Professional Documents
Culture Documents
4-Practise Standard For Project Estimation PDF
4-Practise Standard For Project Estimation PDF
PRACTICE STANDARD
FOR PROJECT ESTIMATING
TABLE OF CONTENTS
PREFACE
xi
CHAPTER 1 - INTRODUCTION
1.1
1.2
1.3
1.4
1.5
Introduction..
Scope of Project Estimating
Estimating Roles
Estimating Life Cycle Stages
Evolving Estimates
Use of Metrics
Causes of Estimating Variances
Characteristics of a Good Estimate
Industry Differences
Summary
Introduction
Inputs
3.2.1 Project Documents
3.2.2 Experts
3.2.3 Estimating Techniques
3.2.4 Constraints and Assumptions
3.2.5 Additional Influences
3.2.6 Historical Project Information
1
1
3
4
5
5
7
7
7
7
8
8
8
9
9
9
10
10
.12
13
13
14
15
15
17
17
17
17
18
19
19
19
19
TABLE OF CONTENTS
3.3
Activities
3.3.1 Create Project Estimating Approach
3.4 Outputs
3.4.1 Project Estimating Approach
3.4.2 Information and Resources to Create the Estimate
3.5 Considerations
3.5.1 Allocate Appropriate Time to Plan
3.5.2 Proper Stakeholder Expectations Management
3.5.3 False Perception of Level of Accuracy
3.6 Summary
4.3
4.4
4.5
4.6
Introduction
Inputs
4.2.1 Project Estimating Approach
4.2.2 Estimating Information
4.2.3 Estimators
4.2.4 Enterprise Environmental Factors and Organizational
Process Assets Influences
Activities
4.3.1 Use of Analogous Techniques
4.3.2 Use of Parametric Techniques
4.3.3 Use of Bottom-Up Techniques
Outputs
4.4.1 Completed Estimates
4.4.2 Basis of Estimates
Considerations
4.5.1 Optimism in Estimates
4.5.2 Progressive Elaboration of Estimates
4.5.3 Cost-Schedule Interrelationship
4.5.4 Normalization of Historical Data
4.5.5 Accounting for Time
4.5.6 Expert Judgment
Summary
Introduction
Inputs
20
20
22
.....22
22
22
22
22
23
23
25
25
25
25
26
26
27
27
28
....30
31
32
32
32
32
32
33
33
33
33
34
34
35
35
36
TABLE OF CONTENTS
5.3
5.4
5.5
5.6
Introduction
Inputs
6.2.1 Project Information
6.2.2 Project Estimating Approach
6.2.3 Historical Project Information
6.2.4 Baseline Estimates
6.2.5 Updated Estimates/Forecasts
6.2.6 Change Log
6.2.7 Actual Versus Estimate Data
6.2.8 Stakeholder Feedback
6.2.9 Organizational Process Assets
6.3 Activities
6.3.1 Gather Estimating Information
6.3.2 Assess Estimating Process
6.3.3 Determine Root Causes and Lessons Learned
36
37
37
38
38
39
39
40
42
43
43
43
44
44
44
44
44
44
44
45
45
47
47
47
48
48
49
49
49
49
49
50
50
50
50
50
50
50
50
52
52
52
52
52
52
52
REFERENCES
53
55
A.1 Introduction
APPENDIX B - EVOLUTION OF PMI'S PRACTICE STANDARD
FOR PROJECT ESTIMATING
B.1 Pre-Project
B.2 Development Work
B.3 Exposure and Consensus
APPENDIX C - CONTRIBUTORS AND REVIEWERS OF THE
PRACTICE STANDARD FOR PROJECT ESTIMATING
C.1 Practice Standard for Project Estimating
Core Committee (Development Phase)
C.2 Significant Contributors
C.3 Practice Standard for Project Estimating Reviewers
C.4 Practice Standard for Project Estimating SME Reviewers
C.5 Practice Standard for Project Estimating
Core Committee (Research Phase)
C.6 Practice Standard for Project Estimating
Committee Members (Research Phase)
C.7 Final Exposure Draft Reviewers and Contributors
C.8 PMI Standards Member Advisory Group (MAG)
C.9 Staff Contributors
...:
APPENDIX D - ESTIMATING MODELS
GLOSSARY
INDEX
55
57
57
58
59
61
61
61
62
62
62
.63
64
65
65
67
...69
75