Rate Analysis

Item Description : Excavation to foundations, maximum depth 2m to 5m. Rate to include for setting
out, leveling, excavating, dewatering, trimming, preparation of excavated surface
and earthwork supports where necessary.

Rate No : R.A. 03

Unit Rate Amount


Description Unit Qty
/(Rs.) /(Rs.)
3
Consider 30 m of excavation

Labour

Skilled Labor Day 2.00 1,500.00 3,000.00

Unskilled Labor Day 4.00 1,200.00 4,800.00

Machinery
Survey equipments Item 1.00 2,000.00 2,000.00

Backhoe excavator Hrs. 1.00 4,500.00 4,500.00

Crawler tractor disposing Hrs. 2.00 2,500.00 5,000.00


excavated material

Miscellaneous

Allow for dewatering Item 1.00 10,000.00 10,000.00

Allow for earth support Item 1.00 6,000.00 6,000.00

Total Cost of Excavation to foundations, maximum depth 2m to 5m for 30 cum 32,300.00

Add 17% on the total cost for overhead and profit 5,491.00
3 37,791.00
The total cost for 30.0 m with overhead and profit
3 1,259.70
The total cost for 1.0 m with overhead and profit

Say, Unit Rate 1,260.00