Professional Documents
Culture Documents
(2) 0 th Year
Material
Sl No Item of work Mandays Labour cost
cost in Rs. Total cost in
@Rs200/- Rs.
i) Survey,Demarcation, site preperation,
alignment & stacking
4.50 900.00 25.00 925.00
ii) Digging of pits (45cmx45cm x45cm) 21.00 4200.00 0 4200
iii) CDM(125 cft @ 0.5 cft per pit 2000.00 2000.00
iv) Contigency 125.00 125
Total 25.50 5100.00 2150.00 7250.00
5 1000.00 0 1000.00
v) Provision of soil & water conservation
measures by providing circular trench in flat
land & half moon trench in slope area
Providing Avenue plantation with cost of 8 month old seeding , transportation to site of
planting and making survey ,demarkation, preparation of alignment,digging of pits
,planting of seeding including application of CR & basal dose 50 gm and pesticides
ii) Taking avenue plantation to be made ie 10 Times of above = 406 x10 4060 Nos
@ Rs 835.14/each plant Rs 3,390,668.40
Forest working for Cutting ,Processing and transporting of trees to
iii) OFDC Depot. Rs 465,625.00
Total Rs 3,856,293.40
Say Rs 3,856,300.00
Assistant Engineer,
N.H.Section, Aska
WORKS DEPARTMENT
NAME OF THE WORK : WIDENING TO DOUBLE LANE WITH PAVED SHOULDER FROM KM
294/280 TO KM 319/280 (NABARANGPUR TO BORIGUMMA) OF NH-26 FOR THE YEAR
2019-20 IN THE STATE OF ODISHA.
GENERAL ABSTRACT
A) ROAD PROPER 25.000 km Rs 36,64,41,094.09
Road Safety Rs 96,96,913.67
Bus Bay & Bus Shelter 1 No Rs 1816283.26
Truck lay Bye 1 No Rs 48,09,642.11
Rs 38,27,63,933.13
B) C.D WORKS.
Rs. 5,97,44,973.90
C) PROTECTION WORK & DRAIN.
i RCC Drain & Drain cum footpath 17340.00 m Rs 19,03,76,324.80
ii Toe Wall Height 0.6M Above GL 1150.00 m Rs 46,10,757.97
iii Toe Wall Height 1.0M Above GL 330.00 m Rs 16,48,336.87
iv Retaining wall 2.0M height above GL 910.00 m Rs 1,81,04,334.00
v Crash Barrier 2310.00 m Rs 1,37,62,980.00
vi Water Harvesting structure 50.00 Nos Rs 39,82,900.00
Rs 23,24,85,633.64
D) TOTAL(A+B+C) Rs. 67,49,94,541.00
E) Add Maintenance cost 2.5% Above (D) 1,68,74,864.00
SAY Rs 91,90,18,000.00
Design Traffic
N=365x[(1+r)n-1]xAXDxF/r 18292634.187901
Say, 18 MSA
However, as per clause 3.5.1 of IRC:SP:73-2018 (Manual) Flexible pavement design period
of 15 years,subject to the condition that design traffic shall not be less than 20 msa. Hence
20 msa has been considered for the design.
Crust Detail
Chainage. Length in C.B.R MSA Existing Crust Required Crust Proposed Crust As per IITPave
Meter.
TY Items. Items. Wideni Items. On widening On On
PE ng portion. Reconstruction overlaying
portion portion. portion
.
Assistant Engineer
I On flexible 16980.00 6.0 20 GSB 150 GSB 200 GSB graded 200 Phulbani
200 R&B Sub-Division, Sou
widening/reconstruction/overlay Gr-IV
portion
WMM 220
DBM 90
BC 35 BC 40
495 - - - 40
ROAD PROPER
Proposed Crust Detail in Flexible In widening In overlaying In
Pavement Portion Portion reconstruction
portion
b. Dismantling Rubble stone masonry in cement mortar including T&P and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres.
a. Above 600 mm to 900 mm dia 6 12.50 (Avg) 75.00 Mtr. 262.50 19,687.50
5 Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment,
scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in
table 300-2 for embackment section (As per clause 305.3.4 of MORTH 5th revision.)
7 Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading,
grading to required slope and compacting to meet requirement of table 300-2. (As per clause 305 of MORTH 5th revision.)
9 Furnishing and laying of the live sods of perrinial turf grass on embankment slope within 5km average lead by mechanical means
and 1.5m initial lift. (As per clause 307 of MORTH 5th revision.)
40461.28 cum
Add 2% for extra widening in curve 809.23 cum
portion & Superelevation
Add for major junction (Majhiguda) 1 400.00 15.00 0.200 1200.00 cum
1st layer
In widening portion 2 13476.00 2.750 0.125 9264.75 cum
2nd layer
In widening portion 2 13476.00 2.625 0.125 8843.63 cum
28704.47 cum
Add 2% for extra widening in curve portion & Superelevation 574.09 cum
Add for major junction (Majhiguda) 1 400.00 10.00 0.250 1000.00 cum
For arterial road 36 30.00 6.25 0.15 1012.50 Cum
31291.06 cum 1,774.80 55,535,373.29
SL Description
No Length Width Depth Volume Unit Rate Amount
No
12 Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and -
spraying primer at the rate of 0.60 kg/sqm using mechanical means.(As per clause 502 of MORTH 5th revision.)
202812.00 Sqm -
Add 2% for extra widening in curve portion & Superelevation 4056.24 Sqm -
Add for major junction (Majhiguda) 1 400.00 10.00 4000.00 Sqm
For arterial road 36 30.00 6.25 6750.00 Sqm
217618.24 Sqm 20.80 4,526,459.39
13 Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the -
prepared bituminous/granular surface cleaned with mechanical broom.(As per clause 503 of MORTH 5th revision.)
15022.20 cum
15 Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the -
prepared bituminous/granular surface cleaned with mechanical broom.(As per clause 503 of MORTH 5th revision.)
In widening portion 1 13476.00 12.000 161712.00 Sqm
In re-construction portion 1 3425.00 12.000 41100.00 Sqm
In Strengthening portion (7.0m) 1 5596.00 7.000 39172.00 Sqm
In Strengthening portion (10.0m) 1 2400.00 10.000 24000.00 Sqm
265984.00 Sqm -
Add 2% for extra widening in curve portion & Superelevation 5319.68 Sqm -
Add for major junction (Majhiguda) 1 400.00 10.000 4000.00 Sqm
275303.68 Sqm 7.40 2,037,247.23
16 Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonne per hour -
using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 percent of mix and filler transporting the hot
mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled vibratory and tandem rollers to achieve the desired compaction as per MORT&H specifications Clause 509 complete in all
respects.
In Entire DL+PS portion 1 16901.00 12.00 0.040 8112.48 cum
10639.36 Cum -
Add 2% for extra widening in curve 212.79 Cum -
portion & Superelevation
Add for major junction (Majhiguda) 1 400.00 10.00 0.040 160.00 cum
For arterial road 36 30.00 6.25 0.040 270.00 cum
Fro rumble strips 580.00 12.00 0.25 0.008 13.05 cum
11295.20 Cum 7,244.50 81,828,076.40
SL Description
No Length Width Depth Volume Unit Rate Amount
No
17 Providing and laying factory made
chafered edge cement concrete paver
block of required strength, thickness&
size/ shape ,made by table vibratory
method to attain superior ,smooth finish
using PU or equivalent moulds , laid in
required drey colour & pattern over
50mm thick compacted bed of coarse
sand ,compacting and proper
embeding / laying of inter locking paver
block into the sand bedding layer
through vibratory compaction by using
plate vibrator
366,441,094.09
Road Safety
-
Middle. 1 25000.00 0.33 0.100 825.00 -
Sides. 2 25000.00 1.00 0.150 7500.00 -
8325.00
Sqm 511.40 4,257,405.00
-
3 Providing and fixing of retro-reflectorised, cautionary, mandatory and informatory sign as per IRC-67 made of high intensity grade sheeting vide clause 801.3
,fixed over aluminium sheeting, 1.5mm thick supported on mld steel angle post 75m x 75mm x 6mm firmly fixed to the ground by means of properly designed
foundation with M-15 grade cement concrete 45cm x 45cm x 60cm, 60cm below ground level as per approved drawing.
TOTAL 9,696,913.67
Assistant Engineer Junior Engineer Assistant Executive Engineer Assistant Engineer
.Soro (R&B) Section
Khajuripada R&B Section .Soro (R&B) Sub-Division North R&B Sub-Division,Phulbani
Assistant Engineer Dy Executive Engineer Executive Engineer
.NH. Section Aska .NH. Sub Division Berhampur NH.Division Berhampur
294280 0 7.479 0
183894.84 57869.98
So,
2
1
S.NO.
2
BRIDGE NO
3
LOCATION (Km.)
116/2
113/4
Name of Project :
NAME OF RIVER
4
BRIDGE
KHANDI
LOHANA
DAM BRIDGE
YEAR OF
5
98
COSTRUCTION
5.07.19
NUMBER OF
6
2
6
SPANS
SPAN
ARRANGEMENT
(EXPANSION
7
12
JOINT TO
42.3
ENPANSION
JOINT)(m)
8
CLEAR SPANS
41
10
LENGTH OF
BRIDGE FACE TO
9
FACE OF
84.4
71.6
ABUTMENTS (m)
HIGH LEVEL OR
10
SUBMISSIBLE
WIDTH BETWEEN
7.5
7.5
KERBS(m)
TOTAL OUTER
12
WIDTH
OF BRIDGE (m)
WIDTH OF
13
0.5
FOOTPATH(m)
0.45
14
GRADIENT
AS PER IRC:SP:19-2001
15
TYPE
BRIDGE INVENTORY & CONDITION SURVEY
surveyor name
TYPE OF
16
BEARING
DATE OF INVENTORY
THICKNESS OF
:
17
3.2
0.8
SLAB (m)
SUPER STRUCTURE
MATERIAL OF
18
SLAB
RCC
RCC
HANDRAIL
PARAPET
19
THICKNESS &
HEIGHT (m)
0.29X0.85
0.27X0.75
20
TYPE
BT
BT
THICKNE
21
DETAILS OF
SS(m)
WEARING COAT
22
TYPE
1
2
1
S.NO.
23
TOP
2.5
PIER(m)
3
24
BOTTOM
THICKNESS OF
HEIGHT OF
3
25
PIER &
ABUTMENT (m)
ABUTME
26
NT
27
PIER
MATERIALS USED
SUB-STRUCTURE
28
TYPE
MATERIA
29
L
PIER FOUNDATION
30
TYPE
MATERIA
31
L
ABUTMENT FOUNDATION
32
BED
APPROA
33
CH
PROTECTION WORK
SKEW ANGLE
34
(Degree)
VERTICAL
CLEARANCE
35
(Below Bottom of
Deck Slab (m)
ROAD FORMATION
36
LEVEL (m)
DIRECTION OF
37
FLOW
38
ABUTMENTS
39
PIERS
40
SLAB
41
BEARINGS
PERSENT CONDITION OF BRIDGE
1
2
1
N OF BRIDGE
S.NO.
42
PARAPET
CLEAR WATER
43
WAY (m)
41.0
10.0
DESIGN OF
44
LOADING
HIGH FLOOD
45
NO
NO
LEVEL (H.F.L.)
LOWEST WATER
46
LEVEL (L.W.L.)
DESIGN
DISCHARGE
47
(Cum/sec.)
MIXIMUM DESIGN
48
VELOCITY (m/sec.)
49
REMARKS
CONSTRUCTION OF PASSENGER SHELTER
DETAIL LOCATION
DETAIL ESTIMATE
LENGTH OF WALL
10" WALL
Long Wall 2 X 5.50
Short Wall 2 X 3.00
Tot mtr
al
Filler Wall
1st. Foot 1 X 17.00 X 0.250 = 3.188 cum
2nd Foot 1 X 17.00 X 0.250 = 2.656 cum
3rd. Foot 1 X 17.00 X 0.250 = 2.125 cum
4th. Foot 1 X 17.00 X 0.450 = 2.869 cum
Steps 2 X 1.00 X 0.150 = 0.300 cum
2 X 1.00 X 0.150 = 0.225 cum
2 X 1.00 X 0.150 = 0.150 cum
2 X 1.00 X 0.150 = 0.075 cum
11.59 cum
Qnty for 1 Nos 11.5875 Cum 4085.00 Rs 47335.00
71.439 qntl
OR say 7.14 MT
Qnty for 1 Nos 7.14 Mt 5,596.00 Rs 39978.00
12 16mm(5/8") thick Cement Plaster (1:6)
over odd side surface of the wall
including cost, conveyance royalty &
taxes of all materials, labour T& P
required for the work etc complete .
5 Providing fitting and erecting of Gantry signs structure with square pipes and
M.S.plates including cost of all materials and labour, T&P etc. complete
6 Providing, fitting and fixing of Aluminium Retro Reflective Signage board including
cost, conveyance, taxes of all materials, cost of all labour, sundries and T&P etc.
required for the work complete as directed by the Engineer-in-charge.
7 Providing and applying two coats of ready mix paint of approved brand on steel
surface after through cleaning of surface to give an even shade
say 737939.00
Proposals
Span Arrangement
Existing Chainage Design chainage Type of Structures Internal Span
Sl. No and Total Ventway Proposed Widening /
(km) (km) (Pipe. Slab Box. Arch) width (m) arrangeme
(No.x BxD) (m) type Reconstruction
nt
1 2 3 4 6 7.00 25 26 27
1 295069 295069 R.C.C. SLAB 1x3.0x2.4 11.50 Retained
2 296315 296315 R.C.C. SLAB 1x1.2xx1.10 11.60 Retained
3 297520 297520 R.C.C. SLAB 1x1.2xx1.11 11.60 Retained
4 298173 298173 HP 1x1.2 12.50 Retained
5 299526 299526 R.C.C. SLAB 1x3.0x1.5 9.00 Retained
6 300072 300072 HP 1x1.2 12.00 Retained
MINOR BRIDGE
7 300400 300400 3x12.65x5.0 7.50 Widening
PLULJODI
8 301227 301227 HP 5x1.2 12.00 Retained
9 301610 301610 HP 5x1.2 12.00 Retained
10 301865 301865 HP 1x1.2 12.00 Retained
2x4.0x7.77+1x31.0x7
H.L.BRIDGE
11 302155 302155 .5+1x47.0xx7.5+2x18 7.50 Retained with provision of crash barrier.
INDIRABATI
.0x7.50
12 302600 302600 HP 1x1.2 12.00 Widening
13 302710 302710 HP 1x1.2 12.00 Widening
14 303106 303106 R.C.C. SLAB 1x1.0 12.00 SLAB 1.5X1.0 Reconstruction
15 303455 303455 HP 2x1.2 11.20 Widening
16 303671 303671 R.C.C. SLAB 1x2.3 11.00 SLAB 3.0X1.0 Reconstruction
17 304420 304420 New Proposal HPC 1x1.2 Reconstruction
18 305180 305180 New Proposal HPC 1x1.2 Reconstruction
19 305282 305282 R.C.C. SLAB 1.0X1.5 12.00 Widening
20 305597 305597 R.C.C. SLAB 1x3.0 9.80 Box 1/32/0 Reconstruction
21 305909 305909 R.C.C. SLAB 1x3.0 9.60 Box 1/32/0 Reconstruction
22 306773 306773 R.C.C. SLAB 1x6.0x1.5 11.20 Widening
23 307380 307380 New Proposal HPC 1x1.2 Reconstruction
24 307940 307940 New Proposal HPC 1x1.2 Reconstruction
25 308339 308339 HP 2x1.2 11.20 SLAB 2.0X1.0 Reconstruction
26 308709 308709 HP 14x1.2 11.70 Box 2/82/0 Reconstruction
27 309534 309534 R.C.C. SLAB 1x1.6x1.5 12.00 Box 1/22/0 Reconstruction
28 310291 310291 HP 2x0.9 9.40 SLAB 2.0X1.0 Reconstruction
29 310604 310604 HP 2x0.9 9.40 SLAB 2.0X1.0 Reconstruction
30 311797 311797 R.C.C. SLAB 1x6.0x1.0 11.00 Box 1/62/0 Reconstruction
31 312888 312888 R.C.C. SLAB 1x1.0x1.0 11.00 Widening
32 313080 313080 R.C.C. SLAB 1x5.8x2.0 11.60 Box 1/62/0 Reconstruction
R.C.C. SLAB (M
33 313390 313390 3x16.56x7.0 11.10 No Improvement
BRIDGE PARLI)
34 314428 314428 HP 2x0.6 11.60 HPC 2 x 1.2 Reconstruction
35 314522 314522 R.C.C. SLAB 1x1.8x1.5 11.60 BOX 1/22/0 Reconstruction
36 315670 315670 HP 2x0.9 9.40 BOX 1/22/0 Reconstruction
37 316530 316530 R.C.C. SLAB 1x1.2x1.0 12.00 BOX 1/22/0 Reconstruction
38 316560 316560 R.C.C. SLAB 1x1.8x1.0 9.20 BOX 1/22/0 Reconstruction
39 317130 317130 HP 2x0.9 11.90 BOX 1/22/0 Reconstruction
40 317755 317755 HP 3x1.0 11.90 BOX 1/32/0 Reconstruction
41 317840 317840 R.C.C. SLAB 1x1.6x2.0 12.00 Widening
42 318240 318240 R.C.C. SLAB 1x1.0x0.8 12.00 HPC 1x1.2 Reconstruction
43 318678 318678 HP 5x1.2 11.90 Box 3/32/0 Reconstruction
CD Schedule
AS PER IRC:SP:19-2001
Road Name :SORADA KALASANDHAPUR ROAD NH-59
Section : 295/0 to 304/0 Km
CarriaG
Span Width of
Type of Structures oode-
Sl. Culvert Thickness of Arrangement Culvert
Chainage (Pipe. Slab Box. way Condition Effective Span
No No. Slab (m) (No.x BadxD) (m)
Arch) width
(m) Internal Type Span
(m)
2 295443.244 296/2 Slab 0.3 1X1.5X2 7.3 11.3 Good Widening 1X2X3
1
X
3 295595.733 296/3 HP 1X1.0 7.2 11.5 Good Widening 1
.
3
4 295876.504 296/4 Slab 0.5 1X1.5X1.5 7 10.6 Good Widening 1X2X2.5 5
X
1
5 296019.039 297/1 HP 1X1.0 7.1 11.7 Good Widening .
1
5
6 296481.784 297/2 Slab 0.2 1X0.90X1 7 11.7 Bad HPC 1X1.2
7 296746.61 297/3 Stone Slab 0.5 1X1.75X0.90 7.1 11.0 Bad HPC 2X1.2
17 299122.838 300/1 Slab (NEW) 0.7 1X4.7X3 7.1 11.2 Good Widening 1X5X4
20 299905.032 300/4 Slab (NEW) 0.3 1X1.3X1.3 7 11.05 Good Widening 1X2X2
21 300441.087 301/1 Slab 0.5 1X4X1.5 7.1 11.1 Good Widening 1X5X2.5
29 303279.633 304/2 Slab 0.4 1X1.5X0.60 7.2 11.9 Bad Widening 1X2X1.5
30 303339.639 304/3 Slab 0.4 1X1.3X0.70 7.1 11.1 Good Widening 1X2X1.5
31 303639.736 304/4 Slab 0.2 1X2X2 7.1 12.4 Damage Box 1/22/0
CarriaG
Span Width of
Type of Structures oode-
Sl. Culvert Thickness of Arrangement Culvert
Chainage (Pipe. Slab Box. way Condition Effective Span
No No. Slab (m) (No.x BadxD) (m)
Arch) width
(m) Internal Type Span
(m)
CarriaG
Span Width of
Type of Structures oode-
Sl. Culvert Thickness of Arrangement Culvert
Chainage (Pipe. Slab Box. way Condition Effective Span
No No. Slab (m) (No.x BadxD) (m)
Arch) width
(m) Internal Type Span
(m)
73 325106.091 95/1 SLAB 0.4 1x6.6x1.70 7.4 BAD SLAB 1x6.6x1.70 Widening
75 326159.666 97/1 SLAB 0.3 1x1.5x0.7 10.8 GOOD BOX 1/22/0 Reconstruction
77 327249.808 97/3 SLAB 0.85 1x1.5x1.0 11.2 GOOD SLAB 1x1.5x1.0 Widening
83 328978.417 99/1 SLAB 0.4 1x1.7x0.7 10.9 BAD BOX 1/22/0 Reconstruction
84 329040.902 99/2 SLAB 0.4 1x1.5x0.7 11.2 BAD BOX 1/22/0 Reconstruction
86 329973.298 99/4 BRIDGE 0.3 2x8.5x2.4 10.8 GOOD Bridge 2x8.5x2.4 Reconstruction
88 330749.713 100/1 SLAB 0.4 1x2.9x0.8 8.9 BAD SLAB 1x3.5x1.5 Reconstruction
89 331260 101/1 SLAB 0.7 1x2.0x1.7 8.30 GOOD BOX 1/22/0 Reconstruction
94 333044.316 103/1 SLAB 0.5 1x3.0x1.65 10.9 GOOD SLAB 1x3.0x1.65 Widening
95 333691.365 103/2 SLAB 0.8 1x3.0x1.9 10.8 GOOD BOX 1/33/0 Reconstruction
Subudhi Associates
CarriaG
Span Width of
Type of Structures oode-
Sl. Culvert Thickness of Arrangement Culvert
Chainage (Pipe. Slab Box. way Condition Effective Span
No No. Slab (m) (No.x BadxD) (m)
Arch) width
(m) Internal Type Span
(m)
100 336085.804 104/3 BOX 0.4 1x1.5x1.5 12.0 GOOD BOX 1/22/0 Reconstruction
101 336766.316 104/4 BOX 0.35 1x1.5x1.5 12.0 GOOD BOX 1/22/0 Reconstruction
102 337188.432 104/5 SLAB 0.45 1x2.0x1.4 11.0 BAD BOX 1/22/0 Reconstruction
103 337830.303 104/6 SLAB 1x6.0x1.1 10.6 GOOD SLAB 1x6.0x1.1 Widening
104 338309.5 105/1 BOX 0.4 1/22/2 12.0 GOOD BOX 1/22/0 Widening
106 338474.701 106/1 SLAB 0.4 1x5.0x3.1 16.0 GOOD SLAB 1x5.0x3.1 Widening
Subudhi Associates
CarriaG
Span Width of
Type of Structures oode-
Sl. Culvert Thickness of Arrangement Culvert
Chainage (Pipe. Slab Box. way Condition Effective Span
No No. Slab (m) (No.x BadxD) (m)
Arch) width
(m) Internal Type Span
(m)
CD Schedule
CD Name Span Nos
Box 1/22/0 1
Box 1/33/0 1
Box 2/22/0 1
HP 1x1.0 2
Subudhi Associates
CarriaG
Span Width of
Type of Structures oode-
Sl. Culvert Thickness of Arrangement Culvert
Chainage (Pipe. Slab Box. way Condition Effective Span
No No. Slab (m) (No.x BadxD) (m)
Arch) width
(m) Internal Type Span
(m)
HP 1x1.2 5
HP 2x1.2 1
Slab 1x2.5x2.5 1
HP Widening
1x1.0 2
5m
Slab Widening
1X2X2.5 2
2m
Slab Widening
1X1.5X2 3
2m
Slab Widening
1X2X2 2
2m
Retain 4
Total Nos of CD 33
Amount
#VALUE!
Total No. of Box culvert 6 Note : This culvert is without approach slab and as per Plate 15 of SP
13:2004
Length 15
Box Detail
No. of span 1
Each Span Width 2
Total length, a 2.00
Height, b 2.00
Offset, c 0.50
Deck Slab, d 0.35
Raft, e 0.38
Wall(s), f 0.3
Depth of Key, Dk 1.20
Height from GL to FRL of culvert= 2.13
Return Wall
Length= 3.70 h3 = 2.40
Height, Hmax= 3.63 h4 = 1.50
Width, W= 3.150 b1 = 2.04
h1= 0.30 b2 = 0.41
h2= 0.15 b3 = 0.700
PCC thickness = 0.10
Revetment
Radius of revetment = 3.20
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 2.00
Length at end = 6.17
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 2.00
Length at end of trapzoidal section = 8.40
Width of trapezoidal section = 3.20
Width of rectangular section = 2.80
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent
required and utilising the remaining earth locally for road work.
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the Engineer-in-charge including cost, conveyance, royality
taxes of all materials conforming to the MORTH techanical specification.
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 6.17 1.30 0.80 6.42 cum
U/S curtain wall 2nd footing 1 6.17 0.45 0.75 2.08 cum
U/S curtain wall 3rd footing 1 6.17 0.20 0.45 0.56 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
D/S curtain wall 1st footing 1 14.00 1.65 0.55 12.71 cum
D/S curtain wall 2nd footing 1 14.00 0.75 0.75 7.88 cum
D/S curtain wall 3rd footing 1 14.00 0.45 0.75 4.73 cum
D/S curtain wall 4th footing 1 14.00 0.20 0.45 1.26 cum
Total Qty. for 1 No. 35.64 Cum
Qty. for 6Nos. 213.84 Cum 4,361.20 932,599.01
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical Specifications.
Box Portion
For Raft 1 15.000 3.600 0.380 20.52 cum
Key 2 3.600 0.710 0.820 4.19 cum
Return wall , 1st footing 4 3.70 3.15 0.30 13.99 cum
2nd footing 4 3.70 1.78 0.15 3.95 cum
Total Qty. for 1 No. 42.65 Cum
Qty. for 6Nos. 255.90 Cum 4,828.40 1,235,587.56
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 2 15.000 0.300 2.000 18.000 cum
For Hunch (1x4x1/2) 2 15.000 0.150 0.150 0.680 cum
Return wall stem, 1st lift 4 3.70 0.36 0.78 4.16 cum
2nd lift 4 3.70 0.30 2.40 10.66 cum
Total Qty. for 1 No. 33.500 Cum
Qty. for 6Nos. 201.000 Cum 5,099.20 1,024,939.20
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 15.000 2.600 0.350 13.650 Cum
Kerb wall 2 2.600 0.450 0.300 0.700 Cum
Total Qty. for 1 No. 14.350 Cum
Qty. for 6Nos. 86.100 Cum 5550.6 477,906.66
7 Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
drawing and technical specifications MORT&H Technical Specification no- 1600 .
Foundation (80 Kg/cum) 80 x 42.650 3412.000 Kg
Substructure (80 Kg/cum) 80 x 33.500 2680.000 Kg
Superstructure (80 Kg/cum) 80 x 14.350 1148.000 Kg
Wearing coat 75 x 16.260 1219.500 Kg
8459.500 Kg
Total Qty. for 1 No. 8.460 MT
Qty. for 6Nos. 50.760 MT 57402.50 2,913,750.90
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size towards the wall
behind walls 2 14.400 0.600 2.000 34.560 Cum
behind return walls 4 3.100 0.300 2.680 9.970 Cum
Total Qty. for 1 No. 44.530 Cum
Qty. for 6Nos. 267.180 Cum 1,920.90 513,226.06
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm, leaving adequate space
Qty. for 1 No. 2 2.600 5.200 Rm
Qty. for 6Nos. 31.200 Rm 1481.50 46,222.80
10
Gravel backing to revetment
4 1/4 38.64 0.15 5.80 cum
For 1No 5.80 cum
Qty. for 6Nos. 34.800 cum 820.70 28,560.36
11 Boulder Appron
Revetment 4 1/4 38.64 0.3 11.59 cum
Boulder appron at u/s 1 4.09 3.00 0.3 3.68 cum
Boulder appron at d/s 1 5.20 3.20 0.3 4.99 cum
Boulder appron d/s 7.06 cum
rectangular portion 1 8.40 2.80 0.3
For 1No 27.32 cum
Qty. for 6Nos. 163.920 cum 1,300.50 213,177.96
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :
20H towards drawing foce. Complete as per drawing and Technical Specifications
Length
No. of No. of hole no. of
of each Total
wall in a row rows
hole
13 Providing and laying Cement concrete wearing coat M-30 grade excluding reinforcement
complete as per drawing and Technical Specifications. (including cost of steel)
1 2.60 13.900 0.075 2.71 Cum
Total Qty. for 1 No. 2.71 Cum
Qty. for 6Nos. 16.26 Cum 5170.00 84,064.20
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 2.00
Length at end = 4.15
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 2.00
Length at end of trapzoidal section = 11.46
Width of trapezoidal section = 4.73
Width of rectangular section = 1.27
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and bracing,
14.000 removal0.870
5.500 of stumps and other
66.99 cum
For Key 2 5.500 0.690 0.780 5.92 cum
Return wall 4 5.23 4.43 1.60 148.28 cum
Up stream curtain wall 1 4.15 1.50 2.45 15.25 cum
Down stream curtain wall, 1 14.00 1.85 2.95 76.41 cum
Boulder appron at u/s 1 3.08 3.00 0.60 5.54 cum
Deduct already excavated in
1 -4.15 0.85 0.60 -2.12 cum
curtain wall (U/s)
Boulder appron at d/s 1 6.73 4.73 0.60 19.10 cum
Boulder appron d/s
1 11.46 1.27 0.60 8.73 cum
rectangular portion
Deduct already excavated in
1 -14.00 1.02 0.60 -8.53 cum
curtain waal (d/s)
Total Qty. for 1 No. 335.57 cum
Err:509 Err:509 cum 130.80 Err:509
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the
For Base slab 1 Engineer-in-charge
11.840 5.500 including
0.150cost, conveyance,9.77
royality
cum
For Key 2 5.500 1.400 0.150 2.31 cum
Return wall 4 5.23 4.43 0.100 9.27 cum
Up stream curtain wall 1 4.15 1.50 0.150 0.93 cum
Down stream curtain wall, 1 14.00 1.85 0.150 3.89 cum
Total Qty. for 1 No. 26.17 Cum
Err:509 Err:509 Cum 4,121.40 Err:509
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 4.15 1.30 0.80 4.32 cum
U/S curtain wall 2nd footing 1 4.15 0.45 0.75 1.40 cum
U/S curtain wall 3rd footing 1 4.15 0.20 0.45 0.37 cum
D/S curtain wall 1st footing 1 14.00 1.65 0.55 12.71 cum
D/S curtain wall 2nd footing 1 14.00 0.75 0.75 7.88 cum
D/S curtain wall 3rd footing 1 14.00 0.45 0.75 4.73 cum
D/S curtain wall 4th footing 1 14.00 0.20 0.45 1.26 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
Total Qty. for 1 No. 32.67 Cum
Err:509 Err:509 Cum 4,361.20 Err:509
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
For Raft 1 14.000 5.300 0.420 31.16 cum
Key 2 5.300 0.690 0.780 5.70 cum
Return wall , 1st footing 4 5.23 4.23 0.30 26.55 cum
2nd footing 4 5.23 2.39 0.20 10.00 cum
Total Qty. for 1 No. 73.41 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 2 14.000 0.350 3.000 29.400 cum
For Hunch (1x4x1/2) 2 14.000 0.150 0.150 0.630 cum
Return wall stem, 1st lift 4 5.23 0.43 1.75 15.74 cum
2nd lift 4 5.23 0.30 2.40 15.06 cum
Total Qty. for 1 No. 60.830 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 14.000 2.700 0.370 13.990 Cum
Kerb wall 2 2.700 0.450 0.300 0.730 Cum
Total Qty. for 1 No. 14.720 Cum
Err:509 Err:509 Cum 5550.6 Err:509
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per
80 drawingx and 73.410
technical specifications
5872.800 Kg
Substructure (80 Kg/cum) 80 x 60.830 4866.400 Kg
Supestructure (80 Kg/cum) 80 x 14.720 1177.600 Kg
Weraing coat 75 x Err:509 Err:509 Kg
Err:509 Kg
Total Qty. for 1 No. Err:509 MT
Err:509 Err:509 MT 57402.50 Err:509
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down
behind in clause 2504.2.2. of MoRTH
walls 2 specifications
13.400 0.600 to a thickness
3.000 of not less than 600 mm
48.240 Cum
behind return walls 4 4.630 0.300 3.650 20.280 Cum
Total Qty. for 1 No. 68.520 Cum
Err:509 Err:509 Cum 1,920.90 Err:509
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line
Qty.and
for 1grade,
No. tolerance of vertical 2RCC post2.700
not to exceed 1 in 500, centre to centre5.400
spacing
Rm
Err:509 Err:509 Rm 1481.50 Err:509
10
Gravel backing to revetment
4 1/4 84.45 0.15 12.67 cum
For 1No 12.67 cum
Err:509 Err:509 cum 820.70 Err:509
11 Boulder Appron
Revetment 4 1/4 84.45 0.3 25.34 cum
Boulder appron at u/s 1 3.08 3.00 0.3 2.77 cum
Boulder appron at d/s 1 6.73 4.73 0.3 9.55 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
Boulder appron d/s 4.37 cum
rectangular portion 1 11.46 1.27 0.3
For 1No 42.03 cum
Err:509 Err:509 cum 1,300.50 Err:509
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :
Length
No. of No. of hole no. of
of each Total
wall in a row rows
hole
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical
1 Specifications.
2.70 (including0.075
12.900 cost of steel) 2.61 Cum
Total Qty. for 1 No. 2.61 Cum
Err:509 Err:509 Cum 5170.00 Err:509
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 3.00
Length at end = 6.85
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 3.00
Length at end of trapzoidal section = 9.60
Width of trapezoidal section = 3.30
Width of rectangular section = 2.70
Cut-off wall type-II
U/S
Length = 6.85
Section
Height, H = 2.00
Bottom Foundation width, W = 1.50
PCC thickness = 0.15 GL to Bottom of footing ht.= 2.15
1st footing ht.,h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht.,h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht.,h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S
Length = 15.00
Section
Height, H = 2.50
Bottom Foundation width, W = 1.85 GL to Bottom of footing ht.= 2.65
PCC thickness = 0.15 1st footing width, b1= 1.65
1st footing ht.,h1 = 0.55 2nd footing width,b2= 0.75
2nd footing ht.,h2 = 0.75 3rd footing width,b3= 0.45
3rd footing ht.,h3 = 0.75 4th footing width,b4= 0.20
4th footing ht.,h4 = 0.45
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent
required and utilising the remaining earth locally for road work.
U/S curtain wall 1st footing 1 6.85 1.30 0.80 7.12 cum
U/S curtain wall 2nd footing 1 6.85 0.45 0.75 2.31 cum
U/S curtain wall 3rd footing 1 6.85 0.20 0.45 0.62 cum
D/S curtain wall 1st footing 1 15.00 1.65 0.55 13.61 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
D/S curtain wall 2nd footing 1 15.00 0.75 0.75 8.44 cum
D/S curtain wall 3rd footing 1 15.00 0.45 0.75 5.06 cum
D/S curtain wall 4th footing 1 15.00 0.20 0.45 1.35 cum
Total Qty. for 1 No. 38.51 Cum
Qty. for 3Nos. 115.53 Cum 4,361.20 503,849.44
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical Specifications.
Box Portion
For Raft 1 15.000 5.640 0.420 35.53 cum
Key 2 5.640 0.690 0.780 6.07 cum
Return wall , 1st footing 4 3.80 3.15 0.30 14.36 cum
2nd footing 4 3.80 1.78 0.15 4.06 cum
Total Qty. for 1 No. 60.02 Cum
Qty. for 3Nos. 180.06 Cum 4,828.40 869,401.70
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 2 15.000 0.420 2.000 25.200 cum
For Hunch (1x4x1/2) 2 15.000 0.150 0.150 0.680 cum
Return wall stem, 1st lift 4 3.80 0.36 0.85 4.65 cum
2nd lift 4 3.80 0.30 2.40 10.94 cum
Total Qty. for 1 No. 41.470 Cum
Qty. for 3Nos. 124.410 Cum 5,099.20 634,391.47
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 15.000 3.840 0.420 24.190 Cum
Kerb wall 2 3.840 0.450 0.300 1.040 Cum
Total Qty. for 1 No. 25.230 Cum
Qty. for 3Nos. 75.690 Cum 5550.6 420,124.91
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement in super-structure complete as per drawing and technical specifications
10
Gravel backing to revetment
4 1/4 41.12 0.15 6.17 cum
For 1No 6.17 cum
Qty. for 3Nos. 18.510 cum 820.70 15,191.16
11 Boulder Appron
Revetment 4 1/4 41.12 0.3 12.34 cum
Boulder appron at u/s 1 4.93 3.00 0.3 4.44 cum
Boulder appron at d/s 1 6.30 3.30 0.3 6.24 cum
Boulder appron d/s 7.78 cum
rectangular portion 1 9.60 2.70 0.3
For 1No 30.80 cum
Qty. for 3Nos. 92.400 cum 1,300.50 120,166.20
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :
20H towards drawing foce. Complete as per drawing and Technical Specifications.
Length
No. of No. of hole no. of
of each Total
wall in a row rows
hole
In wall of box 2 15 3 0.42 37.30 Rm
Return wall 4 4 4 0.36 23.04 Rm
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical
1 Specifications.
3.84 (including0.075
13.900 cost of steel) 4.00 Cum
Total Qty. for 1 No. 4.00 Cum
Qty. for 3Nos. 12.00 Cum 5170.00 62,040.00
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 3.00
Length at end = 4.51
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 3.00
Length at end of trapzoidal section = 11.54
Width of trapezoidal section = 6.00
Width of rectangular section = 0.00
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and bracing,
14.000 removal0.930
7.560 of stumps and other
98.43 cum
For Key 2 7.560 0.660 0.720 7.19 cum
Return wall 4 6.85 5.14 2.10 295.76 cum
Up stream curtain wall 1 4.51 1.50 2.45 16.57 cum
Down stream curtain wall, 1 11.54 1.85 2.95 62.98 cum
Boulder appron at u/s 1 3.76 3.00 0.60 6.77 cum
Deduct already excavated in
1 -4.51 0.85 0.60 -2.30 cum
curtain wall (U/s)
Boulder appron at d/s 1 7.27 6.00 0.60 26.17 cum
Boulder appron d/s
1 11.54 0.00 0.60 0.00 cum
rectangular portion
Deduct already excavated in
1 -11.54 1.02 0.60 -7.03 cum
curtain waal (d/s)
Total Qty. for 1 No. 504.54 cum
Err:509 Err:509 cum 130.80 Err:509
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the
For Base slab 1 Engineer-in-charge
11.960 7.560 including
0.150cost, conveyance, royality
13.56 cum
For Key 2 7.560 1.320 0.150 2.99 cum
Return wall 4 6.85 5.14 0.100 14.08 cum
Up stream curtain wall 1 4.51 1.50 0.150 1.01 cum
Down stream curtain wall, 1 11.54 1.85 0.150 3.20 cum
Total Qty. for 1 No. 34.84 Cum
Err:509 Err:509 Cum 4,121.40 Err:509
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 4.51 1.30 0.80 4.69 cum
U/S curtain wall 2nd footing 1 4.51 0.45 0.75 1.52 cum
U/S curtain wall 3rd footing 1 4.51 0.20 0.45 0.41 cum
D/S curtain wall 1st footing 1 11.54 1.65 0.55 10.47 cum
D/S curtain wall 2nd footing 1 11.54 0.75 0.75 6.49 cum
D/S curtain wall 3rd footing 1 11.54 0.45 0.75 3.89 cum
D/S curtain wall 4th footing 1 11.54 0.20 0.45 1.04 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
Total Qty. for 1 No. 28.51 Cum
Err:509 Err:509 Cum 4,361.20 Err:509
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
For Raft 1 14.000 7.360 0.480 49.46 cum
Key 2 7.360 0.660 0.720 6.99 cum
Return wall , 1st footing 4 6.85 4.94 0.30 40.61 cum
2nd footing 4 6.85 2.82 0.30 23.18 cum
Total Qty. for 1 No. 120.24 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 2 14.000 0.480 4.000 53.760 cum
For Hunch (1x4x1/2) 2 14.000 0.150 0.150 0.630 cum
Return wall stem, 1st lift 4 6.85 0.50 3.23 44.25 cum
2nd lift 4 6.85 0.30 2.40 19.73 cum
Total Qty. for 1 No. 118.370 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 14.000 3.960 0.450 24.950 Cum
Kerb wall 2 3.960 0.450 0.300 1.070 Cum
Total Qty. for 1 No. 26.020 Cum
Err:509 Err:509 Cum 5550.6 Err:509
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per
80 drawingx and120.240
technical specifications
9619.200 Kg
Substructure (80 Kg/cum) 80 x 118.370 9469.600 Kg
Supestructure (80 Kg/cum) 80 x 26.020 2081.600 Kg
Weraing coat 75 x Err:509 Err:509 Kg
Err:509 Kg
Total Qty. for 1 No. Err:509 MT
Err:509 Err:509 MT 57402.50 Err:509
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down
behind in clause 2504.2.2. of MoRTH
walls 2 specifications
13.400 0.600 to a thickness
4.000 of not less than 600 mm
64.320 Cum
behind return walls 4 6.250 0.300 5.130 38.480 Cum
Total Qty. for 1 No. 102.800 Cum
Err:509 Err:509 Cum 1,920.90 Err:509
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line
Qty.and
for 1grade,
No. tolerance of vertical 2RCC post3.960
not to exceed 1 in 500, centre to centre7.920
spacing
Rm
Err:509 Err:509 Rm 1481.50 Err:509
10
Gravel backing to revetment
4 1/4 152.21 0.15 22.83 cum
For 1No 22.83 cum
Err:509 Err:509 cum 820.70 Err:509
11 Boulder Appron
Revetment 4 1/4 152.21 0.3 45.66 cum
Boulder appron at u/s 1 3.76 3.00 0.3 3.38 cum
Boulder appron at d/s 1 7.27 6.00 0.3 13.09 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
Boulder appron d/s 0.00 cum
rectangular portion 1 11.54 0.00 0.3
For 1No 62.13 cum
Err:509 Err:509 cum 1,300.50 Err:509
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :
Length
No. of No. of hole no. of
of each Total
wall in a row rows
hole
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical
1 Specifications.
3.96 (including0.075
12.900 cost of steel) 3.83 Cum
Total Qty. for 1 No. 3.83 Cum
Err:509 Err:509 Cum 5170.00 Err:509
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 4.00
Length at end = 5.18
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 4.00
Length at end of trapzoidal section = 9.47
Width of trapezoidal section = 6.00
Width of rectangular section = 0.00
#VALUE!
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and bracing,
14.000 removal 1.070
9.260 of stumps and other deleterious
138.71 cum
For Key 2 9.260 0.590 0.580 6.34 cum
Return wall 4 8.45 5.30 2.10 376.19 cum
Up stream curtain wall 1 5.18 1.50 2.45 19.04 cum
Down stream curtain wall, 1 9.47 1.85 2.95 51.68 cum
Boulder appron at u/s 1 4.59 3.00 0.60 8.26 cum
Deduct already excavated in
1 -5.18 0.85 0.60 -2.64 cum
curtain wall (U/s)
Boulder appron at d/s 1 6.74 6.00 0.60 24.26 cum
Boulder appron d/s
1 9.47 0.00 0.60 0.00 cum
rectangular portion
Deduct already excavated in
1 -9.47 1.02 0.60 -5.77 cum
curtain waal (d/s)
Total Qty. for 1 No. 616.07 cum
Err:509 Err:509 cum 130.80 Err:509
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the
For Base slab 1 Engineer-in-charge
12.240 9.260 including cost, conveyance,17.00
0.150 royality
cum
For Key 2 9.260 1.120 0.150 3.11 cum
Return wall 4 8.45 5.30 0.100 17.91 cum
Up stream curtain wall 1 5.18 1.50 0.150 1.17 cum
Down stream curtain wall, 1 9.47 1.85 0.150 2.63 cum
Total Qty. for 1 No. 41.82 Cum
Err:509 Err:509 Cum 4,121.40 Err:509
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 5.18 1.30 0.80 5.39 cum
U/S curtain wall 2nd footing 1 5.18 0.45 0.75 1.75 cum
U/S curtain wall 3rd footing 1 5.18 0.20 0.45 0.47 cum
D/S curtain wall 1st footing 1 9.47 1.65 0.55 8.59 cum
D/S curtain wall 2nd footing 1 9.47 0.75 0.75 5.33 cum
D/S curtain wall 3rd footing 1 9.47 0.45 0.75 3.20 cum
D/S curtain wall 4th footing 1 9.47 0.20 0.45 0.85 cum
Total Qty. for 1 No. 25.58 Cum
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
Err:509 Err:509 Cum 4,361.20 Err:509
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
For Raft 1 14.000 9.060 0.620 78.64 cum
Key 2 9.060 0.590 0.580 6.20 cum
Return wall , 1st footing 4 8.45 5.10 0.30 51.71 cum
2nd footing 4 8.45 2.95 0.33 32.90 cum
Total Qty. for 1 No. 169.45 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 2 14.000 0.630 5.000 88.200 cum
For Hunch (1x4x1/2) 2 14.000 0.150 0.150 0.630 cum
Return wall stem, 1st lift 4 8.45 0.55 4.28 79.57 cum
2nd lift 4 8.45 0.30 2.40 24.34 cum
Total Qty. for 1 No. 192.740 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 14.000 5.260 0.520 38.290 Cum
Kerb wall 2 5.260 0.450 0.300 1.420 Cum
Total Qty. for 1 No. 39.710 Cum
Err:509 Err:509 Cum 5550.6 Err:509
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per80 drawingx and technical
169.450 specifications
13556.000 Kg
Substructure (80 Kg/cum) 80 x 192.740 15419.200 Kg
Supestructure (80 Kg/cum) 80 x 39.710 3176.800 Kg
Weraing coat 75 x Err:509 Err:509 Kg
Err:509 Kg
Total Qty. for 1 No. Err:509 MT
Err:509 Err:509 MT 57402.50 Err:509
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down
behind in clause 2504.2.2. of MoRTH
walls 2 specifications
13.400 0.600to a thickness
5.000of not less than80.400
600 mm with
Cum
behind return walls 4 7.850 0.300 6.180 58.220 Cum
Total Qty. for 1 No. 138.620 Cum
Err:509 Err:509 Cum 1,920.90 Err:509
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line
and
Qty. grade, tolerance of vertical RCC2 post not5.260
for 1 No. to exceed 1 in 500, centre to centre spacing
10.520 Rm
Err:509 Err:509 Rm 1481.50 Err:509
10
Gravel backing to revetment
4 1/4 238.64 0.15 35.80 cum
For 1No 35.80 cum
Err:509 Err:509 cum 820.70 Err:509
11 Boulder Appron
Revetment 4 1/4 238.64 0.3 71.59 cum
Boulder appron at u/s 1 4.59 3.00 0.3 4.13 cum
Boulder appron at d/s 1 6.74 6.00 0.3 12.13 cum
Boulder appron d/s 0.00 cum
rectangular portion 1 9.47 0.00 0.3
For 1No 87.85 cum
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
Err:509 Err:509 cum 1,300.50 Err:509
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
towards drawing foce. Complete as per drawing and Technical
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete
as per drawing and Technical Specifications.
1 (including12.900
5.26 cost of steel)
0.075 5.09 Cum
Total Qty. for 1 No. 5.09 Cum
Err:509 Err:509 Cum 5170.00 Err:509
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 6.00
Length at end = 6.95
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 6.00
Length at end of trapzoidal section = 10.15
Width of trapezoidal section = 6.00
Width of rectangular section = 0.00
#VALUE!
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and bracing,
14.000 removal of
11.500 stumps and other
1.250 deleterious
201.25 cum
For Key 2 11.500 0.500 0.400 4.60 cum
Return wall 4 10.22 8.60 2.60 914.08 cum
Up stream curtain wall 1 6.95 1.50 2.45 25.54 cum
Down stream curtain wall, 1 10.15 1.85 2.95 55.39 cum
Boulder appron at u/s 1 6.48 3.00 0.60 11.66 cum
Deduct already excavated in
1 -6.95 0.85 0.60 -3.54 cum
curtain wall (U/s)
Boulder appron at d/s 1 8.08 6.00 0.60 29.09 cum
Boulder appron d/s
1 10.15 0.00 0.60 0.00 cum
rectangular portion
Deduct already excavated in
1 -10.15 1.02 0.60 -6.18 cum
curtain waal (d/s)
Total Qty. for 1 No. 1231.89 cum
Err:509 Err:509 cum 130.80 Err:509
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the
For Base slab 1 Engineer-in-charge
12.600 11.500 including cost, conveyance,21.74
0.150 royality
cum
For Key 2 11.500 0.870 0.150 3.00 cum
Return wall 4 10.22 8.60 0.100 35.16 cum
Up stream curtain wall 1 6.95 1.50 0.150 1.56 cum
Down stream curtain wall, 1 10.15 1.85 0.150 2.82 cum
Total Qty. for 1 No. 64.28 Cum
Err:509 Err:509 Cum 4,121.40 Err:509
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 6.95 1.30 0.80 7.23 cum
U/S curtain wall 2nd footing 1 6.95 0.45 0.75 2.35 cum
U/S curtain wall 3rd footing 1 6.95 0.20 0.45 0.63 cum
D/S curtain wall 1st footing 1 10.15 1.65 0.55 9.21 cum
D/S curtain wall 2nd footing 1 10.15 0.75 0.75 5.71 cum
D/S curtain wall 3rd footing 1 10.15 0.45 0.75 3.43 cum
D/S curtain wall 4th footing 1 10.15 0.20 0.45 0.91 cum
Total Qty. for 1 No. 29.47 Cum
Err:509 Err:509 Cum 4,361.20 Err:509
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
For Raft 1 14.000 11.300 0.800 126.56 cum
Key 2 11.300 0.500 0.400 4.52 cum
Return wall , 1st footing 4 10.22 8.40 0.30 103.02 cum
2nd footing 4 10.22 4.78 0.60 117.24 cum
Total Qty. for 1 No. 351.34 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 2 14.000 0.850 6.000 142.800 cum
For Hunch (1x4x1/2) 2 14.000 0.150 0.150 0.630 cum
Return wall stem, 1st lift 4 10.22 0.73 5.68 169.50 cum
2nd lift 4 10.22 0.30 2.40 29.43 cum
Total Qty. for 1 No. 342.360 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 14.000 7.700 0.700 75.460 Cum
Kerb wall 2 7.700 0.450 0.300 2.080 Cum
Total Qty. for 1 No. 77.540 Cum
Err:509 Err:509 Cum 5550.6 Err:509
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per
80 drawingx and technical
351.340 specifications
28107.200 Kg
Substructure (80 Kg/cum) 80 x 342.360 27388.800 Kg
Supestructure (80 Kg/cum) 80 x 77.540 6203.200 Kg
Weraing coat 75 x Err:509 Err:509 Kg
Err:509 Kg
Total Qty. for 1 No. Err:509 MT
Err:509 Err:509 MT 57402.50 Err:509
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down
behind in clause 2504.2.2. of MoRTH
walls 2 specifications to a thickness
13.400 0.600 6.000of not less than 96.480
600 mmCum
with
behind return walls 4 9.620 0.300 7.580 87.500 Cum
Total Qty. for 1 No. 183.980 Cum
Err:509 Err:509 Cum 1,920.90 Err:509
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm, leaving adequate space
10
Gravel backing to revetment
4 1/4 356.72 0.15 53.51 cum
For 1No 53.51 cum
Err:509 Err:509 cum 820.70 Err:509
11 Boulder Appron
Revetment 4 1/4 356.72 0.3 107.02 cum
Boulder appron at u/s 1 6.48 3.00 0.3 5.83 cum
Boulder appron at d/s 1 8.08 6.00 0.3 14.54 cum
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
towards drawing foce. Complete as per drawing and Technical
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete
as per drawing and Technical Specifications.
1 (including12.900
7.70 cost of steel)
0.075 7.45 Cum
Total Qty. for 1 No. 7.45 Cum
Err:509 Err:509 Cum 5170.00 Err:509
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 6.00
Length at end = 6.95
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 6.00
Length at end of trapzoidal section = 10.15
Width of trapezoidal section = 6.00
Width of rectangular section = 0.00
#VALUE!
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and4.500 bracing, removal of
11.500 stumps and other64.69
1.250 deleterious
cum
For Key 2 11.500 0.500 0.400 4.60 cum
Return wall 4 10.22 8.60 2.60 914.08 cum
Up stream curtain wall 1 6.95 1.50 2.45 25.54 cum
Down stream curtain wall, 1 10.15 1.85 2.95 55.39 cum
Boulder appron at u/s 1 6.48 3.00 0.60 11.66 cum
Deduct already excavated in
1 -6.95 0.85 0.60 -3.54 cum
curtain wall (U/s)
Boulder appron at d/s 1 8.08 6.00 0.60 29.09 cum
Boulder appron d/s
1 10.15 0.00 0.60 0.00 cum
rectangular portion
Deduct already excavated in
1 -10.15 1.02 0.60 -6.18 cum
curtain waal (d/s)
Total Qty. for 1 No. 1095.33 cum
Err:509 Err:509 cum 130.80 Err:509
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the
For Base slab 1 Engineer-in-charge
3.100 11.500 including cost, conveyance, royality
0.150 5.35 cum
For Key 2 11.500 0.870 0.150 3.00 cum
Return wall 4 10.22 8.60 0.100 35.16 cum
Up stream curtain wall 1 6.95 1.50 0.150 1.56 cum
Down stream curtain wall, 1 10.15 1.85 0.150 2.82 cum
Total Qty. for 1 No. 47.89 Cum
Err:509 Err:509 Cum 4,121.40 Err:509
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 6.95 1.30 0.80 7.23 cum
U/S curtain wall 2nd footing 1 6.95 0.45 0.75 2.35 cum
U/S curtain wall 3rd footing 1 6.95 0.20 0.45 0.63 cum
D/S curtain wall 1st footing 1 10.15 1.65 0.55 9.21 cum
D/S curtain wall 2nd footing 1 10.15 0.75 0.75 5.71 cum
D/S curtain wall 3rd footing 1 10.15 0.45 0.75 3.43 cum
D/S curtain wall 4th footing 1 10.15 0.20 0.45 0.91 cum
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
Total Qty. for 1 No. 29.47 Cum
Err:509 Err:509 Cum 4,361.20 Err:509
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
For Raft 1 4.500 11.300 0.800 40.68 cum
Key 2 11.300 0.500 0.400 4.52 cum
Return wall , 1st footing 4 10.22 8.40 0.30 103.02 cum
2nd footing 4 10.22 4.78 0.60 117.24 cum
Total Qty. for 1 No. 265.46 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 2 4.500 0.850 6.000 45.900 cum
For Hunch (1x4x1/2) 2 4.500 0.150 0.150 0.200 cum
Return wall stem, 1st lift 4 10.22 0.73 5.68 169.50 cum
2nd lift 4 10.22 0.30 2.40 29.43 cum
Total Qty. for 1 No. 245.030 Cum
Err:509 Err:509 Cum 5,099.20 Err:509
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 4.500 7.700 0.700 24.260 Cum
Kerb wall 2 7.700 0.450 0.300 2.080 Cum
Total Qty. for 1 No. 26.340 Cum
Err:509 Err:509 Cum 5550.6 Err:509
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per
80 drawingx and technical
265.460 specifications
21236.800 Kg
Substructure (80 Kg/cum) 80 x 245.030 19602.400 Kg
Supestructure (80 Kg/cum) 80 x 26.340 2107.200 Kg
Weraing coat 75 x Err:509 Err:509 Kg
Err:509 Kg
Total Qty. for 1 No. Err:509 MT
Err:509 Err:509 MT 57402.50 Err:509
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down
behind in clause 2504.2.2. of MoRTH
walls 2 specifications
3.900 to a thickness
0.600 6.000of not less than 28.080
600 mmCum
with
behind return walls 4 9.620 0.300 7.580 87.500 Cum
Total Qty. for 1 No. 115.580 Cum
Err:509 Err:509 Cum 1,920.90 Err:509
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm, leaving adequate space
10
Gravel backing to revetment
4 1/4 356.72 0.15 53.51 cum
For 1No 53.51 cum
Err:509 Err:509 cum 820.70 Err:509
11 Boulder Appron
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
Revetment 4 1/4 356.72 0.3 107.02 cum
Boulder appron at u/s 1 6.48 3.00 0.3 5.83 cum
Boulder appron at d/s 1 8.08 6.00 0.3 14.54 cum
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
towards drawing foce. Complete as per drawing and Technical
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete
as per drawing and Technical Specifications.
1 (including3.400
7.70 cost of steel)
0.075 1.96 Cum
Total Qty. for 1 No. 1.96 Cum
Err:509 Err:509 Cum 5170.00 Err:509
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 6.00
Length at end = 9.08
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 6.00
Length at end of trapzoidal section = 13.38
Width of trapezoidal section = 3.69
Width of rectangular section = 2.31
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and15.000
bracing,8.240
removal of1.170
stumps and other144.61
deleterious
cum
For Key 2 8.240 0.540 0.480 4.27 cum
Return wall 4 4.19 3.35 1.60 89.83 cum
Up stream curtain wall 1 9.08 1.50 2.45 33.37 cum
Down stream curtain wall, 1 18.00 1.85 2.95 98.24 cum
Boulder appron at u/s 1 7.54 3.00 0.60 13.57 cum
Deduct already excavated in
1 -9.08 0.85 0.60 -4.63 cum
curtain wall (U/s)
Boulder appron at d/s 1 9.69 3.69 0.60 21.45 cum
Boulder appron d/s rectangular
1 13.38 2.31 0.60 18.54 cum
portion
Deduct already excavated in
1 -18.00 1.02 0.60 -10.96 cum
curtain waal (d/s)
Total Qty. for 1 No. 408.29 cum
Qty. for 2Nos. 816.58 cum 130.80 106,808.66
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the1 Engineer-in-charge
For Base slab 13.440 8.240 including cost, conveyance, royality
0.150 16.61 cum
For Key 2 8.240 0.980 0.150 2.42 cum
Return wall 4 4.19 3.35 0.100 5.61 cum
Up stream curtain wall 1 9.08 1.50 0.150 2.04 cum
Down stream curtain wall, 1 18.00 1.85 0.150 5.00 cum
Total Qty. for 1 No. 31.68 Cum
Qty. for 2Nos. 63.36 Cum 4,121.40 261,131.90
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical
U/S curtainSpecifications.
wall 1st footing 1 9.08 1.30 0.80 9.44 cum
U/S curtain wall 2nd footing 1 9.08 0.45 0.75 3.06 cum
U/S curtain wall 3rd footing 1 9.08 0.20 0.45 0.82 cum
D/S curtain wall 1st footing 1 18.00 1.65 0.55 16.34 cum
D/S curtain wall 2nd footing 1 18.00 0.75 0.75 10.13 cum
D/S curtain wall 3rd footing 1 18.00 0.45 0.75 6.08 cum
D/S curtain wall 4th footing 1 18.00 0.20 0.45 1.62 cum
Total Qty. for 1 No. 47.49 Cum
Qty. for 2Nos. 94.98 Cum 4,361.20 414,226.78
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical Specifications.
Box Portion
For Raft 1 15.000 8.040 0.720 86.83 cum
Key 2 8.040 0.540 0.480 4.17 cum
Return wall , 1st footing 4 4.19 3.15 0.30 15.84 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
2nd footing 4 4.19 1.78 0.15 4.47 cum
Total Qty. for 1 No. 111.31 Cum
Qty. for 2Nos. 222.62 Cum 5,099.20 1,135,183.90
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 2 15.000 0.720 2.000 43.200 cum
Middle wall 0 15.000 0.000 2.000 0.000 cum
For Hunch (1x4x1/2) 2 15.000 0.150 0.150 0.680 cum
Return wall stem, 1st lift 4 4.19 0.36 1.11 6.70 cum
2nd lift 4 4.19 0.30 2.40 12.07 cum
Total Qty. for 1 No. 62.650 Cum
Qty. for 2Nos. 125.300 Cum 5,099.20 638,929.76
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 15.000 7.440 0.680 75.890 Cum
Kerb wall 2 7.440 0.450 0.300 2.010 Cum
Total Qty. for 1 No. 77.900 Cum
Qty. for 2Nos. 155.800 Cum 5550.6 864,783.48
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per80drawing and
x technical
111.310specifications
8904.800 Kg
Substructure (80 Kg/cum) 80 x 62.650 5012.000 Kg
Supestructure (80 Kg/cum) 80 x 77.900 6232.000 Kg
Weraing coat 75 x 15.520 1164.000 Kg
21312.800 Kg
Total Qty. for 1 No. 21.310 MT
Qty. for 2Nos. 42.620 MT 57402.50 2,446,494.55
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements laid
down
behindinwalls
clause 2504.2.2. of MoRTH specifications
2 14.400to a thickness
0.600 of not less than 600 mm
2.000 withCum
34.560
behind return walls 4 3.590 0.300 3.010 12.970 Cum
Total Qty. for 1 No. 47.530 Cum
Qty. for 2Nos. 95.060 Cum 1,920.90 182,600.75
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line
and
Qty. grade, tolerance of vertical RCC 2post not to
for 1 No. exceed 1 in 500, centre to centre spacing
7.440 between
14.880 Rm
Qty. for 2Nos. 29.760 Rm 1481.50 44,089.44
11 Boulder Appron
Revetment 4 1/4 51.41 0.3 15.42 cum
Boulder appron at u/s 1 7.54 3.00 0.3 6.79 cum
Boulder appron at d/s 1 9.69 3.69 0.3 10.73 cum
Boulder appron d/s rectangular 9.27 cum
portion 1 13.38 2.31 0.3
For 1No 42.21 cum
Qty. for 2Nos. 84.420 cum 1,300.50 109,788.21
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete
as per drawing and Technical Specifications.
1 (including
7.44 cost of steel)0.075
13.900 7.76 Cum
Total Qty. for 1 No. 7.76 Cum
Qty. for 2Nos. 15.52 Cum 5170.00 80,238.40
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 17.20
Length at end = 19.96
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 17.20
Length at end of trapzoidal section = 25.10
Width of trapezoidal section = 3.95
Width of rectangular section = 2.05
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and bracing,
15.000 removal1.550
22.400 of stumps and other
520.80 cum
For Key 2 22.400 0.450 0.300 6.05 cum
Return wall 4 4.45 8.60 2.60 398.01 cum
Up stream curtain wall 1 19.96 1.50 2.45 73.35 cum
Down stream curtain wall, 1 29.20 1.85 2.95 159.36 cum
Boulder appron at u/s 1 18.58 3.00 0.60 33.44 cum
Deduct already excavated in
1 -19.96 0.85 0.60 -10.18 cum
curtain wall (U/s)
Boulder appron at d/s 1 21.15 3.95 0.60 50.13 cum
Boulder appron d/s
1 25.10 2.05 0.60 30.87 cum
rectangular portion
Deduct already excavated in
1 -29.20 1.02 0.60 -17.78 cum
curtain waal (d/s)
Total Qty. for 1 No. 1244.05 cum
Qty. for 1Nos. 1244.05 cum 130.80 162,721.74
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the
For Base slab 1 Engineer-in-charge
13.800 22.400 including
0.150cost, conveyance, royality
46.37 cum
For Key 2 22.400 0.720 0.150 4.84 cum
Return wall 4 4.45 8.60 0.100 15.31 cum
Up stream curtain wall 1 19.96 1.50 0.150 4.49 cum
Down stream curtain wall, 1 29.20 1.85 0.150 8.10 cum
Total Qty. for 1 No. 79.11 Cum
Qty. for 1Nos. 79.11 Cum 4,121.40 326,043.95
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 19.96 1.30 0.80 20.76 cum
U/S curtain wall 2nd footing 1 19.96 0.45 0.75 6.74 cum
U/S curtain wall 3rd footing 1 19.96 0.20 0.45 1.80 cum
D/S curtain wall 1st footing 1 29.20 1.65 0.55 26.50 cum
D/S curtain wall 2nd footing 1 29.20 0.75 0.75 16.43 cum
D/S curtain wall 3rd footing 1 29.20 0.45 0.75 9.86 cum
D/S curtain wall 4th footing 1 29.20 0.20 0.45 2.63 cum
Total Qty. for 1 No. 84.72 Cum
Qty. for 1Nos. 84.72 Cum 4,361.20 369,480.86
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
For Raft 1 15.000 22.200 1.100 366.30 cum
Key 2 22.200 0.450 0.300 5.99 cum
Return wall , 1st footing 4 4.45 8.40 0.30 44.86 cum
2nd footing 4 4.45 4.78 0.60 51.05 cum
Total Qty. for 1 No. 468.20 Cum
Qty. for 1Nos. 468.20 Cum 5,099.20 2,387,445.44
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 3 15.000 1.200 2.000 108.000 cum
For Hunch (2x4x1/2) 4 15.000 0.150 0.150 1.350 cum
Return wall stem, 1st lift 4 4.45 0.73 1.83 23.78 cum
2nd lift 4 4.45 0.30 2.40 12.82 cum
Total Qty. for 1 No. 145.950 Cum
Qty. for 1Nos. 145.950 Cum 5,099.20 744,228.24
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 15.000 19.600 0.850 249.900 Cum
Kerb wall 2 19.600 0.450 0.300 5.290 Cum
Total Qty. for 1 No. 255.190 Cum
Qty. for 1Nos. 255.190 Cum 5550.6 1,416,457.61
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per
80 drawingx and 468.200
technical specifications
37456.000 Kg
Substructure (80 Kg/cum) 80 x 145.950 11676.000 Kg
Supestructure (80 Kg/cum) 80 x 255.190 20415.200 Kg
Weraing coat 75 x 20.430 1532.250 Kg
71079.450 Kg
Total Qty. for 1 No. 71.080 MT
Qty. for 1Nos. 71.080 MT 57402.50 4,080,169.70
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down
behind in clause 2504.2.2. of MoRTH
walls 2 specifications to a thickness
14.400 0.600 2.000 of not less than34.560
600 mm
Cum
behind return walls 4 3.850 0.300 3.730 17.230 Cum
Total Qty. for 1 No. 51.790 Cum
Qty. for 1Nos. 51.790 Cum 1,920.90 99,483.41
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line
and
Qty. grade, tolerance of vertical RCC2 post not
for 1 No. to exceed 1 in 500, centre to centre spacing
19.600 39.200 Rm
Qty. for 1Nos. 39.200 Rm 1481.50 58,074.80
10
Gravel backing to revetment
4 1/4 58.89 0.15 8.83 cum
For 1No 8.83 cum
Qty. for 1Nos. 8.830 cum 820.70 7,246.78
11 Boulder Appron
Revetment 4 1/4 58.89 0.3 17.67 cum
Boulder appron at u/s 1 18.58 3.00 0.3 16.72 cum
Boulder appron at d/s 1 21.15 3.95 0.3 25.06 cum
Boulder appron d/s 15.44 cum
rectangular portion 1 25.10 2.05 0.3
For 1No 74.89 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
Qty. for 1Nos. 74.890 cum 1,300.50 97,394.45
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width Length
of the structure with slope of 1V :
No. of No. of hole no. of
of each Total
wall in a row rows
hole
In wall of box 2 15 3 1.20 106.56 Rm
Return wall 4 5 6 0.73 87.60 Rm
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical
1 Specifications. (including 0.075
19.60 13.900 cost of steel) 20.43 Cum
Total Qty. for 1 No. 20.43 Cum
Qty. for 1Nos. 20.43 Cum 5170.00 105,623.10
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 18.30
Length at end = 21.15
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 18.30
Length at end of trapzoidal section = 26.04
Width of trapezoidal section = 3.87
Width of rectangular section = 2.13
#VALUE!
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and15.000
bracing,21.000
removal of1.400
stumps and other441.00
deleterious
cum
For Key 2 21.000 0.450 0.300 5.67 cum
Return wall 4 4.37 4.43 2.10 162.62 cum
Up stream curtain wall 1 21.15 1.50 2.45 77.73 cum
Down stream curtain wall, 1 30.30 1.85 2.95 165.36 cum
Boulder appron at u/s 1 19.73 3.00 0.60 35.51 cum
Deduct already excavated in
1 -21.15 0.85 0.60 -10.79 cum
curtain wall (U/s)
Boulder appron at d/s 1 22.17 3.87 0.60 51.48 cum
Boulder appron d/s rectangular
1 26.04 2.13 0.60 33.28 cum
portion
Deduct already excavated in
1 -30.30 1.02 0.60 -18.45 cum
curtain waal (d/s)
Total Qty. for 1 No. 943.41 cum
Qty. for 1Nos. 943.41 cum 130.80 123,398.03
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the1 Engineer-in-charge
For Base slab 13.800 21.000including cost, conveyance, royality
0.150 43.47 cum
For Key 2 21.000 0.720 0.150 4.54 cum
Return wall 4 4.37 4.43 0.100 7.74 cum
Up stream curtain wall 1 21.15 1.50 0.150 4.76 cum
Down stream curtain wall, 1 30.30 1.85 0.150 8.41 cum
Total Qty. for 1 No. 68.92 Cum
Qty. for 1Nos. 68.92 Cum 4,121.40 284,046.89
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical
U/S curtainSpecifications.
wall 1st footing 1 21.15 1.30 0.80 22.00 cum
U/S curtain wall 2nd footing 1 21.15 0.45 0.75 7.14 cum
U/S curtain wall 3rd footing 1 21.15 0.20 0.45 1.90 cum
D/S curtain wall 1st footing 1 30.30 1.65 0.55 27.50 cum
D/S curtain wall 2nd footing 1 30.30 0.75 0.75 17.04 cum
D/S curtain wall 3rd footing 1 30.30 0.45 0.75 10.23 cum
D/S curtain wall 4th footing 1 30.30 0.20 0.45 2.73 cum
Total Qty. for 1 No. 88.54 Cum
Qty. for 1Nos. 88.54 Cum 4,361.20 386,140.65
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
For Raft 1 15.000 20.800 0.950 296.40 cum
Key 2 20.800 0.450 0.300 5.62 cum
Return wall , 1st footing 4 4.37 4.23 0.30 22.18 cum
2nd footing 4 4.37 2.39 0.20 8.36 cum
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
Total Qty. for 1 No. 332.56 Cum
Qty. for 1Nos. 332.56 Cum 5,099.20 1,695,789.95
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 3 15.000 0.950 2.000 85.500 cum
Middle wall 1 15.000 0.400 2.000 12.000 cum
For Hunch (2x4x1/2) 4 15.000 0.150 0.150 1.350 cum
Return wall stem, 1st lift 4 4.37 0.43 1.68 12.63 cum
2nd lift 4 4.37 0.30 2.40 12.59 cum
Total Qty. for 1 No. 124.070 Cum
Qty. for 1Nos. 124.070 Cum 5,099.20 632,657.74
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 15.000 20.200 0.800 242.400 Cum
Kerb wall 2 20.200 0.450 0.300 5.450 Cum
Total Qty. for 1 No. 247.850 Cum
Qty. for 1Nos. 247.850 Cum 5550.6 1,375,716.21
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per80drawing and
x technical
332.560specifications
26604.800 Kg
Substructure (80 Kg/cum) 80 x 124.070 9925.600 Kg
Supestructure (80 Kg/cum) 80 x 247.850 19828.000 Kg
Weraing coat 75 x 21.060 1579.500 Kg
57937.900 Kg
Total Qty. for 1 No. 57.940 MT
Qty. for 1Nos. 57.940 MT 57402.50 3,325,900.85
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements laid
down
behindinwalls
clause 2504.2.2. of MoRTH specifications
2 to a thickness
14.400 0.600 of not less than 600 mm
2.000 withCum
34.560
behind return walls 4 3.770 0.300 3.580 16.200 Cum
Total Qty. for 1 No. 50.760 Cum
Qty. for 1Nos. 50.760 Cum 1,920.90 97,504.88
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line
and
Qty. grade, tolerance of vertical RCC 2post not20.200
for 1 No. to exceed 1 in 500, centre to centre spacing between
40.400 Rm
Qty. for 1Nos. 40.400 Rm 1481.50 59,852.60
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
No. of No. of hole no. of Length of
Total
wall in a row rows each hole
In wall of box 2 15 3 0.95 84.36 Rm
Return wall 4 5 5 0.43 43.00 Rm
Total Qty. for 1 No. 127.36 Rm
Qty. for 1Nos. 127.36 Rm 162.10 20,645.06
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete
as per drawing and Technical Specifications.
1 (including cost of steel)0.075
20.20 13.900 21.06 Cum
Total Qty. for 1 No. 21.06 Cum
Qty. for 1Nos. 21.06 Cum 5170.00 108,880.20
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 10.74
Length at end = 14.46
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 10.74
Length at end of trapzoidal section = 17.44
Width of trapezoidal section = 3.35
Width of rectangular section = 2.65
#VALUE!
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including
For Base setting
slab out, construction of shoring
1 and15.000
bracing,12.780
removal of0.950
stumps and other182.12
deleterious
cum
For Key 2 12.780 0.650 0.700 11.63 cum
Return wall 4 3.85 3.35 1.60 82.54 cum
Up stream curtain wall 1 14.46 1.50 2.45 53.14 cum
Down stream curtain wall, 1 22.74 1.85 2.95 124.10 cum
Boulder appron at u/s 1 12.60 3.00 0.60 22.68 cum
Deduct already excavated in
1 -14.46 0.85 0.60 -7.37 cum
curtain wall (U/s)
Boulder appron at d/s 1 14.09 3.35 0.60 28.32 cum
Boulder appron d/s rectangular
1 17.44 2.65 0.60 27.73 cum
portion
Deduct already excavated in
1 -22.74 1.02 0.60 -13.85 cum
curtain waal (d/s)
Total Qty. for 1 No. 511.04 cum
Qty. for 1Nos. 511.04 cum 130.80 66,844.03
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the1 Engineer-in-charge
For Base slab 13.000 12.780including cost, conveyance, royality
0.150 24.92 cum
For Key 2 12.780 1.290 0.150 4.95 cum
Return wall 4 3.85 3.35 0.100 5.16 cum
Up stream curtain wall 1 14.46 1.50 0.150 3.25 cum
Down stream curtain wall, 1 22.74 1.85 0.150 6.31 cum
Total Qty. for 1 No. 44.59 Cum
Qty. for 1Nos. 44.59 Cum 4,121.40 183,773.23
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical
U/S curtainSpecifications.
wall 1st footing 1 14.46 1.30 0.80 15.04 cum
U/S curtain wall 2nd footing 1 14.46 0.45 0.75 4.88 cum
U/S curtain wall 3rd footing 1 14.46 0.20 0.45 1.30 cum
D/S curtain wall 1st footing 1 22.74 1.65 0.55 20.64 cum
D/S curtain wall 2nd footing 1 22.74 0.75 0.75 12.79 cum
D/S curtain wall 3rd footing 1 22.74 0.45 0.75 7.67 cum
D/S curtain wall 4th footing 1 22.74 0.20 0.45 2.05 cum
Total Qty. for 1 No. 64.37 Cum
Qty. for 1Nos. 64.37 Cum 4,361.20 280,730.44
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical
Box PortionSpecifications.
For Raft 1 15.000 12.580 0.500 94.35 cum
Key 2 12.580 0.650 0.700 11.45 cum
Return wall , 1st footing 4 3.85 3.15 0.30 14.55 cum
2nd footing 4 3.85 1.85 0.20 5.70 cum
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
Total Qty. for 1 No. 126.05 Cum
Qty. for 1Nos. 126.05 Cum 5,099.20 642,754.16
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical
For Walls Specifications. 4 15.000 0.470 2.000 56.400 cum
Middle wall 2 15.000 0.400 2.000 24.000 cum
For Hunch (3x4x1/2) 6 15.000 0.150 0.150 2.030 cum
Return wall stem, 1st lift 4 3.85 0.43 0.83 5.50 cum
2nd lift 4 3.85 0.30 2.40 11.09 cum
Total Qty. for 1 No. 99.020 Cum
Qty. for 1Nos. 99.020 Cum 5,099.20 504,922.78
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical
For Slab Specifications. 1 15.000 11.680 0.450 78.840 Cum
Kerb wall 2 11.680 0.450 0.300 3.150 Cum
Total Qty. for 1 No. 81.990 Cum
Qty. for 1Nos. 81.990 Cum 5550.6 455,093.69
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement
Foundation (80inKg/cum)
super-structure complete as per80drawing and
x technical
126.050specifications
10084.000 Kg
Substructure (80 Kg/cum) 80 x 99.020 7921.600 Kg
Supestructure (80 Kg/cum) 80 x 81.990 6559.200 Kg
Weraing coat 75 x 12.180 913.500 Kg
25478.300 Kg
Total Qty. for 1 No. 25.480 MT
Qty. for 1Nos. 25.480 MT 57402.50 1,462,615.70
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements laid
down
behindinwalls
clause 2504.2.2. of MoRTH specifications
2 to a thickness
14.400 0.600 of not less than 600 mm
2.000 withCum
34.560
behind return walls 4 3.250 0.300 2.730 10.650 Cum
Total Qty. for 1 No. 45.210 Cum
Qty. for 1Nos. 45.210 Cum 1,920.90 86,843.89
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line
and
Qty. grade, tolerance of vertical RCC 2post not11.680
for 1 No. to exceed 1 in 500, centre to centre spacing between
23.360 Rm
Qty. for 1Nos. 23.360 Rm 1481.50 34,607.84
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
No. of No. of hole no. of Length of
Total
wall in a row rows each hole
In wall of box 2 15 3 0.47 41.74 Rm
Return wall 4 4 4 0.43 27.52 Rm
Total Qty. for 1 No. 69.26 Rm
Qty. for 1Nos. 69.26 Rm 162.10 11,227.05
Breadt
S No Description Nos Length (L) Height (H) Quantity Unit rate amount
h (B)
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete
as per drawing and Technical Specifications.
1 (including cost of steel)0.075
11.68 13.900 12.18 Cum
Total Qty. for 1 No. 12.18 Cum
Qty. for 1Nos. 12.18 Cum 5170.00 62,970.60
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 9.84
Length at end = 13.69
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 9.84
Length at end of trapzoidal section = 16.44
Width of trapezoidal section = 3.30
Width of rectangular section = 2.70
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent
required and utilising the remaining earth locally for road work.
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the Engineer-in-charge including cost, conveyance, royality
taxes of all materials conforming to the MORTH techanical specification.
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 13.69 1.30 0.80 14.24 cum
U/S curtain wall 2nd footing 1 13.69 0.45 0.75 4.62 cum
U/S curtain wall 3rd footing 1 13.69 0.20 0.45 1.23 cum
D/S curtain wall 1st footing 1 21.84 1.65 0.55 19.82 cum
D/S curtain wall 2nd footing 1 21.84 0.75 0.75 12.29 cum
D/S curtain wall 3rd footing 1 21.84 0.45 0.75 7.37 cum
D/S curtain wall 4th footing 1 21.84 0.20 0.45 1.97 cum
Total Qty. for 1 No. 61.54 Cum
Qty. for 1Nos. 61.54 Cum 4,361.20 268,388.25
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical Specifications.
Box Portion
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
For Raft 1 15.000 12.480 0.420 78.62 cum
Key 2 12.480 0.690 0.780 13.43 cum
Return wall , 1st footing 4 3.80 3.15 0.30 14.36 cum
2nd footing 4 3.80 1.78 0.15 4.06 cum
Total Qty. for 1 No. 110.47 Cum
Qty. for 1Nos. 110.47 Cum 4,828.40 533,393.35
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 4 15.000 0.420 2.000 50.400 cum
For Hunch (3x4x1/2) 6 15.000 0.150 0.150 2.030 cum
Return wall stem, 1st lift 4 3.80 0.36 0.85 4.65 cum
2nd lift 4 3.80 0.30 2.40 10.94 cum
Total Qty. for 1 No. 68.020 Cum
Qty. for 1Nos. 68.020 Cum 5,099.20 346,847.58
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 15.000 10.680 0.420 67.280 Cum
Kerb wall 2 10.680 0.450 0.300 2.880 Cum
Total Qty. for 1 No. 70.160 Cum
Qty. for 1Nos. 70.160 Cum 5550.6 389,430.10
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement in super-structure complete as per drawing and technical specifications
10
Gravel backing to revetment
4 1/4 41.12 0.15 6.17 cum
For 1No 6.17 cum
Qty. for 1Nos. 6.170 cum 820.70 5,063.72
11 Boulder Appron
Revetment 4 1/4 41.12 0.3 12.34 cum
Boulder appron at u/s 1 11.77 3.00 0.3 10.59 cum
Boulder appron at d/s 1 13.14 3.30 0.3 13.01 cum
Boulder appron d/s 13.32 cum
rectangular portion 1 16.44 2.70 0.3
For 1No 49.26 cum
Qty. for 1Nos. 49.260 cum 1,300.50 64,062.63
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :
20H towards drawing foce. Complete as per drawing and Technical Specifications.
Length
No. of No. of hole no. of
of each Total
wall in a row rows
hole
In wall of box 2 15 3 0.42 37.30 Rm
Return wall 4 4 4 0.36 23.04 Rm
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical
1 Specifications. (including0.075
10.68 13.900 cost of steel) 11.13 Cum
Total Qty. for 1 No. 11.13 Cum
Qty. for 1Nos. 11.13 Cum 5170.00 57,542.10
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved
drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all
materials conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 6.640 1.400 0.150 2.79
b) Pipe 1 15.40 1.840 0.520 14.73
deduction -1 15.40 0.290 -4.47
Total Qty. for 1 No. Cum 13.05
Qty. for 5Nos. Cum 65.250 4,121.40 268,921.35
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 6.640 0.830 2.670 29.43
Parapet wall 2 6.640 0.400 0.400 2.12
deduction 2 0.820 1.630 -2.67
Total Qty. for 1 No. Cum 28.88
Qty. for 5Nos. Cum 144.400 4,605.03 664,966.33
5 Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete an
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications .
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved
drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all
materials conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 8.600 1.400 0.150 3.61
b) Pipe 1 15.42 3.800 0.520 30.47
deduction -2 15.42 0.290 -8.94
Total Qty. for 1 No. Cum 25.14
Qty. for 1Nos. Cum 25.140 4,121.40 103,612.00
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 8.600 0.830 2.650 37.83
Parapet wall 2 8.600 0.400 0.400 2.75
deduction 4 0.820 1.540 -5.05
Total Qty. for 1 No. Cum 35.53
Qty. for 1Nos. Cum 35.530 4,605.03 163,616.72
5 Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry works in head walls
and parapets .
1200mm dia pipe 2.00 17.50 35.00
Total Qty. for 1 No. Rm 35.00
Qty. for 1Nos. Rm 35.000 12,988.70 454,604.50
Length Breadth
S No Description Nos Height (H) Unit Quantity Rate Amount
(L) (B)
6
Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
U/S 2 4.170 0.150 1.25
D/S 2 6.400 0.150 1.92
Total Qty. for 1 No. Cum 3.17
Qty. for 1Nos. Cum 3.170 820.70 2,601.62
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications .
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved
drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all
materials conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 6.640 1.400 0.150 2.79
b) Pipe 1 2.90 1.840 0.520 2.77
deduction -1 2.90 0.290 -0.84
Total Qty. for 1 No. Cum 4.72
Qty. for 2Nos. Cum 9.440 4,121.40 38,906.02
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 6.640 0.830 2.670 29.43
Parapet wall 2 6.640 0.400 0.400 2.12
deduction 2 0.820 1.630 -2.67
Total Qty. for 1 No. Cum 28.88
Qty. for 2Nos. Cum 57.760 4,605.03 265,986.53
5 Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete an
6 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
U/S 2 4.330 0.150 1.30
D/S 2 6.590 0.150 1.98
Total Qty. for 1 No. Cum 3.28
Qty. for 2Nos. Cum 6.560 820.70 5,383.79
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications .
Junior Engineer
Junior Engineer Phulbani R&B Executive Engineer
Asst. Executive Engineer
NH. Section, Boriguma Section North. NH.Division Jeypore
NH. Sub Division Boriguma.
Pipe Culvert 2 x 1.2m dia widening
Length Breadth
S No Description Nos Height (H) Unit Quantity Rate Amount
(L) (B)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent
required and utilising the remaining earth locally for road work.
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved
drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all
materials conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 8.680 1.400 0.150 3.65
b) Pipe 1 2.90 3.880 0.520 5.85
deduction -2 2.90 0.290 -1.68
Total Qty. for 1 No. Cum 7.82
Qty. for 1Nos. Cum 7.820 4,121.40 32,229.35
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 8.680 0.830 2.670 38.47
Parapet wall 2 8.680 0.400 0.400 2.78
deduction 4 0.820 1.630 -5.35
Total Qty. for 1 No. Cum 35.90
Qty. for 1Nos. Cum 35.900 4,605.03 165,320.58
5 Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete an
6 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
U/S 2 4.330 0.150 1.30
D/S 2 6.590 0.150 1.98
Total Qty. for 1 No. Cum 3.28
Qty. for 1Nos. Cum 3.280 820.70 2,691.90
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications .
Junior Engineer
Phulbani R&B
Section North.
#VALUE!
Total No. of Box culvert 2 Note : This culvert is without approach slab and as per Plate 15 of SP
13:2004
Length 15
Box Detail
No. of span 1
Each Span Width 3
Total length, a 3.00
Height, b 3.00
Offset, c 0.90
Deck Slab, d 0.42
Raft, e 0.42
Wall(s), f 0.42
Depth of Key, Dk 1.20
Height from GL to FRL of culvert= 3.20
Return Wall
Length= 5.30 h3 = 2.40
Height, Hmax= 4.70 h4 = 1.50
Width, W= 4.23 b1 = 2.68
h1= 0.30 b2 = 0.55
h2= 0.20 b3 = 1.00
PCC thickness = 0.10
Revetment
Radius of revetment = 4.80
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 3.00
Length at end = 5.11
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 3.00
Length at end of trapzoidal section = 12.60
Width of trapezoidal section = 4.80
Width of rectangular section = 1.20
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent
required and utilising the remaining earth locally for road work.
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the Engineer-in-charge including cost, conveyance, royality
taxes of all materials conforming to the MORTH techanical specification.
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 5.11 1.30 0.80 5.31 cum
U/S curtain wall 2nd footing 1 5.11 0.45 0.75 1.72 cum
U/S curtain wall 3rd footing 1 5.11 0.20 0.45 0.46 cum
D/S curtain wall 1st footing 1 15.00 1.65 0.55 13.61 cum
D/S curtain wall 2nd footing 1 15.00 0.75 0.75 8.44 cum
D/S curtain wall 3rd footing 1 15.00 0.45 0.75 5.06 cum
D/S curtain wall 4th footing 1 15.00 0.20 0.45 1.35 cum
Total Qty. for 1 No. 35.95 Cum
Qty. for 2Nos. 71.90 Cum 4,361.20 313,570.28
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical Specifications.
Box Portion
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
For Raft 1 15.000 5.640 0.420 35.53 cum
Key 2 5.640 0.690 0.780 6.07 cum
Return wall , 1st footing 4 5.30 4.23 0.30 26.90 cum
2nd footing 4 5.30 2.39 0.20 10.13 cum
Total Qty. for 1 No. 78.63 Cum
Qty. for 2Nos. 157.26 Cum 4,828.40 759,314.18
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 2 15.000 0.420 3.000 37.800 cum
For Hunch (1x4x1/2) 2 15.000 0.150 0.150 0.680 cum
Return wall stem, 1st lift 4 5.30 0.43 1.80 16.41 cum
2nd lift 4 5.30 0.30 2.40 15.26 cum
Total Qty. for 1 No. 70.150 Cum
Qty. for 2Nos. 140.300 Cum 5,099.20 715,417.76
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 15.000 3.840 0.420 24.190 Cum
Kerb wall 2 3.840 0.450 0.300 1.040 Cum
Total Qty. for 1 No. 25.230 Cum
Qty. for 2Nos. 50.460 Cum 5550.6 280,083.28
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement in super-structure complete as per drawing and technical specifications
10
Gravel backing to revetment
4 1/4 86.99 0.15 13.05 cum
For 1No 13.05 cum
Qty. for 2Nos. 26.100 cum 820.70 21,420.27
11 Boulder Appron
Revetment 4 1/4 86.99 0.3 26.10 cum
Boulder appron at u/s 1 4.06 3.00 0.3 3.65 cum
Boulder appron at d/s 1 7.80 4.80 0.3 11.23 cum
Boulder appron d/s 4.54 cum
rectangular portion 1 12.60 1.20 0.3
For 1No 45.52 cum
Qty. for 2Nos. 91.040 cum 1,300.50 118,397.52
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :
20H towards drawing foce. Complete as per drawing and Technical Specifications.
Length
No. of No. of hole no. of
of each Total
wall in a row rows
hole
In wall of box 2 15 4 0.42 49.73 Rm
Return wall 4 6 5 0.43 51.60 Rm
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical
1 Specifications.
3.84 (including0.075
13.900 cost of steel) 4.00 Cum
Total Qty. for 1 No. 4.00 Cum
Qty. for 2Nos. 8.00 Cum 5170.00 41,360.00
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 5.04
Length at end = 8.98
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 5.04
Length at end of trapzoidal section = 11.58
Width of trapezoidal section = 3.27
Width of rectangular section = 2.73
#VALUE!
S Breadt Height
Description Nos Length (L) Quantity Unit rate amount
No h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes
of all materials conforming to the MORTH techanical specificat
For Base slab 1 12.800 6.580 0.150 12.63 cum
For Key 2 6.580 1.430 0.150 2.82 cum
Return wall 4 3.77 3.35 0.100 5.05 cum
Up stream curtain wall 1 8.98 1.50 0.150 2.02 cum
Down stream curtain wall, 1 17.04 1.85 0.150 4.73 cum
Total Qty. for 1 No. 27.25 Cum
Qty. for 0Nos. 0.00 Cum 4,121.40 -
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and Technical
Specifications.
U/S curtain wall 1st footing 1 8.98 1.30 0.80 9.34 cum
U/S curtain wall 2nd footing 1 8.98 0.45 0.75 3.03 cum
U/S curtain wall 3rd footing 1 8.98 0.20 0.45 0.81 cum
D/S curtain wall 1st footing 1 17.04 1.65 0.55 15.46 cum
D/S curtain wall 2nd footing 1 17.04 0.75 0.75 9.59 cum
D/S curtain wall 3rd footing 1 17.04 0.45 0.75 5.75 cum
S Breadt Height
Description Nos Length (L) Quantity Unit rate amount
No h (B) (H)
D/S curtain wall 4th footing 1 17.04 0.20 0.45 1.53 cum
Total Qty. for 1 No. 45.51 Cum
Qty. for 0Nos. 0.00 Cum 4,361.20 -
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and Technical
Specifications.
Box Portion
For Raft 1 15.000 6.380 0.400 38.28 cum
Key 2 6.380 0.700 0.800 7.15 cum
Return wall , 1st footing 4 3.77 3.15 0.30 14.25 cum
2nd footing 4 3.77 1.78 0.15 4.03 cum
Total Qty. for 1 No. 63.71 Cum
Qty. for 0Nos. 0.00 Cum 4,828.40 -
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 3 15.000 0.370 2.000 33.300 cum
Middle wall 1 15.000 0.300 2.000 9.000 cum
For Hunch (2x4x1/2) 4 15.000 0.150 0.150 1.350 cum
Return wall stem, 1st lift 4 3.77 0.36 0.83 4.51 cum
2nd lift 4 3.77 0.30 2.40 10.86 cum
Total Qty. for 1 No. 59.020 Cum
Qty. for 0Nos. 0.000 Cum 5,099.20 -
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 15.000 5.780 0.400 34.680 Cum
Kerb wall 2 5.780 0.450 0.300 1.560 Cum
Total Qty. for 1 No. 36.240 Cum
Qty. for 0Nos. 0.000 Cum 5550.6 -
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement in super-structure complete as per drawing and technical specifications
Foundation (80 Kg/cum) @ 80 x 63.710 5096.800 Kg
Substructure (80 Kg/cum) @ 80 x 59.020 4721.600 Kg
Supestructure (80 Kg/cum) @ 80 x 36.240 2899.200 Kg
Weraing coat @ 75 x 0.000 0.000 Kg
12717.600 Kg
Total Qty. for 1 No. 12.720 MT
Qty. for 0Nos. 0.000 MT 57402.50 -
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements laid
down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
towards drawing foce. Complete as per drawing and Technical Specifications.
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as
per drawing and Technical Specifications. (excluding cost of steel)
1 5.78 13.900 0.075 6.03 Cum
Total Qty. for 1 No. 6.03 Cum
Qty. for 0Nos. 0.00 Cum 5170.00 -
Total cost -
#VALUE!
Total No. of Box culvert 1 Note : This culvert is without approach slab and as per Plate 15 of SP13:2004
Length 15
Box Detail
No. of span 2
Each Span Width 3
Total length, a 7.10
Height, b 2.00
Offset, c 0.30
Deck Slab, d 0.45
Raft, e 0.45
Wall(s), f 0.40
Moddle Wall(s), g 0.30
Depth of Key, Dk 1.20
Height from GL to FRL of culvert= 2.23
Return Wall
Length= 3.85 h3 = 2.40
Height, Hmax= 3.73 h4 = 1.50
Width, W= 3.15 b1 = 2.04
h1= 0.30 b2 = 0.41
h2= 0.150 b3 = 0.70
PCC thickness = 0.10
Revetment
Radius of revetment = 3.35
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 7.10
Length at end = 10.82
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 7.10
Length at end of trapzoidal section = 13.80
Width of trapezoidal section = 3.35
Width of rectangular section = 2.65
#VALUE!
S Breadt Height
Description Nos Length (L) Quantity Unit rate amount
No h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes
of all materials conforming to the MORTH techanical specificat
For Base slab 1 12.900 8.700 0.150 16.83 cum
For Key 2 8.700 1.360 0.150 3.55 cum
Return wall 4 3.85 3.35 0.100 5.16 cum
Up stream curtain wall 1 10.82 1.50 0.150 2.43 cum
Down stream curtain wall, 1 19.10 1.85 0.150 5.30 cum
Total Qty. for 1 No. 33.27 Cum
Qty. for 1Nos. 33.27 Cum 4,121.40 137,118.98
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and Technical
Specifications.
U/S curtain wall 1st footing 1 10.82 1.30 0.80 11.25 cum
U/S curtain wall 2nd footing 1 10.82 0.45 0.75 3.65 cum
U/S curtain wall 3rd footing 1 10.82 0.20 0.45 0.97 cum
D/S curtain wall 1st footing 1 19.10 1.65 0.55 17.33 cum
D/S curtain wall 2nd footing 1 19.10 0.75 0.75 10.74 cum
D/S curtain wall 3rd footing 1 19.10 0.45 0.75 6.45 cum
S Breadt Height
Description Nos Length (L) Quantity Unit rate amount
No h (B) (H)
D/S curtain wall 4th footing 1 19.10 0.20 0.45 1.72 cum
Total Qty. for 1 No. 52.11 Cum
Qty. for 1Nos. 52.11 Cum 4,361.20 227,262.13
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and Technical
Specifications.
Box Portion
For Raft 1 15.000 8.500 0.450 57.38 cum
Key 2 8.500 0.680 0.750 8.67 cum
Return wall , 1st footing 4 3.85 3.15 0.30 14.55 cum
2nd footing 4 3.85 1.78 0.15 4.11 cum
Total Qty. for 1 No. 84.71 Cum
Qty. for 1Nos. 84.71 Cum 4,828.40 409,013.76
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 3 15.000 0.400 2.000 36.000 cum
Middle wall 1 15.000 0.300 2.000 9.000 cum
For Hunch (2x4x1/2) 4 15.000 0.150 0.150 1.350 cum
Return wall stem, 1st lift 4 3.85 0.36 0.88 4.88 cum
2nd lift 4 3.85 0.30 2.40 11.09 cum
Total Qty. for 1 No. 62.320 Cum
Qty. for 1Nos. 62.320 Cum 5,099.20 317,782.14
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 15.000 7.900 0.450 53.330 Cum
Kerb wall 2 7.900 0.450 0.300 2.130 Cum
Total Qty. for 1 No. 55.460 Cum
Qty. for 1Nos. 55.460 Cum 5550.6 307,836.28
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement in super-structure complete as per drawing and technical specifications
Foundation (80 Kg/cum) @ 80 x 84.710 6776.800 Kg
Substructure (80 Kg/cum) @ 80 x 62.320 4985.600 Kg
Supestructure (80 Kg/cum) @ 80 x 55.460 4436.800 Kg
Weraing coat @ 75 x 8.240 618.000 Kg
16817.200 Kg
Total Qty. for 1 No. 16.820 MT
Qty. for 1Nos. 16.820 MT 57402.50 965,510.05
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements laid
down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
towards drawing foce. Complete as per drawing and Technical Specifications.
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as
per drawing and Technical Specifications. (excluding cost of steel)
1 7.90 13.900 0.075 8.24 Cum
Total Qty. for 1 No. 8.24 Cum
Qty. for 1Nos. 8.24 Cum 5170.00 42,600.80
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 18.50
Length at end = 19.88
Width of trapezoidal section = 3.00
Width of rectangular section = 0.00
D/S
Total width of floor apron = 6.00
Length near culvert = 18.50
Length at end of trapzoidal section = 25.55
Width of trapezoidal section = 6.00
Width of rectangular section = 0.00
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes
of all materials conforming to the MORTH techanical specificat
For Base slab 1 6.800 21.200 0.150 21.62 cum
For Key 2 21.200 0.720 0.150 4.58 cum
Return wall 4 7.37 5.30 0.100 15.62 cum
Up stream curtain wall 1 19.88 1.50 0.150 4.47 cum
Down stream curtain wall, 1 25.55 1.85 0.150 7.09 cum
Total Qty. for 1 No. 53.38 Cum
Qty. for 1Nos. 53.38 Cum 4,121.40 220,000.33
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and Technical
Specifications.
U/S curtain wall 1st footing 1 19.88 1.30 0.80 20.68 cum
U/S curtain wall 2nd footing 1 19.88 0.45 0.75 6.71 cum
U/S curtain wall 3rd footing 1 19.88 0.20 0.45 1.79 cum
D/S curtain wall 1st footing 1 25.55 1.65 0.55 23.19 cum
D/S curtain wall 2nd footing 1 25.55 0.75 0.75 14.37 cum
D/S curtain wall 3rd footing 1 25.55 0.45 0.75 8.62 cum
S Breadt Height
Description Nos Length (L) Quantity Unit rate amount
No h (B) (H)
D/S curtain wall 4th footing 1 25.55 0.20 0.45 2.30 cum
Total Qty. for 1 No. 77.66 Cum
Qty. for 1Nos. 77.66 Cum 4,361.20 338,690.79
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and Technical
Specifications.
Box Portion
For Raft 1 8.000 21.000 0.950 159.60 cum
Key 2 21.000 0.450 0.300 5.67 cum
Return wall , 1st footing 4 7.37 5.10 0.30 45.10 cum
2nd footing 4 7.37 2.95 0.33 28.70 cum
Total Qty. for 1 No. 239.07 Cum
Qty. for 1Nos. 239.07 Cum 4,828.40 1,154,325.59
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 3 8.000 0.950 4.000 91.200 cum
Middle wall 1 8.000 0.600 4.000 19.200 cum
For Hunch (2x4x1/2) 4 8.000 0.150 0.150 0.720 cum
Return wall stem, 1st lift 4 7.37 0.55 3.56 57.72 cum
2nd lift 4 7.37 0.30 2.40 21.23 cum
Total Qty. for 1 No. 190.070 Cum
Qty. for 1Nos. 190.070 Cum 5,099.20 969,204.94
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 8.000 20.400 0.800 130.560 Cum
Kerb wall 2 20.400 0.450 0.300 5.510 Cum
Total Qty. for 1 No. 136.070 Cum
Qty. for 1Nos. 136.070 Cum 5550.6 755,270.14
7 HYSD / MORT&H Technical Specification no- 1600Supplying, fitting and placing HYSD bar
reinforcement in super-structure complete as per drawing and technical specifications
Foundation (80 Kg/cum) @ 80 x 239.070 19125.600 Kg
Substructure (80 Kg/cum) @ 80 x 190.070 15205.600 Kg
Supestructure (80 Kg/cum) @ 80 x 136.070 10885.600 Kg
Weraing coat @ 75 x 10.560 792.000 Kg
46008.800 Kg
Total Qty. for 1 No. 46.010 MT
Qty. for 1Nos. 46.010 MT 57402.50 2,641,089.03
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements laid
down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
towards drawing foce. Complete as per drawing and Technical Specifications.
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as
per drawing and Technical Specifications. (excluding cost of steel)
1 20.40 6.900 0.075 10.56 Cum
Total Qty. for 1 No. 10.56 Cum
Qty. for 1Nos. 10.56 Cum 5170.00 54,595.20
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved drawing
and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all materials
conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 6.430 1.400 0.150 2.70
b) Pipe 1 2.94 1.630 0.520 2.49
deduction -1 2.94 0.290 -0.85
Total Qty. for 1 No. Cum 4.34
Qty. for 1Nos. Cum 4.340 4,121.40 17,886.88
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 6.430 0.830 2.470 26.36
Parapet wall 2 6.430 0.400 0.400 2.06
deduction 2 0.820 1.190 -1.95
Total Qty. for 1 No. Cum 26.47
Qty. for 1Nos. Cum 26.470 4,605.03 121,895.14
5 Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete an
1000mm dia pipe 1.00 5.00 5.00
Total Qty. for 1 No. Rm 5.00
Qty. for 1Nos. Rm 5.000 10,342.60 51,713.00
Length Breadth
S No Description Nos Height (H) Unit Quantity Rate Amount
(L) (B)
6 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification.
U/S 2 2.880 0.150 0.86
D/S 2 4.770 0.150 1.43
Total Qty. for 1 No. Cum 2.29
Qty. for 1Nos. Cum 2.290 820.70 1,879.40
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid
dry in front of toe of embankment complete as per drawing and Technical specifications .
Floor Apron
U/S
Total width of floor apron = 3.00
Length near culvert = 1.40
Length at end = 6.30
Width of trapezoidal section = 2.45
Width of rectangular section = 0.55
D/S
Total width of floor apron = 6.00
Length near culvert = 1.40
Length at end of trapzoidal section = 6.30
Width of trapezoidal section = 2.45
Width of rectangular section = 3.55
#VALUE!
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent
required and utilising the remaining earth locally for road work.
2 Cement concrete M 15 Levelling coarse with 40 mm size C.B. Metal of approved quality as per
approved drawing and direction of the Engineer-in-charge including cost, conveyance, royality
taxes of all materials conforming to the MORTH techanical specification
3 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
U/S curtain wall 1st footing 1 7.40 1.30 0.80 7.70 cum
U/S curtain wall 2nd footing 1 7.40 0.45 0.75 2.50 cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
U/S curtain wall 3rd footing 1 7.40 0.20 0.45 0.67 cum
D/S curtain wall 1st footing 1 13.40 1.65 0.55 12.16 cum
D/S curtain wall 2nd footing 1 13.40 0.75 0.75 7.54 cum
D/S curtain wall 3rd footing 1 13.40 0.45 0.75 4.52 cum
D/S curtain wall 4th footing 1 13.40 0.20 0.45 1.21 cum
Total Qty. for 1 No. 36.30 Cum
Qty. for 1Nos. 36.30 Cum 4,361.20 158,311.56
4 RCC M20 grade Reinforced Cement Concrete in Foundation complete as per Drawing and
Technical Specifications.
Box Portion
For Raft 1 5.000 3.000 0.380 5.70 cum
Key 2 3.000 0.710 0.820 3.49 cum
Return wall , 1st footing 4 2.95 2.65 0.30 9.38 cum
2nd footing 4 2.95 1.48 0.00 0.00 cum
Total Qty. for 1 No. 18.57 Cum
Qty. for 1Nos. 18.57 Cum 4,828.40 89,663.39
5 RCC M20 grade Reinforced Cement Concrete in sub-structure complete as per Drawing and
Technical Specifications.
For Walls 2 5.000 0.300 1.500 4.500 cum
For Hunch (1x4x1/2) 2 5.000 0.150 0.150 0.230 cum
Return wall stem, 1st lift 4 2.95 0.30 -0.37 -1.31 cum
2nd lift 4 2.95 0.30 2.70 9.56 cum
Total Qty. for 1 No. 12.980 Cum
Qty. for 1Nos. 12.980 Cum 5,099.20 66,187.62
6 RCC M20 grade Reinforced Cement Concrete in super-structure complete as per Drawing and
Technical Specifications.
For Slab 1 5.000 2.000 0.350 3.500 Cum
Kerb wall 2 2.000 0.450 0.300 0.540 Cum
Total Qty. for 1 No. 4.040 Cum
Qty. for 1Nos. 4.040 Cum 5550.6 22,424.42
7 Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
drawing and technical specifications MORT&H Technical Specification no- 1600
Foundation (80 Kg/cum) 80 x 18.570 1485.600 Kg
Substructure (80 Kg/cum) 80 x 12.980 1038.400 Kg
Supestructure (80 Kg/cum) 80 x 4.040 323.200 Kg
Weraing coat 75 x 0.590 44.250 Kg
2891.450 Kg
Total Qty. for 1 No. 2.890 MT
Qty. for 1Nos. 2.890 MT 57402.50 165,893.23
8 Providing and laying of Filter media with stone crushed aggregates satisfying the requirements
laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size towards the wall
behind walls 2 4.400 0.600 1.500 7.920 Cum
behind return walls 4 2.350 0.300 1.830 5.160 Cum
Total Qty. for 1 No. 13.080 Cum
Breadt Height
S No Description Nos Length (L) Quantity Unit rate amount
h (B) (H)
Qty. for 1Nos. 13.080 Cum 1,920.90 25,125.37
9 Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm, leaving adequate space
Qty. for 1 No. 2 2.000 4.000 Rm
Qty. for 1Nos. 4.000 Rm 1481.50 5,926.00
10
Gravel backing to revetment
4 1/4 22.65 0.15 3.40 cum
For 1No 3.40 cum
Qty. for 1Nos. 3.400 cum 820.70 2,790.38
11 Boulder Appron
Revetment 4 1/4 22.65 0.3 6.80 cum
Boulder appron at u/s 1 3.85 3.00 0.3 3.47 cum
Boulder appron at d/s 1 3.85 2.45 0.3 2.83 cum
Boulder appron d/s 6.71 cum
rectangular portion 1 6.30 3.55 0.3
For 1No 19.81 cum
Qty. for 1Nos. 19.810 cum 1,300.50 25,762.91
12 Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :
20H towards drawing foce. Complete as per drawing and Technical Specifications.
Length
No. of No. of hole no. of
of each Total
wall in a row rows
hole
13 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical Specifications. (including cost of steel)
1 2.00 3.900 0.075 0.59 Cum
Total Qty. for 1 No. 0.59 Cum
Qty. for 1Nos. 0.59 Cum 5170.00 3,050.30
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved drawing
and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all materials
conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 6.430 1.400 0.150 2.70
b) Pipe 1 12.94 1.630 0.520 10.97
deduction -1 12.94 0.290 -3.75
Total Qty. for 1 No. Cum 9.92
Qty. for 2Nos. Cum 19.840 4,121.40 81,768.58
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 6.430 0.830 2.470 26.36
Parapet wall 2 6.430 0.400 0.400 2.06
deduction 2 0.820 1.190 -1.95
Total Qty. for 1 No. Cum 26.47
Qty. for 2Nos. Cum 52.940 4,605.03 243,790.29
5 Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete an
6 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid
dry in front of toe of embankment complete as per drawing and Technical specifications .
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved
drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all
materials conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 8.680 1.400 0.150 3.65
b) Pipe 1 12.90 3.880 0.520 26.03
deduction -2 12.90 0.290 -7.48
Total Qty. for 1 No. Cum 22.20
Qty. for 1Nos. Cum 22.200 4,121.40 91,495.08
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 8.680 0.830 2.670 38.47
Parapet wall 2 8.680 0.400 0.400 2.78
deduction 4 0.820 1.630 -5.35
Total Qty. for 1 No. Cum 35.90
Qty. for 1Nos. Cum 35.900 4,605.03 165,320.58
5 Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete an
1200mm dia pipe 2.00 15.00 30.00
Total Qty. for 1 No. Rm 30.00
Qty. for 1Nos. Rm 30.000 12,988.70 389,661.00
Length Breadth
S No Description Nos Height (H) Unit Quantity Rate Amount
(L) (B)
6 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
U/S 2 4.330 0.150 1.30
D/S 2 6.590 0.150 1.98
Total Qty. for 1 No. Cum 3.28
Qty. for 1Nos. Cum 3.280 820.70 2,691.90
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications .
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved
drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all
materials conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 6.400 1.400 0.150 2.69
b) Pipe 1 5.45 1.600 0.520 4.53
deduction -1 5.45 0.290 -1.58
Total Qty. for 1 No. Cum 5.64
Qty. for 2Nos. Cum 11.280 4,121.40 46,489.39
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 6.400 0.830 2.450 26.03
Parapet wall 2 6.400 0.400 0.400 2.05
deduction 2 0.820 1.130 -1.85
Total Qty. for 1 No. Cum 26.23
Qty. for 2Nos. Cum 52.460 4,605.03 241,579.87
5 Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete an
6 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications .
Profile
1 94637 95/1 SLAB 0.4 1X3.0X2.4 7.2 11.5 BAD 11.9 Box 1/45/0
correction
3 95110 96/1 SLAB 0.3 1x2.5x1.75 7.2 11.5 GOOD 10.4 RETAIN
Alignment
5 95696 96/3 BOX 0.85 1X6.3X6.0 7.4 11.5 GOOD 8.1 Box Widening 2.5m
Correction
8 96547 97/2 SLAB 0.35 1X2.4X1.6 7.1 11.1 GOOD 10.7 RETAIN
Profile
10 97008 98/1 SLAB 1 X 2.1 X 1.75 11.4 Box 1/33/0
correction
Profile
11 97737 98/2 SLAB 0.4 1X3.0X2.2 7.2 10.8 GOOD 11.2 Box 1/33/0
correction
14 98687 99/3 SLAB 0.3 1x1.6x1.0 7.4 10.4 GOOD 2.65 RETAIN
15 98956 99/4 SLAB 0.35 1x1.4x1.5 7.1 11.4 GOOD 9.0 RETAIN
16 99459 100/1 SLAB 0.4 1X1.45X0.75 6.9 11.2 GOOD 2.4 RETAIN
Due to Bad
26 103231 104/2 HP BLOCK 7 11.3 BAD HP 1x1.0
Condition
Profile
30 103777 104/6 SLAB 0.45 1X1.5X0.4 7 11.1 BAD 9 Box 1/22/0
correction
Profile
32 104043 105/1 SLAB 0.4 1X1.5X1.2 7 11.0 GOOD 9.1 Box 1/22/0
correction
Insufficient
46 108116 109/2 SLAB 0.5 1X1.5X1.0 7 9.1 F 6.7 Slab Widening 2.0m formation
width
Due to Bad
53 109321 110/3 SLAB 2X4.0X2.5 7 10.0 BAD BOX 3/33/0
Condition
In Existing
ARCH stretch against
55 111173 112/1 1 1X3.7X2.2 8 9.7 GOOD 39.1 RETAIN
CULVERT Realignment
portion
Realignment
56 111180 New Box 1/66/0
portion
Alignment
57 111483 112/2 SLAB 0.3 1X1.5X1.3 7 11.2 F Box 1/22/0
Correction
In Existing
stretch against
58 111583 112/3 SLAB 0.4 1X1.6X0.9 7 11.1 F 9 RETAIN
Realignment
portion
Realignment
59 111585 New BOX 1/22/0
portion
Alignment
60 111659 112/4 SLAB 0.4 1X1.5X1.1 7 11.0 F 9 Slab Widening 5m
Correction
Alignment
61 112057 113/1 SLAB 0.6 1X1.5X1.3 7 11.0 F 9 Slab Widening 2.5m
Correction
Due to Bad
65 113379 114/3 SLAB 0.3 1X1.4X1.3 7 11.1 BAD BOX 1/22/0
Condition
Alignment
69 116466 117/3 HP 1x1.0 16.0 HP Widening 5.0m
Correction
G = Good P = Poor
CD Schedule
CD Name Span Nos
Box 1/22/0 7
Box 1/23/0 1
Box 1/33/0 2
Box 1/34/0 1
Box 1/45/0 1
Box 1/63/0 1
Box 1/66/0 1
Box 2/65/0 1
Box 3/33/0 1
Box Widening
1/66/0 2
4.5m
HP 1x1.2 3
HP Widening
1x1.0 2
7.5m
Slab 1x2.5x2 3
Slab Widening
1x2.5x1.5 5
2.0m
Slab Widening
1x2.5x2.0 6
2.0m
Slab Widening
1x2.5x2.5 12
2.0m
Slab Widening
1x2.5x3 1
2.0m
Slab Widening
1x2.5x4 1
2.0m
Slab Widening
1x3x2.5 1
2.0m
Slab Widening
1x3x3 1
2.0m
Slab Widening
1x3.5x2.5 1
2.0m
Slab Widening
1x3.5x4 1
2.0m
Slab Widening
1x4x2 3
2.0m
Slab Widening
1x4x2.5 1
2.0m
Slab Widening
1x4x3 1
2.0m
Slab Widening
1x6x3 1
2.0m
Slab Widening
1x7x3 1
2.0m
Slab Widening
1x8x2.5 1
2.0m
Slab Widening
1x8x4 1
2.0m
Retain 13
Subudhi Associates
Total Nos of CD 77
17
Pipe Culvert 2 x 1.2m dia
Length Breadth
S No Description Nos Height (H) Unit Quantity Rate Amount
(L) (B)
1 Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with approved material.
Excavation for Structures / MORT&H Technical Specification no- 304
3 Cement concrete (M-15) with 40 mm size C.B. Metal of approved quality as per approved
drawing and direction of the Engineer-in-charge including cost, conveyance, royality taxes of all
materials conforming to the MORTH techanical specification.
Levelling course
a) Head wall 2 8.600 1.400 0.150 3.61
b) Pipe 1 2.92 3.800 0.520 5.77
deduction -2 2.92 0.290 -1.69
Total Qty. for 1 No. Cum 7.69
Qty. for 1Nos. Cum 7.690 4,121.40 31,693.57
4 M15 grade Plain Cement Concrete in Open Foundation, wall complete as per Drawing and
Technical Specifications.
Sub structure
Wall 2 8.600 0.830 2.650 37.83
Parapet wall 2 8.600 0.400 0.400 2.75
deduction 4 0.820 1.540 -5.05
Total Qty. for 1 No. Cum 35.53
Qty. for 1Nos. Cum 35.530 4,605.03 163,616.72
5 Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry works in head walls
and parapets .
1200mm dia pipe 2.00 5.00 10.00
Total Qty. for 1 No. Rm 10.00
Qty. for 1Nos. Rm 10.000 12,988.70 129,887.00
Length Breadth
S No Description Nos Height (H) Unit Quantity Rate Amount
(L) (B)
6
Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
U/S 2 4.170 0.150 1.25
D/S 2 6.400 0.150 1.92
Total Qty. for 1 No. Cum 3.17
Qty. for 1Nos. Cum 3.170 820.70 2,601.62
7 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications .
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 74.07 0.3 22.22 cum -
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Boulder appron U/S Trapizodial
1 3.67 3.00 0.3 3.30 cum -
portion
Boulder appron U/S
1 3.67 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 6.93 4.43 0.3 9.21 cum -
Boulder appron D/S rectangular
5.35 cum
portion 1 11.36 1.57 0.3
Culvert inside 1 15.00 2.50 0.3 11.25 cum -
For 1No 51.33 cum -
For 0Nos. 0 cum 1,300.50 -
17 Synthetic Enamel paint on concrete
surface 2 5.10 1.3 13.26 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 13.98 Sqm -
For 0Nos. 0 Sqm 64.80 -
Total cost -
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 1 No
Height = 3.30
Effective Span = 3.00
Slab thick ness = 0.375
Abutment Detail Length == 15.00 b3 = 1.00
H = 3.30 b4 = 0.20
b1 = 0.30 B1 = 2.70
b2 = 1.10 B2 = 4.30
Height from GL to FRL of culvert = 2.950 Cap Thk. = 0.5
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 74.07 0.3 22.22 cum -
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Boulder appron U/S Trapizodial
1 3.17 3.00 0.3 2.85 cum -
portion
Boulder appron U/S
1 3.17 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 6.43 4.43 0.3 8.55 cum -
Boulder appron D/S rectangular
5.12 cum
portion 1 10.86 1.57 0.3
Culvert inside 1 15.00 2.00 0.3 9.00 cum -
For 1No 47.74 cum -
For 1Nos. 47.74 cum 1,300.50 62,085.87
17 Synthetic Enamel paint on concrete
surface 2 4.60 1.3 11.96 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 12.68 Sqm -
For 1Nos. 12.68 Sqm 64.80 821.66
Total cost 2,952,407.26
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 1 No
Height = 2.30
Effective Span = 4.00
Slab thick ness = 0.425
Abutment Detail Length == 15.00 b3 = 1.00
H = 2.30 b4 = 0.10
b1 = 0.25 B1 = 2.50
b2 = 0.95 B2 = 3.90
Height from GL to FRL of culvert = 2.000 Cap Thk. = 0.5
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications.
-
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Revetment 4 1/4 33.98 0.3 10.19 cum -
Boulder appron U/S Trapizodial
1 6.00 3.00 0.3 5.40 cum -
portion
Boulder appron U/S
1 6.00 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 6.00 3.00 0.3 5.40 cum -
Boulder appron D/S rectangular
8.10 cum
portion 1 9.00 3.00 0.3
Culvert inside 1 15.00 3.00 0.3 13.50 cum -
For 1No 42.59 cum -
For 1Nos. 42.59 cum 1,300.50 55,388.30
17 Synthetic Enamel paint on concrete
surface 2 5.60 1.3 14.56 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 15.28 Sqm -
For 1Nos. 15.28 Sqm 64.80 990.14
Total cost 2,469,759.06
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 1 No
Height = 2.80
Effective Span = 4.00
Slab thick ness = 0.425
Abutment Detail Length == 15.00 b3 = 1.00
H = 2.80 b4 = 0.10
b1 = 0.25 B1 = 2.50
b2 = 0.95 B2 = 3.90
Height from GL to FRL of culvert = 2.500 Cap Thk. = 0.5
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications.
-
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Revetment 4 1/4 53.10 0.3 15.93 cum -
Boulder appron U/S Trapizodial
1 4.50 3.00 0.3 4.05 cum -
portion
Boulder appron U/S
1 4.50 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 6.75 3.75 0.3 7.59 cum -
Boulder appron D/S rectangular
7.09 cum
portion 1 10.50 2.25 0.3
Culvert inside 1 15.00 3.00 0.3 13.50 cum -
For 1No 48.16 cum -
For 1Nos. 48.16 cum 1,300.50 62,632.08
17 Synthetic Enamel paint on concrete
surface 2 5.60 1.3 14.56 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 15.28 Sqm -
For 1Nos. 15.28 Sqm 64.80 990.14
Total cost 2,731,974.48
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 1 No
Height = 2.00
Effective Span = 7.00
Slab thick ness = 0.525
Abutment Detail Length == 15.00 b3 = 1.00
H = 2.00 b4 = 0.00
b1 = 0.20 B1 = 2.10
b2 = 0.60 B2 = 3.30
Height from GL to FRL of culvert = 1.800 Cap Thk. = 0.5
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications.
-
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Revetment 4 1/4 27.53 0.3 8.26 cum -
Boulder appron U/S Trapizodial
1 8.70 2.70 0.3 7.05 cum -
portion
Boulder appron U/S
1 8.70 0.30 0.78 cum
rectangular portion 0.3
Boulder appron at D/S 1 8.70 2.70 0.3 7.05 cum -
Boulder appron D/S rectangular
11.29 cum
portion 1 11.40 3.30 0.3
Culvert inside 1 15.00 6.00 0.3 27.00 cum -
For 1No 61.43 cum -
For 1Nos. 61.43 cum 1,300.50 79,889.72
17 Synthetic Enamel paint on concrete
surface 2 8.60 1.3 22.36 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 23.08 Sqm -
For 1Nos. 23.08 Sqm 64.80 1,495.58
Total cost 2,612,933.48
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 1 No
Height = 2.00
Effective Span = 1.90
Slab thick ness = 0.375
Abutment Detail Length == 15.00 b3 = 0.50
H = 2.00 b4 = 0.00
b1 = 0.20 B1 = 1.70
b2 = 0.70 B2 = 2.90
Height from GL to FRL of culvert = 1.650 Cap Thk. = 0.5
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 23.21 0.3 6.96 cum -
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Boulder appron U/S Trapizodial
1 3.88 2.48 0.3 2.89 cum -
portion
Boulder appron U/S
1 3.88 0.52 0.61 cum
rectangular portion 0.3
Boulder appron at D/S 1 3.88 2.48 0.3 2.89 cum -
Boulder appron D/S rectangular
6.72 cum
portion 1 6.36 3.52 0.3
Culvert inside 1 15.00 1.40 0.3 6.30 cum -
For 1No 26.37 cum -
For 1Nos. 26.37 cum 1,300.50 34,294.19
17 Synthetic Enamel paint on concrete
surface 2 3.00 1.3 7.8 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 8.52 Sqm -
For 1Nos. 8.52 Sqm 64.80 552.10
Total cost 1,538,356.99
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 1 No
Height = 1.80
Effective Span = 1.50
Slab thick ness = 0.375
Abutment Detail Length = 5.00 b3 = 0.58
H = 1.80 b4 = 0.00
b1 = 0.20 B1 = 1.70
b2 = 0.70 B2 = 2.90
Height from GL to FRL of culvert = 1.450 Cap Thk. = 0.5
Boulder appron U/S rectangular portion 1 3.10 0.82 0.60 1.53 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 17.93 0.3 5.38 cum -
Boulder appron U/S Trapizodial portion 1 3.10 2.18 0.3 2.03 cum -
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 1.50
Length at end of trapzoidal section = 4.23
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 1.50
Length at end of trapzoidal section = 9.46
Width of trapezoidal section = 3.98
Width of rectangular section = 2.02
Cut-off wall type-II
U/S Length = 4.23
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 13.50
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder
apron laid dry in front of toe of embankment complete as per drawing and Technical
specifications.
-
Revetment 4 1/4 59.79 0.3 17.94 cum -
Boulder appron U/S Trapizodial
1 2.87 3.00 0.3 2.58 cum -
portion
Boulder appron U/S
1 2.87 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 5.48 3.98 0.3 6.54 cum -
Boulder appron D/S rectangular
5.73 cum
portion 1 9.46 2.02 0.3
Culvert inside 1 3.00 1.50 0.3 1.35 cum -
For 1No 34.14 cum -
For 1Nos. 34.14 cum 1,300.50 44,399.07
17 Synthetic Enamel paint on concrete
surface 2 3.10 1.3 8.06 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 8.78 Sqm -
For 1Nos. 8.78 Sqm 64.80 568.94
Total cost 1,079,593.70
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 1.50
Length at end of trapzoidal section = 5.57
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 1.50
Length at end of trapzoidal section = 7.96
Width of trapezoidal section = 3.23
Width of rectangular section = 2.77
Cut-off wall type-II
U/S Length = 5.57
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 13.50
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 39.37 0.3 11.81 cum -
Boulder appron U/S Trapizodial
1 3.54 3.00 0.3 3.19 cum -
portion
Boulder appron U/S rectangular
1 3.54 0.00 0.00 cum
portion 0.3
Boulder appron at D/S 1 4.73 3.23 0.3 4.58 cum -
Boulder appron D/S rectangular
6.61 cum
portion 1 7.96 2.77 0.3
Culvert inside 1 2.00 1.50 0.3 0.90 cum -
For 1No 27.09 cum -
For 2Nos. 54.18 cum 1,300.50 70,461.09
17 Synthetic Enamel paint on concrete
surface 2 3.10 1.3 8.06 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 8.78 Sqm -
For 2Nos. 17.56 Sqm 64.80 1,137.89
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total cost 1,642,533.94
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 3 No
Height = 2.00
Effective Span = 1.50
Slab thick ness = 0.375
Abutment Detail Length == 2.00 b3 = 0.50
H = 2.00 b4 = 0.00
b1 = 0.20 B1 = 1.70
b2 = 0.70 B2 = 2.90
Height from GL to FRL of culvert = 1.650 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 1.00
Length at end of trapzoidal section = 5.96
Width of trapezoidal section 2.48
Width of rectangular section 0.52
D/S Total width of floor apron = 6.00
Length near culvert = 1.00
Length at end of trapzoidal section = 5.96
Width of trapezoidal section = 2.48
Width of rectangular section = 3.52
Cut-off wall type-II
U/S Length = 7.00
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 13.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front
of toe of embankment complete as per drawing and Technical specifications. -
Revetment 4 1/4 23.21 0.3 6.96 cum -
Boulder appron U/S Trapizodial
1 3.48 2.48 0.3 2.59 cum -
portion
Boulder appron U/S
1 3.48 0.52 0.54 cum
rectangular portion 0.3
Boulder appron at D/S 1 3.48 2.48 0.3 2.59 cum -
Boulder appron D/S rectangular
6.29 cum
portion 1 5.96 3.52 0.3
Culvert inside 1 2.00 1.00 0.3 0.60 cum -
For 1No 19.57 cum -
For 3Nos. 58.71 cum 1,300.50 76,352.36
17 Synthetic Enamel paint on concrete
surface 2 2.60 1.3 6.76 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 7.48 Sqm -
For 3Nos. 22.44 Sqm 64.80 1,454.11
Total cost 1,762,523.04
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 1.50
Length at end of trapzoidal section = 6.46
Width of trapezoidal section 2.48
Width of rectangular section 0.52
D/S Total width of floor apron = 6.00
Length near culvert = 1.50
Length at end of trapzoidal section = 6.46
Width of trapezoidal section = 2.48
Width of rectangular section = 3.52
Cut-off wall type-II
U/S Length = 7.50
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 13.50
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front
of toe of embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 23.21 0.3 6.96 cum -
Boulder appron U/S Trapizodial
1 3.98 2.48 0.3 2.96 cum -
portion
Boulder appron U/S
1 3.98 0.52 0.62 cum
rectangular portion 0.3
Boulder appron at D/S 1 3.98 2.48 0.3 2.96 cum -
Boulder appron D/S rectangular
6.82 cum
portion 1 6.46 3.52 0.3
Culvert inside 1 2.00 1.50 0.3 0.90 cum -
For 1No 21.22 cum -
For 2Nos. 42.44 cum 1,300.50 55,193.22
17 Synthetic Enamel paint on concrete
surface 2 3.10 1.3 8.06 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 8.78 Sqm -
For 2Nos. 17.56 Sqm 64.80 1,137.89
Total cost 1,209,571.97
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Assistant Engineer Dy Executive Engineer Executive Engineer
.NH. Section Aska .NH. Sub Division Berhampur NH.Division Berhampur
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 4.00
Length at end of trapzoidal section = 7.62
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 4.00
Length at end of trapzoidal section = 10.78
Width of trapezoidal section = 3.39
Width of rectangular section = 2.61
Cut-off wall type-II
U/S Length = 7.62
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 16.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications. -
Revetment 4 1/4 43.39 0.3 13.02 cum -
Boulder appron U/S Trapizodial
1 5.81 3.00 0.3 5.23 cum -
portion
Boulder appron U/S
1 5.81 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 7.39 3.39 0.3 7.52 cum -
Boulder appron D/S rectangular
8.44 cum
portion 1 10.78 2.61 0.3
Culvert inside 1 2.00 4.00 0.3 2.40 cum -
For 1No 36.61 cum -
For 1Nos. 36.61 cum 1,300.50 47,611.31
17 Synthetic Enamel paint on concrete
surface 2 6.60 1.3 17.16 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 17.88 Sqm -
For 1Nos. 17.88 Sqm 64.80 1,158.62
Total cost 996,942.22
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Assistant
AssistantEngineer
Engineer DyDyExecutive
ExecutiveEngineer
Engineer Executive Engineer
Executive Engineer
.NH.
.NH.Section
SectionAska
Aska .NH. Sub Division Berhampur NH.Division Berhampur
NH.Division Berhampur
NH. Sub Division
Berhampur.
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 3 No
Height = 1.50
Effective Span = 2.00
Slab thick ness = 0.375
Abutment Detail Length = 2.00 b3 = 0.50
H = 1.50 b4 = 0.00
b1 = 0.15 B1 = 1.45
b2 = 0.50 B2 = 2.65
Height from GL to FRL of culvert = 1.150 Cap Thk. = 0.5
Boulder appron U/S rectangular portion 1 3.23 1.27 0.60 2.46 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 11.29 0.3 3.39 cum -
Boulder appron U/S Trapizodial portion 1 3.23 1.73 0.3 1.68 cum -
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 4.00
Length at end of trapzoidal section = 5.73
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 4.00
Length at end of trapzoidal section = 15.28
Width of trapezoidal section = 5.64
Width of rectangular section = 0.36
Cut-off wall type-II
U/S Length = 5.73
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 16.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and Technical specifications. -
Revetment 4 1/4 120.10 0.3 36.03 cum -
Boulder appron U/S Trapizodial
1 4.87 3.00 0.3 4.38 cum -
portion
Boulder appron U/S
1 4.87 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 9.64 5.64 0.3 16.31 cum -
Boulder appron D/S rectangular
1.65 cum
portion 1 15.28 0.36 0.3
Culvert inside 1 2.00 4.00 0.3 2.40 cum -
For 1No 60.77 cum -
For 2Nos. 121.54 cum 1,300.50 158,062.77
17 Synthetic Enamel paint on concrete
surface 2 6.60 1.3 17.16 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 17.88 Sqm -
For 2Nos. 35.76 Sqm 64.80 2,317.25
Total cost 3,524,931.25
Assistant Engineer
.NH. Section Aska
VILLAGE AREA
chainage
LENGTH Name side
from To
16600 17500 900 MARKET AREA BOTH
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 2.00
Length at end of trapzoidal section = 4.73
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 2.00
Length at end of trapzoidal section = 9.96
Width of trapezoidal section = 3.98
Width of rectangular section = 2.02
Cut-off wall type-II
U/S Length = 4.73
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 14.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 59.79 0.3 17.94 cum -
Boulder appron U/S Trapizodial
1 3.37 3.00 0.3 3.03 cum -
portion
Boulder appron U/S
1 3.37 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 5.98 3.98 0.3 7.14 cum -
Boulder appron D/S rectangular
6.04 cum
portion 1 9.96 2.02 0.3
Culvert inside 1 2.00 2.00 0.3 1.20 cum -
For 1No 35.35 cum -
For 1Nos. 35.35 cum 1,300.50 45,972.68
17 Synthetic Enamel paint on concrete
surface 2 3.60 1.3 9.36 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 10.08 Sqm -
For 1Nos. 10.08 Sqm 64.80 653.18
Total cost 991,541.30
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 4.00
Effective Span = 2.50
Slab thick ness = 0.375
Abutment Detail Length == 2.00 b3 = 0.50
H = 4.00 b4 = 0.50
b1 = 0.40 B1 = 2.60
b2 = 1.40 B2 = 4.80
Height from GL to FRL of culvert = 3.650 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 2.00
Length at end of trapzoidal section = 3.79
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 2.00
Length at end of trapzoidal section = 12.96
Width of trapezoidal section = 5.48
Width of rectangular section = 0.52
Cut-off wall type-II
U/S Length = 3.79
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 14.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 113.35 0.3 34.01 cum -
Boulder appron U/S Trapizodial
1 2.90 3.00 0.3 2.61 cum -
portion
Boulder appron U/S
1 2.90 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 7.48 5.48 0.3 12.30 cum -
Boulder appron D/S rectangular
2.02 cum
portion 1 12.96 0.52 0.3
Culvert inside 1 2.00 2.00 0.3 1.20 cum -
For 1No 52.14 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 3.60 1.3 9.36 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 10.08 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 3.00
Effective Span = 3.00
Slab thick ness = 0.375
Abutment Detail Length == 2.00 b3 = 0.50
H = 3.00 b4 = 0.20
b1 = 0.30 B1 = 2.20
b2 = 1.10 B2 = 4.80
Height from GL to FRL of culvert = 2.650 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 2.50
Length at end of trapzoidal section = 5.23
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 2.50
Length at end of trapzoidal section = 10.46
Width of trapezoidal section = 3.98
Width of rectangular section = 2.02
Cut-off wall type-II
U/S Length = 5.23
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 14.50
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 59.79 0.3 17.94 cum -
Boulder appron U/S Trapizodial
1 3.87 3.00 0.3 3.48 cum -
portion
Boulder appron U/S
1 3.87 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 6.48 3.98 0.3 7.74 cum -
Boulder appron D/S rectangular
6.34 cum
portion 1 10.46 2.02 0.3
Culvert inside 1 2.00 2.50 0.3 1.50 cum -
For 1No 37.00 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 4.10 1.3 10.66 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 11.38 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 2.50
Effective Span = 3.50
Slab thick ness = 0.375
Abutment Detail Length == 2.00 b3 = 1.00
H = 2.50 b4 = 0.10
b1 = 0.25 B1 = 2.50
b2 = 0.95 B2 = 3.90
Height from GL to FRL of culvert = 2.150 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 2.50
Length at end of trapzoidal section = 6.57
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 2.50
Length at end of trapzoidal section = 8.96
Width of trapezoidal section = 3.23
Width of rectangular section = 2.77
Cut-off wall type-II
U/S Length = 6.57
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 14.50
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 39.37 0.3 11.81 cum -
Boulder appron U/S Trapizodial
1 4.54 3.00 0.3 4.09 cum -
portion
Boulder appron U/S
1 4.54 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 5.73 3.23 0.3 5.55 cum -
Boulder appron D/S rectangular
7.45 cum
portion 1 8.96 2.77 0.3
Culvert inside 1 2.00 2.50 0.3 1.50 cum -
For 1No 30.40 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 5.10 1.3 13.26 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 13.98 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 4.00
Effective Span = 3.50
Slab thick ness = 0.375
Abutment Detail Length == 2.00 b3 = 1.00
H = 4.00 b4 = 0.50
b1 = 0.40 B1 = 3.10
b2 = 1.40 B2 = 5.30
Height from GL to FRL of culvert = 3.650 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 2.50
Length at end of trapzoidal section = 4.29
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 2.50
Length at end of trapzoidal section = 13.46
Width of trapezoidal section = 5.48
Width of rectangular section = 0.52
Cut-off wall type-II
U/S Length = 4.29
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 14.50
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 113.35 0.3 34.01 cum -
Boulder appron U/S Trapizodial
1 3.40 3.00 0.3 3.06 cum -
portion
Boulder appron U/S
1 3.40 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 7.98 5.48 0.3 13.12 cum -
Boulder appron D/S rectangular
2.10 cum
portion 1 13.46 0.52 0.3
Culvert inside 1 2.00 2.50 0.3 1.50 cum -
For 1No 53.79 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 5.10 1.3 13.26 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 13.98 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 2.50
Effective Span = 4.00
Slab thick ness = 0.425
Abutment Detail Length == 2.00 b3 = 1.00
H = 2.50 b4 = 0.10
b1 = 0.25 B1 = 2.50
b2 = 0.95 B2 = 3.90
Height from GL to FRL of culvert = 2.200 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 3.00
Length at end of trapzoidal section = 6.85
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 3.00
Length at end of trapzoidal section = 9.60
Width of trapezoidal section = 3.30
Width of rectangular section = 2.70
Cut-off wall type-II
U/S Length = 6.85
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 15.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 41.12 0.3 12.34 cum -
Boulder appron U/S Trapizodial
1 4.93 3.00 0.3 4.44 cum -
portion
Boulder appron U/S
1 4.93 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 6.30 3.30 0.3 6.24 cum -
Boulder appron D/S rectangular
7.78 cum
portion 1 9.60 2.70 0.3
Culvert inside 1 2.00 3.00 0.3 1.80 cum -
For 1No 32.60 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 5.60 1.3 14.56 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 15.28 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 3.00
Effective Span = 4.00
Slab thick ness = 0.425
Abutment Detail Length == 2.00 b3 = 1.00
H = 3.00 b4 = 0.20
b1 = 0.30 B1 = 2.70
b2 = 1.10 B2 = 4.30
Height from GL to FRL of culvert = 2.700 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 3.00
Length at end of trapzoidal section = 5.66
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 3.00
Length at end of trapzoidal section = 11.10
Width of trapezoidal section = 4.05
Width of rectangular section = 1.95
Cut-off wall type-II
U/S Length = 5.66
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 15.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 61.93 0.3 18.58 cum -
Boulder appron U/S Trapizodial
1 4.33 3.00 0.3 3.90 cum -
portion
Boulder appron U/S
1 4.33 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 7.05 4.05 0.3 8.57 cum -
Boulder appron D/S rectangular
6.49 cum
portion 1 11.10 1.95 0.3
Culvert inside 1 2.00 3.00 0.3 1.80 cum -
For 1No 39.34 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 5.60 1.3 14.56 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 15.28 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 3.00
Effective Span = 7.00
Slab thick ness = 0.575
Abutment Detail Length == 2.00 b3 = 1.00
H = 3.00 b4 = 0.20
b1 = 0.30 B1 = 2.60
b2 = 1.00 B2 = 4.20
Height from GL to FRL of culvert = 2.850 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 6.00
Length at end of trapzoidal section = 8.45
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 6.00
Length at end of trapzoidal section = 14.56
Width of trapezoidal section = 4.28
Width of rectangular section = 1.72
Cut-off wall type-II
U/S Length = 8.45
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 18.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 69.14 0.3 20.74 cum -
Boulder appron U/S Trapizodial
1 7.23 3.00 0.3 6.51 cum -
portion
Boulder appron U/S
1 7.23 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 10.28 4.28 0.3 13.20 cum -
Boulder appron D/S rectangular
7.51 cum
portion 1 14.56 1.72 0.3
Culvert inside 1 2.00 6.00 0.3 3.60 cum -
For 1No 51.56 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 8.60 1.3 22.36 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 23.08 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 2.50
Effective Span = 8.00
Slab thick ness = 0.675
Abutment Detail Length == 2.00 b3 = 1.00
H = 2.50 b4 = 0.10
b1 = 0.25 B1 = 2.40
b2 = 0.85 B2 = 3.80
Height from GL to FRL of culvert = 2.450 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 7.00
Length at end of trapzoidal section = 10.10
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 7.00
Length at end of trapzoidal section = 14.36
Width of trapezoidal section = 3.68
Width of rectangular section = 2.32
Cut-off wall type-II
U/S Length = 10.10
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 19.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 51.11 0.3 15.33 cum -
Boulder appron U/S Trapizodial
1 8.55 3.00 0.3 7.70 cum -
portion
Boulder appron U/S
1 8.55 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 10.68 3.68 0.3 11.79 cum -
Boulder appron D/S rectangular
9.99 cum
portion 1 14.36 2.32 0.3
Culvert inside 1 2.00 7.00 0.3 4.20 cum -
For 1No 49.01 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 9.60 1.3 24.96 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 25.68 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total ### No
Height = 4.00
Effective Span = 8.00
Slab thick ness = 0.675
Abutment Detail Length == 2.00 b3 = 1.00
H = 4.00 b4 = 0.50
b1 = 0.40 B1 = 3.10
b2 = 1.40 B2 = 5.30
Height from GL to FRL of culvert = 3.950 Cap Thk. = 0.5
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 7.00
Length at end of trapzoidal section = 8.63
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 7.00
Length at end of trapzoidal section = 18.86
Width of trapezoidal section = 5.93
Width of rectangular section = 0.07
Cut-off wall type-II
U/S Length = 8.63
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 19.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 132.74 0.3 39.82 cum -
Boulder appron U/S Trapizodial
1 7.82 3.00 0.3 7.04 cum -
portion
Boulder appron U/S
1 7.82 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 12.93 5.93 0.3 23.00 cum -
Boulder appron D/S rectangular
0.40 cum
portion 1 18.86 0.07 0.3
Culvert inside 1 2.00 7.00 0.3 4.20 cum -
For 1No 74.46 cum -
Err:509 Err:509 cum 1,300.50 Err:509
17 Synthetic Enamel paint on concrete
surface 2 9.60 1.3 24.96 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 25.68 Sqm -
Err:509 Err:509 Sqm 64.80 Err:509
Total cost Err:509
#VALUE!
BILL : SLAB CULVERT
SL
DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
NO
Total 1 No
Height = 2.30
Effective Span = 2.00
Slab thick ness = 0.375
Abutment Detail Length = 5.00 b3 = 0.50
H = 2.30 b4 = 0.00
b1 = 0.20 B1 = 1.70
b2 = 0.70 B2 = 2.90
Height from GL to FRL of culvert = 1.950 Cap Thk. = 0.5
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 2.90 2.15 62.35 cum
Return wall 4 3.43 2.85 1.10 43.01 cum
Up stream curtain wall 1 7.50 1.50 1.85 20.81 cum
Down stream curtain wall, 1 13.50 1.85 2.35 58.69 cum
Boulder appron at U/S 1 4.43 2.93 0.60 7.79 cum
Boulder appron U/S rectangular portion 1 4.43 0.07 0.60 0.19 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 32.40 0.3 9.72 cum -
Boulder appron U/S Trapizodial portion 1 4.43 2.93 0.3 3.89 cum -
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 2.90 2.15 62.35 cum
Return wall 4 2.23 2.20 1.10 21.59 cum
Up stream curtain wall 1 8.20 1.50 1.85 22.76 cum
Down stream curtain wall, 1 14.20 1.85 2.35 61.73 cum
Boulder appron at U/S 1 3.93 1.73 0.60 4.08 cum
Boulder appron U/S rectangular portion 1 3.93 1.27 0.60 2.99 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 11.29 0.3 3.39 cum -
Boulder appron U/S Trapizodial portion 1 3.93 1.73 0.3 2.04 cum -
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 3.40 2.15 73.10 cum
Return wall 4 3.58 2.85 1.10 44.89 cum
Up stream curtain wall 1 7.27 1.50 1.85 20.17 cum
Down stream curtain wall, 1 14.50 1.85 2.35 63.04 cum
Boulder appron at U/S 1 4.89 3.00 0.60 8.80 cum
Boulder appron U/S rectangular portion 1 4.89 0.00 0.60 0.00 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 35.80 0.3 10.74 cum -
Boulder appron U/S Trapizodial portion 1 4.89 3.00 0.3 4.40 cum -
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 5.30 2.15 113.95 cum
Return wall 4 5.68 4.43 1.60 161.04 cum
Up stream curtain wall 1 4.91 1.50 1.85 13.63 cum
Down stream curtain wall, 1 15.00 1.85 2.35 65.21 cum
Boulder appron at U/S 1 3.96 3.00 0.60 7.13 cum
Boulder appron U/S rectangular portion 1 3.96 0.00 0.60 0.00 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 101.28 0.3 30.38 cum -
Boulder appron U/S Trapizodial portion 1 3.96 3.00 0.3 3.56 cum -
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 3.90 2.15 83.85 cum
Return wall 4 3.50 3.35 1.60 75.04 cum
Up stream curtain wall 1 9.20 1.50 1.85 25.53 cum
Down stream curtain wall, 1 15.20 1.85 2.35 66.08 cum
Boulder appron at U/S 1 6.20 3.00 0.60 11.16 cum
Boulder appron U/S rectangular portion 1 6.20 0.00 0.60 0.00 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 33.98 0.3 10.19 cum -
Boulder appron U/S Trapizodial portion 1 6.20 3.00 0.3 5.58 cum -
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 3.80 2.15 81.70 cum
Return wall 4 3.59 3.35 1.60 76.97 cum
Up stream curtain wall 1 8.70 1.50 1.85 24.14 cum
Down stream curtain wall, 1 16.00 1.85 2.35 69.56 cum
Boulder appron at U/S 1 6.35 3.00 0.60 11.43 cum
Boulder appron U/S rectangular portion 1 6.35 0.00 0.60 0.00 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 36.05 0.3 10.82 cum -
Boulder appron U/S Trapizodial portion 1 6.35 3.00 0.3 5.72 cum -
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 5.30 2.15 113.95 cum
Return wall 4 5.84 4.43 1.60 165.58 cum
Up stream curtain wall 1 6.44 1.50 1.85 17.87 cum
Down stream curtain wall, 1 16.60 1.85 2.35 72.17 cum
Boulder appron at U/S 1 5.52 3.00 0.60 9.94 cum
Boulder appron U/S rectangular portion 1 5.52 0.00 0.60 0.00 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 107.67 0.3 32.30 cum -
Boulder appron U/S Trapizodial portion 1 5.52 3.00 0.3 4.97 cum -
#VALUE!
1 Earth work in excavation
Abutment wall 2 5.00 3.80 2.15 81.70 cum
Return wall 4 3.59 3.35 1.60 76.97 cum
Up stream curtain wall 1 10.70 1.50 1.85 29.69 cum
Down stream curtain wall, 1 18.00 1.85 2.35 78.26 cum
Boulder appron at U/S 1 8.35 3.00 0.60 15.03 cum
Boulder appron U/S rectangular portion 1 8.35 0.00 0.60 0.00 cum
16 Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical specifications.
-
Revetment 4 1/4 36.05 0.3 10.82 cum -
Boulder appron U/S Trapizodial portion 1 8.35 3.00 0.3 7.52 cum -
Floor Apron
U/S Total width of floor apron = 3.00
Length near culvert = 6.00
Length at end of trapzoidal section = 8.82
Width of trapezoidal section 3.00
Width of rectangular section 0.00
D/S Total width of floor apron = 6.00
Length near culvert = 6.00
Length at end of trapzoidal section = 13.80
Width of trapezoidal section = 3.90
Width of rectangular section = 2.10
Cut-off wall type-II
U/S Length = 8.82
Section =
Height, H = 2.00
Bottom Foundation width W = 1.50
PCC thickness = 0.15 Bed Level to Bottom of footing ht.= 2.15
1st footing ht. h1 = 0.80 1st footing width,b1= 1.30
2nd footing ht. h2 = 0.75 2nd footing,b2= 0.45
3rd footing ht. h3 = 0.45 3rd footing,b3= 0.20
Cut-off wall type-I
D/S Length = 18.00
Section =
Height, H = 2.50
Bottom Foundation width W = 1.85 Bed Level to Bottom of footing ht.= 2.65
#VALUE!
-
Revetment 4 1/4 57.43 0.3 17.23 cum -
Boulder appron U/S Trapizodial
1 7.41 3.00 0.3 6.67 cum -
portion
Boulder appron U/S
1 7.41 0.00 0.00 cum
rectangular portion 0.3
Boulder appron at D/S 1 9.90 3.90 0.3 11.58 cum -
Boulder appron D/S rectangular
8.69 cum
portion 1 13.80 2.10 0.3
Culvert inside 1 2.00 6.00 0.3 3.60 cum -
For 1No 47.77 cum -
For 1Nos. 47.77 cum 1,300.50 62,124.89
17 Synthetic Enamel paint on concrete
surface 2 8.60 1.3 22.36 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 23.08 Sqm -
For 1Nos. 23.08 Sqm 64.80 1,495.58
18 Construction of RCC railing of M30
Grade in-situ with 20 mm nominal
size aggregate
Qty. for 1 No. 1 8.600 8.600 Rm
For 1No 8.600 Rm 1763.8 15168.68
Total cost 1,207,584.53
#VALUE!
Boulder appron D/S rectangular portion 1 30.16 0.42 0.60 7.60 cum
5 R C C-M20 in foundation
Abutment wall 2nd footing 2 8.00 4.90 0.30 23.52 cum
Abutment wall 3rd footing lower 2 8.00 4.50 0.60 43.20 cum
Abutment wall 3rd footing upper 2 8.00 4.30 0.60 41.28 cum
Pier 1st footing lower 1 18.85 1.20 22.62 cum
Pier 1st footing upper 1 9.92 0.60 5.95 cum
Return wall Raft, 1st footing 4 6.08 5.10 0.30 37.21 cum
Return wall Raft, 1st footing taper
4 6.08 2.95 0.33 23.32 cum
portion
197.10 cum 5,027.14 990,849.29
6 R C C M-20 in wall
Return wall stem, 1st lift 4 6.08 0.55 2.70 36.12 cum
2nd lift 4 6.08 0.30 2.40 17.51 cum
Abutment wall up to cap 2 8.00 2.20 3.70 130.24 cum
Pier upto cap 1 7.85 3.70 29.05 cum
Pier Cap 1 8.00 0.80 0.50 3.20 cum
Abutment Cap 2 8.00 1.50 0.50 12.00
Dirtwall 2 8.00 0.30 1.245 5.98 cum
Parapet wall 2 11.10 0.40 0.45 4.00 cum
For 1No 238.10 cum
For 1Nos. 238.10 cum 5,309.44 1,264,177.66
9 M30 CC wearing coat including steel. 1 7.20 21.60 0.075 11.66 cum -
For 1No 11.66 cum -
For 1Nos. 11.66 cum 5170.00 60,282.20
10 HYSD Bar
-
Taking 100 kg/cum for Foundation,Wall &
1 0.10 572.02 57.20 MT
super structure -
For 1No 57.20 MT -
For 1Nos. 57.20 MT 57402.50 3,283,423.00
12
No. No. of Length
no. of
Providing weepholes of hole in of each Total
rows
wall a row hole
Abutment 2 8 4.00 1.95 124.80 Rm -
Return wall 4 7.00 4.00 0.55 61.60 Rm -
For 1No 186.40 Rm -
For 1Nos. 186.40 Rm 162.10 30,215.44
15 Boulder Appron -
Revetment 4 1/4 117.56 0.3 35.27 cum -
Boulder appron U/S Trapizodial portion 17.89 cum
1 19.88 3.00 0.3 -
Boulder appron U/S rectangular
1 19.88 0.00 0.00 cum
portion 0.3
Boulder appron at D/S 1 24.58 5.58 0.3 41.15 cum -
Boulder appron D/S rectangular portion 1 30.16 0.42 0.3 3.80 cum
Culvert inside 1 8.00 8.50 0.3 20.40 cum -
For 1No 118.51 cum -
For 1Nos. 118.51 cum 1,300.50 154,122.26
16
Synthetic Enamel paint on concrete surface 2 21.60 1.3 56.16 Sqm -
4 0.40 0.45 0.72 Sqm -
For 1No 56.88 Sqm -
For 1Nos. 56.88 Sqm 64.80 3,685.82
#VALUE!
Boulder appron D/S rectangular portion 1 59.61 0.00 0.60 0.00 cum
4 R C C-M20 in foundation -
Abutment wall 2nd footing 2 8.00 4.90 0.30 23.52 cum -
Abutment wall 3rd footing lower 2 8.00 4.50 0.60 43.20 cum -
Abutment wall 3rd footing upper 2 8.00 4.30 0.60 41.28 cum -
Pier 1st footing lower 2 18.85 1.20 45.24 cum
Pier 1st footing upper 2 15.08 0.60 18.10 cum
Return wall Raft, 1st footing 4 9.83 5.10 0.30 60.16 cum -
SL NO DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
0.00 cum 4180.03 -
4 PCC M15 in curtain wall foundation.
U/S curtain wall 1st footing 1 41.94 1.30 0.80 43.62 cum -
U/S curtain wall 2nd footing 1 41.94 0.45 0.75 14.15 cum -
U/S curtain wall 3rd footing 1 41.94 0.20 0.45 3.77 cum -
D/S curtain wall 1st footing 1 59.61 1.65 0.55 54.10 cum -
D/S curtain wall 2nd footing 1 59.61 0.75 0.75 33.53 cum -
D/S curtain wall 3rd footing 1 59.61 0.45 0.75 20.12 cum -
D/S curtain wall 4th footing 1 59.61 0.20 0.45 5.36 cum -
For 1No 174.65 cum -
For 1Nos. 174.65 cum 4,361.20 761,683.58
5 P C C-M15 in Substructure -
Abutment wall up to cap 2 8.00 2.20 6.20 218.24 cum -
Pier 2 7.85 6.20 97.34 cum
Parapet wall 2 15.25 0.40 0.45 5.49 cum
For 1No 321.07 cum -
For 1Nos. 0.00 cum 3,639.85 -
6 R C C M-20 in foundation -
Return wall Raft, 1st footing 4 9.83 5.10 0.30 60.16 cum -
2nd footing 4 9.83 2.95 0.33 38.28 cum -
For 1No 98.44 cum -
For 1Nos. 0.00 Sqm 4180.03 -
5 R C C-M20 in foundation
Abutment wall 2nd footing 2 8.00 4.90 0.30 23.52 cum
Abutment wall 3rd footing lower 2 8.00 4.50 0.60 43.20 cum
Abutment wall 3rd footing upper 2 8.00 4.30 0.60 41.28 cum
Pier 1st footing lower 2 18.85 1.20 45.24 cum
Pier 1st footing upper 2 9.92 0.60 11.90 cum
Return wall Raft, 1st footing 4 9.83 5.10 0.30 60.16 cum
Return wall Raft, 1st footing taper
4 9.83 2.95 0.33 37.70 cum
portion
263.00 cum 5,027.14 1,322,137.82
6 R C C M-20 in wall
Return wall stem, 1st lift 4 9.83 0.55 5.20 112.46 cum
2nd lift 4 9.83 0.30 2.40 28.31 cum
Abutment wall up to cap 2 8.00 2.20 6.20 218.24 cum
Pier upto cap 2 7.85 6.20 97.34 cum
Pier Cap 2 8.00 0.80 0.50 6.40 cum
Abutment Cap 2 8.00 1.50 0.50 12.00
Dirtwall 2 8.00 0.30 1.245 5.98 cum
Parapet wall 2 15.25 0.40 0.45 5.49 cum
For 1No 486.22 cum
For 1Nos. 486.22 cum 5,309.44 2,581,555.92
9 M30 CC wearing coat including steel. 1 7.20 43.55 0.075 23.52 cum -
For 1No 23.52 cum -
For 1Nos. 23.52 cum 5170.00 121,598.40
10 HYSD Bar
-
Taking 0.1% of skin reinforcement 0 ### 174.65 0.00 MT -
Taking 100 kg/cum for Foundation,Wall &
1 0.10 1,028.72 102.87 MT
super structure -
For 1No 102.87 MT -
For 1Nos. 102.87 MT 57402.50 5,904,995.18
12
No. No. of Length
no. of
Providing weepholes of hole in of each Total
rows
wall a row hole
Abutment 2 8 6.00 1.95 187.20 Rm -
Return wall 4 11.00 7.00 0.55 169.40 Rm -
For 1No 356.60 Rm -
For 1Nos. 356.60 Rm 162.10 57,804.86
15 Boulder Appron -
Revetment 4 1/4 328.67 0.3 98.60 cum -
Boulder appron U/S Trapizodial portion 37.31 cum
1 41.45 3.00 0.3 -
Boulder appron U/S rectangular
1 41.45 0.00 0.00 cum
portion 0.3
Boulder appron at D/S 1 50.28 6.00 0.3 90.50 cum -
Boulder appron D/S rectangular portion 1 59.61 0.00 0.3 0.00 cum
Culvert inside 1 8.00 12.65 0.3 30.36 cum -
For 1No 256.77 cum -
For 1Nos. 256.77 cum 1,300.50 333,929.39
16
Synthetic Enamel paint on concrete surface 2 43.55 1.3 113.23 Sqm -
4 0.40 0.45 0.72 Sqm -
SL NO DESCRIPTION NO LENGTH WIDTH HEIGHT QTY UNIT Rate Amount
For 1No 113.95 Sqm -
For 1Nos. 113.95 Sqm 64.80 7,383.96
18 Construction of RCC railing of M30 Grade
in-situ with 20 mm nominal size aggregate
Total 4,975,135.00
Junior Engineer Assistant
Phulbani
Junior Engineer
Junior R&B Section
Engineer Assistant
Assistant Engineer
Engineer EngineerExecutive Executive Engineer
Phulbani
.Sagada
Junior South.
R&B
Engineer
R&B Section .West
Phulbani
Assistant
Assistant Sub- Phulbani R&B
R&B Sub-Division
R&B
Engineer
Engineer Engineer
Executive Kalahandi R&B
Section
Boinda
Phulbani
R&B North.
R&B
Section Division,
.Angul
Phulbani
R&B North.
R&B Sub-Division,
Sub-Division
Sub- Phulbani R&B
Engineer .Division
Section. North. Division, North. South.Phulbani
Division.
R&B
Division.
Total 0 m
Total 0 m
Proposed Toe Wall Schedule 1.0m Height Above GL
SL CHAINAGE
DISTANCE SIDE REMARKS
NO FROM TO
1 295100 295150 50 LHS In sufficient Land
2 295200 295340 140 RHS In sufficient Land
3 296070 296130 60 BOTH In sufficient Land
4 296200 296470 270 LHS In sufficient Land
5 296500 296740 240 LHS In sufficient Land
6 297150 297420 540 BOTH In sufficient Land
7 297440 297720 560 BOTH In sufficient Land
8 297980 298030 50 LHS In sufficient Land
9 303470 303610 280 BOTH In sufficient Land
Total 2190.00 m
Total 2620.00 m
Drain schedule
CHAINAGE
SIDE LENGTH Remarks
FROM TO
295200 298000 BHS 5600
298000 299000 BHS 2000
299000 300300 BHS 2600
304420 305180 BHS 1520
307380 307940 BHS 1120
309590 310290 BHS 1400
308300 308550 BHS 500
314900 315100 BHS 400
316700 316900 BHS 400
RCC Drain
cum footpath
318400 319300 BHS in Boriguma
Town potion.
1800
Total 17340
5 Supplying, fitting and placing HYSD bar reinforcement in slab complete as per drawing
and technical specifications.
Junior
For Slab Engineer 4104.000 @ 60.000Executive
kg/cum Engineer
246240.00
Phulbani R&B Phulbani R&B
MT 246.24 56874.20 14,004,703.01
Section North. Division.
6 Construction of cement concrete kerb with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying
machine, foundation concrete laid manually, all complete as per clause 408
2 17340.000 Rm 34680.00 263.60 9,141,648.00
7 Providing, fitting and fixing mild steel railing complete as per drawing and Technical
Specification
2 17340.000 Rm 34680.00 2529.40 87,719,592.00
Total 190,376,324.80
Junior Engineer Assistant Engineer Executive Engineer
Nilgiri R&B Section. Nilgiri R&B Sub-Division. Balasore R&B Division.
1 Earth work in excavation of foundation in hard soil including dewatering , shoring and shuttering etc..
400
600
G.L.
M-15
300
540
P.C.C.(M15) 150
SAND 150
840
C.C. TOE WALL -1.0 Mtr Height above ground level
1 Earth work in excavation of foundation in hard soil including dewatering , shoring and shuttering etc..
400
1000
G.L.
M-15
350
800
P.C.C.(M15) 150
SAND 150
1100
C.C. TOE WALL -1.50 Mtr Height above ground level
1 Earth work in excavation of foundation in hard soil including dewatering , shoring and shuttering etc..
400
1500
G.L.
M-15
700
1300
P.C.C.(M15) 150
SAND 150
1600
Total 13,762,980.00
Junior Engineer
Asst. Executive Engineer Executive Engineer
NH. Section, Boriguma
NH. Sub Division Boriguma. NH.Division Jeypore
TOLL PLAZA
Total no of Toll Plaza = 1.00 No
At Chainage:- 101.600km to 102.200km.
Sl. Description of Item (With brief No or % Length in m Width in Depth in Quantity Unit Rate in R Amount in R
No. specification and reference to book m m
of specification.)
1 2 3 4 5 6 7 8 9 10
1 Cleaning and grubbing road land including uprooting vegetation, grass, bushes,
shrubs, saplings and trees girth upto 300mm, removal of stumps of trees cut
earlier and disposal of unserviceable materials and stacking of serviceable
materials to be used or auctioned, upto a lead of 1000m including removal and
disposal of top organic soil not exceeding 150mm in thickness.
7 Construction of cement concrete Kerb with top and bottom width 115 and
165mm respectively 250mm high in M 20 grade P.C.C on M-10 grade foundation
150mm thick foundation having 50mm projection beyond Kerb stone Kerb stone
laid with Kerb laying machine foundation concrete laid manual all complete as per
clause 408 Sl. No.8.1 clause 408.
8 Providing fitting and fixing of High Mast light including cost of all materials
and labour etc.
2.000 Nos
Total 2.000 Nos ### R. 100,000.00
9 Providing fitting and fixing of Street light including cost of all materials and
labour etc.
8.000 Nos
Total 8.000 Nos ### R. 200,000.00
Length of cover drain having 2.0m 1 404.000 2.200 1.700 1510.960 Cum
width Total 1510.960 Cum 130.80 R. 197,633.57
2 45mm size H.G Metal (C B) Jayantigiri Cum 742.86 18 264.07 130.00 1006.93
17 Soling Stone (Spall)(40 to 90) Mangalpur Cum 204.76 18 264.07 130.00 468.83
19 Granite stone screening 2.36mm Jayantigiri Cum 695.24 18 264.07 35.00 959.31
23 Sand for Road Work Telguri Cum 53.33 27.0 343.27 35.00 396.60
24 Sand for mortar Telguri Cum 56.19 27.0 343.27 35.00 399.46
Certified that the lead statement given above are minimum and true to the best of my knowledge.
E
n
g
i
n
e
e
r
N
H
.
S
u
b
D
i
v
i
s
i
o
n
B
o
r
i
NAME OF THE WORK : WIDENING TO DOUBLE LANE WITH PAVED SHOULDER FROM KM 294/280 TO KM 319/280 (NABARANGPUR TO
BORIGUMMA) OF NH-26 FOR THE YEAR 2019-20 IN THE STATE OF ODISHA.
RATE OF ANALYSIS
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
ROAD PROPER
1.00 201 1 Clearing and Grubbing Road Land . Ref page no 21 (DATA BOOK)
Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, saplings
and trees girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable
materials and stacking of serviceable material to be
used or auctioned, up to a lead of 1000 metres
including removal and disposal of top organic soil
not exceeding 150 mm in thickness.
Unit = Hectare
Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable
material with all lifts and up to a lead of 1000 metres and sand filling in the depression/pit.
Unit = Each
1.02a (i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 338.00 6.76
Mazdoors for cutting trees including cutting, refilling, day 0.600 298.00 178.80
compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 200.87 20.09
c) Overhead charges @8% on (a+b) 16.45
d)Contractor's profit @10% on (a+b+c) 22.21
Rate per each tree = a+b+c+d 244.31
Add 1% for Labour Welfare Cess. 2.44
246.75 /Each
Say 246.70 /Each
1.02.b (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 338.00 13.52
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Mazdoors for cutting trees including cutting, refilling, day 0.900 298.00 268.20
compaction of backfilling, and stacking of
serviceable materials within 1000 metres lead by
manual means
b) Machinery
Tractor-trolley hour 0.300 200.87 60.26
c) Overhead charges @8% on (a+b) 27.36
d)Contractor's profit @10% on (a+b+c) 36.93
Rate per each tree = a+b+c+d 406.27
Add 1% for Labour Welfare Cess. 4.06
410.33 /Each
Say 410.30 /Each
1.02.c (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 338.00 27.04
Mazdoors for cutting trees including cutting, refilling, day 2.000 298.00 596.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 200.87 80.35
c) Overhead charges @8% on (a+b) 56.27
d)Contractor's profit @10% on (a+b+c) 75.97
Rate per each tree = a+b+c+d 835.63
Add 1% for Labour Welfare Cess. 8.36
843.99 /Each
Say 844.00 /Each
1.02.d (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 338.00 54.08
Mazdoors for cutting trees including cutting, refilling, day 4.000 298.00 1192.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 200.87 120.52
c) Overhead charges @8% on (a+b) 109.33
d)Contractor's profit @10% on (a+b+c) 147.59
Rate per each tree = a+b+c+d 1623.52
Add 1% for Labour Welfare Cess. 16.24
1639.76 /Each
Say 1639.80 /Each
1.03 202 3 Dismantling of Structures Ref page no 23(DATA BOOK)
Dismantling of existing structures like culverts,
bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled
material, disposal of unserviceable material and
stacking the serviceable material with all lifts and
lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
3.00 B Cement Concrete Grade M-15 & M-20 Ref page no 24(DATA BOOK)
a) Labour
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
b) Machinery
Tractor-trolley hour 0.270 200.87 54.23
c) Overhead charges @8% on (a+b) 35.49
d) Contractor's profit @10% on (a+b+c) 47.91
Cost for 1.25 cum = a+b+c+d 527.03
Rate per cum = (a+b+c+d)/ 1.25 421.62 /Cum.
Add 1% for Labour Welfare Cess. 4.22
425.84 /Cum.
1.03.b A Prestressed/reinforced cement concrete grade M-20 Ref page no 26 (DATA BOOK)
& above.
a) Labour
Mate day 0.050 338.00 16.90
Mazdoor with pneumatic breaker day 0.660 298.00 196.68
Blacksmith. day 0.250 388.00 97.00
Mazdoor for loading and unloading. day 0.250 298.00 74.50
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic
breaker @ 1.00 cum per hour. hour 1.000 179.13 179.13
Tractor-trolley hour 0.270 200.87 54.23
c) Overhead charges @8% on (a+b) 49.48
d) Contractor's profit @10% on (a+b+c) 66.79
Cost for 1.25 cum = a+b+c+d 734.71
Rate per cum = (a+b+c+d)/ 1.25 587.77 /Cum.
Add 1% for Labour Welfare Cess. 5.88
593.65 /Cum.
Say 593.70 /Cum.
1.03.a B Rubble stone masonry in cement mortar. Ref page no 28(DATA BOOK)
a) Labour
Mate day 0.030 338.00 10.14
Mazdoor for dismantling, loading and unloading. day 0.750 298.00 223.50
b) Machinery
Tractor-trolley hour 0.270 200.87 54.23
c) Overhead charges @8% on (a+b) 23.03
d) Contractor's profit @10% on (a+b+c) 31.09
Cost for 1.25 cum = a+b+c+d 341.99
Rate per cum = (a+b+c+d)/ 1.25 273.59
say 273.59 0
Add 1% for Labour Welfare Cess. 2.74
276.33 /Cum.
Say 276.30 /Cum.
6.00 E Dismantling stone pitching/ dry stone spalls. Ref page no 30(DATA BOOK)
a) Labour
Mate day 0.016 338.00 5.41
Mazdoor for dismantling, loading and unloading. day 0.400 298.00 119.20
b) Machinery
Tractor-trolley hour 0.270 200.87 54.23
c) Overhead charges @8% on (a+b) 14.31
d) Contractor's profit @10% on (a+b+c) 19.32
Cost for 1.25 cum = a+b+c+d 212.47
Rate per cum = (a+b+c+d)/ 1.25 169.98
Add 1% for Labour Welfare Cess. 1.70
171.68 /Cum.
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = metre
Taking output = 1 metre
(i) Up to 600 mm dia
a) Labour
Mate day 0.020 338.00 6.76
Mazdoor day 0.520 298.00 154.96
b) Overhead charges @ on (a) 12.94
c) Contractor's profit @ 10 % on (a+b) 17.47
Rate per metre = a+b+c 192.13
Add 1% for Labour Welfare Cess. 1.92
194.05 /Rmt.
Say 194.10 /Rmt.
1.04.b (ii) Above 600 mm to 900 mm dia
a) Labour
Mate day 0.030 338.00 10.14
Mazdoor day 0.700 298.00 208.60
b) Overhead charges @8% on (a) 17.50
c) Contractor's profit @ 10 % on (a+b) 23.62
Rate per metre = a+b+c 259.86
Add 1% for Labour Welfare Cess. 2.60
262.46 /Rmt.
Say 262.50 /Rmt.
652.27 /Cum.
Say 652.30 /Cum.
10.00 301 Excavation in Soil by Manual Means . Ref page no 48(DATA BOOK)
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000
metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 338.00 608.40
Mazdoor day 45.000 298.00 13410.00
b) Machinery
Truck 5.5 cum capacity hour 10.000 506.09 5060.90
Basic value 19079.30
c) Overhead charges @8% on (a+b) 1526.34
d) Contractor's profit @10% on (a+b+c) 2060.56
Cost of 120 cum = a+b+c+d 22666.20
Rate per cum = (a+b+c+d)/120 188.89
Add 1% for Labour Welfare Cess. 1.89
190.78 /Cum.
Say 190.80 /Cum.
unit = cum
Taking output = 1cum
a) Labour
Mate day 0.030 338.00 10.14
Semi skilled mazdoor for operating pneumatic tools day 0.500 298.00 149.00
Mazdoors as helpers including loading & unloading day 0.500 298.00 149.00
b) Machinery
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Air compressor 250 cfm with two leads for hour 1.000 179.13 179.13
pneumatic cutters/hammers @ 1cum per hour
Tractor Trolley hour 0.400 200.87 80.35
Joint cutting Machine with 2-3 blades hour 1.000 260.87 260.87
unit = sqm
Taking output = 72.46 sqm (2 tonnes) (0.869 cum)
assuming a density of 2.3 tonnes/cum
a) Labour
Mate day 1.021 338.00 345.04
Mazdoor day 22.917 298.00 6829.17
Mazdoors skilled day 2.604 338.00 880.21
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.125 200.00 25.00
Air compressor 250 cfm hour 0.125 179.13 22.39
Mastic Cooker 1 tonne capacity hour 12.500 1379.13 17239.13
Bitumen boiler 1500 litres capacity hour 12.500 111.30 1391.25
Tractor for towing & positiong of mastic cooker & hour 2.083 200.87 418.48
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60%
Coarse aggregates (3.35 mm to 9.5 mm ) = 40%
Proportion of material required for mastic asphalt
with coarse aggregates (based on mix design done
by CRRI for a specific case)
v) Pre-coated stone chips of 13.2mm nominal size cum 0.036 1364.07 49.11
for skid resistance = 72.46x0.005/10=0.036
vi) Bitumen for coating of chips @ 2% by weight kg 1.050 32013.55 33614.23
=0.036x1.456x2/100= 0.001048 MT=1.05kg
iv) Coarse aggregates 3.35mm to 9.5mm @ 40% by cum 1.146 82.50 94.53
weight mix = 2x40/100=0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2mm nominal size cum 0.036 130.00 4.68
for skid resistance = 72.46x0.005/10=0.036
a) Labour
Mate day 1.021 338.00 345.04
Mazdoor day 22.917 298.00 6829.17
Mazdoors skilled day 2.604 298.00 776.04
b) Machinery
Supply of complete assembly of strip seal expansion RM 12.000 8260.87 99130.44
joint comprising of edge beams, anchorage, strip
seal element & complete accessories as per
approved specifications & drawings.
2.01 (a) 301 5 Excavation in soil using hydrolic excavator CK-90 Ref page no 52(DATA BOOK)
with tipper and disposal upto 1000 mtr.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 338.00 27.04
Mazdoor day 2.000 298.00 596.00
b) Machinery
Hydraulic excavator for 0.90 cum. Bucket capacity
60 cum. Per hour. hour 6.000 730.43 4382.58
Tipper. hour 16.000 506.09 8097.44
13.00 301.0 Excavation in Hard Rock (blasting prohibited) Ref page no 54(DATA BOOK)
16904.76
c)Overhead charges @8% on (a+b) 1352.38
d)Contractor's profit @10% on (a+b+c) 1825.71
Cost for 16 cum = a+b+c+d 20082.85
Rate per cum = (a+b+c+d)/16 1255.18
Net cost per cum. say 1255.18 0
Add 1% for Labour Welfare Cess. 12.55
1267.73 /Cum.
2.03 305.4.3 6 Scarifying Existing Bituminous Surface to a depth of Ref page no 67(DATA BOOK)
50 mm by Mechanical Means
2.02 305 8 Construction of Embankment with Material obtained Ref page no 68(DATA BOOK)
from Borrowpits
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 864.35 864.35
c) Material
Cost of water(Assume Rate) KL 24.000 15.60 374.40
2.05 305 9 Construction of Embankment with Material obtained Ref page no 70(DATA BOOK)
from Roadway cutting.
Construction of embankment with approved material
deposited at site from road way cutting and
excavation from drain and foundation of other
structures graded and compacted to meet
requirement of table-300-2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 338.00 6.76
Mazdoor day 0.500 298.00 149.00
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 1592.17 796.09
Motor grader for grading @ 100 cum per hour hour 1.000 1343.48 1343.48
Water tanker6 KL capacity hour 4.000 506.09 2024.36
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 864.35 864.35
c) Material
Cost of water(Assume Rate) KL 24.000 15.60 374.40
d) Overhead charges @8% on (a+b+c) 444.68
e) Contractor's profit @10% on (a+b+c+d) 600.31
Cost for 100 cum = a+b+c+d+e 6603.43
Rate per cum = (a+b+c+d+e)/100 66.03
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
3.18 305 Construction of Sub-grade and Earthen shoulder. Ref page no 71(DATA BOOK)
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 1592.17 796.09
Motor grader for grading @ 100 cum per hour hour 2.000 1343.48 2686.96
Water tanker6 KL capacity hour 4.000 506.09 2024.36
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.250 864.35 1080.44
c) Material
Cost of water(Assume Rate) KL 24.000 15.60 374.40
d) Overhead charges @8% on (a+b+c) 871.99
e) Contractor's profit @10% on (a+b+c+d) 1177.18
Cost for 100 cum = a+b+c+d+e 12949.01
f) Add for cost of Royalty
Royalty cum 100.000 35.00 3500.00
16449.01
Rate per cum = (a+b+c+d+e+f)/100 164.49
say 164.49
Add 1% for Labour Welfare Cess. 1.64
166.13 /Cum
3.18 305 Construction of Subgrade and Earthen Shoulders Ref page no 71(DATA BOOK)
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 338.00 13.52
Mazdoor day 1.000 298.00 298.00
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60
cum per hour hour 1.670 730.43 1219.82
Tipper 10 tonne capacity : lead 5 km tonne.km 175xL(10) 2.17 3797.50
Add 10 per cent of cost of carriage to cover cost of
loading and unloading 379.75
Dozer 80 HP for spreading @ 200 cum per hour
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Dozer 80 HP for spreading @ 200 cum per hour
hour 0.500 1592.17 796.09
Motor grader for grading @ 50 cum per hour
hour 2.000 1343.48 2686.96
Water tanker with 6 km lead hour 4.000 506.09 2024.36
Vibratory roller 8-10 tonnes @ 80 cum per hour
hour 1.250 864.35 1080.44
c) Material
Cost of water(Assume Rate) KL 24.000 15.60 374.40
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 338.00 3407.04
Mazdoor skilled day 2.000 388.00 776.00
Mazdoor day 250.000 298.00 74500.00
b) Machinery
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000 294.78 3537.36
Water tanker 6 KL capacity hour 24.000 506.09 12146.16
c) Material
90mm to 40mm(Hard Stone) cum 435.600 468.83 204222.35
Cost of moorum cum 108.000 197.29 21307.32
Cost of water KL 144.000 10.00 1440.00
d) Overhead charges @ on (a+b+c) 25706.90
e) Contractor's profit @10% on (a+b+c+d) 34704.31
e) Add for royalty
90mm to 40mm(Hard Stone) cum 435.600 130.00 56628.00
Cost of moorum cum 108.000 35.00 3780.00
Cost for 600 cum = a+b+c+d+e 442155.44
Rate per cum = (a+b+c+d+e)/360 1228.21
Add 1% for Labour Welfare Cess. 12.28
1240.49 /cum
2.04 305.3.4 11 Compacting Original Ground
Compacting original ground supporting Embankment Ref page no 73(DATA BOOK)
150mm below Sub-grade.
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
21.00 301 Excavation in Hilly Area in Ordinary Rock by Ref page no 85 (DATA BOOK)
Mechanical Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring
blasting by mechanical means including cutting and
trimming of slopes and disposal of cut material with
all lift and lead upto 1000 metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 338.00 108.16
Mazdoor day 8.000 298.00 2384.00
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 2190.43 13142.58
Front end loader hour 7.000 452.17 3165.19
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 506.09 3542.63
c)Overhead charges @8% on (a+b) 1787.40
d)Contractor's profit @10% on (a+b+c) 2413.00
Cost for 170 cum = a+b+c+d 26542.96
Rate per cum = (a+b+c+d)/170 156.14
Add 1% for Labour Welfare Cess. 1.56
157.70 /M3
Say 157.70 /M3
2.01 (b) 301 13 Excavation in Hilly Areas in Hard Rock Requiring Ref page no 86 (DATA BOOK)
Blasting
4.10 401 Granular Sub- Base with Close Graded Material Ref page no 94(DATA BOOK)
(Table-400-1)
A. Mix in Place Method
Construction of granular sub-base by providing close
graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in
place method with rotavator at OMC, and
compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300cum
a) Labour
Mate day 0.480 338.00 162.24
Mazdoor skilled day 2.000 388.00 776.00
Mazdoor day 10.000 298.00 2980.00
b) Machinery 3918.24
Motor grader 110 HP hour 6.000 1343.48 8060.88
Vibratory roller 8-10 t. hour 6.000 864.35 5186.10
Tractor - Rotavator hour 12.000 210.43 2525.16
Water tanker 6 KL capacity hour 3.000 506.09 1518.27
c) Material 17290.41
For Grading II material.
Total(a+b+c)
d)Overhead charges @8% on (a+b+c) 26086.61
e) Contractor's profit @10% on (a+b+c) 35216.93
Cost for 300 cum = a+b+c+d+e 387386.21
f) Add for cost of Royalty.
26.5mm to 9.5mm @ 35 per cent. cum 134.400 130.00 17472.00
9.5mm to 2.36mm @ 25 per cent. cum 96.000 82.50 7920.00
2.36mm below 40% (2.36mm+Dust) cum 153.600 35.00 5376.00
418154.21
Rate per cum = (a+b+c+d+e+f)/300 1393.85
Add 1% for Labour Welfare Cess. 13.94
1407.79 /cum
Say, 1407.80 /cum
3.01 (ii) 401 14 Granular Sub-Base with Coarse Graded Material Ref page no 95(DATA BOOK)
(Table:- 400- 2)
Construction of granular sub-base by providing
coarse graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by
mix in place method with rotavator at OMC, and
compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 338.00 135.20
Mazdoor skilled day 2.000 388.00 776.00
Mazdoor day 8.000 298.00 2384.00
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 1343.48 8060.88
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
A By Manual Means
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 338.00 135.20
Mazdoor skilled day 2.000 388.00 776.00
Mazdoor day 8.000 298.00 2384.00
b) Machinery 3295.20
Motor grader 110 HP 50 cum/ hour. hour 6.000 1343.48 8060.88
Vibratory roller. hour 6.000 864.35 5186.10
Rotavator + tractor. hour 12.000 210.43 2525.16
Water tanker. hour 3.000 506.09 1518.27
c) Material 17290.41
Grade-II
4.20 401 (b) Granular Sub-base Course graded. Ref page no 95(DATA BOOK)
A By Manual Means
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 338.00 135.20
Mazdoor skilled day 2.000 388.00 776.00
Mazdoor day 8.000 298.00 2384.00
b) Machinery 3295.20
Motor grader 110 HP 50 cum/ hour. hour 6.000 1343.48 8060.87
Vibratory roller. hour 6.000 864.35 5186.09
Rotavator + tractor. hour 12.000 210.43 2525.22
Water tanker. hour 3.000 506.09 1518.26
c) Material 17290.44
Grade-II
Unit = cum
a) Labour
Mate day 0.080 338.00 27.04
Mazdoor day 2.000 298.00 596.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 200.00 560.00
Air compressor 250 cfm hour 2.800 179.13 501.57
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 448.70 897.39
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.700 27263.55 19084.49
d) Overhead charges @8% on (a+b+c) 1733.32
e) Contractor's profit @10% on (a+b+c+d) 2339.98
Cost for 3500 sqm = a+b+c+d+e 25739.79
Rate per sqm = (a+b+c+d+e)/3500 7.35
Add 1% for Labour Welfare Cess. 0.07
7.42 /Sqm.
Say 7.40 /Sqm.
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 338.00 283.92
Mazdoor working with HMP, mechanical broom, day 14.000 298.00 4172.00
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 388.00 1940.00
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 9710.43 58262.61
actual output
Air compressor 250 cfm hour 2.200 179.13 394.09
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1500.00 9000.00
cum per hour
Generator 250KVA hour 6.000 978.26 5869.57
Front end loader 1 cum bucket capacity hour 6.000 452.17 2713.04
Tipper 10 tonne capacity tonne.km 450 x L 2.17 5859.00
Add 10 per cent of cost of carriage to cover cost of (working distance/4) 585.90
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 294.78 1149.64
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 864.35 3370.96
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Finish rolling with 6-8 tonnes smooth wheeled hour 6.00x0.65* 641.74 2502.78
tandem roller.
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.85 27263.55 404863.72
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
GradingII(19 mm nominal size)
20 - 10 mm 40 per cent cum 116.040 1356.45 157402.46
(Avg rate of 25mm and 10mm )
10 - 5 mm 40 per cent cum 116.040 1215.98 141101.74
(Avg rate of 10mm and 4.7mm )
5 mm and below 20 per cent cum 58.020 666.93 38694.99
(Rate of 4.74+dust/2)
* Any one of the alternative may be adopted as per approved design
(ii) for GradingII(19 mm nominal size)
d) Overhead charges @8% on (a+b+c) 67053.31
e) Contractor's profit @10% on (a+b+c+d) 90521.97
Cost for 205 cum = a+b+c+d+e 995741.70
f) Add for cost of Royalty.
Unit = cum
Taking output = 195cum (450 tonnes)
a) Labour
Mate day 0.840 338.00 283.92
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Mazdoor working with HMP, mechanical broom, day 14.000 298.00 4172.00
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 388.00 1940.00
b) Machinery
Batch mix HMP 100-120 TPH @ 75 tonne per hour hour 6.000 7765.22 46591.32
actual output
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1500.00 9000.00
cum per hour
Generator 250KVA hour 6.000 978.26 5869.57
Front end loader 1 cum bucket capacity hour 6.000 452.17 2713.04
Tipper 10 tonne capacity tonne.km 450 x L 2.17 5859.00
Add 10 per cent of cost of carriage to cover cost of 585.90
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 294.78 1149.64
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 864.35 3370.96
Finish rolling with 6-8 tonnes smooth wheeled hour 6.00x0.65* 641.74 2502.78
tandem roller.
c) Material
i) Bitumen@ 4.25 per cent of weight of mix. tonne 19.13 32013.55 612419.21
weight of mix = 195 x 2.31 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 338.00 283.92
Mazdoor working with HMP, mechanical broom, day 14.000 338.00 4732.00
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 388.00 1940.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 11167.00 67002.00
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 1725.00 10350.00
cum per hour
Generator 250 KVA hour 6.000 1125.00 6750.00
Front end loader 1 cum bucket capacity hour 6.000 520.00 3120.00
Tipper 10 tonne capacity tonne.km 450 x L 2.17 5859.00
Add 10 per cent of cost of carriage to cover cost of (working distance/4) 585.90
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 294.78 1149.64
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 994.00 3876.60
Finish rolling with 6-8 tonnes smooth wheeled hour 6.00x0.65* 738.00 2878.20
tandem roller
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix (CRMB-55) tonne 22.500 32013.55 720304.88
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 1215.98 197535.14
(Avg rate of 10mm and 4.7mm)
4.75 and below@ 41 per cent cum 116.850 666.93 77930.19
(Avg rate of 4.7mm and Dust)
(dust) Filler @ 2 per cent of weight of aggregates. cum 5.747 360.26 2070.41
Assuming 2 tonne / cum of crusher dust
*Any one of the alternative may be adopted as per
approved design
1332058.07
Rate per cum = (a+b+c+d+e+f)/195 (For Grading-II) 6831.07
Add 1% for Labour Welfare Cess. 68.31
6899.38 /Cum.
Say 6899.40 /Cum.
Unit = sqm
Taking output = 9000 sqm
32.00 Case - II 13 mm nominal size chipping
a) Labour
Mate day 0.440 338.00 148.72
Mazdoor day 9.000 298.00 2682.00
Mazdoor skilled day 2.000 388.00 776.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 200.00 1440.00
Air compressor 250 cfm hour 7.200 179.13 1289.74
Hydraulic self propelled chip spreader @ 1500 sqm
per hour hour 6.000 1478.26 8869.57
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
hour 6.000 506.09 3036.52
Front end loader 1 cum bucket capacity hour 6.000 452.17 2713.04
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
Case-I : Type A
a) Labour
Mate day 0.240 338.00 81.12
Mazdoor day 6.000 298.00 1788.00
b) Machinery
Hydraulic self propelled chips spreader hour 6.000 1478.26 8869.57
Tipper 5.5 cum capacity. hour 6.000 506.09 3036.54
Front end loader 1 cum bucket capacity. hour 6.000 452.17 2713.04
Bitumen pressure distributor @ 1750 sqm. per hour. hour 6.000 601.74 3610.43
Smooth wheeled roller 8-10 tonne weight. hour 6.000 294.78 1768.68
c) Material
Bitumen @ 9.80 kg. per 10 sqm. tonne 10.050 27263.55 273998.68
Crushed stone chipping of 6.7mm size defined as cum 92.25 1039.31 95876.35
100 per cent passing 11.2mm sieve and retained on
2.36 mm sieve applied @ 0.09 cum per 10 sqm.
468618.73
Rate per sqm = (a+b+c+d+e+f)/10250 45.72
Add 1% for Labour Welfare Cess. 0.46
46.18 /M2
Say 46.20 /M2
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Printing new letter and figures of any shade with Ref page no 211(DATA BOOK)
synthetic enamel paint black or any other approved
colour to give an even shade.
Unit = Each.
Taking output = One traffic sign.
(i) Excavation of foundation. cum 0.216 129.53 27.98
(ii) Cement concrete M-15 grade. cum 0.120 4157.01 498.84
(iii) Painting angle Iron post two coats. Sqm. 0.430 56.80 24.42
551.24
a) Labour (for fixing at site.)
Mate. day. 0.010 338.00 3.38
Mazdoor. day. 0.250 298.00 74.50
77.88
b) Material.
Mild steel angle 75 x75 x6mm. Kg. 19.000 30.55 580.51
Aluminium sheeting fixed with encapsulated lens
type reflective sheeting of size including lettering
and signs as applicable
Add 2% of cost of angle iron towards cost of drilling 11.61
holes, nuts, bolts.
(i) 90 cm equilateral Triangle. Sqm. 0.350 7000.00 2450.00
(ii) 80mm x 60mm Retangular. Sqm. 0.480 7000.00 3360.00
(iii) 60cm. Circular. Sqm. 0.283 7000.00 1981.00
(iv) 90 cm. circular. Sqm. 0.636 7000.00 4452.00
(v) 60 cm x 45 cm rectangular sqm 0.270 7000.00 1890.00
(vi) 60 cm x 60 cm square sqm 0.360 7000.00 2520.00
(vii) 90 cm high octagon sqm 0.672 7000.00 4704.00
(c ) Machinery.
Tractor Trolley. hour 0.010 200.87 2.01
E 60 cm x 45 cm rectangular 3113.25
d) Overhead charges @8% on (a+b+c) 204.96
e) Contractor's profit @10% on (a+b+c+d) 221.36
Rate per traffic sign = a+b+c+d+e 3539.57 /Each.
Add 1% for Labour Welfare Cess. 35.40
3574.97 /Each
Say 3575.00 /Each
8.07 (a) 801 21 Direction and place Identification Signs upto 0.9 Ref page no 215(DATA BOOK)
(ii) sqm. Size Board.
Unit = Sqm.
Taking output = 0.90 Sqm.
A) (i) Excavation of foundation. cum 0.216 129.53 27.98
(ii) Cement concrete M-15 grade. cum 0.120 4157.01 498.84
(iii) Painting angle Iron post two coats. Sqm. 0.430 56.80 24.42
551.24
a) Labour (for fixing at site.)
Mate. day. 0.010 338.00 3.38
Mazdoor. day. 0.200 298.00 59.60
62.98
b) Material.
Mild steel angle 75 x75 x6mm 2,85 mt. long. Kg. 19.000 30.55 580.51
Alluminium sheeting fixed with encapsulated lengs, Sqm. 0.900 7000.00 6300.00
type reflective sheeting of size 0.9 sqm.
Add 2% of cost of angle iron towards cost of drilling 137.61
holes, nuts, bolts.
(c ) Machinery.
Tractor Trolley. hour 0.020 200.87 4.02
A+a+b+c 7636.36
8.07 (a) 801 22 Direction and place identification signs, with size Ref page no 215(DATA BOOK)
(iii) more than 0.9 sqm. Size board.
Unit = Sqm.
Taking output = 1.50 Sqm.
(i) Excavation of foundation. cum 0.430 129.53 55.70
(ii) Cement concrete M-15 grade. cum 0.240 4157.01 997.68
(iii) Painting angle Iron post two coats. Sqm. 0.860 56.80 48.85
1102.23
a) Labour (for fixing at site.)
Mate. day. 0.010 338.00 3.38
Mazdoor. day. 0.300 298.00 89.40
92.78
b) Material.
Mild steel angle 75 x75 x6mm 2,85 mt. long = 2 Nos. Kg. 38.000 30.55 1161.03
Alluminium sheeting fixed with encapsulated lengs, Sqm. 1.500 7000.00 10500.00
type reflective sheeting of size 0.9 sqm.
Add 2% of cost of angle iron towards cost of drilling 233.22
holes, nuts, bolts.
(c ) Machinery.
Tractor Trolley. hour 0.020 200.87 4.02
13093.28
Aluminium sheet
B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 338.00 6.76
Blacksmith day 0.100 388.00 38.80
Mazdoor day 0.150 298.00 44.70
b) Material
Aluminium alloy plate,2 mm thick, fixed with high sqm 1.000 11000.000 11000.00
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting 0.90
arrangement, like ladders, pulleys, ropes etc
b) Material
Aluminium alloy plate,2 mm thick, fixed with high sqm 1.000 11000.000 11000.000
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting 0.90
arrangement, like ladders, pulleys, ropes etc
c) Overhead charges @ 10% on (a+b) 1109.12
Rate per sqm = (a+b+c+d) 12200.28
say 12200.28
8.09 805 24 Road Delineators Ref page no 215(DATA BOOK)
8.09.a Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100 cm
high above ground level, painted black and white in 15 cm wide strips, fitted with 80 x 100 mm rectangular or
75 mm dia circular reflectorised panels at the top, buried or pressed into the ground and conforming toIRC-79
and the drawings.
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 338.00 13.52
Mazdoor for fixing day 1.000 298.00 298.00
b) Material
Cost of approved type of delineators from ISI each 30.000 400.00 12000.00
certified firm as per the standard drawing given in
IRC - 79
Add 10 per cent cost of material for installation 1200.00
5.15, 803 26 Painting Two Coats on New Concrete Surfaces Ref page no 220(DATA BOOK)
8.04,
9.09
Painting two coats after filling the surface with
synthetic enamel paint in all shades on new
plastered concrete surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 338.00 40.56
Painter day 2.000 448.00 896.00
Mazdoor day 1.000 298.00 298.00
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 151.97 911.82
(market Rate)
Add for scaffolding @ 1 per cent of labour cost 12.35
where required
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.03 338.00 10.14
Painter day 0.45 448.00 201.60
Mazdoor day 0.25 298.00 74.50
b) Material
Paint ready mixed approved brancd Litres 1.25 151.97 189.96
Add @ 1% on cost of material in scaffolding. 1.90
Add @ 5% cost of labour and materials to prepare
the surface by filling minute roughness on the
surface before laying 2nd. Coat of painting.
8.06 (i) 803 27 Road Marking with Hot Applied Thermoplastic Ref page no 225(DATA BOOK)
Compound with Reflectorising Glass Beads on
Bituminous Surface
Providing and laying of hot applied thermoplastic
compound 2.5 mm thick including reflectorising
glass beads @ 250 gms per sqm area, thickness of
2.5 mm is exclusive of surface applied glass beads
as per IRC:35 .The finished surface to be level,
uniform and free from streaks and holes.
Unit = sqm
Taking output = 640 sqm
a) Labour
Mate day 0.500 338.00 169.00
Mazdoor day 2.000 298.00 596.00
b) Machinery
Road marking machine @ 60 sqm per hour hour 8.000 52.17 417.39
Tractor-trolley hour 8.000 200.87 1606.96
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
c) Material
Hot applied thermoplastic compound(market rate) Litre 2000.00 130.00 260000.00
Reflectorising glass beads kg 200.000 50.00 10000.00
d) Overhead charges @8% on (a+b+c) 21823.15
e) Contractor's profit @10% on (a+b+c+d) 29461.25
Cost for 640 sqm = a+b+c+d+e 324073.75
Rate per sqm = a+b+c+d+e)/640 506.37
Add 1% for Labour Welfare Cess. 5.06
511.43 /Sqm
Say 511.40 /Sqm
8.02 (b) (ii) Ordinary kilometer stone (precast) Ref page no 227(DATA BOOK)
Unit = Nos.
Taking output = 14 Nos.
a) M-15 grade of concrete cum 3.770 4317.98 16278.78
Ref vide item no 12.8
b) Steel reinforcement @ 5 kg per sqm kg 26.320 56.31 1482.11
8.02 (a) (iii) Hectometer stone (precast) Ref page no 227(DATA BOOK)
Unit = Nos.
Taking output = 33 Nos.
a) M-15 grade of concrete cum 1.580 4317.98 6822.41
Ref vide item no 12.8
b) Steel reinforcement @ 5 kg per sqm( ref basic
rate/1000 of item no 12.4 kg 66.000 56.31 3716.53
Ref vide item no 12.40.
c) Excavation in soil for foundation cum 1.390 129.53 180.05
Ref vide item no 3.1.
d) Painting two coats on concrete surface sqm 6.270 64.11 402.00
Ref vide item no 8.8
e) Lettering on km post (average 1 letter of 10 cm per cm per
height each) letter 330.00 0.80 264.00
Transportation and fixing
f) Labour
Mate day 0.340 338.00 114.92
Mason day 1.500 448.00 672.00
Mazdoor day 7.000 298.00 2086.00
g) Machinery
Tractor-trolley hour 6.000 200.87 1205.22
h) Overhead charges @8% on (f+g) 326.25
i) Contractor's profit @10% on (f+g+h) 440.44
Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+ g+h+i) 16229.82
Rate for each Hectometer stone = (a+b +c +d+e+f+ g+h+i) 33 491.81
Add 1% for Labour Welfare Cess. 4.92
496.73 /Each
Say 496.70 /Each
Guard post
8.16 806 Reinforcement cement concrete M-15 using 10mm Ref page no 229(DATA BOOK)
to 12mm size chips for guard posts of standard
design as per IRC-25-1967 fixed in position
including finishing and lettering including painting
Unit-Each Taking out put= 57 nos. for Guard posts
Data Book P-229 Sr. 8.16 (806)
d) Lettering, each 10 cm high per letter per cm high 2280.00 0.80 1824.00
Transportation and fixing
e) Labour
Mate day 0.570 338.00 192.66
Mazdoor day 14.250 298.00 4246.50
f) Machinery
Tractor-trolley hour 6.000 200.87 1205.22
g) Material
Stone spall cum 11.970 468.83 5611.90
h) Overhead charges @8% on (e+f+g) 900.50
i) Contractor's profit @10% on (e+f+g+h) 1215.68
Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i ) 26476.13
j) Add for cost of Royalty.
Stone spall cum 11.970 130.00 1556.10
28032.23
Rate for each boundary pillar = (a+b+c+d+e+ 491.79
f+g+h+i+j)/57
Add 1% for Labour Welfare Cess. 4.92
496.71 /Each
Say 496.70 /Each
9.10 30 Guard Post (precast)
Unit = Nos.
Taking output = 14 Nos.
a) M-15 grade of concrete cum 0.424 4317.98 1830.82
b) Steel reinforcement @ 5 kg per sqm kg 25.410 56.31 1430.86
c) Excavation in soil for foundation cum 2.770 129.53 358.80
Transportation and fixing
f) Labour
Mate day 0.320 338.00 108.16
Mason day 1.000 448.00 448.00
Mazdoor day 7.000 298.00 2086.00
g) Machinery
Tractor-trolley hour 6.000 200.87 1205.22
h) Overhead charges @ 8% on (f+g) 307.79
i) Contractor's profit @ 10% on (f+g+h) 415.52
Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i) 8191.17
Rate for each ordinary km stone = (a+b+ c +d+e+f+g+h+j) /14 585.08
Add 1% for Labour Welfare Cess. 5.85
590.93 /Each
Say 590.90 /Each
8.03 408 31 Cast in Situ Cement Concrete M20 Kerb Ref page no 207(DATA BOOK)
Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high
in M =20Running
Unit grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb
metre
stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
Taking
408 output = 360 metre
A Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61
cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 338.00 243.36
Mason day 2.000 388.00 776.00
Mazdoor day 16.000 298.00 4768.00
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 173.91 1043.48
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Concrete mixer 0.4 / 0.28 cum capacity hour 12.000 153.91 1846.96
Water tanker6 KL capacity hour 5.000 506.09 2530.43
c) Material
Crushed stone aggregate 20 mm nominal size 59 cum 21.790 1356.45 29557.05
per centsand 30 per cent
Coarse cum 10.900 399.46 4354.11
Cement 11 per cent tonne 5.700 5404.94 30808.16
Cost of water KL 30.000 15.60 468.00
d) Overhead charges @10% on (a+b+c) 7639.55
i) Contractor's profit @ 8% on (f+g+h) 6722.81
e) Royalty
Crushed stone aggregate 20 mm nominal size 59 cum 21.790 130.00 2832.70
per centsand 30 per cent
Coarse cum 10.900 35.00 381.50
Cost for 360 meter= a+b+c+d+e 93972.11
Rate per RM = (a+b+c+d+e)/360 261.03
Add 1% for Labour Welfare Cess. 2.61
263.64 /Rm
Say 263.60 /Rm
9.20 Laying Reinforced Cement Concrete Pipe Ref page no 273(DATA BOOK)
NP4/Presterssed Concrete Pipe on first Class
Bedding in Single Row.
Laying reinforced cement concrete pipe NP4/
prestressed concrete pipe for culverts on first class
bedding of granular material in single row including
fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete
land masonry works in head walls and parapets.
Unit = metre.
Taking output = 12.5 metre( 5 pipes of 2.5m length
each)
1200mm dia.
a) Labour
Mate day 0.280 338.00 94.64
Mason (2nd. Class) day 1.000 388.00 388.00
Mazdoor day 6.000 298.00 1788.00
b) Material.
Sand at site. Cum. 0.090 396.60 35.69
Cement at site. Tonne 0.070 5404.94 4375.00
RCC pipe NP-4/ prestressed concrete pipe including Meter. 12.500 1441.60 18020.00
collar at site.
Sales Tax @ 12.5% on cost of pipe 2252.50
Lead of pipe (considering the capacity of the truck 3 Meter. 12.500 1119.77 13997.13
no of pipes / trip, i.e 3 x 2.50 m = 7.50 m / trip)
Granular material passing 5-6 mm sieve for class cum. 5.000 197.29 986.45
bedding.
c) Overhead charges @8% on (a+b) 3174.79
d) Contractor's profit @10% on (a+b+c) 4285.97
Cost for 12.5 meter = a+b+c+d 47145.67
12.10 Earth work in excavation of foundation of structures Ref page no 323(DATA BOOK)
as per drawing and technical specification, including
setting out construction of shoring and bracing
removal of stumps and other deleterious materials,
dressing of sides and bottoms backfilling the
excavation earth to the extent required and utilising
the remaining earth locally for road work Data book
Page-323 Sr. 12.1 Data for 240 cum. Unit 1 cum.
Unit = cum
Data for = 240 cum
By Mech. Means.(Depth upto 3. mtr.)
a) Mate/Supervisor day 0.320 338.00 108.16
Mazdoor day 8.000 298.00 2384.00
Hydraulic excavator. Hr. 6.000 730.43 4382.61
Basic value 6874.77
b) Overhead charges @8% on (a) 549.98
c) Contractor's profit @10% on (a+b) 742.48
Cost of 240 cum = a+b+c 8167.23
Rate per cum = (a+b+c) 34.03
Add 1% for Labour Welfare Cess. 0.34
34.37 /Cum.
Say 34.40 /Cum.
12.10 Earth work in excavation of foundation of structures Ref page no 323(DATA BOOK)
as per drawing and technical specification, including
setting out construction of shoring and bracing
removal of stumps and other deleterious materials,
dressing of sides and bottoms backfilling the
excavation earth to the extent required and utilising
the remaining earth locally for road work Data book
Page-323 Sr. 12.1 Data for 240 cum. Unit 1 cum.
Unit = cum
Data for = 240 cum
A) By Mech. Means.(Depth upto 3. mtr.)
a) Mate/Supervisor day 0.320 338.00 108.16
Mazdoor day 8.000 298.00 2384.00
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = cum
Data for = 210 cum
B) By Mech. Means.(Depth upto 3mtr. To 6 mtr.)
a) Mate/Supervisor day 0.320 338.00 108.16
Mazdoor day 8.000 298.00 2384.00
Hydraulic excavator. Hr. 6.000 730.43 4382.61
Basic value 4490.77
b) Overhead charges @8% on (a) 549.98
c) Contractor's profit @10% on (a+b) 742.48
Cost of 240 cum = a+b+c 8167.23
Rate per cum = (a+b+c) 38.89
Add 7.5% for cost of dewatering. 2.92
41.81
Add 1% for Labour Welfare Cess. 0.42
42.23 /Cum.
Say 263.60 /Cum.
3.03, 304 32 Sand filling in foundation trenches as per drawing & Ref page no 331(DATA BOOK)
5.02, technical specification .
7.02,
9.03
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.010 338.00 3.38
Mazdoor day 0.300 298.00 89.40
b) Materials.
Sand (assuming 20% voids) Cum. 1.200 396.60 475.92
Basic value 568.70
c) Overhead charges @8% on (a+b) 45.50
d) Contractor's profit @10% on (a+b+c) 61.42
Cost of 1 cum = a+b+c+d 675.62
Rate per cum = (a+b+c+d) 675.62
e) Add for cost of royalty.
Sand (assuming 20% voids) Cum. 1.200 35.00 42.00
717.62
Add 1% for Labour Welfare Cess. 7.18
724.80 /Cum.
Say 724.80 /Cum.
9.06 2100 33.0 PCC 1:3:6 in Foundation Ref page no 331(DATA BOOK)
Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in
foundation and compacted by vibration including
curing for 14 days.
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 338.00 216.32
Mason day 1.00 388.00 388.00
Mazdoor day 15.00 298.00 4470.00
b) Material
40 mm Aggregate cum 13.50 1031.69 13927.82
coarse Sand cum 6.75 399.46 2696.36
cement tonne 3.45 5404.94 18647.04
Cost of water(Assume Rate) KL 18.00 15.60 280.80
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.48
Generator 33 KVA hour 6.00 208.70 1252.17
Water tanker 6 KL capacity hour 2.00 506.09 1012.17
d) Overhead charges @8% on (a+b+c) 3505.13
e) Contractor's profit @10% on (a+b+c+d) 4731.93
Cost for 15 cum = a+b+c+d+e 52051.22
f) Add for cost of Royalty.
40 mm Aggregate cum 13.50 130.00 1755.00
coarse Sand cum 6.75 35.00 236.25
54042.47
Rate per cum = (a+b+c+d+e+f)/15 3602.83
Add 1% for Labour Welfare Cess. 36.03
3638.86 /Cum.
Say 3638.90 /Cum.
5.03, 1100& 34.0 Levelling Course Ref page no 335(DATA BOOK)
6.02, 1700
7.03 (a),
9.02
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5404.94 22322.40
Coarse sand cum 6.75 399.46 2696.36
40 mm aggregate cum 8.10 1031.69 8356.69
20 mm Aggregate cum 4.05 1356.45 5493.62
10 mm Aggregate cum 1.35 1458.36 1968.79
b) Labour
Mate day 0.86 338.00 290.68
Mason day 1.50 388.00 582.00
Mazdoor day 20.00 298.00 5960.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.48
Generator 33 KVA hour 6.00 208.70 1252.17
d) Overhead charges @ 8% on (a+b+c) 3987.69
e) Contractor's profit @ 10% on (a+b+c+d) 5383.39
Granular material passing 5-6 mm sieve for class cum. 4.500 197.29 887.81
bedding.
c) Overhead charges @8% on (a+b) 7223.91
d) Contractor's profit @10% on (a+b+c) 9752.28
Cost for 12.5 meter = a+b+c+d 107275.05
e) Add for cost of Royalty
Sand at site. Cum. 0.070 35.00 2.45
Granular material passing 5-6 mm sieve for class cum. 4.500 35.00 157.50
bedding.
107435.00
Rate per meter = (a+b+c+d+e)/12.5 8594.80
say 8594.80
Add 1% for Labour Welfare Cess. 85.95
8680.75 /Meter.
Say 8680.80 /Meter.
6.04 (a) 2900 35 Laying Reinforced Cement Concrete Pipe Ref page no 272(DATA BOOK)
NP4/Presterssed Concrete Pipe on first Class
Bedding in Single Row.
Laying reinforced cement concrete pipe NP4/
prestressed concrete pipe for culverts on first class
bedding of granular material in single row including
fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete
land masonry works in head walls and parapets.
Unit = metre.
Taking output = 12.5 metre( 5 pipes of 2.5m length
each)
1000mm dia.
a) Labour
Mate day 0.180 338.00 60.84
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Granular material passing 5-6 mm sieve for class cum. 4.500 197.29 887.81
bedding.
c) Overhead charges @8% on (a+b) 8608.91
d) Contractor's profit @10% on (a+b+c) 11622.03
Cost for 12.5 meter = a+b+c+d 127842.30
e) Add for cost of Royalty
Sand at site. Cum. 0.070 35.00 2.45
Granular material passing 5-6 mm sieve for class cum. 4.500 35.00 157.50
bedding.
128002.25
Rate per meter = (a+b+c+d+e)/12.5 10240.18
say 10240.18
Add 1% for Labour Welfare Cess. 102.40
10342.58 /Meter.
Say 10342.60 /Meter.
6.04 (b) 2900 36 Laying Reinforced Cement Concrete Pipe Ref page no 273(DATA BOOK)
NP4/Presterssed Concrete Pipe on first Class
Bedding in Single Row.
Laying reinforced cement concrete pipe NP4/
prestressed concrete pipe for culverts on first class
bedding of granular material in single row including
fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete
land masonry works in head walls and parapets.
Unit = metre.
Taking output = 12.5 metre( 5 pipes of 2.5m length
each)
1200mm dia.
a) Labour
Mate day 0.280 338.00 94.64
Mason (2nd. Class) day 1.000 388.00 388.00
Mazdoor day 6.000 298.00 1788.00
b) Material.
Sand at site. Cum. 0.090 399.46 35.95
Cement at site. Tonne 0.070 5404.94 378.35
RCC pipe NP-4/ prestressed concrete pipe including Meter. 12.500 10519.28 131491.00
collar at site.
Granular material passing 5-6 mm sieve for class cum. 5.000 197.29 986.45
bedding.
c) Overhead charges @8% on (a+b) 10812.99
d) Contractor's profit @10% on (a+b+c) 14597.54
Cost for 12.5 meter = a+b+c+d 160572.92
e) Add for cost of Royalty
Sand at site. Cum. 0.090 35.00 3.15
Granular material passing 5-6 mm sieve for class cum. 5.000 35.00 175.00
bedding.
160751.07
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
49.00 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand) Ref page no 333(DATA BOOK)
analysis Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 5404.94 2756.52
Sand cum 1.05 399.46 419.43
b) Labour
Mate day 0.04 338.00 13.52
Mazdoor day 0.90 298.00 268.20
Total Material and Labour = (a+b) 3457.67 /Cum.
7.03(b), 1500, 37.0 Plain/Reinforced Cement Concrete in Open Ref page no 335(DATA BOOK)
9.02 (b) 1700 & Foundation complete as per Drawing and Technical
2100 Specifications.
a) Material
Cement tonne 4.13 5404.94 22322.40
Coarse sand cum 6.75 399.46 2696.36
40 mm Aggregate cum 8.10 1031.69 8356.69
20 mm Aggregate cum 4.05 1356.45 5493.62
10 mm Aggregate cum 1.35 1458.36 1968.79
b) Labour
Mate day 0.86 338.00 290.68
Mason day 1.50 388.00 582.00
Mazdoor day 20.00 298.00 5960.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.48
Generator 63 KVA hour 6.00 369.57 2217.39
Per Cum Basic Cost of Labour, Material & 50811.41
Machinery (a+b+c)
d) Overhead charges @8% on (a+b+c+d) 4064.91
e) Contractor's profit @10% on (a+b+c+d+e) 5487.63
Cost for 15 cum = a+b+c+d+e 60363.95
f) Add for cost of royalty.
B) For Foundation
(a+b+c) material + Labour + Machinery. 50811.41
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
52843.87
e) Overhead charges @8% on (a+b+c+d) 4227.51
a+b+c+d+e 57071.38
f) Contractor's profit @10% on (a+b+c+d+e) 5707.14
Cost for 15 cum = a+b+c+d+e+f 62778.51
g) Add for cost of royalty.
a) Material
Cement tonne 5.16 5404.94 27889.49
Coarse sand cum 6.75 399.46 2696.36
40 mm Aggregate cum 5.40 1031.69 5571.13
20 mm Aggregate cum 5.40 1356.45 7324.83
10 mm Aggregate cum 2.70 1458.36 3937.57
b) Labour
Mate day 0.86 338.00 290.68
Mason day 1.50 388.00 582.00
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
B) For Sub-structure.
(a+b+c) material + Labour + Machinery. 56427.71
d) Formwork @ 10 per cent on cost of concrete 5642.77
i.e. cost of material, labour and machinery
62070.48
e) Overhead charges @8% on (a+b+c+d) 4965.64
a+b+c+d+e 67036.12
f) Contractor's profit 10% 6703.61
Cost for 15 cum = a+b+c+d+e+f 73739.73
g) Add for cost of royalty.
67713.25
e) Overhead charges @8% on (a+b+c+d) 5417.06
a+b+c+d+e 73130.31
f) Contractor's profit 10% 7313.03
Cost for 15 cum = a+b+c+d+e+f 80443.34
g) Add for cost of royalty.
5.06 1500, 39.0 Plain/Reinforced Cement Concrete in Superstructure Ref page no 338(DATA BOOK)
1700 & complete as per Drawing and Technical
2100 Specifications.
63291.46
e) Overhead charges @"&'Lead Statement.'! 5063.32
C42&" on (a+b+c+d)
a+b+c+d+e 68354.78
f) Contractor's profit 10% 6835.48
Cost for 15 cum = a+b+c+d+e+f 75190.26
g) Add for cost of royalty.
a) Material
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
73204.58
e) Overhead charges @8% on (a+b+c+d) 5856.37
a+b+c+d+e 79060.95
f) Contractor's profit 10% 7906.10
Cost for 15 cum = a+b+c+d+e+f 86967.05
g) Add for cost of royalty.
9.08 1300 & 40 Plastering with cement mortar (1:3 ) on brick work in Ref page no 452(DATA BOOK)
2200 sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 3457.67 497.90
b) Labour
Mate day 0.04 338.00 13.52
Mason day 0.50 388.00 194.00
Mazdoor day 0.50 298.00 149.00
c) Overhead charges @8% on (a+b) 68.35
d) Contractor's profit @10% on (a+b+c) 92.28
Rate per 10 sqm (a+b+c+d) 1015.05
say 1015.05
Rate per 1.0 sqm say 101.51
Say 101.50
Add for cost of Royalty.
For Cement mortar 1:3
Sand 0.015 35.00 0.53
0.15 cum /10 Sqm. Cum. 102.03
Add 1% for Labour Welfare Cess. 1.02
103.05 /Sqm.
Say 103.00 /Sqm.
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
9.07 1400 & 41 Stone masonry work in cement mortar 1:3 for Ref page no 453(DATA BOOK)
2200 substructure complete as per drawing and Technical
Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 464.94 464.94
Through and bond stone(7No) cum 0.16 468.83 75.01
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3457.67 1141.03
b) Labour
Mate day 0.10 338.00 33.80
Mason day 1.20 388.00 465.60
Mazdoor day 1.20 298.00 357.60
Add for scaffolding @ 5 per cent of cost of a) 0.00
Material and b) Labour
c) Overhead charges @8% on (a+b) 203.04
d) Contractor's profit @10% on (a+b+c) 274.10
Rate per cum (a+b+c+d) 3015.12
e) Add for cost of Royalty.
Stone + through stone cum 1.16 130.00 150.80
Sand for 0.33 cum. cum 0.35 35.00 12.25
3178.17
Add 1% for Labour Welfare Cess. 31.78
3209.95 /Cum.
Say 3210.00 /Cum.
13.50 1500, Plain/Reinforced cement concrete in super-structure Ref page no 455(DATA BOOK)
1700 & complete as per drawing and Technical
2200 Specifications
Unit = cum
Taking output = 1 cum
5.11, 2706 & 42 Providing weep holes in Brick masonry/Plain/ Ref page no 461(DATA BOOK)
9.05 2200 Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and
Technical Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per metre 31.50 100.00 3150.00
cent )(market Rate)
Average length of weep hole is taken as one metre
for the purpose of estimating.
MS clamp(market Rate) each. 30.00 10.00 300.00
collar for AC pipe (average) taking 10% of above each. 10.00 15.00 150.00
pipe rate(market Rate)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3457.67 172.88
b) Labour
Mate day 0.03 338.00 10.14
Mason day 0.50 388.00 194.00
Mazdoor day 0.25 298.00 74.50
c)Overhead charges @8% on (a+b) 324.12
d)Contractor's profit @10% on (a+b+c) 437.56
Cost for 30 no. = a+b+c+d 4813.20
Add for cost of Royalty.
For Cement mortar 1:3
Sand Cum. 0.050 35.00 1.75
1.05 cum /1 cum. Cum. 4814.95
Rate per No. (a+b+c+d)/30 160.50
Per 1 mtr length. say 160.50 0
Add 1% for Labour Welfare Cess. 1.61
162.11 /Rm
Say 162.10 /Rm
Ref. 13.8 2706 & Providing weep holes in Brick masonry/Plain/ Ref page no 461(DATA BOOK)
2200 Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and
Technical Specifications with metal block 0.3 x 0.3 x
0.3 m
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per metre 31.50 100.00 3150.00
cent )(market Rate)
Average length of weep hole is taken as one metre
for the purpose of estimating.
MS clamp(market Rate) each. 30.00 10.00 300.00
collar for AC pipe (average) taking 10% of above each. 10.00 15.00 150.00
pipe rate(market Rate)
Metal block : 30 x 0.3 x 0.3 x 0.3 = 0.81 cum 0.81 1031.69 835.67
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3457.67 172.88
b) Labour
Mate day 0.03 338.00 10.14
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
6.05 710.1.4 43 Back filling behind abutment, wing wall and return Ref page no 462(DATA BOOK)
.of wall complete as per drawing and Technical
IRC:78 Specification
& 2200 Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 338.00 94.64
Mazdoor day 7.00 298.00 2086.00
b) Material
Moorum. cum 12.00 197.29 2367.48
c) Machinery
Plate compactor/power rammer hour 2.50 86.96 217.39
Water Tanker hour 0.05 506.09 25.30
c)Overhead charges @8% on (a+b+c) 383.26
d)Contractor's profit @10% on (a+b+c+d) 517.41
Cost for 10 cum of granular backfill = a+b+c+d+e 5691.48
f) Add for cost of Royalty.
Moorum. cum 12.00 35.00 420.00
6111.48
Rate per cum = (a+b+c+d+e+f)/10 611.15
Add 1% for Labour Welfare Cess. 6.11
617.26 /Cum.
Say 617.30 /Cum.
5.10 710.1.4 44 Providing and laying of Filter media with granular Ref page no 463(DATA BOOK)
.of materials/stone crushed aggregates satisfying the
IRC:78 requirements laid down in clause 2504.2.2. of
and MoRTH specifications to a thickness of not less than
2200 600 mm with smaller size towards the soil and
bigger size towards the wall and provided over the
entire surface behind abutment, wing wall and return
wall to the full height compacted to a firm condition
complete as per drawing and Technical
Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 338.00 108.16
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Mazdoor for filling, watering, ramming etc. day 7.00 298.00 2086.00
Mazdoor (Skilled) day 1.00 388.00 388.00
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 1006.93 12083.16
2504.2.2. of MORTH specifications IRC-Gr.III
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 506.09 30.37
d)Overhead charges @8% on (a+b+c) 1175.66
e)Contractor's profit @10% on (a+b+c+d) 1587.14
cost for 10 cum of Fiter Media = a+b+c+d+e 17458.49
f) Add for cost of royalty.
Filter media of stone aggregate conforming to clause cum 12.00 130.00 1560.00
2504.2.2. of MORTH specifications IRC-Gr.III
19018.49
Rate per cum = (a+b+c+d+e+f)/10 1901.85
Add 1% for Labour Welfare Cess. 19.02
1920.87 /Cum.
Say 1920.90 /Cum.
74660.61
Rate per cum = (a+b+c+d+e+f+g)/15 4977.37
Add 1% for Labour Welfare Cess. 49.77
5027.14 /Cum.
FORM WORK 10%
Basic Cost of Labour, Material & Machinery (a+b+c) 58816.82
for 15 cum
For formwork and staging add the following:
14.1B (i) For substructure formwork 10% Ref page no 472(DATA BOOK)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) 58816.82
for 15 cum
d) Formwork and staging 10 per cent of 20.00 5881.68
(a+b+c)
e) Overhead charges @ on (a+b+c+d) 5175.88
f) Contractor's profit @10% on (a+b+c+d+e) 6987.44
Cost for 15 cum = a+b+c+d+e+f 76861.82
g) Add for Cost of Royalty.
Coarse sand cum 6.75 35.00 236.25
20 mm Aggregate cum 8.10 130.00 1053.00
10 mm Aggregate cum 5.40 130.00 702.00
78853.07
Rate per cum = (a+b+c+d+e+f+g)/15 5256.87
Add 1% for Labour Welfare Cess. 52.57
5309.44 /Cum.
59.00 (i) For T-beam & slab , 25-35 per cent of (a+b+c)
Case I (i) For T-beam & slab , 25-35 per cent of (a+b+c) Ref page no 483(DATA BOOK)
6861.88 /Cum.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and tonne 1.05 42073.67 44177.35
wastage
Binding wire (market Rate) Kg 6.00 67.23 403.38
b) Labour for cutting, bending, shifting to site,
tying and placing in position
Mate day 0.40 338.00 135.20
Blacksmith day 2.00 448.00 896.00
Mazdoor day 6.00 298.00 1788.00
Basic value 47399.93 47399.93
c) Overhead charges @8% on (a+b) 3791.99
d) Contractor's profit @10% on (a+b+c) 5119.19
Rate for per MT (a+b+c+d) 56311.11
Add 1% for Labour Welfare Cess. 563.11
56874.22 /M.T.
Say 56874.20 /M.T.
1600 & (ii) Supplying, fitting and placing HYSD bar Ref page no 459(DATA BOOK)
2200 reinforcement in sub-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and tonne 1.05 42073.67 44177.35
wastage
Binding wire (market Rate) Kg 6.00 67.23 403.38
b) Labour for cutting, bending, tying and placing
in position
Mate day 0.34 338.00 114.92
Blacksmith day 2.00 448.00 896.00
Mazdoor day 6.50 298.00 1937.00
Basic Cost of Labour & Material (a+b) 47528.65
c)Overhead charges @8% on (a+b) 3802.29
d)Contractor's profit @10% on (a+b+c) 5133.09
Rate per MT = a+b+c+d 56464.03
Add 1% for Labour Welfare Cess. 564.64
57028.67 /MT.
Say 57028.70 /MT.
1600.0 (iii) Supplying, fitting and placing HYSD bar Ref page no 489(DATA BOOK)
reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and tonne 1.05 42073.67 44177.35
wastage
Binding wire (market Rate) Kg 8.00 67.23 537.84
b) Labour for cutting, bending, tying and placing
in position
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Average rate of in foundation, substructure & 56874.22 58304.46 57028.67 57402.45 /Mt.
superstructure.
Say 57402.50 /Mt.
5.08 46.0 Providing & fixing 20 mm thick compressible fibre Ref page no 508(DATA BOOK)
board in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.01 338.00 3.38
Mazdoor day 0.10 298.00 29.80
5.09 2702.0 47.0 Providing and laying Cement concrete wearing coat Ref page no 492(DATA BOOK)
M-30 grade excluding reinforcement complete as
per drawing and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.00 4256.58 4256.58
concrete in Item 14.1 excluding formwork(ref vide
basic cost of RCC M30/15)
HYSD bar reinforcement Rate as per item No tonne 0.000 47840.16 0.00
14.2(Excluding OH & CP)
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.15 298.00 44.70
c) Overhead charges @8% on (a+b) 344.10
d) Contractor's profit @10% on (a+b+c) 464.54
Rate per cum (a+b+c+d) 5109.92
e) Add for cost of Royalty.
Coarse sand cum 0.45 35.00 1.05
20 mm Aggregate cum 0.54 130.00 4.68
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
14.50 515 & 2702 Mastic Asphalt. Ref page no 493(DATA BOOK)
Providing and laying 12mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in Table 500-29, prepared by
using mastic cooker and laid to required level and
slope after cleaning the surface, including providing
anti-skid surface with bitumen precoated fine
grained hard stone chipping of 9.5 mm nominal size
at the rate of 0.005 cum per 10 sqm. and at an
approximate spacing of 10 cm. center to center in
both directions, pressed into surface when the
temperature of surfaces not less than 1000 C,
protruding 1mm to 4mm over mastic surface, all
complete as per Clause 515.
Unit = sqm
Taking output = 72.46 Sqm (2 tonnes) ( 0.869 cum)
assuming a density of 2.3 tonnes/cum)
a) Labour
Mate day 0.490 338.00 165.62
Mazdoor day 11.000 298.00 3278.00
Mazdoor skilled. day 1.250 388.00 485.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 200.00 12.00
Air compressor 250 cfm hour 0.060 179.13 10.75
Mastic cooker 1 tonne capacity. hour 6.000 1379.13 8274.78
Bitumen boiler 1500 litres capacity. hour 6.000 111.30 667.83
Tractor for towing and positioning of mastic cooker hour 1.000 210.43 210.43
and bitumen boiler.
c) Material
Base mastic (without coarse aggregates) 50 per cent.
Coarse aggregate(3.35 mm to 9.5mm)= 40 per cent.
Proportion of material required for mastic asphalt
with coarse aggregates (base on mix design done
by CRRI for a specific case)
i) Bitumen 85/25 or 30/40 @ 10.2 percent by weight of tonne 0.204 45286.59 9238.46
mix 2 x 10.2 /100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix Cum. 0.390 360.26 140.50
= 2 x 31.9/100= 0.638 tonnes= 0l.638/1.625=0.39
iii) Lime stone dust filler with calcium carbonate content MT 0.360 360.26 129.69
not less than 80 per cent by weight @ 17.92 per
cent weight of mix= 2 x 17.92/100=0.36.
iv) Coarse aggregates 3.35 mm to 9.5mm @ 40 per Cum. 0.550 1248.84 686.86
cent by weight of mix= 2 x 40/100= 0.8 MT=
0.8/1.456=0.55
v) Precoated stone chips of 13.2mm nominal size for Cum. 0.036 1364.07 49.11
skid resistance= 72.46 x 0.005/10= 0.036
vi) Bitumen for coating of chips @ 2 per cent by MT 0.001 27263.55 27.26
weight= 0.036 x 1.456 x 2/1000= 0.001048 MT=
1.05 kg.
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Lime stone dust filler with calcium carbonate content MT 0.360 35.00 12.60
not less than 80 per cent by weight @ 17.92 per
cent weight of mix= 2 x 17.92/100=0.36.
Coarse aggregates 3.35 mm to 9.5mm @ 40 per Cum. 0.550 32.20 17.71
cent by weight of mix= 2 x 40/100= 0.8 MT=
0.8/1.456=0.55
Precoated stone chips of 13.2mm nominal size for Cum. 0.036 130.00 4.68
skid resistance= 72.46 x 0.005/10= 0.036
27819.67
Rate per sqm = (a+b+c+d+e+f)/70 397.42
Add 1% for Labour Welfare Cess. 3.97
401.39 /M2
65.00 2703, Construction of RCC railing of M 30 grade in-situ Ref page no 497(DATA BOOK)
1500, with 20mm nominal size aggregate, true to line and
1600 & grade, tolerance of vertical RCC post not to exceed
1700 1 in 500, centre to centre spacing between vertical
post not to exceed 2000 mm, leaving adequate
space between vertical post for expansion, complete
as per approved drawings and Technical
Specifications.
Unit = 1 RM
Taking output= 2 x 24 m span= 48 m.
a) Material
i) M 30 Grade Reinforced Cement Concrete. Cum. 4.092 6321.02 25865.61
No. of vertical posts= (12+2)/2= 28 Nos. External
area of vertical post 0.25 x 0.275= 0.069 sqm.
Concrete in vehicle posts= 0.069 x 28= 1.932 cum.
Hand rail in 3 tiers= 3 x 24 = 72 m External area=
0.170 x 0.175 - 0.03 sqm Concrete in hand rails=
0.03 x 72= 2.16 cum.
Total concrete= 1.932 +2.16 = 4.092 cum (Refer
MoRT&H SD/202).
(Rate as per item No. 14.1, except cost of formwork)
Add 12 per cent of above cost for formwork. 2616.40
II) HYSD bar reinforcement (Rate as per item No. MT 0.865 47840.16 41381.74
14.2) Refer MoRT&H SD/202)
Cost for 48m= a 69863.75
66.00 1500, Reinforced cement concrete approach slab including Ref page no 500(DATA BOOK)
1600, reinforcement and form work complete as per
1700 & drawing and Technical Specifications.
2704
Unit = 1 cum.
Taking output= 1 cum.
a) Material
Cement concrete RCC M30 Grade (Refer relevant Cum. 1.000 6453.77 6453.77
item of concrete in item No. 12.8 (G) except that
formwork may be added at the rate of 2 per cent of
cost against 4 per cent provided in the foundation
concrete.
HYSD bar reinforcement (Rate as per item No. 14.2) MT 0.050 49134.55 2456.73
15.10 2503 Providing and laying boulders apron on river bed for Ref page no 520(DATA BOOK)
protection against scour with stone boulders
weighing not less than 40 kg. each complete as per
drawing and Technical Specifications.
a) Material
Stone. cum 1.00 464.94 464.94
Stone spalls. cum 0.20 468.83 93.77
b) Labour
Mate day 0.04 170.00 6.80
Mason day 0.35 205.00 71.75
Mazdoor day 0.75 150.00 112.50
c) Overhead charges @8% on (a+b) 59.98
d) Contractor's profit @10% on (a+b+c) 80.97
Rate per cum = (a+b+c+d) 890.71
e) Add for cost of royalty.
Stone. cum 1.00 130.00 130.00
Stone spalls. cum 0.20 43.83 8.77
1029.48
Add 1% for Labour Welfare Cess. 10.29
1039.77 /Cum.
5.13, 2504 50.0 Providing and laying Pitching on slopes laid over Ref page no 522(DATA BOOK)
6.06 prepared filter media including boulder apron laid dry
in front of toe of embankment complete as per
drawing and Technical specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 464.94 464.94
Stone spalls of minimum 25 mm size cum 0.20 468.83 93.77
b) Labour
Mate day 0.04 338.00 13.52
Mason day 0.35 448.00 156.80
Mazdoor day 0.75 298.00 223.50
c) Overhead charges @8% on (a+b) 76.20
d) Contractor's profit @10% on (a+b+c) 102.87
Rate per cum = (a+b+c+d) 1131.60
e) Add for cost of royalty.
Stone weighing not less than 40kg cum 1.00 130.00 130.00
Stone spalls of minimum 25 mm size cum 0.20 130.00 26.00
1287.60
Add 1% for Labour Welfare Cess. 12.88
1300.48 /Cum.
Say 1300.50 /Cum.
5.12 2504 51 Providing and laying filter materials underneath Ref page no 523(DATA BOOK)
pitching in slopes complete as per drawing and
Technical Specifications.
Unit = cum
Taking output = 1 cum.
a) Labour
Mate day 0.05 338.00 16.90
Mazdoor (Skilled) day 0.25 388.00 97.00
Mazdoor. day 1.00 298.00 298.00
b) Material
Moorum. cum 1.20 197.29 236.75
c)Overhead charges @8% on (a+b+c) 51.89
d)Contractor's profit @10% on (a+b+c+d) 70.05
cost for 10 cum of Fiter Media = a+b+c+d 770.59
e) Add for cost of royalty.
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = cum
Taking output = 1 cum
a) Material
Stone. Cum. 1.000 464.94 464.94
Stone spalls. Cum. 0.200 468.83 93.77
558.71
b) Labour.
Mate. Day. 0.050 338.00 16.90
Mason. Day. 0.250 448.00 112.00
Mazdoor Day. 1.000 298.00 298.00
426.90
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 338.00 378.56 L-12
Mazdoor skilled day 6.000 388.00 2328.00 L-15
Mazdoor day 22.000 298.00 6556.00 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 452.17 2713.04 P&M-
Cement concrete batch mix plant @ 75 cum hour 6.000 2400.00 14400.00 017
P&M-
per hourgenerator 100 KVA
Electric hour 6.000 391.30 2347.83 068
P&M-
Paver with electronic sensor hour 6.000 391.30 2347.83 080
P&M-
Vibratory roller 8-10 t capacity hour 8.000 864.35 6914.78 034
P&M-
Water tanker6 KL capacity hour 8.000 506.09 4048.70 059
P&M-
Tipper tonne.km 990 x L 2.17 12889.80 060
Lead
Add 10 per cent of cost of carriage to cover cost of L=2.5 1288.98 =input
loading and unloading km &
P&M-
c) Material
058
Crushed stone coarse aggregate of 25 mm cum 405.000 1136.45 460262.25 M-052
and 12.5 mm nominal sizes graded as per and M-
table 600-1 @ 0.90 cum/cum of concrete 054
conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum 203.000 396.60 80509.80 M-004
cum/cum of concrete
Cement @ 150 kg/cum of concrete tonne 67.500 5404.94 364833.45 M-081
Cost of water KL 48.000 10.00 480.00 M-189
d) Overhead charges @ 8% on (a+b+c) 76983.92
e) Contractor's profit @ 10% on (a+b+c+d) 103928.29
f) Royalty
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 338.00 676.00 L-12
Mazdoor skilled day 15.000 388.00 5820.00 L-15
Mazdoor day 35.000 298.00 10430.00 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 200.00 560.00 P&M-
Front end loader 1 cum bucket capacity hour 18.000 452.17 8139.13 031
P&M-
Cement concrete batch mix plant @ 175 hour 6.000 4486.96 26921.74 017
P&M-
cum per hour (effective output) 067
Electric generator 250 KVA hour 6.000 978.26 5869.57 P&M-
Slip form Slip form paver with electronic hour 6.000 1500.00 9000.00 081
P&M-
sensor with electronic sensor 006
Water tanker6 KL capacity hour 36.000 506.09 18219.24 P&M-
Transit truck agitator 5 cum capacity. tonne.km 2415xL 2.17 31443.30 060
Lead
Add 10 per cent of cost of carriage to cover cost of 3144.33 =input
loading and unloading km &
P&M-
Concrete joint cutting machine . hour 12.000 300.00 3600.00 P&M-
058
083
Texturing machine . hour 12.000 250.00 3000.00 P&M-
088
c) Material
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Crushed stone coarse aggregates of 25mm cum 945.000 1136.45 1073945.25 M-052
and 12.5mm nominal size @ 0.90 cum/cum and M-
of concrete conforming to clause 602.2.4. . 054
Sand as per IS: 383 and conforming to cum 473.000 399.46 188944.58 M-004
clause 602.2.4 @ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.000 5404.94 2237645.16 M-081
32 mm mild steel dowel bars of grade S 240 tonne 9.450 42073.67 397596.18 M-126
16 mm deformed steel tie bars of grade S tonne 1.170 42073.67 49226.19 M-082
415
Separation Membrane of impermeable sqm 3675.000 3.00 11025.00 AR-06-
plastic sheeting 125 micron thick Pg-191
Pre moulded Joint filler, 25 mm thick for sqm 16.330 80.00 1306.40 M-141
expansion joint.
Joint sealant kg 875.000 50.00 43750.00 AR-06-Pg-191
Sealant primer kg 116.670 30.00 3500.10 AR-06-Pg-191
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 90.00 4200.30 M-138
Curing compound liter 1850.000 20.00 37000.00 M-090
Super plastisizer admixture IS marked as kg 2070.000 40.00 82800.00
per 9103-1999 @ 0.5 per cent by weight of AR-06-
cement PG-192
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 338.00 94.64
BoQ
Ref. Sr. No. Description Unit Quantity Rate Rs Cost Rs
Item No.
Provision RCC Crah Barrier at the edges of the Ref page no 237(DATA BOOK)
road, approaches to bridge structures & medians,
constructed with M40 grade concrete with HYSD
reinforcement confroming to IRC:21 & dowel bars
25mm dia, 450mm long at expansion joint filled with
pre-moulded asphalt filler board, keyed to the
structure.........................
E
n
g
i
n
e
e
r
P
h
u
l
b
a
n
i
R
&
B
S
e
c
t
i
o
n
CHECK LIST FOR ESTIMATES
CHECKING
3.12 (a) Whether Survey Details Checked by the Assistant : Yes
Engineer
(b) Whether Survey Details Checked by the : Yes
Executive Engineer
3.13 (a) whether Test Samples Collected Yes
(b) whether Test Samples Checked Yes
3.14 (a) Whether the Assistant Engineer checked sub -soil : Yes
exploration
(b) Whether the Executive Engineer inspected the : Yes
sub-soil exploration and conducted sample check
27 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 4,860.87
28 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 10,226.09
29 Kerb Casting Machine Kerb Making Rm/hour 80 hour 173.91
30 Mastic Cooker Mastic Wearing coat capacity in 1 hour 1,379.13
tonne
31 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 200.00
32 Motor Grader 3.35 mtr blade Clearing /Spreading cum/hour 200/200/50/ hour 1,343.48
/GSB /WBM 50
33 Mobile slurry seal equipment Mixing and laying slurry sqm/hour 2700 hour 565.22
seal
34 Paver Finisher Hydrostatic with sensor control 100 TPH Paving of DBM/ BM/SDC/ cum/hour 40 hour 1,500.00
Premix
35 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving cum/hour 40/30 hour 642.61
of DLC
36 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Rm/hour 2 to 3 hour 3,065.22
Boring attachment
37 Pneumatic Road Roller Rolling of Asphalt cum/hour 25 hour 697.39
Surface
38 Pneumatic Sinking Plant Pneumatic Sinking of cum/hour 1.5 to 2.00 hour 2,339.13
wells
39 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 508.70
40 Prestressing Jack with Pump & access Stressing of steel hour 72.17
wires/stands
41 Ripper Scarifying cum/hour 60 hour 15.65
42 Rotavator Scarifying cum/hour 25 hour 9.57
43 Road marking machine Road marking Sqm/hour 100 hour 52.17
44 Smooth Wheeled Roller 8 tonne Soil Compaction /BM cum/hour 70/25 hour 294.78
Compaction
45 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 641.74
56 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 17.39
57 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 506.09
58 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 1.74
tonne.km
59 Vibratory Roller 8 tonne Earth or soil / GSB / cum/hour 100/60/60 hour 864.35
WBM
60 Water Tanker Water Transport capacity in KL 6 hour 506.09
Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1,043.48
Bitumen Pressure Distributor Applying bitumen tack sqm/hour 1750 hour 601.74
coat
Bitumen Boiler oil fired Bitumen Spraying capacity in 1500 hour 111.30
litre
Concrete Paver Finisher with 40 HP Motor Paving of concrete cum / hour 20 hour 1,608.70
surface
Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 143.48
Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 153.91
Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 9,710.43
Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy cum/hour 60 /60 /60 hour 730.43
/ Soil Unsuitable
Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 4,860.87
Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 10,226.09
Motor Grader 3.35 mtr blade Clearing /Spreading cum/hour 200/200/50/ hour 1,343.48
/GSB /WBM 50
Mobile slurry seal equipment Mixing and laying slurry sqm/hour 2700 hour 565.22
seal
Paver Finisher Hydrostatic with sensor control 100 TPH Paving of DBM/ BM/SDC/ cum/hour 40 hour 1,500.00
Premix
Paver Finisher Mechanical 100 TPH Paving of WMM /Paving cum/hour 40/30 hour 642.61
of DLC
Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Rm/hour 2 to 3 hour 3,065.22
Boring attachment
Pneumatic Road Roller Rolling of Asphalt cum/hour 25 hour 697.39
Surface
Pneumatic Sinking Plant Pneumatic Sinking of cum/hour 1.5 to 2.00 hour 2,339.13
wells
Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 508.70
Prestressing Jack with Pump & access Stressing of steel hour 72.17
wires/stands
Ripper Scarifying cum/hour 60 hour 15.65
Smooth Wheeled Roller 8 tonne Soil Compaction /BM cum/hour 70/25 hour 294.78
Compaction
Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 641.74
Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 17.39
Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 506.09
Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 1.74
tonne.km
Vibratory Roller 8 tonne Earth or soil / GSB / cum/hour 100/60/60 hour 864.35
WBM
Water Tanker Water Transport capacity in KL 6 hour 506.09
Water Tanker Water Transport capacity in KL 6 km 13.57
Joint Cutting Machine with 2-3 blades (for rigid hour 260.87
pavement)
Plate compactor hour 86.96
Texturing machine (for rigid pavement) hour 217.39
Concrete Paver Finisher with 40 HP Motor Paving of concrete cum / hour 175 hour 14,076.52
surface