GODREJ PROPERTIES LIMITED SOP No.

: GPL-WP-LIFTPIT-004
STANDARD OPERATING PROCEDURE Rev No.: 0
LIFT PIT WATERPROOFING Date: 31-03-2020

Water Proofing Manual


Basement
 Element : Lift Pit
 Recommended System for all regions: 1.2 mm thick preapplied HDPE membrane at
positive side and 2 component cementitious coating with screed protection at
negative side

Sketch of Recommended System:-

Method Statement:
 The purpose of this method statement is to provide a well waterproofed lift pit, such
that there is negligible possibility of water leakage.
 The method statement describes, creation of an exterior envelope completely
covering the lift pit from outer side and providing additional protection from the
negative side.
 In order to achieve the exterior envelope, it is necessary to cast the lift pit during the
casting of raft slab and maintain complete enclosure with concrete.
 The PCC for raft is casted first. As the HDPE membrane cannot be bent to 90 degree
angle, it is also important to provide rounded 45 degree chamfer at the edge of the
PCC for raft please refer the document for raft waterproofing.

1|Page
GODREJ PROPERTIES LIMITED SOP No.: GPL-WP-LIFTPIT-004
STANDARD OPERATING PROCEDURE Rev No.: 0
LIFT PIT WATERPROOFING Date: 31-03-2020

 After this, cast plum concrete for the lift pit wall support. A 45 degree coving shall be
provided at the corner of the lift pit base PCC and the plum concrete from inside. This
will ensure that the HDPE membrane can be taken to the vertical side without a sharp
bent.
 Then the PCC is laid at the base of the lift pit. After the concrete is properly set, HDPE
membrane is loosely laid at base of lift pit with the non-adhesive side towards the PCC
and continued on vertical portions of lift pit. Mechanically fasten the membrane
vertically using flat headed fixings appropriate to the substrate.
 Use fixings at typically 600 mm centres or as per agreed site condition/ requirement
to secure the membrane flat against the substrate. Fixing can be made through selvage
using flat headed fastens, this allows firmly rolled overlaps which is covered by
subsequent strip of HDPE membrane.
 The membrane should be carried to a minimum of 300 mm and up to 500 mm above
the level of PCC for raft and secured on the shuttering and protected with temporary
aluminium flashing. Apply the HDPE membrane with plastic surface against the
levelled substrate (plum concrete is preferred or 20 mm thick plywood shuttering).
 Then the reinforcements are placed at the base of the lift pit and formwork is provided
for casting of lift pit base. Once this concrete is cured, hydrophilic water stop is placed
at the centre of the section between the base and vertical walls. Then the
reinforcement and formwork for vertical sections is installed and the concrete is
poured up to the base of the chamfered edge of PCC for raft.
 Once the concrete is set, another hydrophilic water stop is laid all across the lift pit in
similar way that of the bottom hydrophilic water stop.
 Before the raft concrete is laid the HDPE membrane is laid over the PCC for raft slab
and joined with the overhang from the vertical section of lift pit as shown in the
drawing. An overlap of 100 mm is made and covered with one sided HDPE self adhesive
tape of the same membrane.
 Then the process of casting raft slab is commenced.
 Once the raft is casted and sufficiently cured, an upstand of 100 to 150 mm is created
using concrete exactly around the edge of the lift pit.
 Once the raft slab achieves minimum compressive strength of 20 MPa, check for the
leakages within the lift pit before starting internal (negative side) waterproofing.
 Either dampen the surface with water if primer is not recommended or apply primer
as per vender’s recommendation.
 Fillet is made at the junction of horizontal and vertical surface to eliminate the sharp
corners on internal side.

2|Page
GODREJ PROPERTIES LIMITED SOP No.: GPL-WP-LIFTPIT-004
STANDARD OPERATING PROCEDURE Rev No.: 0
LIFT PIT WATERPROOFING Date: 31-03-2020

 2 component elastomeric cementitious coating is applied in two coats to achieve


minimum thickness of 2 mm, with the help of brush or roller. The coating is carried
over the concrete upstand and 300 mm beyond on the raft concrete.
 Water proofing coating is cured for at least 72hours.
 Protection screed / cement sand mortar screed of minimum 50 mm thick is applied
over 2 component cementitious coating for protection on horizontal side and 20 to 30
mm plaster is applied on vertical side. The protection plaster is also carried over the
concrete upstand and covering the elastomeric cementitious coating over the raft
surface.
 Protection screed and plaster is cured.
Check List
1. Material Delivery
Description Yes No
The thickness of HDPE membrane is 1.2 mm?
Is the elastomeric cementitious coating received in its original packing and proper
proportions?
Is the material expiry date at least minimum 6 months from the receipt date?
Material test certificate received

2. Installation
Description Yes No
Is the PCC surface for the raft and at base of lift pit without any cracks, holes, loose
materials and standing or running water?
Is the 45 degree chamfered edge provided on both the horizontal sides of the PCC for raft?
Has the plywood shuttering or plump concrete laid as per the requirement?
Is the surface free from damage and sound to receive membrane? (In case of plywood)
Is the surface clean and free from any loose material? (In case of plum concrete)
Is the surface free from protrusions and smooth to receive membrane? (In case of plum
concrete)
Are there any leakages or running water over the plum concrete surface? (In case of plum
concrete)
Is the 45 degree chamfered edge provided within shuttering or plum concrete at the base of
lift pit?
Is the membrane laid with non-adhesive side against levelled substrate?
Is there overlap of 70-80 mm between two sheets of HDPE membrane?
Check whether an overlap of 100mm is provided between vertical and horizontal portions
of HDPE membrane?
Are the overlaps proper without any adhesion issues?
Are the ends properly bonded with single side HDPE adhesive tape?

3|Page
GODREJ PROPERTIES LIMITED SOP No.: GPL-WP-LIFTPIT-004
STANDARD OPERATING PROCEDURE Rev No.: 0
LIFT PIT WATERPROOFING Date: 31-03-2020

Has the raft and vertical area concreting been completed and ready for receiving negative
side waterproofing?
Has the concrete upstand been created as per the method statement?
Has the surface been dampened or primer applied?
Are fillets made at junctions of horizontal and vertical surfaces at base of lift pit?
Is 2 component elastomeric cementitious coating applied in two coats with help of brush or
roller up to the raft surface over the upstand?
Is the average thickness 2 mm for the 2 component elastomeric cementitious coating?
Has the protection screed been laid on horizontal surface and protective plaster for vertical
surfaces at thickness mentioned in the method statement?

3. Post Membrane Installation


Description Yes No
Is there any puncture to the HDPE membrane?
Is there any damage at the joining of the two adjacent HDPE membrane?
Was there any repair of HDPE membrane done by the waterproofing contractor?
If yes has the damage been completely repaired?
Have the repair patches been plotted on as built drawing?
Has the waterproofing contractor inspected the HDPE membrane and approved the
concrete pour for raft, bottom surface of the lift pit and vertical portions?
Is the raft concrete without any damage?
Is there any separation or lifting of concrete at the edges?
Has the waterproofing contractor completed the application of 2 component elastomeric
cementitious coating along with protection screed?

BOQ Description:
Description Unit
Supplying and installing waterproofing treatment by using 1.2 mm pre applied HDPE membrane, M2
double sided HDPE adhesive tapes, single sided HDPE tapes, 2 component elastomeric
cementitious coating, primer if specified and protected with screed as shown in drawing. All
installation shall be in strict accordance with the manufacturer’s instructions and shall provide an
intimate bond to resist water migration.
The item rate shall include base preparation which includes wire-brushing the concrete surface &
cleaning with oil free compressed air, treating all construction joints, cracks, honeycombs on
concrete surface as per manufactures specification and approved methodology or application on
plywood shuttering. Item rate also include cost of all materials, miscellaneous consumables,
labours, transportation of material to all required locations by recommended means, curing, tools,
plant and machinery, hire and fuel charges and all other incidental charges etc., all required as per
specifications, drawings and as directed by site engineer. The item rates shall hold good for work
at all levels, lead, lifts, heights, depths, basements, trenches, pits, tunnels, water tanks etc and
providing guarantee of water proofing work on stamp paper in approved format for a period of 10

4|Page
GODREJ PROPERTIES LIMITED SOP No.: GPL-WP-LIFTPIT-004
STANDARD OPERATING PROCEDURE Rev No.: 0
LIFT PIT WATERPROOFING Date: 31-03-2020

years from date of virtual completion of entire project and not only of individual item. Item rate
shall also include testing charges required for quality check as per approved quality plan.
Rate shall be quoted considering any of the above make for all waterproofing items for the project.
Mode of measurement: Measurement as per drawing dimensions shall be paid, overlap should be
considered in Rate.