vertical clearance

No

5.3

Minimum Horizontal Clearance from centre No


line

5.4

Minimum Horizontal Clearance

No

5.5

Bridge Length

No

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 25 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix A Structures Management System Inventory Attributes

Attribute

Controlled Values

5.6

Deck Width

No

5.7

No of spans

No

5.8

No. of Lanes

No

5.9

No of beams per span

No

5.11

Used as underpass

No

5.12

Barrel Length

No

5.13

Cell Width/diameter (Culvert only)

No

5.14

Cell Height (Culvert only)

No

5.15

No of cells (Culvert only)

No

5.16

No. of tracks

No

5.17

Track Alignment

Yes

5.18

Walkway

No

5.19

Walkway width

No

5.20

Track Centre line to Walkway Handrail

No

5.21

Refuge

No

5.22

Design super elevation

No

5.23

Guard Rails

No

5.24

Rail Level to Invert Level

No

6. GPS Data
6.1

Easting

No

6.2

Northing

No

6.3

Map Zone

No

7. Paint Details
7.1

Painted

No

7.2

Lead paint

No

7.3

Paint Condition

Yes

7.4

Recommended Repaint Year

No

7.5

Last Painted Year

No

7.6

Cost of Repaint

No

8. Transom Details
8.1

Transom Material

8.2

Height

No
No

8.3

Width

No

8.4

Length

No

8.5

No of Transoms

No

8.6

Transom spacing

No

8.7

Transom Bolt Diameter

No

8.8

Transom Bolt Type

Yes

8.9

When Renewed

No

8.11

Packing under transom

No

8.12

Type of sleeper plate

No

9. Utilities

Version 1.4

9.1

Description of service

No

9.2

Service Type

No

9.3

Service Owner

No

9.4

Maintains Contract Details

No

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 26 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix A Structures Management System Inventory Attributes

Attribute

Controlled Values

10. Documents
10.1

Subjects

Yes

10.2

Site Environment

No

11. Photographs
11.1

Photo Name

Yes

11.2

Date

No

11.3

Photo File Name

No

11.4

Description

No

12. Bridge Capacity


12.1

Load rating (As-New)

No

12.2

Load rating (As-Is)

No

12.3

Line Rating

No

12.4

Permitted track speed (Passenger and


Freight)

No

12.5

Posted track speed (Passenger and Freight)

No

12.6

Defect Related (Track Speed)

No

12.7

Capacity Calculated (Track Speed)

No

12.8

Temporary speed restriction (Up/Down)

No

12.9

Train Consist

No

12.10

Capacity Ratio

No

12.11

Dynamic Load Allowance

No

12.12

Vehicle Load Effects (for Train consist)

No

12.13

Theoretical Remaining Fatigue Life

No

12.14

Live Load Factor

No

12.15

Fatigue Damage

No

12.16

Posted Load Limit (overbridge only)

No

13. Structural Element Group

13.1

Deck

Yes

13.2

Superstructure

Yes

13.3

Substructure

Yes

13.4

Tunnel

Yes

13.5

Other

Yes

13.6

Location

No

For structures in NSW the value for this attribute is imported directly from Ellipse.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 27 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix B Asset Register Attributes Controlled Values

Appendix B Asset Register Attributes


Controlled Values
Asset Class

Structure Types for the Asset Class

Bridges

Overbridge
Underbridge
Footbridge

Culverts

Small Culvert
Large Culvert

Tunnels

Tunnel

Miscellaneous Structures

Access (i.e. stairs, walkways)


Buffer stop (includes Stop block)
Culvert non-track
Flood structure
Lighting Gantry
Lighting Tower
Loading Structures (e.g. Loading Bank)
Overhead Service crossing
Retaining wall
Signal gantry
Sound barrier (including fencing)
Turntable
Water Structures
Weighbridge

State
NSW
VIC
SA
WA

Region
North South (North)

Kalgoorlie to Cootamundra (NSW)

North South (South)

KFC (SA/WA)

North South (South) NSS (Vic)

MAC (Vic)

Hunter Valley (NSW)

MAC (SA)

Residual Lease Network

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 28 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix B Asset Register Attributes Controlled Values

Line

Line

NSW

SOUTH/WESTERN AUSTRALIA

C03-PORT WARATAH ARRIVALS

W11 DRY CREEK TO CRYSTAL BROOK

C05-KOORAGANG JUNCTION

W12 -CRYSTAL BROOK TO SPENCER JUNCTION

C07-KOORAGANG ISLAND

W13 SPENCER JCT TO TARCOOLA

C26- TAHMOOR LOOP

W14 TARCOLA TO COOK

C28-SAXONVALE BRANCH

W15 COOK TO RAWLINNA

C30-BLOOMFIELD BRANCH

W16 RAWLINNA TO KALGOORLIE

C31-PELTON LINE

N21 CRYSTAL BROOK TO PETERBOROUGH

C33-MT THORLEY BRANCH

N22 PETERBOROUGH TO BROKEN HILL

C34- BRANSTON TO BRIX SIDING

S41 SPENCER JCT TO WHYALLA (PORT)

C36-NEWDELL BRANCH

S51 DRY CREEK TO OUTER HARBOUR (PORT)

N00-MAIN NORTH

E61 DRY CREEK TO TAILEM BEND

N40-ULAN LINE

E62 TAILEM BEND TO WOLSELEY

N35- HAMILTON JCT TO ISLINGTON JCT


N51-NORTH COAST

VICTORIA

N60-TELARAH - FARLEY

E71 WOLSELEY TO MAROONA

N70-BINNAWAY TO WERRIS CREEK

E72 MAROONA TO VITE VITE

N73-WERRIS CREEK TO MUNGINDI

E73 VITE VITE TO GHERINGHAP

S00-MAIN SOUTH (LIDCOMBE-ALBURY)

E74 GHERINGHAP TO NEWPORT

S32-PICTON TO MITTAGONG LOOP

E75 NEWPORT TO TOTTENHAM LOOP

M50-MARRICKVILLE LOOP TO BOTANY

E76 TOTTENHAM LOOP TO SPENCER STREET

M52-METROPOLITAN GOODS

E77 APPLETON DOCK JCT TO A/DOCK

M66-CHULLORA JCT TO SEFTON PARK JCT

N82 SOMERTON TO SEYMOUR LOOP

S70-COOTAMUNDRA TO LAKE CARGELLIGO

N83 SEYMOUR LOOP TO ALBURY

W20-ORANGE TO BROKEN HILL

N84 BENALLA TO OAKLANDS

W33-PARKES TO NARROMINE
W34-STOCKINBINGAL TO PARKES
W60-TROY JCT TO MERRYGOEN
W61-DUBBO TO COONAMBLE

Version 1.4

Track Code

Description

Network

ALLT

ALL TRACKS

Owned

ARRV

ARRIVAL ROAD

Leased

COAL

COALS

DEPT

DEPARTURE RD

DNCL

DOWN COAL

DNMN

DOWN MAIN

DRLF

DOWN RELIEF

LOOP

LOOP ROAD

NTRL

Residual

Service Status
In Service

Redunt Infrastc (Redundant


structure)

NOT TRACK RELATED

Not Maintained

Passed onto Civil Group

SIDG

SIDING

Disposed of

Replaced

SNGL

SINGLE TRACK

Partially Maintd

Structure does not exit

UPCL

UP COAL

UPLP

UP LOOP

UPMN

UP MAIN
Date of last revision: 10 Feb 14
This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 29 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix B Asset Register Attributes Controlled Values

Line Class

Span Material / Deck Material

Brick / masonry / stone

Insert ARTC classifications


-

Concrete

Steel

Timber

Wrought iron

Other (e.g. Earthenware, PVC)

Bridge Owner/Maintainer
ARTC

CRIA

Mine

Port Corp

Hunter Water

Private

Other Owner

PWCS

Other Maintainer

RailCorp

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 30 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix B Asset Register Attributes Controlled Values

Span Type Structure

Deck type

Plate web girder riveted

Ballast top

Plate web girder welded

Direct fixation

Plate web girder riveted through

Other

Plate web girder welded through

Pedestrian deck

Rolled section

Road deck

Box girder

Transom top

Broad flange beam


Through truss
Inverted truss

Paint Condition

Timber girder

Protective coating not required

Reinforced concrete girder

Good

Prestressed concrete girder

Fair

Slab

Poor

Rail
Jack arch
Multi-plate

Transom Bolt Type

Arch

Huck bolt

Box

Mild steel bolt

Pipe
Fibre Composite

Track Alignment
Curved: radius < 250m
Curved: radius 250-350m
Curved: radius 350-500m
Curved: radius 500-750m
Curved: radius 750-1000m
Curved: radius > 1000m
Straight

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 31 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix B Asset Register Attributes Controlled Values

Subjects
Previous inspections
Investigation reports
Defect
Drawings
Diary Notes
General
Inspections
Calculations
Miscellaneous
Structural

Photo Name
Deck view
Defect
Elevation
General photo
Soffit (underside) view
Structural detail

Defect Type
Blocked / obstructed / scoured
Broken
Concrete spalling
Corroded
Cracked / split
Crushed / collapsed
Decayed / rot
Deformed / bent
Loose
Missing
Non-compliant (e.g. non-standard)
Piped
Weathered
Refer description

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 32 of 89

Engineering
ETE-09-02 Structures Inspection Procedure

10

Appendix C Structural Elements

Appendix C Structural Elements


Element

Element
Number

Type

Material

Steel (S)

Precast
Cast-In-Situ
Concrete (P) Concrete [C] Timber (T)

Masonry
(M)

Unit of
Other (O) Measurement

Deck
1

Deck

Kerb

Lin m

Walkway/Refuge

Lin m

Railing/Barrier/Parapet/Balustrade

Lin m

Guard Rail

Transom

Ballast Kerb

Longdecking / Running Planks

Safety Screen

Version 1.4

m2

Lin m

Each

Lin m

m2
Y

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Lin m

Page 33 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Element
Number

Type

Appendix C Structural Elements

Steel (S)

Precast
Cast-In-Situ
Concrete (P) Concrete [C] Timber (T)

Masonry
(M)

Unit of
Other (O) Measurement

Superstructure
21

Box Girder

Lin m

22

Main/Top Girder

Lin m

23

Arch

24

Cables/Hangers/Tie Rod

25

Corbel

26

Cross Girder

27

Diaphragm

28

Stringer

Each

29

Bottom Girder

Each

30

Transverse Beam

Each

31

Truss Top Chord

Each

32

Truss Bottom Chord

Each

33

Truss Vertical Member

Each

34

Truss Diagonal Member

Each

35

Truss End Post

Each

36

Truss Sway Bracing

Each

37

Truss Top Chord Wind Bracing

Each

38

Truss Bottom Chord Wind Bracing

Each

39

Truss Portal

Each

40

Girder/Stringer Sway Bracing

Each

41

Girder/Stringer Wind Bracing

Each

42

Bearing

43

Footbridge Stairs/Ramp

Lin m

44

Footbridge Landing

Each

Version 1.4

Lin m
Each

Each

Each

Each

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Each

Page 34 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Element
Number

Type

Appendix C Structural Elements

Steel (S)

Precast
Cast-In-Situ
Concrete (P) Concrete [C] Timber (T)

Masonry
(M)

Unit of
Measurement
for Condition
Other (O) Assessment

Substructure
51

Headstock

52

Sill

53

Columns or Pile

54

Blade Pier

55

Abutment

m2

56

Wingwall

m2

57

Footing/Pile Cap/Sill Log

Each

58

Trestle Bracing

Each

59

Pile Waling

Each

60

Wingwall Pile

Each

61

Ballast Log

Each

62

Mortar Pad/Bearing Pedestal

63

Pipe Culvert

64

Box Culvert

65

Arch Culvert

66

Each

Each

Each

m2

Each

Lin m

Lin m

Lin m

Culvert Invert

Lin m

67

Culvert Apron

Lin m

68

Culvert headwall

Each

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 35 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Element
Number

Type

Appendix C Structural Elements

Steel (S)

Precast
Cast-In-Situ
Concrete (P) Concrete [C] Timber (T)

Masonry
(M)

Unit of
Measurement
for Condition
Other (O) Assessment

Tunnel
81

Tunnel Portal

82

Tunnel Roof

83

Tunnel Wall

84

Tunnel Rock Anchor

85

Tunnel Attachment

m2

m2

m2

Each

Each

Other
91

Bridge Approaches

Each

92

Waterway

Each

93

Approach Traffic Barrier

Lin m

94

Retaining Wall

m2

95

Conduit

Each

96

Water Pipe

Each

97

Sewerage Pipe

Each

98

Signage

Each

99

Miscellaneous Component

Each

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 36 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 37 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 38 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 39 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 40 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 41 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 42 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 43 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix C Structural Elements

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 44 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

11

Version 1.4

Appendix D Element Location

Appendix D Element Location

Element

Label in Diagram

Location

Element
Number

Location
Abbreviation

Abutment

No 1 Abutment

Abutment 1

55

A1/1

Abutment

No 2 Abutment

Abutment 2

55

A2/1

Wingwall

No. 1 Wing

Abutment 1

56

A1/1

Wingwall

No. 2 Wing

Abutment 1

56

A1/2

Wingwall

No. 3 Wing

Abutment 2

56

A2/1

Wingwall

No. 4 Wing

Abutment 2

56

A2/2

Wingwall Pile

No.1 Pile

Abutment 1

60

A1/1

Wingwall Pile

No.2 Pile

Abutment 1

60

A1/2

Wingwall Pile

No.3 Pile

Abutment 1

60

A1/3

Wingwall Pile

No.4 Pile

Abutment 1

60

A1/4

Wingwall Pile

No.5 Pile

Abutment 1

60

A1/5

Wingwall Pile

No.6 Pile

Abutment 1

60

A1/6

Wingwall Pile

No.1 Pile

Abutment 2

60

A2/1

Wingwall Pile

No.2 Pile

Abutment 2

60

A2/2

Wingwall Pile

No.3 Pile

Abutment 2

60

A2/3

Wingwall Pile

No.4 Pile

Abutment 2

60

A2/4

Wingwall Pile

No.5 Pile

Abutment 2

60

A2/5

Wingwall Pile

No.6 Pile

Abutment 2

60

A2/6

Column/Pile

No. 1 Pile

Pier 1

53

P1/1

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 45 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix D Element Location

Element

Label in Diagram

Location

Element
Number

Location
Abbreviation

Column/Pile

No. 2 Pile

Pier 1

53

P1/2

Column/Pile

No. 3 Pile

Pier 1

53

P1/3

Pile Waling

Bottom Waling

Pier 1

59

P1/1

Trestle/Pile Bracing

Bracing No. 1

Pier 1

58

P1/1

Trestle/Pile Bracing

Bracing No. 2

Pier 1

58

P1/2

Headstock

Headstock

Pier 1

51

P1/1

Corbel

Corbel (under
downside)

Pier 1

25

P1/1

Corbel

Corbel (under No. 2)

Pier 1

25

P1/2

Corbel

Corbel (under
upside)

Pier 1

25

P1/3

Bottom Girder

No 1 Girder (span 1)

Span 1

29

S1/1

Bottom Girder

No 2 Girder (span 1)

Span 1

29

S1/2

Bottom Girder

No 3 Girder (span 1)

Span 1

29

S1/3

Bottom Girder

No 1 Girder (span 2)

Span 2

29

S2/1

Bottom Girder

No 2 Girder (span 2)

Span 2

29

S2/2

Bottom Girder

No 3 Girder (span 2)

Span 2

29

S2/3

Top Girder

No 1 Girder (span 1)

Span 1

22

S1/1

Top Girder

No 2 Girder (span 1)

Span 1

22

S1/2

Top Girder

No 3 Girder (span 1)

Span 1

22

S1/3

Top Girder

No 1 Girder (span 1)

Span 2

22

S2/1

Top Girder

No 2 Girder (span 1)

Span 2

22

S2/2

Top Girder

No 3 Girder (span 1)

Span 2

22

S2/3

No.

No.

For components that run across a structure, for example diaphragms, cross girders transoms,
etc, the component number shall be referenced from the start of the span. For example:

Version 1.4

The third cross girder to the second span of a through girder bridge would be labelled Element No 26 Location S2/3.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 46 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix E Inspection of Steel Structural Elements

12

Appendix E Inspection of Steel Structural


Elements

12.1

Steel Degradation
In general, steel deteriorates in service in the following ways:
a) Erosion or corrosion at exposed surfaces, and at timber or concrete interfaces;
b) Cracking in elements or welds;
c)

Relaxation of fastenings;

d) Distortion due to overload, or from direct impact from road or rail vehicles;
e) Fatigue from repetition of external loading.

12.2

Inspection Methods
The principal inspection methods are:
Visual
Most cracks in steel bridges are first detected by visual inspection. Once a crack is found, other
non-destructive inspection methods, such as dye Penetrant and magnetic particle, are used to
further clarify the extent of the crack.
The usual and most reliable sign of fatigue cracks is the oxide or rust stains that develop after
the paint film has cracked. Experience has shown that cracks have generally propagated to a
depth between one-fourth and one-half the plate thickness before the paint film is broken,
permitting the oxide to form. This occurs because the paint is more flexible than the underlying
steel.
In Broad Flange Beams inspect for notches caused by impact from vehicles or equipment.
Report on loss of section on completion of grinding as required.
Inspect for water build-up, especially in areas that could cause corrosion.
Inspect for loose fasteners. The most reliable sign for loose structural fasteners is the leaching
of rust stains from the interface of the connecting elements.
Elements are to be observed under load where possible, and any excessive movement in
elements or fastenings is to be noted.
Hammer Test
When elements are tapped lightly with an inspectors hammer, it will help to identify loose
plates and fastenings, the extent of corrosion, and effectiveness of corrosion protection. Care
must be taken that hammering does not cause unnecessary destruction of protection systems.
Specialist inspection methods, including X-Ray, Ultrasonic, Acoustic Emission, and Laboratory
analysis of steel samples, are beyond the normal scope of Visual Inspections and Engineering
Inspections.
Advanced Inspection Techniques
Magnetic Particle Testing (MPI) or flaw detection penetrant dye will detect suspected cracking
not clearly visible. The local area is to be cleaned back to bare metal to perform the testing. The
bare metal shall be re-primed with an appropriate paint system if no crack is found.
Where protective coatings are showing signs of deterioration, or where remote faces of steel
elements preclude surface inspection, a dry film thickness gauge or ultrasonic flaw detector
device should be used to determine relevant thickness of coating or steel section.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 47 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

12.3

Appendix E Inspection of Steel Structural Elements

Element Inspection
General
Examine elements for:

Corrosion and section loss;

Buckled webs, web stiffeners and flanges;

Cracks in webs, flanges and welds;

Loose bolts, rivets, plates and bars;

Paintwork condition;

Distortion from corrosion products;

Stain trails indicating hidden corrosion;

Polished surfaces indicating movement between elements.

Particular defect areas to be examined are:


Main Girders (Plate Web or Rolled Section)
1) Corrosion under transoms or decking, at toes of bottom flange angles between flange
plates, around bearings, at abutments and piers, at bracing connections, in rivet and bolt
heads.
2) Loose rivets or bolts in flange angles, splices, bracing connections, web stiffeners and
splices, bearing plates.
3) Cracks in bottom flange (tension zone), particularly in the area of mid-span.
4) Cracked welds in flange/flange fillets, web stiffeners with diaphragm bracing, bottom of
web stiffeners, web/flange fillets.
5) Notches in bottom flanges from road vehicle impact, particularly in Broad Flange Beams.
6) Cracks, loss of section or buckling in webs at ends of girders.
7) Buckled webs of unstiffened girders.
Cross Girders
1) Corrosion under transoms or decking, at toes of bottom flange angles between flange
plates, around bearings, at abutments and piers, at bracing connections, in rivet and bolt
heads.
2) Cracks in flanges and webs at ends of girders.
3) Loose rivets or bolts in connections.
Stringer Girders
1) Corrosions under transoms or decking.
2) Cracks in bottom flange, particularly in the area of mid-span.
3) Cracks in top fillets at ends of girders.
4) Loose rivets or bolts in connections.
5) Detailing.
Bearings
1) Corrosion at flange plate/end bearing stiffener connections.
2) Cracks in bearing or bed plates.
3) Cracked welds between flanges and bearing plates.
4) Loose, broken or missing holding down bolts, studs, and clips.
5) Ineffective sliding, roller or segmented expansion bearings.
6) Expansion bearings not working and segmented bearings lying over.
Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 48 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix E Inspection of Steel Structural Elements

Truss Girders
1) Corrosion in top and bottom chords, batten plates and lacing bars, portal and wind bracing
over tracks, gusset plates, rivet and bolt heads.
2) Misalignment or distortion in chords.
3) Cracks in cleats and connector plates.
4) Loose rivets or bolts and turnbuckles.
5) Damaged steelwork from equipment or loads traveling out-of-gauge.
Stepways / Stairways
1) Corrosion at base connection, stepway risers, stringer webs, tread cleats and clips.
2) Loose bolts and clips to treads.
Trestles
1) Corrosion around baseplates, between angles in bracing, in rivet heads and holding down
bolts.
2) Loose rivets or bolts in connections to girders or bracing.
3) Loose turnbuckles in bracing.
Piers/Caissons
1) Corrosion at crosshead connection at water or ground level.
2) Excessive movement of any element under load.
3) Cracks in cylinder walls.
Corrugated Steel Pipes
1) Corrosion in corrugation.
2) Distortion in pipe profile.
3) Breakdown of coating.
4) Change in invert alignment indicating bedding failure.
Rivets
There are two types of rivets in the bridge system.

Structural rivets rivets that need to be tightly fitted e.g. rivets connecting stringer to
cross girder or lacing bars to top and bottom chords. Inspect for leaching of rust stain
or looseness apparent to a hammer tap.

Stitching rivets that do not need to be tightly fitted to hold the elements together e.g.
rivets connecting diagonal lacing bars or lacing bar spacers in truss bridges. Inspect for
slackness due to excessive wear and tear.

Deflection
Deflection in steel elements is normally small. Any clear movement under live load is to be
measured, or closely estimated, and reported.
Temporary Supports
Inspect visually for soundness and effective support, including footing, foundation and drainage.
Packing and wedges are to be tightened and secured as necessary. Where temporary supports
have been in service for more than 1 year they must be thoroughly inspected in the same
manner as other elements of the structure.

12.4

Broad Flange Beam


Introduction
Broad Flange Beam (BFB) spans over roadways are subject to a significant risk of fatigue and/or
brittle fracture if damaged by road vehicle impact. The beams become brittle when the ambient

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 49 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix E Inspection of Steel Structural Elements

temperature is less than 13C. In order to minimize this risk all such structures are included in a
special inspection program during winter months.
Inspection
The spans are to be examined for evidence of flange damage, i.e. cracking, notching, bruising,
distortion, scores, and bends) as well as grinding or other repairs. Note that cracks can develop
from previously ground or repaired areas.
Inspection must be carried out from close proximity to enable measurement of defects, and to
give a reasonable chance of detection of cracking on any surface of the flanges.
Where there are welded flange plates special attention must be given to the BFB flange in the
proximity of the welds, as there is a possibility of crack initiation and propagation from welds.
Recording
Each notch is to be individually measured and recorded. Where the flange is bent laterally or
vertically, an estimate of the distance is to be recorded. The report should indicate whether
damage is in the BFB flange, or the flange plate, or both.
Site action to be taken when cracking or damage occurs.
Where any cracking is found in the BFB bottom flange / flange plate / cover plate area, the
Structures Representative is to be informed immediately and a speed restriction imposed, or the
track closed, or the bridge temporarily supported, depending on the extent of the crack as
detailed below.
If the track is not closed the bridge must be monitored very closely and a speed restriction
imposed to suit. A significant risk and rapid crack growth exists with any unplated BFB showing
any crack, or a plated span showing cracks in both BFB and plate flanges. Plated flanges
showing cracks in one element, but not in both, are less of a risk.
If a span is temporarily supported at a crack, trains may run indefinitely up to 50Km/h
depending on the quality of the supports.
If a span is not temporarily supported at a crack, the following action is required:

If the flange is plated and a crack up to 25mm exists in either the BFB flange or in the
flange plate, speed is to be limited to 20Km/h, and the crack is to be checked after each
train.

If the crack is greater than 25mm but less than 100mm, road traffic is to be suspended
during the passage of rail traffic.

If the crack is greater than 100mm, rail traffic must NOT be permitted.

Where the flange is not plated or both flange and flange plate are cracked, rail traffic
may be permitted if the crack is up to 25mm long. Rail speed must be limited to
20Km/h, road traffic must be stopped during the passage of each train, and the crack is
to be checked after each train.

Where the flange is not plated or both flange and flange plate are cracked, and the
crack is over 25mm, rail traffic is to be stopped.

Repair method
No welding, straightening or cutting is to be done on BFB spans without prior approval of the
Structures Engineer.

12.5

Element Condition Assessment Guidelines


The following guidelines are provided to assist the Structures Engineer assess the condition
state of steel elements.
Condition State 1

Version 1.4

The paint system is generally sound with only minor chalking, peeling or curling but with
no exposure of metal.

All welds, bolts or rivets are in good condition with no movement of plates or sections in
the element.
Date of last revision: 10 Feb 14
This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 50 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix E Inspection of Steel Structural Elements

Condition State 2

Spot rusting of the paint system to 5% surface area is occurring and the paint system is
no longer effective. No corrosion of the section has occurred.

All welds, bolts or rivets are in good condition with no movement of plates or sections in
the element.

Condition State 3

Some surface pitting may be present with active corrosion occurring in isolated areas
but no loss of section area has occurred which will affect the strength of the element.

The paint system has broken down with rust spotting to 10% and surface pitting.

Nuts and bolts may be corroded but are still tight and no cracking of welds has
occurred.

Riveted plates may have very minor movement of 1 or 2mm but rivets are generally
sound. On transom top bridges inadequate or lack of effective bracing between girders
is affecting the lateral distribution of heavy loads between girders. Girders should be
well braced with heavy channel connectors at approximately 5-6m centres. With old
girders, they typically have angle or plate sway bracing to prevent lateral buckling or
bowing under load.

Condition State 4

12.6

Corrosion is well advanced and loss of section has occurred having a detrimental effect
on the strength of the element, ie a flange may be badly corroded over a sizable length.

Bracing may be broken or missing forcing the girder to carry additional live loads than
intended.

There may be some cracking of the welds between the plates.

Rivets or bolts may be severely corroded and no longer carrying full load or functioning
as intended.

Rivets may be broken or missing allowing excessive movement of plates of fabricated


girders.

The paint system has completely broken down with cleaning back to bright metal
required before repainting.

Additional Inspection Requirements


When undertaking an Engineering Inspection for a Steel Bridge the Structures Engineer shall
provide the following additional information:
Paint Condition Rating
Paint Condition Ratings are to be assigned by the Structures Engineer to reflect the condition of
the surface coating for the overall structure. The ratings are defined as follows:

Poor:

Paint broken down throughout. Program to paint within 10 years.

Fair:

Paint broken down locally. Patch paint as required within 5 years.

Good:

Paint in satisfactory condition.

Painting not required: The structure is located in a benign environmental location area
where the rate of corrosion is low and corrosion of steel structural elements will not
significantly affect the design life of the structure.

Non Destructive Testing


Non-destructive testing (NDT) shall be carried out on site to verify cracks and crack lengths
where:

Version 1.4

Cracks on wrought iron structural elements exceed 50mm

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 51 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix E Inspection of Steel Structural Elements

Any new crack, or any extension to a previously noted crack, on steel structural
elements.

The NDT shall include:

Magnetic Particle Testing

Liquid Penetrant Testing.

The Structures Engineer is required to have the competency to undertake the testing, or
arrange for the testing to be undertaken by someone with sufficient competency. The minimum
level of competency acceptable to ARTC is successful completion of a Level 1 Liquid Penetrant
and Magnetic Particle Testing Methods course that meets the requirements of AS 3998 2006 "Non-destructive testingQualification and certification of person.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 52 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix F Inspection of Timber Structural Elements

13

Appendix F Inspection of Timber Structural


Elements

13.1

BridgeWood Decking
The BridgeWood decking consists of specially designed and treated plywood panels which are
specifically designed for both road and rail bridge applications. It requires the similar examinations
to traditional hardwood timber components to ensure continued safety of traffic operation.

13.2

Timber degradation
In general, timber deteriorates in service only when attacked by outside agencies. These can be
categorized as follows:
a) Weathering at exposed surfaces;
b) Decay or rot;
c)

Insect attack, whether termites or borers;

d) Fire;
e) Mechanical damage from vehicles or equipment;
f)

Checks and splits.

Of the above categories, decay and insect attack usually cause deterioration inside an element
and therefore are the hardest to measure.

13.3

Inspection methods
The principal timber inspection methods are:
Visual inspection
All bridge elements are to be inspected for indications of deterioration or damage such as:

Weathering, cracks, shakes, splits;

Bubbles, especially in laminated panel indicating internal de-lamination;

Surface decay where elements join or where elements project behind abutments;

Damp sides of elements, especially of timber decking;

Indicators of internal decay such as troughing, sides bulging, brooming out of fibres,
body bolts hanging out or loose in their holes;

Termite or fungus attack;

Crushing of elements, especially headstocks, at seating and joints;

Spike killing of transoms;

Loose or missing bolts, including transom bolts.

Hammer Testing
Hammering, or sounding, a timber element gives an indication of internal deterioration. The
presence of delamination, rot or termite attack may cause a hollow sound when struck by the
hammer, indicating boring is required. The hammer should weigh about 1kg, with one face flat
and the other face spiked.
Bore and Probe
Test boring is carried out with a 10 mm auger in order to locate internal defects such as pipes,
rot or termites. Holes are bored square to the face of girders, corbels, headstocks, piles, sills
and other elements, as necessary. Boring must not be overdone and holes are to be
Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 53 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix F Inspection of Timber Structural Elements

preservative treated and plugged, leaving the plug 20mm proud. Unused holes are to be
plugged flush. The extent of an internal pipe or other defect is found and measured with a feeler
gauge made from 4 mm steel wire with one end flattened and about 4 mm bent over at right
angle. By probing down the bore hole, the extent of a defect can be felt, measured and
recorded.

NOTE: No boring of BridgeWood decking is required because the Engineered Wood Product is
not subject to piping or internal rot as in sawn hardwood.

Deflection Test
A deflection test gives an indication of girder condition and riding quality.
Deflections are to be measured at the mid-point of all girders in the tested span and recorded.
If deflection limits are exceeded at permitted track speed, temporarily reduce train speed to
suit. If the limit is exceeded at 20 km/h, the Structures Representative is to be advised the
same day.

13.4

Inspection procedure
The following inspections are to be undertaken by the inspector:
Transoms
Inspect for weathering, splitting, crushing, spike killing, fire damage, condition at rail seating,
and condition at girder bearings for intermediate transoms.
Ballast Walls
Inspect for general condition, tightness of bolts, and capacity to retain ballast.
Runners
Inspect for general condition and tightness of bolts.
Decking
Determine the general condition of the timber decking. Note the number, size and location of
pieces split, or with more than twenty percent (20%) section loss.
Ballast Logs
Inspect for general condition and tightness of bolts.
Girders
Inspect visually and hammer test for soundness. Bore new holes and probe girders at each
Engineering Inspection. Inspect compound girders individually. If necessary, the inspector may
bore during a Visual Inspection preferably using existing holes.
Girders are to be inspected for signs of decay, particularly where this may be occurring on the
top surface under the decking of ballast top spans. Bore girders horizontally at mid depth over
corbel ends or sill face and at centre span.
Where a pipe is found over 125 mm wide, cross bore vertically at the location and note size and
position of the pipe. Where visual inspection raises any doubt or where termites appear active,
additional boring is to be carried out as necessary.
Check the bearing areas for crushing of the beams near the bearing seat. Investigate for decay
and insect damage by visual inspection and sounding and/or probing at the ends of the beams
where dirt, debris, and moisture tend to accumulate.
Investigate the area near the supports for the presence of horizontal shear cracking. The
presence of transverse cracks on the underside of the girders or horizontal cracks on the sides
of the girders indicate the onset of shear failure.
Inspect the zones of maximum tension for signs of structural distress. The maximum tension
generally occurs at the bottom half of the middle third of the beam span. Tension cracks in

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 54 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix F Inspection of Timber Structural Elements

timber break the cell structure perpendicular to the grain and are typically preceded by the
appearance of horizontal shear cracks.
Corbels
Inspect in a similar manner to girders. Bore holes to be 300 mm from each end, and at the
centre, but clear of bolt holes. Where packing is installed, the location, size and type are to be
noted.
Headstocks
Inspect visually and hammer test for soundness. Identify solid and double waling types. Bore
and probe ends of elements if hammer test indicates internal decay. Give special attention to
corbel seatings and to pile bearings. Inspect waling headstocks for loose bolts and for bearing
on pile shoulders.
Bracing
Inspect all horizontal and diagonal bracing visually and hammer test for soundness. Inspect for
loose bolts, and effectiveness of bracing in restraining side-sway.
Sills
Inspect visually and hammer test for soundness. Identify solid and double waling types. Inspect
for loose bolts, straps, decay of undersides on concrete bases, and bearing of walings on pile
shoulders.
Piles
Inspect visually and hammer test for soundness. Bore new holes during every Engineering
Inspection and probe at headstock level and at ground level.
Inspection below ground is required during Engineering Inspection, using a backhoe where
possible. Excavate to a depth of 500 mm, or more if necessary, and bore at trench bottom.
Where spliced piles show signs of vertical or sideways movement, the splice rails and pipe
stumps are to be exposed and inspected. All excavations are to be backfilled, rammed, and
scour protection reinstated. If necessary, the Structures Inspector may bore new holes during a
Visual Inspection
Spliced and planted piles are to be specially noted. Depth of splice, or of plant footing, below
bottom waling is to be noted. Where piles have a surrounding concrete collar or invert, the
concrete must not be cut away for inspection unless extensive pile necking or piping is evident.
Inspect piles in permanent water during Engineering Inspection, or more frequently depending
on deterioration shown at the previous inspection, or if major scouring is suspected. The
underwater inspection should be carried out in accordance with the guidance of this Procedure.
At Engineering Inspections, when the cross-sectional area of a pile is found to be degraded to
50% of its original cross sectional area the following procedure is required. The defect is to be
rated a Defect Category D. Subsequently any such degraded pile that is assessed to be
performing satisfactorily and deemed to be able to remain in place, must then have 2 yearly
cyclic boring carried out (i.e. at the normal cyclic visual inspections).
Abutment sheeting and wing capping
Inspect for general condition and for ability to retain backfill. Inspect sheeting behind girders of
end spans.
Walkways and Refuges
Inspect for overall safety.
Truss spans
Inspect truss elements generally, as for girder spans. Bore new holes and probe top chords,
bottom chords, cross girders, stringers and end posts at element ends. Tighten tension
elements, taking care to avoid crushing of timber in joints.
Timber box drains
Inspect visually for general condition, and note any indication of failure of roof or wall timbers.
Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 55 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix F Inspection of Timber Structural Elements

Temporary supports
Inspect visually for soundness and effective support, including footing, foundation and drainage.
Packing and wedges are to be tightened and re-spiked where necessary. Where temporary
supports have been in service for more than 1 year they must be thoroughly inspected,
including new bore holes, in the same manner as other elements of the structure.
Termites and Fungus
Termite infestations found either visually or by boring during inspection are to be reported to
the Structures Representative immediately. Suspected areas of fungal attack could be inspected
by prodding the exposed surface with a sharp probe to detect areas of softness compared to the
surrounding good timber.
Screwing Up
During the inspections, all bolts are to be inspected and tightened as necessary.
Packing is to be inspected, repacked and spiked as necessary.
Site condition
All dry grass, flood debris, and other foreign matter that may cause a fire hazard, or may
accelerate timber decay, must be removed from the immediate vicinity of the bridge element.

13.5

Element Condition Assessment Guidelines


The following guidelines are provided to assist the Structures Engineer assess the condition
state of timber elements.
Condition State 1

The timber elements are in good condition with little decay and piping is less than
100mm diameter in standard 300 x 300mm section. There may be minor splits or
checks having no effect on element strength.

Glue laminated elements have no separation of laminations and no splits or checks


within the laminations.

Condition State 2

Timber elements are in good condition with up to 125mm diameter pipe rot in standard
300 x 300mm section. They may also have minor decay, splitting, checking or crushing
but not loss of efficient to the magnitude to affect the strength of the element.

Glue laminated elements have no separation of laminations but may have minor splits
or checks within the laminations but not of sufficient size or magnitude to effect element
strength.

Condition State 3

Timber elements have up to 150mm diameter pipe rot. They may have large splits or
checks, which may have a reduction in strength of the element. Splits may be
separating under load causing crushing of the element or crushing may be due to water
ingress softening the load bearing areas of the timber.

Glue laminated elements may have fine splitting along laminated joints and the outer
fibres may be peeling or fine cracks may exist in the outer lamination. There may also
be fine splitting within the laminations due to tensile stresses between the fibres.

Condition State 4

Version 1.4

The timber elements may have excessive pipe rot, greater than 150mm diameter,
accompanied by severe splitting or crushing. Strength of the element has been severely
affected and failure may be imminent.

Glue laminated beams have extensive splitting along the lamination joint. Medium level
cracking of the laminations has occurred with the outer fibres splitting apart due to
tensile stresses and the beam has partially failed.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 56 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix G Inspection of Concrete Structural Elements

14

Appendix G Inspection of Concrete Structural


Elements

14.1

Concrete Degradation
In general, concrete deteriorates in service in the following ways:
a) Weathering or spalling at exposed faces, resulting from erosion, poor quality concrete,
chemical action, water action, corrosion of reinforcement, low cover to reinforcing bars,
crushing at bearing surfaces and poorly compacted concrete;
b) Cracking from loading changes, including settlement;
c)

14.2

Mechanical damage, especially collision damage from road or rail vehicles, or abrasion.

Inspection Methods
The principal inspection methods are:
Visual
Visual inspection will detect most defects in concrete structural elements. The inspector is to
look for signs of:

Weathering or spalling of surfaces or mortar joints;

Cracking within elements or at joints;

Stains on surfaces indicating reinforcement corrosion;

Crushing especially at bearings or at prestressing anchorage points;

Changed alignment of elements:

vertically, e.g. abutments;

horizontally, e.g. deck camber; or

laterally, e.g. footings and culverts.

Cracking in concrete structural elements is an indicator of weakness in the element. Cracks


must be examined for size and movement under load, and details recorded. Shrinkage or
hairline cracks need be noted only.
Cracking or crushing around prestressing anchorages must be noted.
Length, width, and location of cracks are to be measured. A short line scribed across the
midpoint of a crack will give easy indication of further movement. Reference points scribed at
each end of the line can be measured to indicate changes in crack width.
Examine all elements for the unplanned ingress of water. Scuppers, weep holes, and other
outlets are to be cleared of rubbish. Any water build-up, or seepage into unwanted areas, is to
be reported.
Hammer Test
Hammer testing, where surfaces are tapped lightly with an examination hammer, can indicate
drumminess (a dull hollow sound) and potential spalling areas.
Advanced Inspection Techniques
Where the cause of cracking or bulging of an element cannot be explained by visual inspection,
specialist testing such as X-Ray, Ultrasonic, and Acoustic Emission can be used to examine the
internal condition of structures and the underlying cause of the observed defects. The inspector
is to note such concerns for follow-up by the Structures Representative.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 57 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

14.3

Appendix G Inspection of Concrete Structural Elements

Locations
Bearing Areas
Examine bearing areas for spalling where friction from thermal movement and high bearing
pressure could cause the concrete to spall. Check for crushing of the stem near the bearing
seat. Check the condition and operation of any bearings.
Shear Zones
Investigate the area near the supports for the presence of shear cracking. The presence of
transverse cracks on the underside of the stems or diagonal cracks on the sides of the stem
indicate the onset of shear failure. These cracks represent lost shear capacity and should be
carefully measured.
Tension Zones
Check for deteriorated concrete in the tension zones, which could result in the debonding of the
tension reinforcement. This would include delamination, spalls, and contaminated concrete.
Cracks greater than 2 mm wide are considered wide cracks and indicate extreme bending
stresses. They should be measured and recorded.
Cracks
Check for efflorescence from cracks and discoloration of the concrete caused by rust stains from
the reinforcing steel. In severe cases, the reinforcing steel may become exposed due to spalling.
Document the effective cross section of reinforcing steel since section loss will decrease live load
carrying capacity of the element.
Deflection
Deflection in concrete elements is normally small. Any clear movement under normal traffic load
is to be measured and reported.
Diaphragms
Diaphragms should be inspected for flexure and shear cracks as well as typical concrete defects.
Cracks in the diaphragms could be an indication of overstress or excessive differential deflection
between adjacent beams.
Areas Exposed to Drainage
Check around scuppers, inlets or drain holes for leaking water or deterioration of concrete.

14.4

Element Condition Assessment Guidelines


The following guidelines are provided to assist the Structures Engineer assess the condition
state of concrete elements.

14.4.1 Reinforced Concrete Elements


Condition State 1

The reinforced concrete elements are in good condition with only very minor fine
cracking due to shrinkage or lack of curing.

Condition State 2

Flexural cracking and cracking associated with reinforcement corrosion is fine, ie up to


0.5mm in width, though no rust is visible in the cracks. A few minor spalls may be
present. Fine cracking may have occurred at the bearing areas of beams.

Condition State 3

Version 1.4

Flexural cracking and cracking due to reinforcement corrosion is medium, i.e. up to


1.5mm in width, and a number of spalls may have occurred, and / or heavy rust
staining is present at the cracks. Where reinforcement is close together, some
delamination of the concrete may have occurred. Loss of section of any corroding
reinforcement is less than 20%. Cracking may have occurred at the ends of beams
affecting the bearing area of the element.
Date of last revision: 10 Feb 14
This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 58 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix G Inspection of Concrete Structural Elements

Condition State 4

Corrosion of the reinforcement is well advanced with loss of bar section greater than
20%. Flexural cracking in the element may be severe with beams noticeably deflecting
under load. Severe spalling may have occurred due to corroding reinforcement or at the
ends of beams at the bearing areas.

14.4.2 Prestressed Concrete Beams


Condition State 1

The prestressed concrete elements are in a good condition with only very minor
cracking due to shrinkage or lack of curing.

Condition State 2

The prestressed concrete elements may have fine cracking due to corroding reinforcing
bars. There may be a few minor spalls but no rust staining in the cracks. Stressing
strands must not be exposed.

Condition State 3

Cracking has increased in size and a few medium spalls and de-laminations have
occurred exposing stressing strands. The stressing strands should only have surface rust
while non-prestressed reinforcement may have up to 20% loss of section. Light flexural
cracking may exist in the beams.

Condition State 4

Version 1.4

Delaminations, spalls and corrosion of reinforcement are prevalent with loss of capacity
of strands. Exposed stressing strands may have corrosion up to 10% of their cross
section or strands may have broken. Heavy cracking or failure of the element may have
occurred. Heavy flexural cracking may be present in beams or in prestressed decking
above supports.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 59 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix H Inspection of Fibre Composite Structural Elements

15

Appendix H Inspection of Fibre Composite


Structural Elements

15.1

Fibre Composite Degradation


In general, Fibre Composite products deteriorate in service in the following ways:

Surface cracking

When overstressed due to excessive loading a non-structural coating or paintwork on


element will show signs of fine cracks or spalling at bottom and on side surfaces at load
point.

On impact the coating may spall, split or crack. Small localised damage is of no
immediate engineering concern however, all damages should be reported.

Crushing

Crushing at load points (on edges at bearings or around bolt holes) is most likely an
indication of excessive loading. The coating will show signs of discoloring/spalling. All
such discoloring/spalling shall be reported.

Wear and tear

Excessive wear and tear or overstressing at bolt holes will show signs of discoloring or
spalling in the coating. Loose fasteners will indicate wearing in threads of material.

Fire Damage

The coating can be subject to fire damage in much the same way as timber however,
the Fibre Composite product itself will withstand intense heat/fire.

To determine the extent to which the element is affected, any lose or charred material
must be removed until unburned material is exposed. If the fire damage is limited to the
protective layer no immediate engineering concern exists however all fire damages
should be reported.

15.1.1 Inspection

15.2

Fibre Composite material will not rot or decay and it is resilient to any attack by
termites or fungus.

A close visual inspection is to be made of all exposed surfaces.

No boring for inspection purpose shall be undertaken as it will not reveal any internal
defects.

No chemical etching or hard tapping with any object shall be undertaken.

Inspection Methods
The principal inspection methods are:
Visual
Visual inspection will detect most defects in fibre composite structural elements. The inspector is
to look for signs of:

Version 1.4

Cracking within elements or at joints;

Stains or discolouring on surfaces indicating overstressing of localised area;

Crushing especially at bearings or load points;

Changed alignment of elements:

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 60 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix H Inspection of Fibre Composite Structural Elements

Cracking in structural elements is an indicator of weakness in the element. Cracks


must be examined for size and movement under load, and details recorded.
Shrinkage or hairline cracks need be noted only.

Length, width, and location of cracks are to be measured. A short line scribed
across the midpoint of a crack will give easy indication of further movement.
Reference points scribed at each end of the line can be measured to indicate
changes in crack width.

Hammer Test
Hammer testing, where surfaces are tapped lightly with an examination hammer, can indicate
drumminess and potential spalling areas.
Advanced Inspection Techniques
Where the cause of cracking or bulging of an element cannot be explained by visual inspection,
specialist testing such as X-Ray, Ultrasonic, and Acoustic Emission can be used to examine the
internal condition of structures and the underlying cause of the observed defects. The inspector
is to note such concerns for follow-up by the Structures Representative.

15.3

Locations
Bearing Areas
Examine bearing areas for spalling where friction from thermal movement and high bearing
pressure could cause the fibre composite to wear/spall. Check for crushing of the stem near the
bearing seat. Check the condition and operation of any bearings.
Shear Zones
Investigate the area near the supports for the presence of shear cracking. The presence of
transverse cracks on the underside of the stems or diagonal cracks on the sides of the stem
indicate the onset of shear failure. These cracks represent lost shear capacity and should be
carefully measured.
Tension Zones
Check for cracks in the tension zones, which could result in the debonding of any tension
reinforcement. This would include delamination and spalls. All cracks must be measured and
recorded.
Cracks
Check for efflorescence from cracks and discoloration of the coating caused by overloading.
Deflection
Deflection in elements is normally small. Any clear movement under normal traffic load is to be
measured and reported.

15.4

Element Condition Assessment Guidelines


The following guidelines are provided to assist the Structures Engineer assess the condition
state of fibre composite elements.

15.4.1 Fibre Composite Elements


Condition State 1

The elements are in good condition with only very minor fine cracking due to shrinkage
or lack of curing.

Condition State 2

Version 1.4

Flexural cracking is fine, i.e. up to 0.5mm in width, though no rust stain or foreign
material is visible in the cracks. A few minor spalls may be present. Fine cracking may
have occurred at the bearing areas of beams.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 61 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix H Inspection of Fibre Composite Structural Elements

Condition State 3

Flexural cracking between 0.5 and 1.5mm in width. Cracking may have occurred at the
ends of beams affecting the bearing area of the element.

Condition State 4

Version 1.4

Flexural cracking in the element may be severe with beams noticeably deflecting under
load.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 62 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix I Inspection of Interflow Expanda & Rotaloc Pipes

16

Appendix I Inspection of Interflow Expanda &


Rotaloc Pipes

16.1

General

16.2

Expanda & Rotaloc pipe products are two different methods of fabricating new drainage
pipes or lining the interior surfaces of severely corroded corrugated steel pipes (CSP) to
strengthen them to railway design loading 300LA.

The liners are designed to sustain full design load without sharing any design loads with
the existing corroded pipe.

The annulus between the Interflow liner and CSP pipe is then pressure grouted with
cementitious grout.

These products are made from PVC or HDPE Plastic by Interflow Ltd, an Australian
based company.

ARTC has approved use of Expanda & Rotaloc pipes/liners for pipes up to 1000mm and
1500mm diameter respectively.

Expanda & Rotaloc Degradation


Unlike steel and concrete, polyethylene and PVC dont corrode in acidic conditions and dont
need protective coatings that need to be maintained. The liners are continuous and dont have
fasteners, bolts, etc.
In general, the products deteriorate in service in the following ways:
Deformation

As the products are flexible, deformation would indicate overstressing due to excessive
loading or loss of embedment support, most likely caused by scouring around the
outside of the liner and would need to be addressed.

Cracked barrel / Joint broken or separated

When overstressed due to excessive loading the pipe will develop cracks or joint
separation.

Abrasion in sectional area

While PVC and Polyethylene are more abrasion resistant than steel or concrete, the
liners/pipes should be inspected for any evidence of abrasion, particularly in floor.

Fire / Ultra Violet Radiation damage

The products could be subject to fire/UVR damage however, they will withstand intense
heat/fire.

16.2.1 Inspection

16.3

Expanda and Rotaloc material will not rot or decay and it is resilient to any attack by
termites or fungus.

A close visual inspection is to be made of all exposed surfaces.

No boring for inspection purpose shall be undertaken as it will not reveal any internal
defects.

No chemical etching or hard tapping with any object shall be undertaken.

Inspection Methods
The principal inspection methods are:

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 63 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix I Inspection of Interflow Expanda & Rotaloc Pipes

Visual
Visual inspection will detect most defects in Expanda and Rotaloc pipes. The inspector is to look
for signs of:

Deformation

Settlement / Changed alignment

Cracking/Disjointing

Abrasion

Fire / UVR damages within elements or at joints.

Deformation and/or cracking in pipes are indicators of weakness. These defects must be
examined for size and movement under load, and details recorded. All cracks need be noted
carefully.
Length, width, and location of cracks are to be measured. A short line scribed across the
midpoint of a crack will give easy indication of further movement. Reference points scribed at
each end of the line can be measured to indicate changes in crack width.
Hammer Test
Hammer testing, where surfaces are tapped lightly with an examination hammer, can indicate
drumminess and potential loss of backfill material or undermining of foundation.

16.4

Locations
Deformation
As the products are flexible, deformation would indicate overstressing due to excessive loading
or loss of embedment support, most likely caused by scouring around the outside of the pipe
and would need to be addressed.
Cracked barrel / Joint broken or separated
When overstressed due to excessive loading the pipe will develop cracks or joint separation.
Abrasion in sectional area
While PVC and Polyethylene are more abrasion resistant than steel or concrete, the liners/pipes
should be inspected for any evidence of abrasion, particularly in floor.
Fire / Ultra Violet Radiation damage
The products could be subject to fire/UVR damage however, they will withstand intense
heat/fire.
Foundation
Examine for differential settlement and undermining of the foundation and around inlet/outlet of
pipe.
Deformation
Check for deformation in highly stressed zones at 10 and 2 0clock and at any other locations
along full length of the pipe.
Tension Zones
Check for cracks in the tension zones, which could result in the disjointing along seams.
cracks must be measured and recorded.

All

Deflection
Deflection in elements is normally small. Any clear movement in roof under normal traffic load
is to be measured and reported.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 64 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

16.5

Appendix I Inspection of Interflow Expanda & Rotaloc Pipes

Element Condition Assessment Guidelines


The following guidelines are provided to assist the Structures Engineer assess the condition
state of plastic pipes.

16.5.1 Expanda & Rotaloc Pipes


Condition State 1

The elements are in good condition with only very minor scratches and wear.

Condition State 2

Minor deformation, settlement, abrasion or disjointing along seams is evident. Signs of


UVR damages.

Condition State 3

Noticeable evidence of deformation, settlement, deflection, abrasion and/or disjointing


or signs of UVR damages are evident.

Condition State 4

Version 1.4

Any flexural cracking, minor to moderate degree of deformation, settlement, abrasion,


disjointing or significant signs of UVR damages.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 65 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix J Inspection of Masonry Structural Elements

17

Appendix J Inspection of Masonry Structural


Elements

17.1

Overview
This section describes typical defects that occur in masonry structures.

17.2

Defects Caused by Structural Distress


Excessive Loading
a) Excessive loading, particularly when applied as a point loading, may cause localised
crushing of masonry or even displacement of individual masonry units;
b) An increase in lateral pressure of earth behind abutments, wing walls and retaining walls
may cause forward movement or tilting leading to distortion of the shape of an arch
structure and may cause transverse cracking of the arch barrel. Recent cracks would
indicate that movement is occurring;
c)

An increase in lateral forces or pressures in the fill material may destabilize spandrel walls
on arch structures.

Arch Shape Deformation


Flattening of the arch may be a sign of outward movement of the abutments. Movements may
be more easily identified by evidence of dips in the courses of the spandrel walls or the parapets
above the arch.
Structural Cracking
Cracks in masonry construction may only affect the appearance but can also be indicative of a
more serious underlying defect. The inspector should observe many aspects of the cracking,
including length, width, variation of width along its length, location, distribution, and, in some
cases, depth. The displacements forwards, backwards and sideways of the masonry on each
side of a crack should also be recorded. The current extent of the displacement should, if
possible, be marked and dated on the surface of the structure to assist future inspections.
The most serious form of cracking is that caused by structural inadequacy or overloading. The
four types of cracking associated with this are described as follows:

Version 1.4

Longitudinal cracks (in direction of span) Differential settlement or movement across


the width of an abutment or pier will produce longitudinal cracks in the arch barrel, as
the structure splits apart, dividing the barrel into independent sections. If accessible,
the depth of the cracks should be probed to reveal whether or not the whole thickness
of the arch barrel has been cracked.

Transverse (lateral) cracks These may be accompanied by permanent deformations of


the arch shape and are caused by partial load failure of the arch or by movement at the
supports.

Diagonal cracks These normally start near the sides of the arch at the springs and
spread up towards the centre of the barrel at the crown. They are generally due to
subsidence at the sides of the abutment or pier and are caused by the resultant twisting
of the arch.

Longitudinal cracks near the spandrel walls Longitudinal cracks near the edge of the
arch barrel may be a sign that the spandrel wall has been forced outward and, instead
of the spandrel wall sliding on the extrados (i.e. the exterior curve) of the arch, the arch
ring itself has cracked.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 66 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

17.3

Appendix J Inspection of Masonry Structural Elements

Defects arising due to the nature of the material


Arch Ring Separation
The load capacity can be significantly reduced if ring separation has occurred. Separation within
the barrel of an arch may be detected by hammer tapping to detect drumminess as opposed
to a solid ring if fully bonded.
Defective Mortar and Pointing
The load carrying capacity of a masonry arch is dependent upon the thickness of the arch ring.
If the mortar is missing, loose, or friable, then that depth of the ring affected is unable to
transmit load and contribute to the strength of the arch.
Displaced or Missing Stones or Bricks
Deterioration of mortar, localised loading or large structure movements may result in masonry
units becoming loose or displaced. The displacement of individual masonry units should be
noted; particular emphasis should be made to those at the crown of arches with shallow depths
of cover over the crown.

17.4

Defects instigated by external agents


Deterioration under these conditions may occur due to one or a combination of two or more of
the following reasons:

17.5

Erosion by water and wind and water borne particles, by frost attack and by vegetation
root growth;

Chemical/biological attack due to acids, sulphates and chemicals either water-borne or


released by water, or from air-borne pollution;

Efflorescence staining;

Moisture and thermal movement of bricks and blocks.

Element Condition Assessment Guidelines


The following guidelines are provided to assist the Structures Engineer assess the condition
state of masonry elements.
Condition State 1

The masonry elements are in good condition only a few minor cracks in the mortar
between the bricks, stones or blocks. There is no cracking due to differential settlement
of the foundation. There should be very limited loss of mortar between the blocks.

Condition State 2

The wall may have a number of fine cracks, up to 0.5mm width, in the mortar between
the brick or blocks but no cracking of the masonry. There may be minor loss of mortar.
There may be fine cracking due to differential settlement of the foundation.

Condition State 3

Medium cracking, up to 1.5mm width, of the mortar between the blocks may be
occurring or moderate mortar loss may be occurring due to water wash. There should
be only minor mortar loss beneath any masonry capping blocks. Medium cracking may
exist due to differential settlement of the foundation.

Condition State 4

Version 1.4

The mortar and blocks may have heavy cracking through them. Mortar loss may be
severe requiring pressure grouting. Loss of mortar below masonry capping blocks may
be moderate. Differential settlement of the foundations may have caused heavy
cracking.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 67 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

18

Appendix K Inspection of Tunnels

Appendix K Inspection of Tunnels


Serious deterioration in the stability of a tunnel is evidenced by bulging, distortion, cracking or
changing geometry in the tunnel.
Inspection requires a working platform and good lighting so that close examination of the
periphery can be made.
Tunnel Inspection should highlight the following indicators:

The general condition of the rock face in unlined tunnels, or of the lining in others;

The condition of joints in concrete, brickwork and stonework;

Cracks, spalling, hollows or bulges in tunnel linings;

Ineffective drainage, especially through weep holes and track drains;

Signs of water seepage remote from constructed drainage outlets;

Condition of attachments to tunnel lining;

Track heave, subsidence, or alignment change;

Condition of tunnel refuges and lighting;

Condition of Portals and movement of portal away from tunnel stem.

Cracks, bulges, and spalled areas are to be measured for length, position and displacement.
Cracks or displacement greater than 10mm should have measurement reference pins.
All extensively cracked areas or individual critical cracks should be adequately mapped and
photographed for easy reference during the next inspection.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 68 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix L Inspection of Substructure Elements

19

Appendix L Inspection of Substructure


Elements

19.1

Introduction
The substructure is the component of a bridge that includes all elements supporting the
superstructure. Its purpose is to transfer the loads from the superstructure to the foundation
soil or rock. The primary structural elements of the bridge substructure are the abutments
(including wingwalls) and the piers (or trestles).

19.2

Inspection procedures
Inspection procedures for substructure elements are the principally the same as superstructure
elements of similar material type, particularly when it involves material deterioration. However,
because stability is a paramount concern, checking for various forms of movement is required.
Vertical Movement
Vertical movement can occur in the form of uniform settlement or differential settlement. A
uniform settlement of all bridge substructure units often will have little effect on the structure,
although it will affect the vertical alignment of the railway track(s) and road onto and off the
structure.
Differential settlement can produce serious distress in a structure. Differential settlement may
occur between different substructure units, causing damage of varying magnitude depending on
span length and structure type. It may also occur under a single substructure unit causing an
opening of the expansion joint between the abutment and wingwall, or it may cause cracking or
tipping of the abutment, pier, or wall.
The most common causes of vertical movement are soil bearing failure, consolidation of soil,
scour, and deterioration of the abutment foundation material.
Inspection for vertical movement, or settlement, should include:

Investigate existing and new cracks for signs of settlement;

Examine the superstructure alignment for evidence of settlement (particularly the bridge
deck kerbs or railing);

Check for scour around abutment and pier footings or foundations;

Inspect the joint that separates the wingwall and abutment for proper alignment;

Check for any new or unusual cracking.

Lateral Movement
Earth retaining structures, such as abutments and retaining walls, are susceptible to lateral
movements, or sliding. Lateral movement occurs when the horizontal earth pressure acting on
the wall exceeds the friction forces that hold the structure in place.
The most common causes of lateral movement are slope failure, water seepage, changes in soil
characteristics, and time consolidation of the original soil.
Inspection for lateral movement, or sliding, should include:

Version 1.4

Inspect the general alignment of abutments, wingwalls, piers and exposed footings;

Check the bearings for evidence of lateral displacement;

Examine the opening in the construction joint between the wingwall and the abutment;

Investigate the joint opening between the primary elements;

Settlement of fill behind the abutment and wingwalls;

Check the expansion gap at the ends of spans;

Examine for clogged drains and/or water seepage;


Date of last revision: 10 Feb 14
This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 69 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix L Inspection of Substructure Elements

Inspect for erosion or scour of the embankment material in front of abutments or pier
footings.

Rotational Movement
Rotational movement, or tilting, of substructure units is generally the result of unsymmetrical
settlements. Abutments and walls are typically subject to this type of movement.
The most common causes of rotational movement are scour, erosion, saturation of backfill, soil
bearing failure, erosion of backfill along the sides of the abutment, and poor design.
Inspection for rotational movement, or tilting, should include:

Version 1.4

Check the vertical plumbness of the substructure;

Examine the clearance between individual spans;

Inspect for clogged drains or weep holes and/or water seepage;

Investigate for cracks, and record the crack width, length, and direction.

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 70 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix M Inspection of Underwater Structural Elements

20

Appendix M Inspection of Underwater


Structural Elements

20.1

Introduction
Where structural elements are continuously submerged, underwater inspections must be
undertaken to establish their condition. Underwater structural elements must be inspected to
the extent necessary to determine with certainty that their condition has not compromised the
structural integrity of the bridge.
In general, the term "underwater inspection" is taken to mean a hands-on inspection that may
require underwater breathing apparatus and related diving equipment.

20.2

Frequency
All structures should receive routine underwater inspections at the time of the Engineering
Inspection, but special inspections may be implemented more frequently where appropriate for
the individual bridge.
Structures Engineer can determine underwater examination frequency greater than 6 years for
structures other than timber piles and shallow footed piers.
The decision must at least be based on the following factors:

Last inspection date;

Structure type;

Water flow characteristics;

Risk of scouring;

Risk of deterioration of elements;

Local environment.

The underwater examination for rail bridges must not lapse more than 12 years.

20.3

Methods of Underwater Inspection


There are three general methods used to perform underwater inspections:

Wading inspection;

Self-contained diving (SCUBA);

Surface-supplied diving.

Wading Inspection
Wading inspection is the basic method of underwater inspection used on structures with shallow
streams. The substructure condition should be evaluated using a probing rod, sounding rod or
line, waders, and possibly a boat.
Self-contained Diving (SCUBA)
In this mode, the diver operates independently from the surface, carrying his/her own supply of
compressed breathing gas (typically air). This dive mode is best used at sites where
environmental and waterway conditions are favourable, and where the duration of the dive is
relatively short.
Extreme care should be exercised when using SCUBA equipment at bridge sites where the
waterway exhibits low visibility and/or high current, and where drift and debris may be present
at any height in the water column.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 71 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix M Inspection of Underwater Structural Elements

Surface-Supplied Diving
Surface-supplied diving uses a breathing gas supply that originates above the water surface
providing the diver with a nearly unlimited supply of breathing gas, and also provides a safety
tether line and hard-wire communications system connecting the diver and above water
personnel. Using surface-supplied equipment, work may be safely completed under adverse
conditions.
Method Selection Criteria
In determining whether a bridge can be inspected by wading or whether it requires the use of
diving equipment, water depth should not be the sole criteria. Many factors combine to
influence the proper underwater inspection method including:

20.4

Water depth;

Water visibility;

Current velocity;

Streambed conditions (softness, mud, "quick" conditions, and slippery rocks);

Debris;

Substructure configuration.

Diving Inspection Intensity Levels


Three diving inspection intensity levels have evolved as follows:

Level I: Visual, tactile inspection;

Level II: Detailed inspection with partial cleaning;

Level III: Highly detailed inspection with nondestructive testing.

Level I
Level I inspection consists of a "swim-by" overview at arms length with minimal cleaning to
remove marine growth. Although the Level I inspection is referred to as a "swim-by" inspection,
it must be detailed enough to detect obvious major damage or deterioration. A Level I
inspection is normally conducted over the total (100%) exterior surface of each underwater
element, involving a visual and tactile inspection with limited probing of the substructure and
adjacent streambed.
The results of the Level I inspection provide a general overview of the substructure condition
and verification of the as-built drawings. The Level I inspection can also indicate the need for
Level II or Level III inspections and aid in determining the extent and selecting the location of
more detailed inspections.
Level II
Level II inspection is a detailed inspection that requires that portions of the structure be cleaned
of marine growth. It is intended to detect and identify damaged and deteriorated areas that
may be hidden by surface growth.
A Level II inspection is typically performed on at least 10% of all underwater elements. The
thoroughness of cleaning should be governed by what is necessary to determine the condition of
the underlying material. Generally, the critical areas are near the low waterline, near the mud
line, and midway between the low waterline and the mud line.
On submerged piles, horizontal bands, approximately 150 to 300 mm in height, should be
cleaned at designated locations. On large elements, such as piers and caissons, areas
approximately 300mm square should be cleaned at three or more levels on each face of the
element (or at quarter points for circular elements). Deficient areas should be measured, and
the extent and severity of the damage recorded.
Level III
A Level III inspection is a highly detailed inspection of a critical structure or structural element,
or an element where extensive repair or possible replacement is contemplated. The purpose of
this type of inspection is to detect hidden or interior damage and loss in cross-sectional area.
Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 72 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix M Inspection of Underwater Structural Elements

This level of inspection includes extensive cleaning, detailed measurements, and selected
nondestructive and partially destructive testing techniques.
Level III inspections are not included in the scope of Engineering Inspections and will be
undertaken as part of a specific investigation. The scope for Level III inspections shall be agreed
with the National Bridges & Structures Engineer prior to commencing work.

20.5

Types of Inspection
Routine Inspections
A routine inspection is typically undertaken as part of an Engineering Inspection. It is an
intermediate level inspection consisting of sufficient observations and measurements:

To determine the physical and functional condition of the bridge;

To identify any change from "inventory" or previously recorded conditions; and

To ensure that the structure continues to satisfy present service requirements.

The scope of work for a routine inspection should include:

A Level I inspection of all the submerged elements;

A Level II inspection on at least 10% of submerged elements.

The dive team should also conduct a scour evaluation at the bridge site, including inspecting the
channel bottom and sides for scour and, in particular, checking for local scour in the vicinity of
submerged elements.
Damage Inspections
Certain conditions and events affecting a bridge may require more frequent, or unscheduled,
inspections to assess structural damage resulting from environmental or accident related
causes.
A Level III inspection may be necessary to determine the need for emergency load restrictions
or closure of the bridge to traffic and to assess the level of effort necessary to repair the
damage. The amount of effort expended on this type of inspection will vary significantly
depending upon the extent of the damage. If major damage has occurred, the inspector must
evaluate section loss, make measurements for misalignment of elements, and check for any loss
of foundation support.
Situations that may warrant a Level I inspections include:

Floods - bridge elements located in streams, rivers, and other waterways with known or
suspected scour potential should be inspected after every major runoff event to the
extent necessary to ensure bridge foundation integrity.

Situations that may warrant Level III inspections include:

20.6

Vessel impact - elements should be inspected underwater if there is visible damage;

Buildup of debris at piers or abutments - the buildup effectively lessens the waterway
opening and may cause scouring currents or increase the depth of scour;

Evidence of deterioration or movement;

Following significant earthquakes.

Qualifications of Diver-Inspectors
All divers shall have a commercial divers license and have all appropriate insurances to
undertake the work.
The underwater inspector must have knowledge and experience in bridge inspection. When
necessary, the Structures Engineer shall be present at site to direct the divers during the
underwater inspection in order to determine the extent of any damage.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 73 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

21

Appendix N Inspection of Miscellaneous Structures

Appendix N Inspection of Miscellaneous


Structures
Generally, the elements that comprise Miscellaneous Structures should be inspected in
accordance with the recommendations given in Appendices E to K of this Procedure.
Where blockage is occurring in a waterway, the inspector is required to make an assessment if
the material causing the blockage will be flushed away during a storm event. Only where the
inspector makes an assessment that the blockage will not be self flushing s/he should allocate a
defect category in accordance with the Standard, ETE09-01.
It should be noted the above descriptions cannot cover every situation and the inspector is
expected to exercise judgement based on local knowledge and experience to identify the
criticality of identified defects and deficiencies during an inspection.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 74 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

22

Appendix O Inspection of Redundant Structures

Appendix O Inspection of Redundant


Structures
Generally, the elements that comprise Redundant Structures should be inspected in accordance
with the recommendations given in Appendices E to K of this Procedure.
Redundant structures could be located in close proximity to operational tracks or anywhere
within the railway corridor.
All redundant structures must be inspected to ensure they do not incur any safety risk to the
public at large and/or normal train operations.
Some typical things to look for during inspections are as follows:

Structural integrity ensuring that it will not fail or collapse under its own dead load,
due to wind load, vibration, etc.

Dangerous sites are properly fenced off.

All ladders attached to structures are at least 3m above ground level to prevent children
from climbing up the structures.

All water tanks and their openings are properly secured to prevent entry of children into
tanks.

All water tanks are empty.

Track side access roads at bridge abutments or at other dangerous locations are
adequately protected by road traffic barriers, earth mounts or other suitable barricades
to prevent vehicles being driven off the high embankments.

Appropriate signage is displayed at all concerned structures, track side access roads,
etc.:

Access for Authorised Persons Only

Danger Falling Objects

Danger No Pedestrian Access

Danger Do Not Climb

Road Closed

Etc, etc.

It should be noted the above descriptions cannot cover every situation and the inspector is
expected to exercise judgement based on local knowledge and experience to identify the
criticality of identified defects and deficiencies during an inspection.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 75 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

23

Appendix P Engineering Inspection Process Flow Chart

Appendix P Engineering Inspection Process


Flow Chart

Appoint Engineer

ENGINEERING INSPECTION

Structures Representative

Structures Engineer

Obtain Engineering Inspection


schedules

Inspector Accreditation

National Bridges &


Structures Engineer

Review Scope
(as requested)

Prepare Brief for Engineering


Inspection
Prepare proposal for
Inspections and submit.

Review Proposal and make


recommendation
(as requested)

Review Proposal and ensure


Inspector Acceditation

Engage Engineer

Inspection Preparation

Organise existing information


including:
Inventory
Previous inspections;
Maintenance history;
Outstanding defects;
Drawings;
Load rating.
Access to BMS

Pre-inspection investigation to
identify key issues for
inspection

Undertake As-New Load


Rating and Fatigue
Assessment
(or review previous ratings)

Arrange inspection schedules

Arrange Track Protrction /


Access if required

Arrange Timber Boring /


Underwater Examination
if required

Prepare Safety Plan

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 76 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Structures Representative

Appendix P Engineering Inspection Process Flow Chart

Structures Engineer

National Bridges &


Structures Engineer

Undertake onsite safety briefing

Receive Inventory Updates


(if any)

Check structure inventory

Assess condition of elements

Inspection

Assess and re-evaluate:


Outstanding deficiencies
Previous observations

Record defects

Receive Inspection Defects

Complete Inspection Defects and


submit

Assess as-is load rating and fatigue


assessment of structure (if required)

Receive Draft Engineering Report


from Engineer

Version 1.4

Complete and submit draft


Engineering Inspection Report,

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 77 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Structures Representative

Appendix P Engineering Inspection Process Flow Chart

Structures Engineer

National Bridges &


Structures Engineer

Review Defect Categories


and Repair Priorities

Accept recommendation

Discuss recommendations

Inspection Review / Approval

Resolved

Discuss recommendations
and advise resolution

Allocate accepted remedial


actions actions

Present Draft Report


Review draft Engineering
Report with Structures
Representative, Structures
Engineer and Asset
Manager
as required

Arrange review of draft


Engineering Report with
Structures Manager,
Structures Engineer and Asset
Manager

Finalise Report in BMS and submit


for approval of overall inspection

Update BMS and Corporate


Asset Management System,
(as required)

Version 1.4

Update BMS for any


specific instruction

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 78 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

24

Appendix Q Visual Inspection Process Flow Chart

Appendix Q Visual Inspection Process Flow


Chart
VISUAL INSPECTION

Inspection preparation

Structures
Representative
Assign Inspections to
internal
Structures Inspector

For appointment of
external structures
inspector refer to
Engineering Inspection
process chart in
Appendix M

Structures Inspector

National Bridges &


Structures Engineer

For each structure obtain


the following information:
Previous defect reports
Inventory

Arrange for:
Access
Track protection as
required

For external structures


inspector refer to
Engineering Inspection
process chart in
Appendix M

Check bridge inventory

Inspection

Assess and re-evaluate:


Outstanding defects
(Category A-D)
Observations (Category
M)

Receive Inspection
Report from Inspector

Version 1.4

Identify new defects:


Category defects
Defect type
Repair priority
Photographs

Complete Inspection Data


Reports

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 79 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Inspection Review / Approval

Structures Representative

Appendix Q Visual Inspection Process Flow Chart

Structures Inspector

National Bridges &


Structures Engineer

Review defects and


modify
recommendations
(as required)

Any significant
changes

Yes

Review changes and


agree required actions

No

Allocate remedial and


MPM actions

Approve overall
inspection in BMS

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 80 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix R Determination of Condition Rating

25

Appendix R Determination of Condition Rating

25.1

Introduction
During an Engineering Inspection, the Structures Engineer is required to visually inspect each
structural element using a standard condition rating system. The analytical process for effective
bridge management relies upon this element condition information.
With a systematic inspection regime in place, monitoring condition over time is a sensitive
means of tracking the performance of an element and ultimately of the bridge. A worsening
change in condition is a clear indicator of element deterioration. In addition, change in condition
may be used to test and demonstrate the effectiveness of adopted maintenance repair
strategies. Structure element condition is a most useful input for identifying maintenance repair
needs.
The Structures Engineer shall make an assessment of the condition of each standard element
and the extent over which that condition applies in accordance with ETE-09-01.

25.2

Measurement
The extent of each condition state affecting an element shall be measured as a percentage of
the whole element. That is, the percentages in each condition state (1, 2, 3 & 4) must add up to
100% of the whole element observed at the site.
Each element to be assessed is quantified in terms of measurement as follows:
i.

Number of units making up the element (each);

ii.

Length of the element (lin m); or

iii. Area of the element (m)


The condition rating and its extent, for each element shall be recorded as a percentage of each
condition state in the appropriate column in the Structures Inspection Database. The quantities
of each element and their condition are not required unless specified elsewhere. The accuracy of
the percentages determined for each condition state shall be within +10%.
In assessing condition rating, the Structures Engineer should first determine the worst condition
affecting the element (i.e. Condition 4) and its extent, and progress through to the best
condition (i.e. Condition 1).
a) When the unit of measurement is based on the area of the element in (m), the percentage
in each condition state is the area affected by the condition divided by the total area of the
element multiplied by 100; i.e.
Area in Condition State

X 100%

Total Area of Element


When rating areas of deteriorated concrete, certain assumptions will be required to
estimate the affected areas. It is common that the damaged area is much larger than the
cracks or spalls visible.
The damaged area shall be taken as an area a quarter of a metre all round the crack or
spall or when interconnected with other cracked or spalled areas then the damaged area
will be a quarter of a metre around the total area of deterioration. This will also apply to
the undersides of the deck where the deck reinforcement is showing at the concrete surface
but no cracking or spalling exists, i.e.
For a small spall the minimum area of deterioration for the condition rating shall be
m.
For a crack across the deck the minimum area will be metre by the width of the deck.
For a corner bar crack in a pier wall the deteriorated area will be a quarter of a metre
(or wall thickness if less) by a quarter of a metre on the wall face by the length of
Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 81 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix R Determination of Condition Rating

crack plus a quarter of a metre if the crack commences at the footing or by metre if
the crack is higher up the wall.
Steel, precast concrete, timber and asphalt areas rated on a square metre percentage
basis shall simply be based on the area of deterioration visible.
b) Where the unit of measurement is based on length (lin m) the percentage in each condition
is:-

Length in Condition State


Total length of Element

x 100%

When rating concrete elements that are measured in lineal metres an estimation of the
length of the cracked or spalled concrete needs to be made. A similar basis to that adopted
for determining areas of concrete affected is used.
If one severe crack occurs through a kerb say over the pier and is assessed as Condition
3 the length in that condition is m (0.25 m each side of the crack). If the total length of
kerb is 100m the overall assessment would be: Condition 4 -

0%

Condition 3 -

1%

Condition 2 -

0%

Condition 1 -

99%

If precast concrete panel is badly cracked or broken, the whole precast panel will require
replacement so the length of the panel should be considered as the damaged length in poor
condition state.
Steel elements with measurements in lineal metres, i.e. box girders and truss top and
bottom chords, that have cracks in welds, or parts of the element which could affect on the
strength of the element, should have the whole element rated in Condition 4.
c)

When rating elements on an each basis, the measurement of a particular condition rating
shall be determined as the number of units affected by that condition as a percentage of
the total number of units. The most severe condition observed on the unit determines its
condition rating.
If total number of beams is 4 and one beam has small areas of Condition 4 with the
remainder in Condition 1, and the other beams are all in perfect order and assessed as
Condition 1, the overall assessment would be:-

Version 1.4

Condition 4 -

25% (i.e. 1 beam)

Condition 3 -

0%

Condition 2 -

0%

Condition 1 -

75% (i.e. 3 beams).

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 82 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix S Load Rating of Bridges and Culverts

26

Appendix S Load Rating of Bridges and


Culverts

26.1

Introduction
In addition to the requirements provided in ARTC Code of Practice Section 9 and ETE-09-01 the
following is provided.

26.2

Load Rating Results


The definition of Rating Factor is provided in AS 5100.7 as:
RF =

Available bridge capacity for live load effects


Live load effects from the nominated rating vehicle

where the nominated rating vehicle is 300LA railway design load.


The structural capacity of a railway bridge or culvert shall be expressed in terms of the
equivalent LA loading (i.e. RF x 300LA).
The live load rating of a road bridge is expressed in terms of standard R and T vehicles.
Where the structure has been rated for specific train consist the results shall be expressed in
terms of:

26.3

The Rating Factor (RF) for that vehicle under full DLA;

The minimum equivalent LA loading ;

Where the value of RF is less than unity (1.0), for each structural element the following
should be reported:

The reduced speed necessary to raise the value of RF to unity (1.0) i.e. reducing
DLA with respect to lower speed;

Calculated load factor (L) for live load with full DLA.

Train Load Effects


The load effects from the following train consists must be considered as a minimum unless
otherwise specified in Scope of Work:

For all lines 300LA design loading with 1.6 live load factor inactive traffic;

RAS 270 locomotives hauling RAS 270 wagons with 1.4 live load factor inactive traffic;

RAS 210 locomotives hauling RAS 210 100T general freight or RAS 210 92T steel
wagons with 1.4 live load factor inactive traffic;

For heavy coal lines Heavy Haulage Coal trains active traffic;

For all main lines Main Line Freight Trains with 25t and 23t axles active traffic.

All the above train consists with their load effects on all elements under consideration must be
uploaded in the BMS.

26.4

Speed Restriction
Railway bridges in Australia have historically been designed and load rated in accordance with
American and British practices and to Australia New Zealand Railway Corporation (ANZRC)
bridge design manual.
In 2004, Australian Standard 5100: Bridge Design was introduced, covering both road and rail
bridges.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 83 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix S Load Rating of Bridges and Culverts

AS 5100 considerably increased the required allowance for dynamic effects (Dynamic Load
Allowance) which must be applied to short-length primary load carrying elements in rail bridges,
in comparison to past railway practices. This generally affects span lengths of less than 8
metres, and particularly span lengths of less than 4 metres.
AS ISO 13822 - 2005: Basis for Design of Structures Assessment of Existing Structures (which
applies to structures generally, not just bridges) aims to provide guidelines for extending the life
of structures, while limiting construction intervention. The guidelines include procedures for
assessment based on past performance.
Adoption of AS13822 -2005
ARTC adopted application of AS 13822 refer Engineering Bulletin ETB09-01 dated September
2008. The application of AS 13822 can allow the existing train operating conditions to prevail
across steel bridges without reducing the operational track speed or undertaking any upgrading
work to conform to AS 5100 requirements.
Application of AS 13822 -2005
Load carrying capacity of structures can be derived using AS 13822 provided the original
physical and structural integrity of element under consideration have not been significantly
altered and similar traffic conditions prevail.
Traffic Conditions for main lines

Train configurations with load effects not exceeding more than the load effects of
current traffic ;

Performance based on at least past 20 years of operation for current traffic.

Element Conditions

Original physical characteristics and structural integrity of element is not altered by


either strengthening or replacing it;

Element has not suffered more than 10% loss in capacity when load rated using
dynamic load allowance factor (impact) from ANZRC Manual 1974. The impact load for
open deck steel bridges is determined by taking a percentage of live load;
I =

31

+ 40 - 3L3

150

Where Y = girder spacing and L = element length up to


25m
For ballasted deck steel bridges use 90% of impact for
open deck.

Application of AS 5100
Where the above traffic and element conditions for the application of AS 13822 cannot be
attained then the load carrying capacity of that element shall be carried out using dynamic load
allowance from AS 5100.
Management System
All the above traffic and element conditions shall be locked in BMS against each affected bridge
where AS 13822 has been utilised to assess its load carrying capacity. The BMS will trigger
requirements of AS 5100 whenever any one of the conditions reaches its prescribed limit.

26.5

Fatigue Rating
The theoretical remaining fatigue life of only steel elements of railway bridges are required
under engineering inspection.

26.6

Wind & Sway Bracing


The wind bracing (secondary elements) of the old steel bridges are fabricated mostly from flat
bars and as such they do not have adequate theoretical capacity for the current railway traffic in
accordance with the AS 5100. The old sway bracing angles and riveted connections also do not
have adequate theoretical capacity.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 84 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix S Load Rating of Bridges and Culverts

However, experience to date has shown that in reality there is no evidence of distress to
suggest that they are being overloaded. Where the existing braces are rated between 0.8 and
0.99 for the current traffic then the Structures Engineer should give firm recommendations on
inspection frequency, intervention levels and responses necessary to maintain safety. Where
rating is below 0.8 then consideration should be given for monthly inspections and replacement
within a reasonable timeframe.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 85 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

26.7

Appendix S Load Rating of Bridges and Culverts

Train Consists
Some typical train consists are shown below:

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 86 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Version 1.4

Appendix S Load Rating of Bridges and Culverts

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 87 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

26.8

Appendix S Load Rating of Bridges and Culverts

Road Vehicles
The R vehicle is a rigid truck with the same configuration as the prime mover portion (first 3
axles) of the T vehicle.

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 88 of 89

Engineering Procedure
ETE-09-02 Structures Inspection Procedure

Appendix S Load Rating of Bridges and Culverts

Road Bridge Load Limit Sign

Version 1.4

Date of last revision: 10 Feb 14


This document is uncontrolled when printed. See ARTC Intranet for latest version.

Page 89 of 89

You might also like